Electricalwiringpermitapplication QC
Electricalwiringpermitapplication QC
QUEZON CITY
DEPARTMENT OF THE BUILDING OFFICIAL
APPLICATION FOR ELECTRICAL PERMIT
APPLICATION NO.
DATE OF APPLICATION:
BOX 1 (TO BE ACCOMPLISHED IN PRINT BY THE OWNER/APPLICANT AND BY THE DESIGN PROFESSIONAL)
OWNER/APPLICANT: LAST NAME FIRST NAME M.I. TIN
LOCATION OF INSTALLATION: LOT NO.: _________________ BLK NO.: ______________________ TCT NO.: ______________ TAX DEC. NO.:_______________
SCOPE OF WORK:
NEW INSTALLATION RECONNECTION OF KWHR METER RELOCATION OF KWHR METER
ANNUAL INSPECTION SEPARATION OF KWHR METER OTHERS (Specify)
TEMPORARY REMODEL OF SERVICE ENTRANCE
Address:
BOX 3
SUPERVISOR IN-CHARGE OF INSTALLATION
PROFESSIONAL ELECTRICAL ENGINEER REGISTERED ELECTRICAL ENGINEER REGISTERED MASTER ELECTRICIAN
Not Exceeding 600 V & 500 kVa
Date:
(Signature over printed name)
Issued at TIN
Address:
BOX 4 BOX 5
APPLICANT: WITH CONSENT: LOT OWNER
Date: Date:
Address: Address:
CTC No. Date Issued Place Issued CTC No. Date Issued Place Issued
BOX 6
Date:
APPLICANT
(Signature Over Printed Name)
Address:
QCG-DBO-CPA02-V01
SCHEDULE DATE OF INSPECTION
1. 2. 3. 4.
ADDRESS:
1. Loads to be connected:
4. Remarks:
I hereby certify that the above data and information are true and correct to the best of my knowledge and belief:
Person In-charge of Installation
ELECTRICAL FEES
PEE/REE/RME (Signed and Sealed Over Printed Name)
ADDRESS
Fee P
Surcharge P PRC REG. NO.: VALIDITY:
Total P PTR NO.: TIN:
CTC NO. DATE ISSUED:
Nature of Work:
INSPECTOR: REMARKS:
RECOMMENDING APPROVAL:
APPROVED: NOTED:
NOTE: Renewal or extension of this permit and / or final certification of the electrical installation are subject and payment of corresponding fees in conformation with pertinent of the “National Building Code” (p.d. 1096)
And its implementing rules and regulations.
QCG-DBO-CPA02-V01