Basis of Design Report Jetty
Basis of Design Report Jetty
Basis of Design Report Jetty
ASSISTANT MAYOR
Seth E. Salver
COUNCIL MEMBERS
David Albaum
Jeffrey P. Freimark
Buzzy Sklar
CADENCE
local landscape architecture & graphic design
MUENGINEERS
structural engineering
BOTEK THURLOW
civing engineering & LEED consulting
EXACTA COMMERCIAL
SURVEYORS
land surveyor
TIERRA SF
geothechnical service, material testing & CEI
TWR ENGINEERS
MEP engineering
SLS
fire protection engineering & life safety
TABLE OF CONTENTS
I. EXECUTIVE SUMMARY
IV. APPENDIX
A. SURVEY
B. TECHNICAL DRAWINGS
C. BENTHIC REPORT
D. STRUCTURAL REPORT
E. CIVIL REPORT
F. DESIGN PRESENTATIONS
Bal Harbour Jetty
I. EXECUTIVE SUMMARY
1
mikyoung kim design
The Jetty and Cutwalk located at the northern tip of the Village of Bal Harbour is
a well-used but unrealized amenity for the residents and visitors of Bal Harbour.
The earliest inception of the southern jetty was constructed in 1927 by the Army
Corps of Engineers as a utilitarian breakwater and mitigation tool to protect the
Haulover Inlet. Subsequent reconstruction projects changed the alignment
and shape to the current configuration as a steel sheet pile jetty reinforced by
granite rubble. The last major repair and revetment of the jetty was in 1986.
It’s current day use as a popular destination and provides a unique vantage
point to walk to the jetty terminus and view the ocean and the beachline of Bal
Harbour.
The project scope is to develop a public space design that re-envisions the
aesthetic and programmatic uses of the Jetty, Cutwalk and beach parking as
part of a holistic vision for the public realm spaces in Bal Harbour. This project
examines the public uses of the spaces, functional and technical requirements
for improvements, public and resident comments and opinions, and permitting
and construction feasibility of developing a cohesive waterfront destination.
Project objectives:
• Creating Places for Visitors and Residents – allow residents that visit the
site daily and visitors that may only visit once to have equally powerful
experiences.
• Establishing an Identity for Public Space – create a place that is unique and
celebrates the natural and raw beauty of the site.
The design team solicited the community and stakeholders for comments
through a series of planned outreach opportunities. Formal community
meetings involved three meetings; 1) community presentation where we
introduced the project and initial concept ideas and surveyed the attendees for
there preferences, 2) community workshop where we developed two conceptual
options and solicited feedback and 3) a community design presentation and
open house where the community saw the evolved design and was able to
interact with design members.
The team’s engagement efforts also included meetings with key stakeholders
including various city departments, the Village Council, representatives from the
Bal Harbour Shops, the Ritz-Carlton, One Bal Harbour, as well as key members
of the community. Working sessions allowed stakeholders to bring up their
goals and visions, concerns and opinions about the project proposals.
The general consensus of issues and concerns from the community and
stakeholder events were addressed in the proposed design iteration.
2
Bal Harbour Jetty
The main issues that were collected from the community were:
• Design should feature the natural elements and engage the beauty of the
site
These comments allowed the design team to refine the proposal and achieve
a general consensus in the final design iteration. This work will continue with
stakeholders throughout the design process as the plans are developed into
construction documents.
Schematic Design
• Along the cutwalk, a series of platforms that extend past the seawall to bring
visitors closer to the water and allowing visitors to view marine activities in
the Haulover Cut as well as sealife in the water. These platforms connect
people physically and emotionally to the ocean through a complete sensory
experience.
• A series of site elements are incorporated into the design to allow for visitor
comfort and safety. Railings and walls are designed along the entire jetty
and cutwalk permit visitors to safely navigate the public spaces along the
water’s edge. A shade canopy and shade trees along with new seating
elements and places to gather along the cutwalk and jetty allow for passive
recreation and respite.
• To allow for increased resiliency and safety, the current jetty walkway will
be capped with precast concrete slabs to raise the jetty walkway elevation
culminating with a lookout promontory. Along the inside of the jetty, large
steps will bring people down to the water. To achieve compliance with
navigational requirements, a light beacon placed at the terminus of the jetty
is designed as an iconic element that can be seen from land and on the
water.
• At the beach parking under the Herman Fultz Bridge, part of the parking
area is proposed to become a garden space that acts as a gateway to the
cutwalk. Pedestrian and cyclist amenities such as seating elements and
bike racks are integrated into the design.
Permitting – Initial steps in permitting has been taken with the Army Corps of
Engineers. It is difficult to predict how the permitting will affect the end design
due to the unique conditions of the project. The team anticipates that this
project will require special review considerations by jurisdictional departments.
Easement rights – As part of the development of the project the Village of Bal
Harbour must evaluate the need to enter into agreements with adjacent property
owners of the Herman B. Fultz parking area, the cutwalk and the jetty to pursue
work along the easement and right-of-way. The legal review of the project may
impact the scope of work that is able to be carried out.
4
Bal Harbour Jetty
5
mikyoung kim design
PROJECT AREA
2019
2019 2020 2021 2022
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
Design
Permitting
Construction
landscape architects
6
Bal Harbour Jetty
A. PROJECT SCOPE
The Jetty and Cutwalk located at the northern tip of the Village of Bal Harbour is
a well-used but unrealized amenity for the residents and visitors of Bal Harbour.
