Progress Report
Progress Report
Project Details
Project Title DANGOTE REFINERY Progress 25%
ROAD CONSTRUCTION percentage %
PROJECT.
Introduction
Relocation of electrical facilities from Eleko Junction to Dangote Refinery Road due to the ongoing
road construction/expansion. These facilities which include Transformers, Feeder Pilars, Gang
Isolators and Poles are expected to be relocated 45m away from the center of the road. The project
covers 27km distance. Other details is narrated below.
Summary of Activities:
Scope
Security Challenge:
- We have experienced various hoodlums attack during the process
of recovery and relocation of electrical facilities, whereby the
hoodlums forcefully demanded for money and left our workers
injured.
Milestones/Accomplishments
(List brief 1 – 2 sentence descriptions of what was accomplished this period
Approval Secure of work approval for the relocation of all 28th Feb Complete
electrical facilities from Disco (EKEDC) 2023
First 10km Removal of all electrical facilities within the June 2023 Not complete
LHS distance of the first 10km
70%
Second 10km Clearing of electrical facilities that fall within the August Complete
LHS alignment of the road. 2023
100%
Outstanding All electrical facilities within the last 7km are to be October Not complete
of 7km taken out of the right of way. 2023
80%
Initial state:
I certify that this document and any attachment was prepared under my direction in accordance with
the terms and conditions of the project. Based on my inquiry of the persons or persons who manage
the project, or those directly responsible for gathering the information, the information submitted is, to
the best of my knowledge and belief, true, accurate, and complete. All information submitted in this
document and all attachments conform to and is in accordance with the project state and I so here
certify with my signature.
Project Director: