Epc Projects Financing - Project Controller Role
Epc Projects Financing - Project Controller Role
March 2022
Summary
I. INTRODUCTION..................................................................................................................................................2
II. PROJECT CONTROLLER INVOLVEMENT ............................................................................................2
1. CASH CALL/CASH STOCK AMOUNT AND PERIOD IDENTIFICATION ...........................3
2. FINANCIAL COST ESTIMATION ............................................................................................................3
3. INTER-PROJECT FINANCING ALTERNATIVE ..............................................................................5
4. FINANCIAL COSTS TRACKING AND MONITORING ..................................................................6
5. PROJECT BANKABILITY IMPROVEMENT ........................................................................................6
III. CONCLUSION....................................................................................................................................................9
I. INTRODUCTION
Most of the EPC projects are securely financed, lenders prefer to see the deepest pocket sponsors
bearing the full risk of the project. Non-recourse/limited recourse financing is exceptional. However,
despite the sponsor equity support, Contractors still suffer from heavy financial costs worsened by a
tightened financial market. Furthermore, lenders continue to seek the availability of any third-party
financial guarantees assuring project delivery.
Thus, an important consideration is to be paid to project financing techniques (models and process),
which become a major competitiveness factor for EPC Contractors. Sure it depends on the sector,
location, size… Nevertheless, throughout the project planning process, the project management team
needs to prepare responses/scenarios for the following points:
In general, the involvement of the project controller in financial matters is very limited. The financial
department of EPC Contractors leads the negotiation with lenders to find project financing ways based
on forecast project cash flow statements. It is rare to see a Project Manager or a Project Controller
setting around the same table with lenders to negotiate a project financing plan. This may be explained
in part by:
Company Organization/Culture
Project Team background
In such organization, the control of the financial cost is very limited for the project management team.
Inputs are provided by the financial department and recorded as Actual Cost by the project team.
Budgeting and monitoring financial costs are mostly out of project control responsibility.
However, most of the inputs and the documents used during negotiation with the lenders are
developed and provided by the project control team.
Based on the project schedule, the project budget, the progress measurement system, and the
contract payment terms, the project controller develops a Project Forecast Cash Flow. Different
scenarios to be analyzed: Optimistic, Realistic, and Pessimistic.
2000
Excess Cash amount/periods
1000
-1000
-2000
Cash call amounts/periods
-3000
Realistic Pessimestic Optimistic
-4000
As illustrated in the above graphic each scenario will generate Excess Cash Amount/Period and
Cash Call Amount/Period. The contractor’s decision-maker will seek to ascertain the best
alternative complying with Contractor Project Targets. (Financial, strategic, commercial,
development…).
Each scenario will generate financial costs, which shall be well estimated by the project controller.
The approval of any Cost Engagement is conditioned upon the related amount to be
invoiced.
Each spent amount should generate revenues.
Project financial objectives shall be precisely defined for the project management team at an early
stage (implemented on Project Charter). Such information will be highly helpful for project
management to consider while developing, tracking, and updating the Project Execution Plan.
Moreover, financial matters could be implemented as constraints/risks (threats or opportunities)
on the project schedule to be monitored and tracked during the project execution. Execution
sequences, priorities, performances, resources, and material mobilization…to be reviewed and
tailored to comply with financial objectives.
There are mainly (not limited) two major inputs to take into account during financial costs
estimation:
For experienced project controllers, the cost estimation/analysis for the first input is not very
complicated. Many tools and techniques could be highly reliable and relevant (e.g: Primavera Risk
Analysis, Monte Carlo Simulation…).
However, regarding the financial cost estimation, project controllers are required to collect the
updated parameters on the financial market to provide a reliable estimation. (e.g: IRR, short-term
interest rates fluctuation, currency trend). There are also many tools and software that could be
helpful.
