Chapter 2.02.1 Construction Planning
"Tf you fail to plan, you are bound to fail"
— Planning is the most important constituent of the
construction management. In the simplest sense
planning is the mental process deciding about the
future line of actions.
It forms the basis for the project scope, schedule,
resources, quality, risk, and integration
Planning is done to
— Eliminate or reduce uncertainty
— Improve efficiency of the operations
— Obtain better understanding of the objectives
— Provide basis for monitoring and controlling. . .
Objectives of planning
* The main objective of planning of a work is to execute the
project or work most economically in terms of money and
time both.
* The effective planning depends upon the following factors:
— Proper design of each element of the project
— Proper selection of plant and equipment
— Proper arrangements of repair of plant and equipment at site
— Procurement of required materials well in advance
— Ensure employment of skilled and unskilled employees
— To provide welfare schemes for the workers
— To provide incentives for good workers
— To arrange constant flow of funds in entire project duration
— To provide required level of safety and compensations
— Proper arrangements of communication and mobility in site2.2 Steps and Stages in Planning
* Steps involved in planning
— Identifying the likely problems to be encountered in the
execution of the work and obtaining necessary information
useful in the execution of the work.
— Ascertaining alternative feasibility of execution of work
and selection of the optimum plan
— Fixing the time of starting the execution of work
— Deciding the time of delivering the materials at site
— Deciding the quantities and duration of various types of
machines and equipment
— Deciding the number of different types of labors for various
works and duration of their employment
— Estimation of financial help if needed
— Estimation of the duration of completion of the work
— Evaluation of the effectiveness of plan adoptedStages of planning
+ Usually the stages of planning are as follows:
— Preplanning
* Setting out objectives
* Cost benefit analysis
* Project go / no-go decision
— Detailed planning
* Detailed design and drawings
+ Specifications
* Quantities calculation
+ WBS is done
* Sequence and scheduling of the activities are done
— Monitoring and controlling
+ In this phase, the progress of construction is monitored as per proposed
scheduled.
+ Updating of schedule can be carried out according to the actual
progress of work.
* Preparation of the revised forecasts regarding the availability of
various resources is done.Planning by the Client /Owner/Employer
* Pre-tender stage planning
— Clients sets clear objectives of the project
— Client communicate the objectives to all the parties and stakeholders
— After proper investigations of the project, client prepares quantity estimates and
determines the quantum of money required for the completion of the work.
— Take respective approval of the project from concerned authority
— Selection of project team and project appraisal
— Select the consultant
— Bidding and contract award (Selection of Contractor)
* Construction stage planning
— Revision in objectives in responding unexpected events
— Make site available for the contractor
— Timely payment and settlement of claims
— Keep the changes less
— Update performance bond of the contractor
— Timely decision
* Post construc stage planning
— Prepares project operation schedule
— Prepares project maintenance schedule
— Project ownershipPlanning by the Contractor
* Pre tender stage planning
* The planning undertaken by the contractor after receipt of tender notice and
before submitting the bid is known as pre tender stage planning.
Careful Study of tender documents and drawings to find out the
quantities of each item of work
Study of specifications and workout the detailed quantities of materials
required for different items
Determine the availability of construction materials at site or nearby
site.
Determine the method of work execution i.e. by labor or equipments
Thorough study of site and site investigationsPlanning by the Contractor contd...
* Construction stage planning
* After the acceptance of the tender, the contractor further needs in-depth
planning. This stage of planning is also known as contract planning.
— Studying the alternative methods of construction and to decide about
subcontracting
— Working out detailed quantities of materials required and examine and
fixing the methods of procurement and sources of them
— Working out detailed about construction workforce like skilled and
unskilled manpower
— Working out details of plants, equipment their layout and repair &
maintenance strategy
— Planning for camp facilities, access, accommodations, site offices and
layout
— Planning for surveillance like proper lighting, ventilation, drinking
water, sanitation, first aid treatment
— Study interdependence of different items of works and fixing the
sequence of them
— Finalize the work program of each item of work and to decide the dates
of their starting and completingPlanning by the Contractor contd.
Post construction stage planning
Demobilization of plants and equipment
Demobilization of labors
Clearance of materials inventory and its stock
Handover the project to client in targeted date
Responsible for the defect liability construction within its period2.4 Preparing Schedule
Scheduling
A construction schedule is a graphic representation which shows the phasing
rate of construction with the starting and completing dates of each activity
and the sequential relationship among various operations in a construction
project.
Use of scheduling
* Following are the use of scheduling
* The quantity of work involved, labor, material, equipment and money
required at each stage of work can be determined by scheduling.
