Lecture 1
Lecture 1
Lecture 1
Involves
Make decisions about which methods, and technologies to be used for project success.
At the lowest level of the WBS, the elements of work are called a work package. A
list of project activities is developed from the work packages.
A work package contains the work defined at the lowest level of WBS for which
cost and duration can be estimated and managed.
Work Breakdown Structure (WBS)
WBS is a tool for managing complex projects.
• A first step in creating a schedule
• Useful for defining the scope of work
Consists of:
Subdividing the task into smaller & smaller portions
• Each task is divided into a simple enough task to estimate the duration
• can assign crews
• each task has a natural sequence relative to other tasks
Work Breakdown Structure (WBS)
Work Breakdown Structure (WBS)
Work Breakdown Structure (WBS)
• A work breakdown structure does not show the sequence in which work is
performed.
• Activity is a unique unit of the project that has a specified duration. In other
words, an activity can be any function or decision in a project that consumes time.
Activity
Activities are classified into three types:
1. Production activities: activities that involve the use of resources such as labor,
equipment, material, or subcontractor.
Examples are excavation, formwork, reinforcement, concreting, etc.
2. Procurement activities: activities that specify the time for procuring materials or
equipment that are needed for production activity. Examples are brick procurement, boiler
manufacturing, delivery, etc.
3. Management activities: activities that are related to management decisions such as
approvals, vacations, etc.
Activity
• An activity can be as small as “steel fixing of first floor columns” or as large as
“construct first floor columns”. This level of details depends on the purpose of
preparing the project plan.
• Accordingly, level of details depends on: planning stage, size of the project,
complexity of the work, management expertise.
Activity
Example: Contractor has the bidding documents, including the drawings and
specifications, for a certain project. Within a certain area in the project's WBS, a
concrete foundation work package is included and the planning exercise for it is
considered here. The first list of activities that might be put together for this work
package is shown in table below.
Activity
Activity Description
A Site clearing
B Removal of Trees
C General Excavation
Which activity(ies) must be finished before the current one can start?
• Activities E (trench excavation) and F (concrete preparation) cannot begin until the
completion of general excavation and grading, since they involve subsequent
excavation and trench preparation.
Activities Relationships
• Activities G (install lines) and H (install utilities) represent installation in the utility trenches
and cannot be attempted until the trenches are prepared so activity E (trench excavation) is
a preceding activity.
• We also assume that the utilities should not be installed until grading is completed to avoid
equipment conflicts, so activity D (general grading) is also preceding activities G (install
sewers) and H (install utilities)
• Finally, an activity I (pour concrete) cannot begin until the sewer line is installed and
formwork and reinforcement are ready, so activities F and G are preceding. Other
utilities(activity H) may be routed over the slab foundation.
Activities Relationships
• Four types of relationships among activities can be defined as and illustrated below.
Typically, relationships are defined from the predecessor to the successor activity.
a) Finish to start (FS). The successor activity can begin only when the current activity
completes.
b) Finish to finish (FF). The finish of the successor activity depends on the finish of the
current activity.
c) Start to start (SS). The start of the successor activity depends on the start of the current
activity.
d) Start to finish (SF). The successor activity cannot finish until the current activity starts.
Activities Relationships
Activities Relationships
Activities Relationships
• A network is a graphical representation of the project activities and their
relationships. A project network is a set of arrows and nodes. Before drawing the
network, it is necessary to ensure that the project has a unified starting and ending
point.
• There are two ways that are commonly used to draw a network diagram for a
project:
• In this method, the arrows represent activities while the nodes represent the start
and the end of an activity (usually named as events).
• The length of the arrow connecting the nodes has no significance and may be
straight, curved, or bent.
• When one activity depends upon another, both appear on the diagram as two
arrows having a common node.
Activities Relationships
Activities Relationships
The following are some rules that need to be followed when constructing an AOA
network diagram:
• Each activity must have a unique i – j numbers, where i (the number at the tail of
the arrow is smaller than j (the number at the head of the arrow).
In some situations, when more than one arrow leave the same node and arrive at
another node, dummy activities must be used.
Activities Relationships
• The dummy activity is an activity with zero duration, consumes no resources, drawn
• A dummy activity is also used when one activity depends upon two preceding
activities and another activity depends only upon one of these two preceding
• This method is also called the precedence diagram method (PDM). In this method,
the nodes represent activities and the arrows represent logical relationships among
the activities.
• If the arrow starts from the end side of an activity (activity A) and ends at the start
side of another activity (activity B), then A is a predecessor of B.
AOA Network
Activities Relationships
• To understand the drawing of the AON, some ordering for the activities may be
necessary. This is done by placing the activities in a sequence step order. A
sequence step may be defined as the earliest logical position in the network that an
activity can occupy while maintaining the logical relationships.
• In this example, as there are two activities (activities A and B) has no predecessor,
then a start activity is added to have one unified start activity (Start) for the project.
Also, a finish activity (Finish) is added as there are two activities without successors
(activities F and G).
Activities Relationships
Determining the sequence steps
Activities Relationships
Note that dummy activities are not required for expressing precedence
relationships in activity-on-node networks.
An AON Network
Activities Relationships
• Exercise 1: Draw the AOA and AON networks for the project given below.
Activities Relationships
• Solution for Exercise 1
• We can estimate the duration from previous similar projects or unit productivity rates
• For example, the duration of an activity Dij such as concrete formwork assembly might be
estimated as:
• Dij = Aij / (Pij * Nij), Where Aij is the required formwork area to assemble (in m2), Pij is the
average productivity of a standard crew in this task (measured in 𝑚2 per hour), and Nij is
the number of crews assigned to the task.
Determination of duration of activities
• Example 1: Activity duration to place 230 𝑚2 of slab formwork, assuming a
production rate of 1.5 𝑚2 /hr. /crew (assuming 8 working hours per day) can be
established as follows
Solution
• Then, for a balanced mix of resources, use 2 steel-fixer crews, one carpenter crew,
and one concreting crew. Accordingly, the activity duration = 50 / 0.5 x 2 = 50 days.
Determination of duration of activities
Exercise 2 If the daily production rate for a crew that works in an activity is 175
units/day and the total crew cost per day is $1800. The material needed for daily
work is 4.5 units at $100/unit.
a. Calculate the time and cost it takes the crew to finish 1400 units
b. Calculate the total unit cost. Consider an eight hour work day.
Solution a. Duration (units of time) = Quantity / Production per unit of time x number
of crews = 1400 / 175 x 1 = 8 days
Determination of duration of activities
Cost (labor cost) = Duration (units of time) x crew cost per unit of time = 8 days x
$1800 / day = $14400
Total direct cost = $14400 + 4.5 units of material x $100 / day x 8 day = $18000