The earliest inception of the southern jetty was constructed in 1927 by the Army
Corps of Engineers as a utilitarian breakwater and mitigation tool to protect the
Haulover Inlet. Subsequent reconstruction projects changed the alignment
and shape to the current configuration as a steel sheet pile jetty reinforced by
granite rubble. The last major repair and revetment of the jetty was in 1986.
It’s current day use as a popular destination and provides a unique vantage
point to walk to the jetty terminus and view the ocean and the beachline of Bal
Harbour.
In the Summer of 2019, Bal Harbour Village secured the Design Services of
Mikyoung Kim Design in developing a plan to enhance the current jetty and
cutwalk and provide a new vision for how to utilize this public resource. The
project scope is focused on the development of the public realm to address
the aesthetic and programmatic uses of the Jetty, Cutwalk and Beach Parking
as part of a holistic vision for the public space network in Bal Harbour. During
the Schematic Design phase, the design team examined the programing and
design of the spaces, functional and technical requirements for improvements,
public and resident comments and opinions, and permitting and construction
feasibility of developing a cohesive waterfront destination.
Bal Harbour Jetty: Vision
A Forward-Thinking Approach
landscape architects
People + Resiliency
Social infrastructure:
how does resiliency infrastructure benefit people?
landscape architects
7
mikyoung kim design
B. PROJECT OBJECTIVES
Bal Harbour Jetty: Vision
Establishing an
Engagement with Identity for Public
Water Space
-Gateways, Integration
-Resiliency
of Art & Landscape
-Wildlife impacts
Balancing
Functional
Creating Places Performance with
for Visitors and Placemaking
Residents -Structural Requirements
-Durability &
-Neighbors Maintenance
-Regulatory Process -Placemaking
landscape architects
Project Objectives
From the initial meeting and discussions with the client, the design team
developed identified the project objectives. These objective articulate important
issues that will make the Jetty Project a success.
• Creating Places for Visitors and Residents – allow residents that visit the
site daily and visitors that may only visit once to have equally powerful
experiences.
• Establishing an Identity for Public Space – create a place that is unique and
celebrates the natural and raw beauty of the site.
8
Bal Harbour Jetty
C. EXISTING CONDITIONS
1. CONTEXT
9
mikyoung kim design
PROJECT AREA
10
Bal Harbour Jetty
2. SITE CHARACTERISTICS
JETTY BOULDERS
11
mikyoung kim design
12
Bal Harbour Jetty
D. COMMUNITY MEETING
13
mikyoung kim design
Community Meeting #1
Agenda
• Project Introduction
• Team Introduction
• Vision
• Concept and Key Considerations
• Project Overview
• Next Steps
Community Meeting #2
Agenda
• Concept Palettes
• Community Meeting Feedback
• Concept Options (two options)
• Next Steps
The goals for the second community meeting was to provide feedback on what
was learned from the previous community meeting and present two developed
concepts for the design. The two design options were: Option 1 – Engaging the
Water and Option 2 – Eddy Spaces. The general preference was that Option 1
was more inline with the vision for the project.
Community Meeting #3
Agenda
This final community meeting was set up as an open house where attendees
can visit with designers on a one-to-one basis. Three stations were set up for
design, environmental, and materials and the public was invited to engage with
different designers and consultants around the room.
14
Bal Harbour Jetty
15
mikyoung kim design
16
Bal Harbour Jetty
The team’s engagement efforts also included meetings with key stakeholders
including various city departments, the Village Council, abutters to the project,
as well as key members of the community. Working sessions allowed
stakeholders to bring up their goals and visions, concerns and opinions about
the project proposals.
Stakeholders meetings:
The general consensus of issues and concerns from the community and
stakeholder events were addressed in the proposed design iteration. The main
issues that were collected from the community were:
These comments allowed the design team to refine the proposal and achieve
a general consensus in the final design iteration. This work will continue with
stakeholders throughout the design process as the plans are developed into
construction documents.
17
mikyoung kim design
18
Bal Harbour Jetty
QUESTIONNAIRE Do you currently utilize the Jetty and cutwalk? If so, how often?
RESULTS
monthly
occatio- weekly, 0 weekly
nally weekly, all weekend for the 6
1 but because of the hazard of view after jogging
not having rails, I don't get ends. Enjoy
to enjoy it as much with my for Yoga.
nephews & nieces.
I'd like to see some rails yes, as often as
incorporated into possible. Usually a
the project. few times per day, a
daily few days a week.
7
What are your opinions about the current Bal Harbour Jetty and the cutwalk?
19
mikyoung kim design
yoga
area playgrounds / running, small I love
sitting areas gym all combine the idea of fun
set would be urban seating &
keep it simple yet art works nice space for street
pleasant & enjoyable should be musical events furniture
for every bal harbour featured or children
resident to enjoy for watch activities
years to come the sunrise no
What is important to me about the Jetty and cutwalk that I want the design
team to know?
What makes Bal Harbour unique from Miami Beach, Miami, and the rest of
southeast Florida?
quiet,
bal harbour calm,
small does not have peace
the hustle and bustle it's community /
size / i am not sure we it is a village! /
privacy of south beach, or the quiet & exclusive /
privacy, tourism part of sunny isles / want fisherman from
other place to come. subdue elegance
security, the people who should be the theme /
elegant come to bal harbour / fishing is ok on
small area but not do not want an
people are what make attraction! /
tranquility / it special. everywhere more we want the jetty to
safe/ beautifully this resort feel, look in tune with
maintained / zone is privacy, better nature!
wonderful views unique sand, elegance +
parking
Provide any other comments you wish to communicate (or provide additional
comments via our project email address):
seaweed is
will do, thank option 2 on the a major issue
every year you for your presentation slide worried because it smell bad i love the idea
the jetty & workshop me. the layout of the & for view / sand of a fun urban boardwalk
cutwalk get boardwalk structure may erosion is another but i think the environment
flooded with a harm the marine life major issue should be the priority
hurricane which resides in the rock maybe floating gardens,
can an formations of the bay. i am create/enhance the habitat,
element of privacy afraid the structure would in a very obvious way &
(fob access?) be displace the marine life if it need better perhaps in all ways possible,
included in design / were to be built use for consider environment.
similar to 102nd street like that. the jetty
resident public
beach access!
20
Bal Harbour Jetty
21
mikyoung kim design
APPROX. TOE OF
RIPRAP JETTY
CHANNEL VIEW
• Along the cutwalk, a series of platforms that extend past the seawall to bring visitors closer to the water and allowing
visitors to view marine activities in the Haulover Cut as well as sealife in the water. These platforms connect people
physically and emotionally to the ocean through a complete sensory experience.
• The placement and design of the platforms and cutwalk extensions minimizes the impacts on existing coral and
wildlife while the use of artificial reef technology will help increase marine habitat and provide resiliency along the
seawall.
• A series of site elements are incorporated into the design to allow for visitor comfort and safety. Railings and walls are
designed along the entire jetty and cutwalk permit visitors to safely navigate the public spaces along the water’s edge.
A shade canopy and shade trees along with new seating elements and places to gather along the cutwalk and jetty
allow for passive recreation and respite.
• To allow for increased resiliency and safety, the current jetty walkway will be capped with precast concrete slabs to
raise the jetty walkway elevation culminating with a lookout promontory. Along the inside of the jetty, large steps will
bring people down to the water. To achieve compliance with navigational requirements, a light beacon placed at the
terminus of the jetty is designed as an iconic element that can be seen from land and on the water.
• At the beach parking under the Herman B. Fultz Bridge, part of the parking area is proposed to become a garden
space that acts as a gateway to the cutwalk. Pedestrian and cyclist amenities such as seating elements and bike
racks are integrated into the design.
22
Bal Harbour Jetty
23
mikyoung kim design
24
Bal Harbour Jetty
JETTY PROMONTORY
AND LIGHT BEACON
STEP-DOWN
PLATFORMS
BEACHSIDE
SHADE CANOPY AMPHITHEATER
JETTY WALK
MAIN ENTRANCE
NATIVE BEACH
RAILING GARDEN
EXISTING RIPRAP
BOULDERS
LOOKOUT
PLATFORM
GRATED
PLATFORM
25
mikyoung kim design
SEA VIEW
CHAIRS
HABITAT VIEWING
CATWALK
26
Bal Harbour Jetty
A. SCHEMATIC DESIGN
N
0 50’ 100’ 200’
27
mikyoung kim design
Safety and resiliency were important factors in designing the Bal Harbour
Jetty. Guardrails and monolithic concrete walls secure every platform
and along the Jetty, facilitating safe encounter with water. To enhance the
waterfront experience and bring people to the ocean side of the seawall,
openings along the seawall were kept to a minimum and can be secured with
flood gates. Alterations to the seawall were designed to maintain the same
level of protection or better than the current condition for better resiliency. In
extreme weather conditions, proposed control gate and flood gate ensure
controlled access to the platforms and jetty promontory. The Jetty elevation
was also raised higher than the existing condition to allow the Jetty to be
more effective against higher wave and tide actions.
Existing Seawall
Existing Seawall to be Removed (Above Ground)
Proposed Wave Protection
Guard Rail
Hand Rail
Control Gate
Flood Gate
9’ 5’
13’ 22.5’ 12.5’
N
0 50’ 100’ 200’
28
Bal Harbour Jetty
3. ACCESSIBILITY
Elevated Platforms
Lower Platforms
ADA-compliant Walkways
Access
(+X.XX) Existing Grade
+X.XX Proposed Grade
+4.5 +11
+4.5 +4.5 +6 +9
+5.3 +9
(+3.3) (+6)
(+3.4) (+4.3) (+8)
-1.00
Access to Grated Walk
Boardwalk Access to Beach
Jetty Walk +9
Garden Access to
Main Entrance (+6)
Entrance Protected Water
from Collins
Ave +15
(+6)
N
0 50’ 100’ 200’
29
mikyoung kim design
4. MARINE DIVERSITY
N
0 50’ 100’ 200’
30
Bal Harbour Jetty
B. FEATURED AREAS
1. WATERFRONT
31
mikyoung kim design
CHANNEL VIEW
CONTEXT MAP
32
Bal Harbour Jetty
METAL GRATING
PLATFORM
WOOD DECK ON
CONCRETE PLATFORM
METAL RAILING
METAL GRATING
CATWALK
33
mikyoung kim design
ARTIFICIAL REEF
PRECAST
PAVERS
SEA VIEW
CHAIRS
34
Bal Harbour Jetty
2. BEACH GARDEN
35
mikyoung kim design
N
0 50’ 100’ 200’
36
Bal Harbour Jetty
WOOD LOOKOUT
PLATFORM
ADVENTURE BOARDWALK
JETTY WALK
NATIVE BEACH GARDEN
MAIN ENTRANCE
PLAY ELEMENTS
37
mikyoung kim design
BEACHSIDE WOOD
AMPHITHEATER
EXISTING
RIPRAP BOULDERS
38
Bal Harbour Jetty
The raised jetty promontory promotes resiliency and provides a destination for
Jetty. An amphitheater with elements of wood creates an “Ocean Room” at the
end of the promontory. Along the inside of the Jetty large stair slabs step-down
to the water allowing another experience for users.