* The actual progress of the work can be checked from time to time by
scheduling
* The project can be carried out in systematic manner by the use of
schedulingClassification of scheduling
Schedules can be classified into groups according to
the requirements as follows:
— Construction schedule
— Materials schedule
— Labor schedule
— Equipment schedule
— Financial schedule
— Control schedule
— Organizational schedule
— Summary schedule
Methods of scheduling
Bar chart or Gantt charts
Milestone charts
Network analysisConstruction schedule and its preparation
Before preparing construction schedule following information must be
known
— Various operations to be done in a particular project
— Quantum of works to be done in each operation
— Unit of measurement
— Rate of progress of work with due allowance of weather conditions
— Number of labors required
— Number and types of plants and equipment required
— Date of starting and completing the activity
— Correlation between different operations
The procedure of preparing construction schedule is as follows:
— The work or project is divided into number of operations and their inter
dependence or relationship is studied. After the careful study of their
interdependence the sequence of operation is decided
— The quantity of work involved in each operation is to be determined
— The time required for the completion of each operation as well as the
completion of total project is determined. This can be done by knowing
the quantum of work involved and the rate2.5 Time Cost Trade- Off
Project cost
For any project total expenditure incurred in terms of
man power, equipment, machinery and materials
and time to achieve a particular goal is known as
total cost of the project. The total sum of the
project is the sum of two distinct costs.
Direct cost
Total cost
Minimum cost
+ The cost of materials, equipment and money spent
on man power form the direct cost. The direct
costs of project are of major concern and behavior
pattern of direct costs with time is of importance.
Direct cost of a project depends on the completion
time of project, but the variation is not linear.
Indirect cost
+ The expenditures which cannot be allotted clearly
to the individual activities of the project, but are
assessed as a whole are called indirect costs. The
indirect cost includes overhead charges,
administrative and establishment _ charges,
supervision charges, loss of revenue, loss in profit
and penalty ete.
Crash Optimum Normal
duration — duration ~—_ durationDefinitions of Terms
Normal time
+ The time usually allowed for an activity by the estimator is known as normal
time. It is the standard time for that activity and is denoted by (Tn).
Crash time
+ The minimum possible time in which an activity can be completed by
deploying extra resources is known as crash time. Beyond the crash time the
duration of an activity cannot be reduced or shortened by any amount of
increase in mobilization. It is denoted by (Te).
Normal cost
+ The direct cost required to complete the activity in the normal duration is
called normal cost and is denoted by (Cn).
Crash cost
+ The direct cost corresponding to the crash time of completing an activity is
known as crash cost and is denoted by (Ce).
Cost slope Crash cost - normal cost
+ The direct cost curv? gasp is#eulee as shown below. But this curve can
be approximated by the straight line or more than one straight lines depending
upon the flatness of the curve. Thus the slope of this straight line is cost slope.
* Cost slope (CS) =
Minimum duration
+ The duration obtained after crashing all activities is known as minimum
duration.Time cost trade-off
Time and cost are the two most important resources that
a project manager deals with. Both of these resources
have constrains and the job of a project manager is to
have judicious balance between them. The judicious.
balance between time and cost is called Time-Cost
trade-off and it can be achieved by studying the
availability and demand of these resources for the given
project.
From the total cost ACB, it can be seen that the total
cost of a project is minimum for certain time duration.
This duration is known as optimum duration for the
corresponding minimum cost. Further if the project
duration is increased, the total cost will also increase.
On the other hand if the project duration is decreased to
the crash value, the project cost will be the highest. The
optimum duration is less than the normal duration
corresponding to the direct costs. This is due to the fact
that both direct and indirect cost increases beyond the
normal duration, whereas below the normal duration
indirect cost decrease, but the direct cost increases.
Total cost
A
Indirect |
‘Minimum cost
TB
Direct | co
Crash,
chiration
>
Optimum Normal
duration — durationSteps in optimization of cost (Cost optimization through Network)
First of all the critical path along with critical activities and non-critical activities which
are likely to become critical during the course of crashing are identified from calculation.
Calculating the cost slopes of all activities and ranking of activities in ascending order of
cost slopes is done.
Calculation of direct cost by adding normal cost of all activities. Calculation of indirect
cost by multiplying the longest duration times the overhead expense.
Crashing the project activity as per ranking, crashing is done starting from the activity of
critical path having least cost slope to the maximum possible extent. Calculate the direct
cost by adding the extra cost of crashing to the normal cost and corresponding indirect
cost of reduced project duration.
During the process of crashing of critical activities, there is possible of emerging new
critical path. Therefore the crashing of project is done simultaneously by re-crashing the
parallel activities.
The activities for crashing are considered serially in the ascending order to their cost
slope so far . The activity lying in common path is selected for optimal solution.
While crashing activities on the critical path or paths which became critical, the activity
on this possible. critical path are also crashed in the same way. If there are more than one
critical path then one activity form each path is selected at one time for crashing
(simultaneous crashing) and so on. This process is continued till the project shortening is
possible.Numerical
1. The following table shows the costs and duration of each activity of a
project. The network is shown. The indirect cost may be taken as Rs. 3150.-
per week. Determine the optimum duration of the project and
corresponding minimum cost.
‘Activity ‘Normal duration | Normal cost Crash duration — | Crash cost
A 7 $000 4 15500
B 9 5000 6 9500
a 5 7000 7 10000
D 6 9000 4 16000
E 6 6000 4 12000
2. If the indirect cost per week is Rs. 3000, find the optimal crashed project completion
time and corresponding minimum cost.
‘Activ ‘Tmmediate “Time (weeks) ‘Cost (Rs)
predecessor [Normal ‘Crash ‘Normal Crash
A = 5 2000 2300
B - 10 8 4000 4300
c A 6 : 3000 3125
D A 9 6 5000 5225
E B 10 9 2500 2700
F B 13 13 5000 -
G DE 5 3 1000 1700oral Cot
Cost Slope