Chapter 4 Theory
Chapter 4 Theory
1. Bar Chart
2. Milestone Chart
3. Linked Bar chart
4. Network Techniques
a) CPM
b) PERT
Gantt Chart/Bar Chart
7
1) It is simple to understand
2) It is easy to prepare, consume less resources and
economical
3) It can be used to show progress
Disadvantages /Limitation of Bar chart
1) Physical limit to the size of the bar chart
2) Interrelationship between them cannot be clearly
depicted
3) Updating the entire chart again and again
Milestone chart
10
Examples:
1. Excavation of foundation
2. Construction of wall
3. Concreting
4. Wiring and electrification
5. Plastering and paining work
Relationship between activities:
15
Serial Activities:
Those activities which are to be performed one
after the other in succession are known as serial
activities. Serial activities cannot be performed
independently.
Activity Duration
17
Dummy activity:
Dummy activity is an imaginary (hypothetical) activity included in a network.
Since it is not a real activity, it does not consume time, money, manpower,
material and other resources. It is included in a network to maintain the
relationship between activities .
5) There should be only one arrow for an activity, i.e. number of arrows
should be equal to number of activities.
Numbering the events(Fulkerson's rule)
26
Ncell Engineer 4 5 9
37
38
Q(12) Draw a PERT network for the following data.
Arrive at the critical path and find out the estimated
39
project duration along the critical path
Activity Predecessor Optimistic Time (to) Most Likely time Pessimistic
(tm) time (tp)
A - 4 5 6
B - 4 6 8
C A 3 5 7
D B 1 3 5
E C,D 2 5 8
F C,D 3 4 11
G E 4 5 12
H E 4 4 10
I F,H 5 6 13
40
41
42
A 4 5 6 5 0.33 0.11
43
B 4 6 8 6 0.67 0.44
C 3 5 7 5 0.67 0.44
D 1 3 5 3 0.34 0.12
E 2 5 8 5 1 1
F 3 4 11 5 1.33 1.77
G 4 5 12 6 1.33 1.77
H 4 4 10 5 1 1
I 5 6 13 7 1.33 1.77
44
Project Crashing:
Spending more money to get something done more quickly
is called crashing .
The main objective of project crashing is to reduce project
duration.
Time cost tradeoff:
Terminologies used in crashing:
(a) Project cost:
The total sum of the project is the sum of two distinct costs:
(i) Direct cost
(ii) Indirect cost
46
Direct cost:
Money spent on materials, manpower and machines are
direct cost.
Indirect cost:
The expenditures which cannot be allotted clearly to
the individual activities of the project, but are assessed
as a whole are called indirect costs.
The indirect cost includes overhead charges,
administrative and establishment charges, supervision
charges, and penalty etc.
47
48
Time-Cost trade-off:
The judicious balance between time and cost is
called Time-Cost trade-off.
Definitions of Terms
(a) Normal time
The time usually allowed for an activity by the
estimator is known as normal time.
It is the standard time for that activity and is
denoted by (Tn).
49
Crash cost
The direct cost corresponding to the crash time of
completing an activity is known as crash cost and is
denoted by (Cc ).
Cost slope:
51
Minimum duration
The duration obtained after crashing all activities is
known as minimum duration.
Q) 2073 Bhadra Regular,TU
The details of a project are shown below. If the
indirect cost per week is Rs 300, find the optimal
crashed result of the project Network. (6 marks)
52
Solution:
54
Here, the path B-C-E is the critical path i.e. longest path.
Therefore,
Total Project Cost = Direct Cost+ Indirect Cost
= Rs 17800+ Rs 6900
= Rs 24700
Now, finding the cost slope of all activities.
Activity Difference in cost (∆c Difference in duration (∆t Cost Slope
= Crash cost-Normal Cost) =Normal Duration-Crash =
Duration ∆c/∆t
A 300 3 100
B 300 2 150
C 125 1 125
D 225 3 75
E 325 1 325
F - 0 -
56
Q) 2073 Magh TU
Consider the data of a project as shown in table
below
Activity Immediate Time (Weeks) Cost (Rs)
predecessor
Normal Crash Normal Crash
A - 8 5 2000 2300
B - 10 8 4000 4300
C A 6 5 3000 3125
D A 9 6 5000 5225
E B 10 9 2500 2700
F B 13 13 5000 -
G D,E 5 3 1000 1700
62
Here, the path B-E-G is the critical path i.e. longest path.
Therefore,
Total Project Cost = Direct Cost+ Indirect Cost
= Rs 22500+75000
= Rs 97500
Now, finding the cost slope of all activities.
Activity Difference in cost (∆c Difference in duration (∆t Cost Slope
= Crash cost-Normal Cost) =Normal Duration-Crash =
Duration ∆c/∆t
A 300 3 100
B 300 2 150
C 125 1 125
D 225 3 75
E 200 1 200
F - 0 -
G 700 2 350
65
Path Duration
A-C 14
A-D-G 20-3=17
B-E-G 20
B-F 21