Project Exchange Gantt Chart
Project Exchange Gantt Chart
6/13 7/4 7/25 8/15 9/5 9/26 10/17 11/7 11/28 12/19 1/9 1/30 2/20
0 Project Exchange Gantt 123 days Mon 8/2/10
1 1 Project Charter 6.5 days Mon 8/2/10
2 1.1 Gather requirements 4 days Mon 8/2/10
3 1.2 Write the charter 2.5 days Fri 8/6/10
4 1.3 Project Charter 0 days Tue 8/10/10 8/10
5 2 Design Phase 20 days Tue 8/10/10
6 2.1 Design the deployment 5 days Tue 8/10/10
7 2.2 Design 2 5 days Tue 8/17/10
8 2.3 Design 3 5 days Tue 8/24/10
9 2.4 Design 4 5 days Tue 8/31/10
10 2.5 Design Phase 0 days Tue 9/7/10 9/7
11 3 Project Plan 24 days Tue 9/7/10
12 3.1 Create WBS 5 days Tue 9/7/10
13 3.2 Create schedule 10 days Tue 9/14/10
14 3.3 Create budget 2 days Tue 9/28/10
15 3.4 Create comm plan 5 days Thu 9/30/10
16 3.5 Create risk plan 2 days Thu 10/7/10
17 3.6 Project Plan 0 days Mon 10/11/10 10/11
18 4 Deployment U.S. 72.5 days Mon 10/11/10
19 4.1 Hardware deployment 17 days Mon 10/11/10
20 4.1.1 Purchase equipmrnt 4 days Mon 10/11/10
21 4.1.2 Asemble servers 6.5 days Fri 10/15/10
22 4.1.3 Unit testing 6.5 days Tue 10/26/10
23 4.1.4 Servers completed 0 days Wed 11/3/10 11/3
24 4.2 Software deployment 55.5 days Wed 11/3/10
25 4.2.1 Install host OS 6.5 days Wed 11/3/10
26 4.2.2 Install Hyper-V 2.5 days Fri 11/12/10
Task External Tasks Manual Task Finish-only
Split External Milestone Duration-only Deadline
Project: Project Exchange Gantt
Milestone Inactive Task Manual Summary Rollup Progress
Date: Mon 8/9/10
Summary Inactive Milestone Manual Summary
Project Summary Inactive Summary Start-only
Page 1
ID Task Name Duration StartMay 21 July 11 September 1 October 21 December 11 February 1
6/13 7/4 7/25 8/15 9/5 9/26 10/17 11/7 11/28 12/19 1/9 1/30 2/20
27 4.2.3 Install guest OS 13.5 days Tue 11/16/10
28 4.2.4 Install Exchange on guests 6.5 days Mon 12/6/10
29 4.2.5 Configure Exchange 6.5 days Tue 12/14/10
30 4.2.6 Integration testing 13.5 days Thu 12/23/10
31 4.2.7 Backup existing mail 2.5 days Tue 1/11/11
32 4.2.8 Migration 4 days Fri 1/14/11
33 4.2.9 Software deployment 0 days Wed 1/19/11 1/19
34 5 Testing 6.5 days Mon 10/11/10
35 5.1 Write test cases 6.5 days Mon 10/11/10
36 6 Deployment Brazil 26.5 days Mon 10/11/10
37 6.1 Hardware deployment 9 days Mon 10/11/10
38 6.1.1 Purchase equipmrnt 1 day Mon 10/11/10
39 6.1.2 Assemble servers 2.5 days Tue 10/12/10
40 6.1.3 Unit testing 2.5 days Wed 10/20/10
41 6.1.4 Servers completed 0 days Fri 10/22/10 10/22
42 6.2 Software deployment 17.5 days Fri 10/22/10
43 6.2.1 Install host OS 2.5 days Fri 10/22/10
44 6.2.2 Install Hyper-V 1 day Wed 10/27/10
45 6.2.3 Install guest OS 2.5 days Thu 10/28/10
46 6.2.4 Install Exchange on guests 1.5 days Mon 11/1/10
47 6.2.5 Configure Exchange 1.5 days Wed 11/3/10
48 6.2.6 Integration testing 5.5 days Thu 11/4/10
49 6.2.7 Backup existing mail 1.5 days Fri 11/12/10
50 6.2.8 Migration 1.5 days Mon 11/15/10
51 6.2.9 Software deployment 0 days Tue 11/16/10 11/16
52 7 Training 59 days Tue 10/26/10
53 7.1 Training Brazil 19 days Tue 10/26/10
Task External Tasks Manual Task Finish-only
Split External Milestone Duration-only Deadline
Project: Project Exchange Gantt
Milestone Inactive Task Manual Summary Rollup Progress
Date: Mon 8/9/10
Summary Inactive Milestone Manual Summary
Project Summary Inactive Summary Start-only
Page 2
ID Task Name Duration StartMay 21 July 11 September 1 October 21 December 11 February 1
6/13 7/4 7/25 8/15 9/5 9/26 10/17 11/7 11/28 12/19 1/9 1/30 2/20
54 7.1.1 Train Exchange administrators 1 day Tue 10/26/10
55 7.1.2 Train desktop support 1 day Fri 11/5/10
56 7.1.3 Train end-users 5 days Mon 11/15/10
57 7.1.4 Training Brazil 0 days Fri 11/19/10 11/19
58 7.2 Training U.S. 56 days Fri 10/29/10
59 7.2.1 Train Exchange administrators 1 day Fri 10/29/10
60 7.2.2 Train desktop support 2 days Tue 12/14/10
61 7.2.3 Train end-users 5 days Mon 1/10/11
62 7.2.4 Training U.S. 0 days Fri 1/14/11 1/14
Page 3