A louvered shade canopy along the southern edge of the jetty walk allows for
comfortable seating opportunities. “BAL HARBOUR” lettering on the top of the
canopy allows for Bal Harbor to be recognized from a birds-eye view.
The light beacon aims to be an iconic feature at the jetty promontory terminus.
It encompasses metal spiral staircases with colored cable wire mesh and a
navigational strobe beacon. RGB LED lighting, integrated into the spires, can be
both wildlife friendly and utilized for special events.
39
mikyoung kim design
40
Bal Harbour Jetty
Stepping Platform
41
mikyoung kim design
Canopy Signage
42
Bal Harbour Jetty
43
mikyoung kim design
Light Beacon
44
Bal Harbour Jetty
DAY VIEW
45
mikyoung kim design
DAY VIEW
46
Bal Harbour Jetty
47
mikyoung kim design
48
Bal Harbour Jetty
49
mikyoung kim design
50
Bal Harbour Jetty
51
mikyoung kim design
Relocate
(6) Parking Spots
Activity Zone
Specialty Pavement
Pedestrian Circulation
Vehicular Circulation
PARKING SPOTS:45
(6 SPOTS RELOCATED)
52
Bal Harbour Jetty
Planting
53
mikyoung kim design
Cutwalk
Seating
Seating
Seating
Service Drive
Entry Garden
Bike Rack
54
Bal Harbour Jetty
1. CONCRETE
55
mikyoung kim design
2. WOOD
There are many new options for wood that is exterior rated
and can be used for marine conditions. Mockups and testing
is recommended to select the best option for wood on the
Jetty and Cutwalk.
56
Bal Harbour Jetty
3. STEEL
57
mikyoung kim design
58
Bal Harbour Jetty
5. PLANTS
COLLINS AVE.
B
CUTWALK
Botanical Name Common Name Native
Arachis glabrata Perennial Peanut N
Bulbine spp. Bulbine N
Cocos nucifera Coconut Palm N
Ernodea littoralis Beach Creeper Y
Borrichia frutescens Silver Sea-ox-eye Daisy Y
Sabal palmetto Sabal Palm Y
Scaevola plumieri Inkberry Y
Spartina patens Marshhay Cordgrass Y
Thrinax radiata Florida Thatch Palm Y
Zamia integrifolia Coontie Y
PLANT LIST
Bal Harbour Jetty | 12.02.2019
59
mikyoung kim design
e
COLLINS AVE.
INLET
BAKER’S HAULOVER
e ATLANTIC OCEAN
CONTEXT MAP
PLANT LIST
Bal Harbour Jetty | 12.02.2019 www.cadence-living.com
60
Bal Harbour Jetty
D. ASSESSMENTS
1. BENTHIC REPORT
61
mikyoung kim design
2. STRUCTURAL
62
Bal Harbour Jetty
3. CIVIL REPORT
63
mikyoung kim design
64
Bal Harbour Jetty
IV. APPENDIX
65
mikyoung kim design
A. SURVEY
B. TECHNICAL DRAWINGS
C. BENTHIC REPORT
D. STRUCTURAL REPORT
E. CIVIL REPORT
F. DESIGN PRESENTATIONS
66
Bal Harbour Jetty mikyoung kim design
A. SURVEY
67
Bal Harbour Jetty mikyoung kim design
68
Bal Harbour Jetty mikyoung kim design
69
Bal Harbour Jetty mikyoung kim design
B. TECHNICAL
DRAWINGS
70
Bal Harbour Jetty mikyoung kim design
71
Bal Harbour Jetty mikyoung kim design
72
Bal Harbour Jetty mikyoung kim design
73
Bal Harbour Jetty mikyoung kim design
74
Bal Harbour Jetty mikyoung kim design
75
Bal Harbour Jetty mikyoung kim design
76
Bal Harbour Jetty
C. BENTHIC REPORT
77
mikyoung kim design
SEPTEMBER 2019
PREPARED FOR:
MIKYOUNG KIM DESIGN
119 BRAINTREE STREET, NO. 103
BOSTON, MA 02134
714 East McNab Road. Pompano Beach, FL 33060 tel. 954. 782.1908 fax. 954.782.1108 www.thechappellgroup.com
Environmental Consultants l Marina & Wetland Permitting l Phase I ESAs l Mitigation Design & Monitoring l T & E Species Surveys
78
Bal Harbour Jetty
I. Introduction
The proposed project site is a cutwalk and jetty located along the Haulover Inlet
and on A1A/Collins Avenue in the Village of Bal Harbour, Miami-Dade County,
Florida (Figure 1). The project site is located along the Haulover Inlet and the
Atlantic Ocean.
