FC20 Installation Instructions

for Insertion Meters


For use with all insertion Fox Thermal Flow Meters
Definition: The FC20 is a flow conditioner installed upstream of a Fox Thermal flow
meter that corrects irregular flow profiles to ensure flow measurement accuracy. The
FC20 is installed between two flanges in schedule 40 pipe with insertion style meters.
Purpose: This procedure describes proper installation of the FC20 to ensure flow
measurement accuracy.
Directions:
1. Determine the correct distance for dimensions 2D and 5D from the table below for
the appropriate schedule 40 pipe.
2. Ensure proper installation of the branch outlet for the flow meter. See Fox Document
107590 for more information.

Figure 1.1: FC20 Minimum Straight Run Requirements

FC20 Flow Conditioner


installed between two flanges Proper
Flow
Branch Outlet
Profile
(installed by customer)
Irregular Flow
F1 F2 F3 F4

Profile

FLOW

5D Min. 2D 5D Min.

Schedule 2D 5D Min. Up/Down- Schedule 2D 5D Min. Up/Down-


40 Pipe Inch (mm) stream 40 Pipe Inch (mm) stream
Size Inch (mm) Size Inch (mm)
1.5 3.22 (82) 8 (203) 8 15.96 (405) 40 (1016)
2 4.14 (105) 10 (254) 10 20.04 (509) 50 (1270)
2.5 4.94 (125) 12 (305) 12 23.88 (607) 60 (1524)
3 6.14 (156) 15 (381) 14 26.24 (666) 66 (1676)
4 8.06 (205) 20 (508) 16 30.00 (762) 75 (1905)
6 12.13 (308) 30 (762) 18 33.75 (857) 84 (2133)

Note: Flow meters that will utilize the FC20 as part of the installation must be identified
at time of order and calibrated with a FC20.
Fox Thermal DOCUMENT NO.: 109193, REV. B
399 Reservation Road, Marina, CA 93933 Page 1 of 2
www.foxthermal.com
831-384-4300
Figure 1.2: Upstream Side of the FC20 Flow Conditioner
UPSTREAM
SIDE

LOUVERS

3. Position the FC20 Flow Conditioner correctly between the flanges.


• The FC20 must be installed between flanges and two gaskets for optimum seal.
• Center the flow conditioner between the flanges.
• The FC20 is equipped with an orientation marker. This marker must be aligned in
parallel with the probe of the flow meter.
• The Orientation marker is also etched with “UPSTREAM” to indicate which side, or
face, of the FC20 must be facing upstream. When installed correctly, the louvers
inside the pipe will point downstream.

Figure 1.3: Orientation of FC20 Flow Conditioner

FC20 ORIENTATION MARKER WITH


"UPSTREAM" ETCHING

ORIENTATION MARKER MUST BE FC20 MARKER FLOW METER


PARALLEL TO FLOW METER
PROBE

PROBE
2D
(SEE TABLE
PREVIOUS PAGE) POINTER, FLOW DIRECTION
BRANCH OUTLET
(CUSTOMER SUPPLIED)

DETAIL A

FLOW

GASKETS, CUSTOMER SUPPLIED

4. Tighten bolts on the flanges to complete installation of the FC20.


Fox Thermal DOCUMENT NO.: 109193, REV. B