EC00515-2 City Center Office Building Addition EC00515-2 City Center Office Building Addition
EC00515-2 City Center Office Building Addition EC00515-2 City Center Office Building Addition
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 4, 2010 Qtr 1, 2011 Qtr 2, 2011 Qtr 3, 2011 Qtr 4, 2011
Duration Complete Oct
Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
EC00515-2 City Center 681d
Office Building Addition 601d 25.88% 01-Nov-2010 03-Jul-2013 0d
A
EC00515-2.D&E Design and Engineering 107d 0d 100% 01-Nov-2010 A06-Apr-2011 A 06-Apr-2011 A, EC00515-2.D&E Design and Engineering
EC1000 Design Building Addition 55d 0d 100% 01-Nov-2010 A19-Jan-2011 A Design Building Addition
EC1010 Start Office Building Addition Project 0d 0d 100% 01-Nov-2010 A Start Office Building Addition Project, 01-Nov-2010 A
EC1030 Review and Approve Designs 22d 0d 100% 17-Jan-2011 A17-Feb-2011 A Review and Approve Designs
EC1050 Assemble Technical Data for Heat Pump 7d 0d 100% 16-Feb-2011 A25-Feb-2011 A Assemble Technical Data for Heat Pump
EC1160 Review Technical Data on Heat Pumps 27d 0d 100% 24-Feb-2011 A06-Apr-2011 A Review Technical Data on Heat Pumps
EC00515-2.Found Foundation 146d 35d 48.62% 23-Feb-2011 A19-Sep-2011 175d 19-Sep-2011, EC00515-2.Foun
EC1090 Begin Building Construction 0d 0d 100% 28-Feb-2011 A Begin Building Construction, 28-Feb-2011 A
EC1100 Site Preparation 43d 0d 100% 23-Feb-2011 A18-Apr-2011 A Site Preparation
EC1230 Excavation 24d 0d 100% 02-May-2011 A06-Jun-2011 A Excavation
EC1320 Install Underground Water Lines 12d 0d 100% 03-Jun-2011 A21-Jun-2011 A Install Underground Water Lines
EC1330 Install Underground Electric Conduit 12d 0d 100% 03-Jun-2011 A21-Jun-2011 A Install Underground Electric Conduit
EC1340 Form/Pour Concrete Footings 24d 0d 100% 21-Jun-2011 A26-Jul-2011 A Form/Pour Concrete Footings
EC1350 Concrete Foundation Walls 24d 19d 20.73% 25-Jul-2011 A 26-Aug-2011 127d Concrete Foundation Walls
EC1360 Form and Pour Slab 12d 12d 0% 26-Aug-2011 14-Sep-2011 127d Form and Pour Slab
EC1370 Backfill and Compact Walls 5d 5d 0% 13-Sep-2011 19-Sep-2011 127d Backfill and Compact Walls
EC1380 Foundation Phase Complete 0d 0d 0% 19-Sep-2011 178d Foundation Phase Complete,
EC00515-2.Structure Structure 151d 151d 0% 19-Sep-2011 20-Apr-2012 306d
EC1390 Erect Structural Frame 48d 48d 0% 19-Sep-2011 25-Nov-2011 127d
EC1410 Begin Structural Phase 0d 0d 0% 25-Nov-2011 418d
EC1420 Floor Decking 34d 34d 0% 25-Nov-2011 13-Jan-2012 127d
EC1430 Concrete First Floor 36d 36d 0% 11-Jan-2012 01-Mar-2012 127d
EC1460 Erect Stairwell and Elevator Walls 24d 24d 0% 01-Mar-2012 04-Apr-2012 139d
EC1470 Concrete Basement Slab 24d 24d 0% 01-Mar-2012 04-Apr-2012 139d
EC1480 Concrete Second Floor 36d 36d 0% 01-Mar-2012 20-Apr-2012 127d