These waters are tidal waters with a direct connection to the Atlantic Ocean. As
the project site is located along the Haulover Inlet, the incoming tidal waters
(flood) at the site move to the west while the outgoing waters move to the east
(ebb).
The project site contains an existing seawall, rip rap jetty and cutwalk. The
proposed project is the improvement of the existing seawall, jetty and cutwalk. As
such, due to environmental permitting regulations related to the modification of
docking facilities, the investigation of the presence and location of benthic
resources within the submerged bottoms is warranted.
II. Purpose
The purpose of this benthic resource study is to identify and locate any seagrass
species (Halophila decipiens, Halophila johnsonii, Thalassia testudinum,
Halodule wrightii, Ruppia maritima, etc.) or other benthic resources that may be
present within the property boundaries of the subject site. Environmental
regulatory agencies require representative data to be acquired from any site that
has potential seagrass habitat.
III. Method
The field work for the benthic resource survey was conducted on September 17,
2019 and September 18, 2019 by four (4) qualified biologists from The Chappell
Group, Inc. This work was performed at high tide (incoming). Line transects were
conducted parallel to the existing seawall, cutwalk and jetty within the proposed
project footprint. The survey area was approximately ±1,433’ adjacent to the
existing shoreline and extended ±60’ waterward of the existing shoreline in the
north and extended ±40’ waterward of the existing shoreline in the south,
respectively. Each diver conducted three (3) line transects parallel to the length
of the property within the Haulover Inlet and adjacent to the Bal Harbour Beach
jetty to ensure complete coverage of the survey area (Figure 2). The biologists
traversed each line along the bottom of the inlet to determine the presence of any
seagrass species and/or other submerged benthic resources. In addition to the
line transects, each diver conducted a meandering transect to ensure complete
1
714 East McNab Road. Pompano Beach, FL 33060 tel. 954.782.1908 fax. 954.782.1108 www.thechappellgroup.com
Environmental Consultants ׀Marina & Wetland Permitting ׀Phase I ESAs ׀Mitigation Design & Monitoring ׀T & E Species Surveys
79
mikyoung kim design
visual coverage and that no additional benthic resources were present adjacent
to the subject site. Due to visibility (<20’), spacing between transects was limited
to 20’ to ensure complete coverage of the survey area.
IV. Findings
The benthic community of the subject site consisted of sand, crushed shell and
rip rap (Appendix A). Depths within the survey area varied from 5’-20’ with depths
increasing with distance towards the center of the inlet. No species of seagrass
were observed. Resources observed within the survey area included numerous
coral growing on the rip rap, including at least three (3) mustard hill coral colonies
(Porites astreoides, >10cm), 139 colonies of white encrusting zoanthid (Palythoa
caribaeorum, >10cm), 224 lesser starlet coral colonies (Siderastrea radians, <1
cm – 30 cm), ten (10) common brain coral (Faviidae spp., 20 cm – 30 cm) and
one (1) smooth star coral (Solenastrea bournoni, >10cm) as shown in Table 1. A
total of 205 riprap boulders were documented to contain 90% coverage of coral
species, predominately the white encrusting zoanthid P. caribaeorum. Coral
colonies were observed on rip rap throughout the survey area, beginning at the
mean low water line approximately 8’ waterward of the cutwalk. Field work was
limited to two (2) days due to budget and time constraints for the schematic
design phase; therefore, a more detailed assessment of corals may be
documented by TCG and agencies during the future permitting process.
Table 1. Corals Observed
Common Name Scientific Name No. Observed Size
Lesser starlet coral Siderastrea radians 224 <1-30cm
Common brain coral Faviidae spp. 10 20-30cm
Mustard hill coral Porites astreoides 3 >10cm
White encrusting Palythoa caribaeorum 139 >10cm
zoanthid
Smooth star coral Solenastrea bournoni 1 >10cm
Fish species observed within the survey area included foureye butterflyfish
(Chaetodon capistratus), sergeant major (Abudefduf saxatilis), Atlantic tarpon
(Megalops atlanticus), rainbow parrotfish (Scarus guacamaia), lionfish (Pterois
volitans), sheepshead (Archosargus probatocephalus), mangrove snapper
(Lutjanus griseus) and checkered puffer (Sphoeroides testudineus). A complete
listing of species observed is included in Table 2 below:
714 East McNab Road. Pompano Beach, FL 33060 tel. 954.782.1908 fax. 954.782.1108 www.thechappellgroup.com
Environmental Consultants ׀Marina & Wetland Permitting ׀Phase I ESAs ׀Mitigation Design & Monitoring ׀T & E Species Surveys
80
Bal Harbour Jetty
V. Conclusions
714 East McNab Road. Pompano Beach, FL 33060 tel. 954.782.1908 fax. 954.782.1108 www.thechappellgroup.com
Environmental Consultants ׀Marina & Wetland Permitting ׀Phase I ESAs ׀Mitigation Design & Monitoring ׀T & E Species Surveys
81
mikyoung kim design
Sincerely,
THE CHAPPELL GROUP INC.
