Project Management
Project Management
Question 1
Build the PERT network for the project with the activities given below.
Tasks Predecessors
A -
B -
C A
D A, B
E C, D
F D
G A, B
H D, G
Question 2
A preliminary study of a project has allowed it to be broken down into 9 tasks. The immediately preceding
tasks and the durations in days under normal time for each task are gathered in the table below:
Duration
Task predecessors
(days)
A 4 -
B 6 -
C 5 A
D 8 -
E 2 F
F 4 D
G 4 A, E, I
H 8 F
I 7 B,D
1. Represent the PERT network for this project.
2. Calculate for each activity its total and free margins.
3. Determine the critical path and deduce the project duration.
4. What will be the effect on the project duration if the durations of tasks G and I each increase by 1 day
simultaneously?
Question 3
The company MADEST has undertaken the construction of a warehouse. The following table summarizes all
the tasks related to this project, along with their durations and predecessors.
Question 4
The production manager at NOVACO Company (subcontractor in the automotive industry) is tasked with
establishing the schedule for a new product and managing the project's progress. The table below summarizes
the various tasks to be carried out to reach the end of the project, including duration estimates (in days) and the
number of workers required for each task.
Quetion 5
For the construction of a yacht, six tasks must be performed according to the PERT network given below. The
expected durations as well as the variances of the various activities are indicated in the following table.
1. What is the most commonly used statistical distribution law to estimate the expected duration of an
activity in a probabilistic project environment?
2. Recall the expressions used to calculate the expected duration of an activity as well as its variance.
3. Estimate the average duration of the construction project and determine its critical path.
4. What would be the effect on the project execution if simultaneously the expected duration of task A
increased by 5 weeks and that of D by 2 weeks? Justify your response without calculation.
5. Calculate the estimated duration of the project with a probability of 90%.
Question 6
For the implementation of a project, indirect costs are estimated at 12,000 dinars per week of work. The table
below presents the costs and durations required for the completion of each task in the project.
Potential Reduction cost
Task Duration (weeks) Predecessor
reduction (Dinars)
A 10 - 3 11000
3000 for the first week and 4000 for the
B 14 A 3
subsequent weeks
C 13 - 2 6000
D 6 C 1 1000
E 15 - 3 6000
F 8 E 1 2000