EC1540 Structure Complete 0d 0d 0% 20-Apr-2012 127d
EC00515-2.Mechanicals 562d
Mechanical/Electrical Systems 486d 10.62% 13-Apr-2011 A26-Jun-2013 0d
EC1490 Rough-In Phase Begins 0d 0d 0% 12-Mar-2012 234d
EC1690 Rough In Complete 0d 0d 0% 05-Feb-2013 0d
EC00515-2.Mechanicals.Lifts Elevator 218d 218d 0% 04-Apr-2012 12-Feb-2013 90d
EC1520 Install Elevator Rails and Equipment 3d 3d 0% 04-Apr-2012 06-Apr-2012 217d
EC1710 Install Elevator Cab and Finishes 5d 5d 0% 05-Feb-2013 12-Feb-2013 91d
EC00515-2.Mechanicals.HVAC HVAC 562d 486d 13.22% 13-Apr-2011 A26-Jun-2013 0d
EC1190 Prepare and Solicit Bids for Heat Pump 15d 0d 100% 13-Apr-2011 A04-May-2011 A Prepare and Solicit Bids for Heat Pump
EC1240 Review Bids for Heat Pump 10d 0d 100% 04-May-2011 A17-May-2011 A Review Bids for Heat Pump
EC1270 Award Contract for Heat Pump 6d 0d 100% 17-May-2011 A25-May-2011 A Award Contract for Heat Pump
EC1290 Fabricate and Deliver Heat Pump and Controls423d 377d 10.77% 25-May-2011 A23-Jan-2013 0d
EC1500 Install HVAC Ducts 24d 24d 0% 12-Mar-2012 13-Apr-2012 186d
EC1630 Insulate Ducts 5d 5d 0% 18-Jun-2012 25-Jun-2012 140d
EC1650 Set Heat Pump 12d 12d 0% 04-Jan-2013 22-Jan-2013 0d
EC1670 Relocate HVAC Chiller 7d 7d 0% 22-Jan-2013 01-Feb-2013 0d
EC1680 Startup and Test HVAC 2d 2d 0% 01-Feb-2013 05-Feb-2013 0d
EC1770 Install AC Grills and Registers 5d 5d 0% 08-Apr-2013 15-Apr-2013 23d
EC1830 Test and Balance HVAC Equipment 2d 2d 0% 21-Jun-2013 26-Jun-2013 0d
258d
EC00515-2.Mechanicals.Systems Plumbing and Electrical 258d 0% 20-Jan-2012 23-Jan-2013 6d
EC1440 Set Mechanical and Electrical Equipment 36d 36d 0% 20-Jan-2012 12-Mar-2012 186d
EC1510 Rough-In Plumbing/Piping 3d 3d 0% 24-Aug-2012 29-Aug-2012 72d
EC1640 Install Wiring and Cable 36d 36d 0% 31-Aug-2012 23-Oct-2012 72d
EC1660 Connect Equipment 1d 1d 0% 22-Jan-2013 23-Jan-2013 6d
EC00515-2.Ex-Finish Exterior Finishes 336d 302d 37.63% 17-Feb-2011 A19-Jun-2012 266d
EC1590 Close-In Phase Begins 0d 0d 0% 15-May-2012 296d
EC1620 Building Enclosed 0d 0d 0% 18-Jun-2012 127d
EC00515-2.Ex-Finish.Brick Brick 312d 278d 60.23% 17-Feb-2011 A15-May-2012 124d
EC1040 Assemble Brick Samples 0d 0d 100% 17-Feb-2011 A Assemble Brick Samples, 17-Feb-2011 A
Qtr 4, 2011 Qtr 1, 2012 Qtr 2, 2012 Qtr 3, 2012 Qtr 4, 2012 Qtr 1, 2013 Qtr 2, 2013 Qtr 3, 2013
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
03-Jul-2013, EC00515-2 City Cent
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 4, 2010 Qtr 1, 2011 Qtr 2, 2011 Qtr 3, 2011 Qtr 4, 2011
Duration Complete Oct
Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
EC1070 Review and Approve Brick Samples 30d 0d 100% 24-Feb-2011 A06-Apr-2011 A Review and Approve Brick Samples