____________________ ____________________
Hayley De Marchis Sarah Chappell
Project Biologist President
714 East McNab Road. Pompano Beach, FL 33060 tel. 954.782.1908 fax. 954.782.1108 www.thechappellgroup.com
Environmental Consultants ׀Marina & Wetland Permitting ׀Phase I ESAs ׀Mitigation Design & Monitoring ׀T & E Species Surveys
82
Bal Harbour Jetty
FIGURE 1
LOCATION MAP
714 East McNab Road. Pompano Beach, FL 33060 tel. 954.782.1908 fax. 954.782.1108 www.thechappellgroup.com
Environmental Consultants ׀Marina & Wetland Permitting ׀Phase I ESAs ׀Mitigation Design & Monitoring ׀T & E Species Surveys
83
mikyoung kim design
84
Bal Harbour Jetty
FIGURE 2
714 East McNab Road. Pompano Beach, FL 33060 tel. 954.782.1908 fax. 954.782.1108 www.thechappellgroup.com
Environmental Consultants ׀Marina & Wetland Permitting ׀Phase I ESAs ׀Mitigation Design & Monitoring ׀T & E Species Surveys
85
mikyoung kim design
86
Bal Harbour Jetty
87
mikyoung kim design
88
Bal Harbour Jetty
APPENDIX A
SITE PHOTOGRAPHS
714 East McNab Road. Pompano Beach, FL 33060 tel. 954.782.1908 fax. 954.782.1108 www.thechappellgroup.com
Environmental Consultants ׀Marina & Wetland Permitting ׀Phase I ESAs ׀Mitigation Design & Monitoring ׀T & E Species Surveys
89
mikyoung kim design
1. Western portion of the property, facing southwest along the Haulover Inlet.
2. Central portion of the property, facing south along the Haulover Inlet.
90
Bal Harbour Jetty
3. Eastern portion of the property, facing east along the Haulover Inlet.
91
mikyoung kim design
6. Southeastern portion of the survey area south of the jetty, ±10’ waterward
of the existing cutwalk and ±1,270’ east of the Haulover Inlet Bridge. Note
lesser starlet coral (Siderastrea radians, >1cm).
92
Bal Harbour Jetty
7. Southeastern portion of the survey area south of the jetty, ±15’ waterward
of the existing cutwalk and ±1,290’ east of the Haulover Inlet Bridge. Note
Palythoa caribaeorum on rip rap (>10cm).
8. Southeastern portion of the survey area south of the jetty, ±20’ waterward
of the existing cutwalk and ±1,300’ east of the Haulover Inlet Bridge. Note
Palythoa caribaeorum on rip rap (>10cm).
93
mikyoung kim design
9. Southeastern portion of the survey area south of the jetty, ±30’ waterward
of the existing cutwalk and ±1,320’ east of the Haulover Inlet Bridge. Note
Palythoa caribaeorum covering riprap (>10cm).
10. Southeastern portion of the survey area south of the jetty, ±40’ waterward
of the existing cutwalk and ±1,330’ east of the Haulover Inlet Bridge. Note
Palythoa caribaeorum on rip rap (>10cm).
94
Bal Harbour Jetty
11. Southeastern portion of the survey area south of the jetty, ±40’ waterward
of the existing cutwalk and ±1,340’ east of the Haulover Inlet Bridge. Note
common brain coral (Faviidae spp., >10cm).
12. Eastern portion of the survey area, ±10’ waterward of the existing cutwalk
and ±1,340’ east of the Haulover Inlet Bridge. Note white encrusting
zoanthid (Palythoa caribaeorum, >10cm) on rip rap.
95
mikyoung kim design
13. Eastern portion of the survey area, ±10’ waterward of the existing cutwalk
and ±1,300’ east of the Haulover Inlet Bridge. Note white encrusting
zoanthid (Palythoa caribaeorum, >10cm) on rip rap.
14. Eastern portion of the survey area, ±15’ waterward of the existing cutwalk
and ±1,250’ east of the Haulover Inlet Bridge. Note white encrusting
zoanthid (Palythoa caribaeorum, >10cm) on rip rap.
96
Bal Harbour Jetty
15. Eastern portion of the survey area, ±15’ waterward of the existing cutwalk
and ±1,200’ east of the Haulover Inlet Bridge. Note common brain coral on
rip rap (Faviidae spp., >10cm).
16. Eastern portion of the survey area, ±20’ waterward of the existing cutwalk
and ±1,150’ east of the Haulover Inlet Bridge. Note Palythoa caribaeorum
on rip rap (>10cm).
97
mikyoung kim design
17. Eastern portion of the survey area, ±20’ waterward of the existing cutwalk
and ±1,000’ east of the Haulover Inlet Bridge. Note lesser starlet coral
(Siderastrea radians, >10 cm).
18. Eastern portion of the survey area, ±25’ waterward of the existing cutwalk
and ±950’ east of the Haulover Inlet Bridge. Note Palythoa caribaeorum on
rip rap (>10cm).
98
Bal Harbour Jetty
19. Central portion of the survey area, ±30’ waterward of the existing cutwalk
and ±900’ east of the Haulover Inlet Bridge. Note Palythoa caribaeorum on
rip rap (>10cm).
