Unit 5 Project Risk and Audit
Unit 5 Project Risk and Audit
RESOURCE SCHEDULING
RESOURCE LEVELLING
RISK ANALYSIS
PROJECT AUDIT
PROJECT TERMINATION & CLOSING
PROJECT CONTROL
Resource scheduling is a project management process that helps
teams ensure the right person is assigned to each job.
Basically resource scheduling refers to the set of actions and
methodology used by organizations to efficiently assign the
resources they have to jobs, tasks or projects they need to
complete, and schedule start and end dates for each task or project
based on resource availability.
Resource scheduling is a process used by teams to organize
and structure their time, so tasks they need to complete are
scheduled based on availability and capability.
It determines the timeline and resources required to complete
a project.
Scheduling resources can be a complicated and time-
consuming process, but it's also a crucial piece of the puzzle
regarding getting projects done
Resource Leveling :
A technique in which start and finish dates are adjusted based on resource
constraints with the goal of balancing demand for resources with the available
supply
Resource Smoothing:
A modified form of resource levelling, where resources are levelled only within the
limits of the float of their activities, so the completion dates of activities are
not delayed .
Resource leveling is used when resources are under or over allocated. Resource
smoothing is used when resources are unevenly allocated.
Perform Qualitative Risk Analysis is the process of prioritizing risks for further
analysis or action by assessing and combining their probability of occurrence
and impact. The key benefit of this process is that it enables project
managers to reduce the level of uncertainty and to focus on high-priority risks.
Perform Qualitative Risk Analysis assesses the priority of identified risks using
their relative probability or likelihood of occurrence, the corresponding impact
on project objectives if the risks occur, as well as other factors such as the time
frame for response and the organization’s risk tolerance associated with the
project constraints of cost, schedule, scope, and quality
Perform Qualitative Risk Analysis is usually a rapid and cost-effective means
of establishing priorities for Plan Risk Responses and lays the foundation for
Perform Quantitative Risk Analysis, if required
Considerable Extensive
Management Must manage and management
Significant required Monitor risk essentials
Likelihood Severity
1.Highly Unlikely 1.Trivial
2.Unlikely 2.Minor Injury
3.Possible 3.Over three day injury
4.Probable 4.Major Injury
5.Certain 5.Incapacity or Death
The Perform Quantitative Risk Analysis process analyzes the effect of those risks
on project objectives. It is used mostly to evaluate the aggregate effect of all risks
affecting the project.
Project Risks 1 - Weather: There is a 25 percent chance of excessive snow fall that’ll
delay the construction for two weeks which will, in turn, cost the project $80,000
In this Expected Monetary Value example, we have two negative project risks
(Weather and Labour Turmoil) and a positive project risks (Cost of Construction
Material). The Expected Monetary Value for the project risks:
Though the highest impact is caused by the Labour Turmoil project risk, the Expected
Monetary Value is the lowest. This is because the probability of it occurring is very
low. This means that if the:
The total project’s Expected Monetary Value based on these project risks is:
Therefore, if all risks occur in the construction project, the project would lose $17,500.
In this scenario, the project manager can add $17,500 to the budget to compensate for
this
The project management closure process also gives the team the
opportunity to review and evaluate the project’s performance to
ensure future projects’ success.
Project closure helps avoid:
Repeating mistakes on future projects and objectives
Having final products or deliverables without dedicated
support and resources
Failing to identify the team or individuals who will own and
maintain the solution following final delivery