Progress Report

The progress report summarizes the relocation of electrical facilities along 27 kilometers of Dangote Refinery Road due to ongoing road construction. So far, 80% of facilities have been relocated along the first 20 kilometers of the left hand side of the road. Key accomplishments include relocating 48 sections of overhead lines and 7 transformers. Challenges have included delays in demolition work and security issues during relocation. The project is 80% complete overall with the final 7 kilometers of relocation still outstanding.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
35 views

Progress Report

The progress report summarizes the relocation of electrical facilities along 27 kilometers of Dangote Refinery Road due to ongoing road construction. So far, 80% of facilities have been relocated along the first 20 kilometers of the left hand side of the road. Key accomplishments include relocating 48 sections of overhead lines and 7 transformers. Challenges have included delays in demolition work and security issues during relocation. The project is 80% complete overall with the final 7 kilometers of relocation still outstanding.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 6

Progress Report 30th November 2023

Project Details
Project Title DANGOTE REFINERY Progress 25%
ROAD CONSTRUCTION percentage %
PROJECT.

Project Start Date January 2023 Finish Date 2024

Reporting Period November 2023 Project manager

Company MERCILIA TECHNOLOGY LTD


Client
Stakeholder

Introduction
Relocation of electrical facilities from Eleko Junction to Dangote Refinery Road due to the ongoing
road construction/expansion. These facilities which include Transformers, Feeder Pilars, Gang
Isolators and Poles are expected to be relocated 45m away from the center of the road. The project
covers 27km distance. Other details is narrated below.

Summary of Activities:

Scope

Relocation of all electrical facility, within the expansion of 27


kilometers at Dangote Refinery Road, Eleko. The facilities
affected are as follow:
Scope/Overview of the project - Sixteen (16) Distribution Transformers are to be relocated.
- 560 poles (both wooden and concrete) are to be relocated
away from the ROW.
- The Project cuts across 2 electrical feeders (33kv and 11kv)
that cross each other.
Process Evaluation: Project Implementation Highlight
We have recovered all electrical facilities from Akodo to Magbon Alade.
This marks the 80% percent of the total space cleared at the LHS.
ACHIEVEMENTS
More breakdown below;

- More than 20 Kilometers electrical facilities have been taken out


of the ROW on 27 Kilometers at the LHS, for the construction
company (HITECH) to carry out their construction work without
any form of obstruction relating to electrical work.

- Total of 48 Sessions of 33kv over-head lines have been recovered.

- 7 Transformers have been successfully repositioned/relocated

CHALLENGES Delay in demotion;


- We are expected to replace and reposition the electrical facilities
immediately after removal of the initial one. Failure to meet this
expectation as, therefore, led to different issues within the
environment, whereby leaders from various communities came
out to challenge us.

- The progress of the electrical relocation is affected due to delay in


demolition.

Security Challenge:
- We have experienced various hoodlums attack during the process
of recovery and relocation of electrical facilities, whereby the
hoodlums forcefully demanded for money and left our workers
injured.

Milestones/Accomplishments
(List brief 1 – 2 sentence descriptions of what was accomplished this period

Include important scheduled milestones if any occurred in this last period)

Milestone Description Delivery Status


Date

Approval Secure of work approval for the relocation of all 28th Feb Complete
electrical facilities from Disco (EKEDC) 2023

Mobilization Mobilization of equipment, Man power, secure 20th March, Complete


store for keeping materials/tools and 2023
accommodation for workers and all other
necessary requirements to kick start the
relocation of the electrical facilities.

MEETING Meeting with stakeholder, such as Community 4th April Complete


Leaders, Civil Engineer Contractors, and Surveyor 2023
team for adequate cooperation.

First 10km Removal of all electrical facilities within the June 2023 Not complete
LHS distance of the first 10km
70%

Second 10km Clearing of electrical facilities that fall within the August Complete
LHS alignment of the road. 2023
100%

Outstanding All electrical facilities within the last 7km are to be October Not complete
of 7km taken out of the right of way. 2023
80%

Initial state:

The initial state


Fig 2: 1-8, Above are pictures of activities on the project;
Fig 2: 9-10 The pictures reflect Clearing of obstruct trees, within the proposed point for the electrical
facilities.

I certify that this document and any attachment was prepared under my direction in accordance with
the terms and conditions of the project. Based on my inquiry of the persons or persons who manage
the project, or those directly responsible for gathering the information, the information submitted is, to
the best of my knowledge and belief, true, accurate, and complete. All information submitted in this
document and all attachments conform to and is in accordance with the project state and I so here
certify with my signature.

Project Director:

Printed Name Signature