20. Eastern portion of the survey area, ±40’ waterward of the existing cutwalk
and ±850’ east of the Haulover Inlet Bridge. Note Palythoa caribaeorum on
rip rap (>10cm).
99
mikyoung kim design
21. Eastern portion of the survey area, ±50’ waterward of the existing cutwalk
and ±800’ east of the Haulover Inlet Bridge. Note Palythoa caribaeorum on
rip rap (>10cm).
22. Eastern portion of the survey area, ±60’ waterward of the existing cutwalk
and ±750’ east of the Haulover Inlet Bridge. Note Palythoa caribaeorum
(>10cm) and common brain coral (Faviidae spp.) on rip rap.
100
Bal Harbour Jetty
23. Eastern portion of the survey area, ±60’ waterward of the existing cutwalk
and ±700’ east of the Haulover Inlet Bridge. Note Palythoa caribaeorum on
rip rap (>10cm).
24. Eastern portion of the survey area, ±60’ waterward of the existing cutwalk
and ±650’ east of the Haulover Inlet Bridge. Note lesser starlet coral
(Siderastrea radians, >10 cm).
101
mikyoung kim design
25. Western portion of the survey area, ±60’ waterward of the existing cutwalk
and ±550’ east of the Haulover Inlet Bridge. Note seawall.
26. Western portion of the survey area, ±60’ waterward of the existing cutwalk
and ±200’ east of the Haulover Inlet Bridge. Note rock substrate.
102
Bal Harbour Jetty
D. STRUCTURAL REPORT
103
mikyoung kim design
MUEngineers, Inc.
3440 NE 12th Avenue
Oakland Park, FL 33334
Phone: (954) 324-4730
CA#: 29348
www.MUEngineers.com
Preliminary Report
Prepared For:
Prepared By:
Marcus Unterweger
Florida P.E.#: 063860
12/3/2019 13:54
Page 1 of 7
p:\active\mue18110201-mik-balharbourvillage\eng\mue18110201-rpt-asmtextseawall191203.docx
104
Bal Harbour Jetty
1. SCOPE .........................................................................................................................................................3
2. 1. LIMITATIONS: .........................................................................................................................................3
3. AVAILABLE RECORD DOCUMENTS ............................................................................................................3
3.1. SKETCH TO ACCOMPANY REPORT ON BEACH EROSION – SHOWING PROPOSED LOCATION OF
GRYNES ...........................................................................................................................................................3
3.2. REPAIRS AND IMPROVEMENTS TO SHORELINE, PROTECTION YTACTYS”C”, “D”, & “E” OCEAN
FRONT ADDTION – BAL HARBOUR VILLARGE DADE COUNTY ........................................................................3
3.3. REPAIR SOUTH BULKHAED BAKERS HAULOVER INLET .......................................................................3
3.4. BAL HARBOUR BEACH RESTORATION PROJECT – GROIN DETAILS ....................................................4
3.5. BAL HARBOUR, FLORIDA: JETTY PLAN AND SECTIONS .......................................................................4
3.6. GROIN REPAIR – BAL HARBOUR VILLAGE ...........................................................................................4
3.7. REPAIRS TO JETTY STRUCTURE – BAKERS HAULOVER INLET .............................................................4
3.8. SOUTH UNDERBRIDGE RESTORATION – BAKERS HAULOVER CUT BRIDE REHABILITATION ..............4
4. GENERAL DESCRIPTION OF THE EXISTING SEAWALL COMPONENTS: ........................................................4
5. STRUCTURAL COMPONENT REVIEW AND FINDINGS AND RECOMMENDATIONS: ....................................5
5.1. FINDINGS ............................................................................................................................................5
5.2. RECOMMENDATION:..........................................................................................................................5
6. SUMMARY ..................................................................................................................................................6
7. LIMITATIONS AND SUFFICIENCY.................................................................................................................6
Page 2 of 7
105
mikyoung kim design
1. SCOPE
Mikyoung Kim Design commissioned MUEngineers, Inc. to perform a limited structural assessment of the
existing seawall east of federal highway and south of the Bakers Haulover Inlet based on review of available
construction documents and non-destructive site observation.
The purpose of this excersise was to gather information about the existing seawall conditions that would
enable us to render an opinion concerning its overall structural integrity. Neither the inspection, nor this
report, is intended to cover hidden defects, mechanical or electrical features
2. 1. LIMITATIONS:
MUEngineers did not use any special tools or instruments, nor did we perform any destructive testing but
performed visual observations of readily accessible seawall sections only.
Structural elements and their connections which were not indicated on the record set of drawings
and which could not be visually observed without destructive testing have not been reviewed, cannot be
commented on and are excluded from this report. It shall further be noted that our field observations
represent only a small sample of the complete structure. This report, our findings and evaluations are based
on these sample observations.
3.1. Sketch To Accompany Report On Beach Erosion – Showing Proposed Location Of Groins
3.2. Repairs And Improvements To Shoreline, Protection Tracts ”C”, “D”, & “E” Ocean Front Addition –
Bal Harbour Village Dade County
Page 3 of 7
106
Bal Harbour Jetty
Based on our review of the available record documents and field observations it appears that the
existing seawall / bulk head consists of metal sheet piles, concrete wall panels and a poured in placed
concrete parapet wall and cap. The record documents do not indicate the structural specifications
and properties or the existing seawall components such as sheet pile type and depth, anchor rod size
Page 4 of 7
107
mikyoung kim design
and spacing, soil anchor type, size and layout, concrete strengths and reinforcing of any existing
concrete components.
