Weekly Construction Schedule Template

This weekly construction schedule outlines the planned work for a 10-week construction project for client Mr. Bradley Greenwood. It shows that in weeks 1-2 plans will be reviewed and contracts signed. In week 3 the land will be cleared and leveled in preparation for the foundation work in weeks 4-5, which will include laying the footings and walls. Framing will then occur from weeks 6-8, covering roof trusses, interior framing, and installing the roof. Mechanical, electrical, plumbing and insulation work is scheduled for weeks 8-9. Drywall installation is planned for week 10 along with final inspections to complete the project.

Uploaded by

Abo Hiba
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
56 views1 page

Weekly Construction Schedule Template

This weekly construction schedule outlines the planned work for a 10-week construction project for client Mr. Bradley Greenwood. It shows that in weeks 1-2 plans will be reviewed and contracts signed. In week 3 the land will be cleared and leveled in preparation for the foundation work in weeks 4-5, which will include laying the footings and walls. Framing will then occur from weeks 6-8, covering roof trusses, interior framing, and installing the roof. Mechanical, electrical, plumbing and insulation work is scheduled for weeks 8-9. Drywall installation is planned for week 10 along with final inspections to complete the project.

Uploaded by

Abo Hiba
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 1

WEEKLY CONSTRUCTION SCHEDULE TEMPLATE

Client: Mr. Bradley Greenwood

W1 W2 W3 W4 W5 W6 W7 W8 W9 W10

Plans & Contracts Plans review & Contract signing

Clear & Level the land

Foundation
Site Work & Masonry

Footings & Walls

Roof trusses installation

Framing Roof drying with a tar paper

All interior framing

HVAC

Plumbing rough-in
Plumbing & Electrical

Electrical rough-in

Foam insulation

Insulation
Drywall

Final Inspections Final inspections