EC1180 Prepare and Solicit Bids for Brick Exterior 15d 0d 100% 18-Mar-2011 A13-Apr-2011 Prepare and Solicit Bids for Brick Exterior
EC1220 Review Bids for Brick 15d 0d 100% 08-Apr-2011 A28-Apr-2011 A Review Bids for Brick
EC1260 Award Contract for Brick 5d 0d 100% 28-Apr-2011 A05-May-2011 A Award Contract for Brick
EC1280 Deliver Brick 1d 0d 100% 05-May-2011 A06-May-2011 A Deliver Brick
EC1550 Brick Exterior Walls 17d 17d 0% 20-Apr-2012 15-May-2012 127d
EC00515-2.Ex-Finish.Roof Roof 24d 24d 0% 15-May-2012 19-Jun-2012 124d
EC1600 Insulation and Built-up Roofing 24d 24d 0% 15-May-2012 19-Jun-2012 127d
EC00515-2.Ex-Finish.Win Doors and Windows 7d 7d 0% 27-Apr-2012 08-May-2012 152d
EC1560 Install Door and Window Frames 3d 3d 0% 27-Apr-2012 01-May-2012 156d
EC1580 Install Exterior Doors and Windows 5d 5d 0% 01-May-2012 08-May-2012 156d
EC00515-2.Int-Finish Interior Finishes 601d 601d 22.33% 24-Feb-2011 A03-Jul-2013 0d
EC1700 Drywall in Offices 36d 36d 0% 05-Feb-2013 27-Mar-2013 0d
EC1820 Touch-up and Clean-up 2d 2d 0% 19-Jun-2013 21-Jun-2013 0d
EC1840 Finishes Complete 0d 0d 0% 26-Jun-2013 0d
EC1850 Punch List 5d 5d 0% 26-Jun-2013 03-Jul-2013 0d
EC1860 Building Addition Complete 0d 0d 0% 03-Jul-2013 0d
EC00515-2.Int-Finish.Fixtures Plumbing and Lighting44d
Fixtures 44d 0% 08-Apr-2013 10-Jun-2013 7d
EC1760 Install Lighting Fixtures 7d 7d 0% 08-Apr-2013 17-Apr-2013 21d
EC1810 Install Plumbing Fixtures 5d 5d 0% 03-Jun-2013 10-Jun-2013 7d
EC00515-2.Int-Finish.Coverings Floor and Carpeting581d 581d 30.74% 24-Feb-2011 A04-Jun-2013 0d
EC1060 Assemble and Submit Flooring Samples 0d 0d 100% 25-Feb-2011 A Assemble and Submit Flooring Samples, 25-Feb-2011 A
EC1080 Review and Approve Flooring 28d 4d 100% 24-Feb-2011 A01-Mar-2011 Review and Approve Flooring
EC1170 Prepare and Solicit Bids for Flooring 24d 0d 100% 04-Apr-2011 A06-May-2011 A Prepare and Solicit Bids for Flooring
EC1250 Review Bids for Flooring 15d 0d 100% 06-May-2011 A27-May-2011 A Review Bids for Flooring
EC1300 Award Contract for Flooring 5d 0d 100% 27-May-2011 A06-Jun-2011 A Award Contract for Flooring
EC1310 Fabricate and Deliver Flooring 279d 239d 14.35% 03-Jun-2011 A06-Jul-2012 231d
EC1790 Install Floor and Carpeting 12d 12d 0% 16-May-2013 04-Jun-2013 0d
EC00515-2.Int-Finish.Carp Carpentry 59d 59d 0% 27-Mar-2013 19-Jun-2013 0d
EC1740 Install Ceiling Grid 36d 36d 0% 27-Mar-2013 16-May-2013 0d
EC1800 Finish Carpentry and Millwork 12d 12d 0% 03-Jun-2013 19-Jun-2013 0d
EC00515-2.Int-Finish.Paint Paint 12d 12d 0% 14-Feb-2013 04-Mar-2013 76d
EC1720 Paint Building Interior 12d 12d 0% 14-Feb-2013 04-Mar-2013 77d
Qtr 4, 2011 Qtr 1, 2012 Qtr 2, 2012 Qtr 3, 2012 Qtr 4, 2012 Qtr 1, 2013 Qtr 2, 2013 Qtr 3, 2013
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul