Project Exchange Gantt Chart

Uploaded by

islamraafat23
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

ID Task Name Duration StartMay 21 July 11 September 1 October 21 December 11 February 1

6/13 7/4 7/25 8/15 9/5 9/26 10/17 11/7 11/28 12/19 1/9 1/30 2/20
0 Project Exchange Gantt 123 days Mon 8/2/10
1 1 Project Charter 6.5 days Mon 8/2/10
2 1.1 Gather requirements 4 days Mon 8/2/10
3 1.2 Write the charter 2.5 days Fri 8/6/10
4 1.3 Project Charter 0 days Tue 8/10/10 8/10
5 2 Design Phase 20 days Tue 8/10/10
6 2.1 Design the deployment 5 days Tue 8/10/10
7 2.2 Design 2 5 days Tue 8/17/10
8 2.3 Design 3 5 days Tue 8/24/10
9 2.4 Design 4 5 days Tue 8/31/10
10 2.5 Design Phase 0 days Tue 9/7/10 9/7
11 3 Project Plan 24 days Tue 9/7/10
12 3.1 Create WBS 5 days Tue 9/7/10
13 3.2 Create schedule 10 days Tue 9/14/10
14 3.3 Create budget 2 days Tue 9/28/10
15 3.4 Create comm plan 5 days Thu 9/30/10
16 3.5 Create risk plan 2 days Thu 10/7/10
17 3.6 Project Plan 0 days Mon 10/11/10 10/11
18 4 Deployment U.S. 72.5 days Mon 10/11/10
19 4.1 Hardware deployment 17 days Mon 10/11/10
20 4.1.1 Purchase equipmrnt 4 days Mon 10/11/10
21 4.1.2 Asemble servers 6.5 days Fri 10/15/10
22 4.1.3 Unit testing 6.5 days Tue 10/26/10
23 4.1.4 Servers completed 0 days Wed 11/3/10 11/3
24 4.2 Software deployment 55.5 days Wed 11/3/10
25 4.2.1 Install host OS 6.5 days Wed 11/3/10
26 4.2.2 Install Hyper-V 2.5 days Fri 11/12/10
Task External Tasks Manual Task Finish-only
Split External Milestone Duration-only Deadline
Project: Project Exchange Gantt
Milestone Inactive Task Manual Summary Rollup Progress
Date: Mon 8/9/10
Summary Inactive Milestone Manual Summary
Project Summary Inactive Summary Start-only

Page 1
ID Task Name Duration StartMay 21 July 11 September 1 October 21 December 11 February 1
6/13 7/4 7/25 8/15 9/5 9/26 10/17 11/7 11/28 12/19 1/9 1/30 2/20
27 4.2.3 Install guest OS 13.5 days Tue 11/16/10
28 4.2.4 Install Exchange on guests 6.5 days Mon 12/6/10
29 4.2.5 Configure Exchange 6.5 days Tue 12/14/10
30 4.2.6 Integration testing 13.5 days Thu 12/23/10
31 4.2.7 Backup existing mail 2.5 days Tue 1/11/11
32 4.2.8 Migration 4 days Fri 1/14/11
33 4.2.9 Software deployment 0 days Wed 1/19/11 1/19
34 5 Testing 6.5 days Mon 10/11/10
35 5.1 Write test cases 6.5 days Mon 10/11/10
36 6 Deployment Brazil 26.5 days Mon 10/11/10
37 6.1 Hardware deployment 9 days Mon 10/11/10
38 6.1.1 Purchase equipmrnt 1 day Mon 10/11/10
39 6.1.2 Assemble servers 2.5 days Tue 10/12/10
40 6.1.3 Unit testing 2.5 days Wed 10/20/10
41 6.1.4 Servers completed 0 days Fri 10/22/10 10/22
42 6.2 Software deployment 17.5 days Fri 10/22/10
43 6.2.1 Install host OS 2.5 days Fri 10/22/10
44 6.2.2 Install Hyper-V 1 day Wed 10/27/10
45 6.2.3 Install guest OS 2.5 days Thu 10/28/10
46 6.2.4 Install Exchange on guests 1.5 days Mon 11/1/10
47 6.2.5 Configure Exchange 1.5 days Wed 11/3/10
48 6.2.6 Integration testing 5.5 days Thu 11/4/10
49 6.2.7 Backup existing mail 1.5 days Fri 11/12/10
50 6.2.8 Migration 1.5 days Mon 11/15/10
51 6.2.9 Software deployment 0 days Tue 11/16/10 11/16
52 7 Training 59 days Tue 10/26/10
53 7.1 Training Brazil 19 days Tue 10/26/10
Task External Tasks Manual Task Finish-only
Split External Milestone Duration-only Deadline
Project: Project Exchange Gantt
Milestone Inactive Task Manual Summary Rollup Progress
Date: Mon 8/9/10
Summary Inactive Milestone Manual Summary
Project Summary Inactive Summary Start-only

Page 2
ID Task Name Duration StartMay 21 July 11 September 1 October 21 December 11 February 1
6/13 7/4 7/25 8/15 9/5 9/26 10/17 11/7 11/28 12/19 1/9 1/30 2/20
54 7.1.1 Train Exchange administrators 1 day Tue 10/26/10
55 7.1.2 Train desktop support 1 day Fri 11/5/10
56 7.1.3 Train end-users 5 days Mon 11/15/10
57 7.1.4 Training Brazil 0 days Fri 11/19/10 11/19
58 7.2 Training U.S. 56 days Fri 10/29/10
59 7.2.1 Train Exchange administrators 1 day Fri 10/29/10
60 7.2.2 Train desktop support 2 days Tue 12/14/10
61 7.2.3 Train end-users 5 days Mon 1/10/11
62 7.2.4 Training U.S. 0 days Fri 1/14/11 1/14

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
Project: Project Exchange Gantt
Milestone Inactive Task Manual Summary Rollup Progress
Date: Mon 8/9/10
Summary Inactive Milestone Manual Summary
Project Summary Inactive Summary Start-only

Page 3