1. The document provides a bill of quantities for fencing 1,160 meters of Romogi Seed Secondary School.
2. It includes estimates for substructure, superstructure, and wall finishes work. The substructure work includes excavation, foundations, and drainage. The superstructure involves brick walling and piers. Wall finishes include rendering and painting of walls.
3. The total cost for the fencing is estimated at 189,807,240 Ugandan Shillings.
1. The document provides a bill of quantities for fencing 1,160 meters of Romogi Seed Secondary School.
2. It includes estimates for substructure, superstructure, and wall finishes work. The substructure work includes excavation, foundations, and drainage. The superstructure involves brick walling and piers. Wall finishes include rendering and painting of walls.
3. The total cost for the fencing is estimated at 189,807,240 Ugandan Shillings.
1. The document provides a bill of quantities for fencing 1,160 meters of Romogi Seed Secondary School.
2. It includes estimates for substructure, superstructure, and wall finishes work. The substructure work includes excavation, foundations, and drainage. The superstructure involves brick walling and piers. Wall finishes include rendering and painting of walls.
3. The total cost for the fencing is estimated at 189,807,240 Ugandan Shillings.
1. The document provides a bill of quantities for fencing 1,160 meters of Romogi Seed Secondary School.
2. It includes estimates for substructure, superstructure, and wall finishes work. The substructure work includes excavation, foundations, and drainage. The superstructure involves brick walling and piers. Wall finishes include rendering and painting of walls.
3. The total cost for the fencing is estimated at 189,807,240 Ugandan Shillings.
Download as XLSX, PDF, TXT or read online from Scribd
Download as xlsx, pdf, or txt
You are on page 1of 4
Bills of Quantities: FENCING OF ROMOGI SEED SECONDARY SCHOOL
Construction in Schools -DRDIP
Item Description Amount ugx
BILL NO: 1 FENCING 1,160M
(320m x 260m) SUMMARY
1 ELEMENT NO. 1: SUBSTRUCTURE 43,350,800
2 ELEMENT NO. 2. SUPERSTRUCTURE 99,230,000
3 ELEMENT NO. 3. WALL FINISHES 38,188,000
SUB TOTAL 180,768,800
Add: 5% Contigency 9,038,440
TOTAL: TOTAL FENCING TO SUMMARY 189,807,240
Item DESCRIPTION UNIT QTY RATE AMOUNT ELEMENT NO 1: SUB STRUCTURE (All Provisional) Excavations and Earthworks for site preparation. Excavate top vegetable soil average 150mm deep and cart to spoil.Clear site of all trees, bushes, shrubs,small trees not exceeding 500mm girth and under growth including grubbing up roots and A removing away from site. m2 2,320 600 1,392,000 - Excavate to reduce levels not exceeding 1.50 metres B deep. m3 800 4,000 3,200,000 -
Load, cart and fill excavated material and remove
from site or dispose on site as directed by the Project Manager.where directed. Filling shall be taken to include all operations necessary to load,haul material from specified areas and to place C and trim material in specific areas as directed. m3 800 1,000 800,000 - Anti-termite treatment to : sides and bottoms of D foundations m2 2,192 400 876,800 Ditto : stripped surfaces of ground m2 800 300 240,000 - - Excavations and Earthworks for foundations. - - Excavate trenches for wall foundations: not E exceeding 600mm deep . m3 480 4,000 1,920,000 - Extra over excavations : breaking up rock met with F in excavations m3 25 10,000 250,000 - Disposal of excavated material - Selected excavated material in filling to foundation trenches : around walling : placed in 100mm layers : G watered and compacted to 95% MDD m3 320 2,000 640,000 - H Remove surplus excavated material from site m3 160 4,000 640,000 Insitu concrete grade 10 / 20mm aggregate as described.(1:4:8) - I 50mm Blinding : to bottoms of excavations m² 800 2,000 1,600,000 - Insitu concrete grade 15 / 20mm aggregate as described.(1:3:6) - 230mm thick Foundation in trenches m 3 184 100,000 18,400,000 - Foundation Walls -
Hard burnt clay bricks to BS 712 & 6750
(3.5N/mm2 compressivestrength) bedded and jointed in cement and sand (1:4) mortar including hoop iron Gauge 16 : lapped 150mm at joints; every after two courses laid in 2No. - J 230 mm thick walling average 400mm deep m 1,160 6,000 6,960,000 - Horizontal Damp proof course : hessian based bitumen felt lapped 150mm on ends laid on cement and sand (1:4) mortar bed: - 200mm Wide : laid under walls LM 1,160 2,000 2,320,000 - Plinth finishes - 15mm Cement and sand (1:4) render : steel trowelled smooth m² 928 2,000 1,856,000 - Prepare and apply three coats bituminous or other approved water resistant paint to : rendered plinth walls m² 928 2,000 1,856,000 - Maintenance for excavations - Allow for upholding and maintaining sides of excavations ITEM 1 200,000 200,000 - Allow for keeping excavations free from surface water ITEM 1 200,000 200,000 - TOTAL ELEMENT NO. 1 SUBSTRUCTURE CARRIED TO SUMMARY 43,350,800 ELEMENT NO. 2 SUPER STRUCTURE WALLING
Hard burnt clay bricks to BS 712 & 6750
(3.5N/mm2 compressivestrength) bedded and jointed in cement and sand (1:4) mortar including hoop iron Gauge 16 : lapped 150mm at joints; every after two courses laid in 2No. I 230 mm thick walling average 2400mm deep m² 2,423 40,000 96,920,000 - Extra over for high brick piers No. 385 6,000 2,310,000 - TOTAL ELEMENT NO. 2 SUPERSTRUCTURE CARRIED TO SUMMARY 99,230,000 ELEMENT NO 3 : WALL FINISHES External and Internal wall finishes Cement and sand (1:4) 20mm thick 3 layer render to walls including tyrolean cement and washed sand (1:2) sprayed onto rendered surface. m² 4,847 2,000 9,694,000 - Prepare surfaces: apply three coats weather guard emulsion paint - Note: The color of the Paint will be given by the Project Manager - Rendered surfaces : walls m² 4,847 2,000 9,694,000 GATE AND SECURITY HOUSE. -
3500mm wide main gate and 900mm wide
pedestrain gate comprising of 300mm x 300mm x 2100mm high reinforced concrete gate columns with 4T12-R8@ 200mm centre in concrete class C25/20 K (1:1.5:3) mix, 25mm x 25mm x 2mm SHS vertical Item 1 6,000,000 6,000,000 members welded at 50mm centre on 40mm x 20mm x 3mm RHS Horizontal members all welded to 60mm x 60mm x 3mm SHS frame including heavy duty gate hinges using 100mm x 6mm flat bar and 25mm round bars by 300mm long as bolts and hooks all connected to the concrete columns. Ditto: Width 1.5 mx2.1m high, single leaf No 2 400,000 800,000 - Provide a provisional sum of Ugx. 10,000,000 (Ten L Million Ugandan Shillings) for constructing a 3000mm x 3000mm secuirty house Item 1 10,000,000 10,000,000 - Allow for installation of Razor Wire with all accessories over the wall fence Item 1 2,000,000 2,000,000 - - - - - - - - - - - TOTAL ELEMENT NO. 3 SUPER STRUCTURE CARRIED TO SUMMARY 38,188,000