Once the financial costs are estimated and budgeted, the project controller needs to ensure close
follow-up to all driving factors. (Schedule, risks, changes, procurement plan, time extension, extra
work…)
Project cash flow remains dynamic throughout the project lifecycle. Therefore, the cash flow burn
rate needs to be well monitored during all project phases.
If the amount was used to expedite PO and avoid currency devaluation impact
If the amount was used as a monetary incentive for early completion
If the amount was used to finance trading operation
Knowing the currency trend, is there any exchange rate profit (postpone works and
consequently the payment)
Zaher Drira 5 March 2022
EPC Projects Financing: Project Controller Role
For EPC Contractors, the inter-project funding model shall be properly evaluated. The project
controller may refer to “A prime lending rate” or “below-market interest rate” to estimate
outcomes generated by cash flow surplus during a specific period.
These rates could be discussed, fixed, and reviewed on yearly basis during PMO meetings
based on internal and external parameters.
Although the following list of the inputs set forth is by no means exhaustive, once properly
analyzed, project controllers will be able to provide liable data to enhance project bankability.
Project Bankability
- Owner/Authorities
- Location
Contract Bankability
- Political situation - Lenders assess the risk allocation between the
- Social matters contractor and the project owner
- Authorizations - Lenders focus on ability of Contractor to
- Dispute resolution (Laws, Liquidated damages..)
claim:
- Price and Currency
- Currency risk * Additional cost
- Smilar Project experience * Time extension
- Contractor technical capability * Extra work
- Project Key persons
- Main Suppliers/Subcontractors - Payment terms/ Forecast Cash flow
- Detailed Execution Strategy/Schedule - Lenders want to know Contractor
- Risk Rgister performance based on relevant experience
- Single point responsibility
-…
Referring to the range of factors/indicators lenders assess project bankability and accordingly the
funding plan and cost will be defined. Certainly, most of the above-listed factors are not controlled
by project controllers (defined from the bidder phase/ linked to the project environment).
However, Project controllers need to improve project bankability while developing/providing
detailed information able to support Contractor negotiators to enhance their position during
negotiation with lenders.
- Project Detailed Schedule: Shall reflect project execution strategy. Main milestones (internal
and external) to be implemented. Risks and constraints shall be highlighted. The proper project
schedule will give an idea to lenders about the Contractor’s capability to claim changes, time
extension, extra works, and additional cost.
The grounds on which the EPC contractor can claim schedule time extension or additional
cost become very limited. It’s one of the major roles of the project controller to raise any
opportunity to enable to proceed with a claim.
- Project Risk Register: External and internal risks shall be well monitored and risks impacts
(cost and time) to be analyzed and highlighted.
As the project progresses, new risks may appear, and risks identified previously may disappear.
EPC risk identification requires a continual update.
III. CONCLUSION
The involvement of project controllers in project financing matters presents meaningful support to
achieve project targets. Financial cost tracking and monitoring are one of the important tasks among
the list of responsibilities to be performed by project controllers.
Although project-financing decision/plan is often under Contractor Top Management responsibility,
also the project-financing map depends on company projects portfolio management, project
controllers are required to:
Ensure good estimation and monitoring of the financial costs
Raise the hidden financial incomes (inter-project financing)
Improve project bankability: enhancement of negotiation terms with lenders
Good assessment of projects risks and take advantage of opportunities (e.g: delay of non-
critical activities could constitute a significant financial opportunity)
Local currency
Vs
Foreign currency
T1 T2 T3
Figure 6: Currency and Schedule Trend Analysis
EPC Contractor needs to take all financial opportunities enable to generate additional incomes. While
improving their bankability and ensuring proper control of tools and parameters, Project controller
shall consider EPC Projects as a short-term investment allowing to generate investment incomes.
EPC Contractors need to ensure continuous financial training for their projects controllers who are
also called to develop their financial knowledge and be always updated with financial market data.
Beyond financial targets, having an efficient financial costs control system consists also a major
tool/input for contract management process (e.g: claim including moratorium interest estimation).