ͷǤͳǤ
ͷǤͳǤͳǤ
Inspection of the seawall revealed continuous cracks and gaps along the joint/interface between the
concrete cap and parapet. The interior face of the concrete parapet and cap along the walkway has
been previously painted and likely repaired and patched, therefore no cracks were observed at the
time of our inspection. Blistered paint and water stains were observed at several scattered locations.
ͷǤͳǤʹǤ
The concrete wall panels exhibit continuous cracks running throughout the front face of the seawall.
Additionally, spalling, delaminated concrete, and exposed and corroded sections of metal sheet piles
were observed at several locations.
It is likely that there are existing tie-back rods and anchors installed to stabilize the top of the existing
sheet pile but these seawall components (if existing) could not be observed and assessed since they
are covered by the existing paved walkway finish.
ͷǤͳǤͶǤ
Zurwelle – Whittaker Inc in 1957, suggests that the existing seawall consists of metal sheet piles; The
type, depth, profile and tie-back conditions are not indicated on any of the available record
documents and cannot be commented on without further destructive testing and exposing the back
/ landside face of the existing seawall.
It is our recommendation to expose the landside face of the seawall to an elevation of not less than
the mean low water elevation, locate and identify all the tie-back anchor rods and soil anchors and
further assess the structural condition and the expected remaining service life of those seawall
components. We further recommend having the seawall section below the mean low water line
inspected and photo and video documented along its complete length by commercial divers.
Page 5 of 7
108
Bal Harbour Jetty
Depending on the results of these further investigations it will then be possible to assess the existing
conditions more accurately and determine and advise if it is feasible to repair the existing seawall
including all cracked, spalled and delaminated concrete sections or if the existing seawall should be
partially or completely replaced instead with a new metal sheet pile seawall immediately south /
landside along the existing seawall.
6. SUMMARY
Based on our limited evaluation of the structure based on the construction documents provided, it is our
professional opinion that the existing seawall is most likely reaching its expected service life. Further
destructive testing will be required to determine if it is feasible to repair the existing seawall or otherwise to
partially or completely replace the existing seawall with a new sheet pile wall, reinforced concrete wall panel
and reinforced concrete parapet wall and cap.
This report is based primarily on the information available from the available construction record documents.
Structural elements and their connections which were not indicated on the available record documents and
could not be readily observed cannot be commented on and will require further investigations.
Nothing in this report shall be construed directly or indirectly as a guarantee or warrantee of any portion of
the structure.
Please note that our opinions and recommendations are based upon our professional engineering judgment
to an extent normal for a structural assessment of this type. Our evaluation was analytical in nature.
This report is prepared for the sole benefit of Mikyoung Kim Design only. Unauthorized use of the information
contained in this report without our permission shall result in no liability or legal exposure to MUEngineers,
Inc.
Page 6 of 7
109
mikyoung kim design
We appreciate this opportunity to be of service to you. If you require any additional information, please feel
free to contact us at your convenience.
MUEngineers, Inc.
Luis A. Sanchez Herrera, P.E. LEED AP Marcus Unterweger, P.E., S.I., LEED AP
Project Manager President
MUEngineers, Inc.
Florida Reg. No: 63860
Certificate of Authorization No. 29348
Page 7 of 7
110
Bal Harbour Jetty
E. CIVIL REPORT
111
mikyoung kim design
BTE Proj. No. 19-0402 Bal Harbor Cut walk and Jetty
Scope of work to include removal of existing cut walk pavers and landscape (planters) and
reconfiguration of cut walk pavers and landscape (planters).
The pervious/impervious ratios will not be increased and therefore will not adversely affect the
existing drainage design. There will be no increase in water quality volume required and no
increased run off volume to the existing drainage system.
The cut walk will be re-graded to maintain existing elevations and available storage volume.
Surface water run off will be maintained to the existing storm drainage inlets located along the cut
walk, if planter drains are required/desired yard drains can be added and connected by piping to
the existing storm drainage structures. Surface water licenses (Department of Environmental
Resources – DERM) can be modified as applicable.
3409 NW 9th Avenue • Suite 1102 • Fort Lauderdale, FL 33309 • p. 954-568-0888, f. 954-568-0757
112
Bal Harbour Jetty
F. DESIGN PRESENTATIONS
COMMUNITY MEETING JULY 2019
113
mikyoung kim design
114
Bal Harbour Jetty
115
mikyoung kim design
116
Bal Harbour Jetty
117
mikyoung kim design
118
Bal Harbour Jetty
119
mikyoung kim design
120
Bal Harbour Jetty
121
mikyoung kim design
122
Bal Harbour Jetty
123
mikyoung kim design
124
Bal Harbour Jetty
125
mikyoung kim design
126
Bal Harbour Jetty
127
mikyoung kim design
128
Bal Harbour Jetty
129
mikyoung kim design
130
Bal Harbour Jetty
131
mikyoung kim design
132
Bal Harbour Jetty
133
mikyoung kim design
134
2019 mikyoung kim design