MGT Ppa
MGT Ppa
MGT Ppa
November, 2022
Wolaita Sodo University, Ethiopia
1|Page
UNIT ONE
INTRODUCTION TO PROJECT
A project is an organizational unit dedicated to the allotment of a goal the successful completion
of a development product in time, within specified budget, in conformance with the pre-
determined performance specifications.
It (a project) is a set of finite activities that are usually prepared only once and have well
designed objectives, using a combination of human and non-human resources within limits of
time.
It consists of a series of non-routine, interrelated activities with a goal that must be completed
with a set amount of resources and within a set time limit.
So, a project is a sequence of unique, complex, and connected activities having one goal or
purpose and that must be completed by a specific time, within limited budget, and according to
specification. The following constitutes each part of the definition.
Project is a scheme or part of a scheme for investing scarce resources, which can be reasonably
evaluated and analyzed as an independent unit.
Project refers to an investment activity in which resources are committed within a given time
framework, to create assets over an extended time in expectations of benefits which exceeds the
committed resources.
Although the definitions above seem different, all definitions imply the same concept: a project
is a set of proposal for investment of resource in to a clearly identified set of actions that are
expected to produce future benefits of a specific kind, the whole series of actions being the
1|Page
subject of individual planning and examination before being adapted and implemented within a
single over all financial and managerial frameworks.
This definition tells us quite a bit about a project. To appreciate just what constitutes a project,
let’s look at each part of the definition.
I. Sequence of Activities
A project comprises of a number of activities that must be completed in some specified order, or
sequence. An activity is a defined as chunk of work. The sequence of the activities is based on
technical requirements, and not on management prerogatives. To determine the sequence, it is
helpful to think in terms of inputs and outputs. You need to ask questions like:
The output of one activity or set of activities becomes input to another activity or set of activities.
Specifying sequence based on resource constraints or statements. Resource constraints must not
be ignored when we actually schedule activities. The decision of what resources to use and when
to use them comes later in the project planning activities.
2
ii. Unique Activities
The activities in a given project must be unique. The assumption must always be that, a project
has never happened before, and it will never happen in the future under the same conditions.
Something is always different each time the activities of a project are repeated. Usually the
variations are random in nature. For example, a part is delayed, someone is sick, a power failure
occurs. These are random events that can happen, but we can never be sure as to where, how or
with what impact the events would happen in the schedule. These random variations are the
challenge for the project manager.
The activities that make up a project are not simple, repetitive acts, such as mowing the lawn,
painting the house, washing the car, or loading the delivery truck. Rather, they are complex. For
example, designing an intuitive user interface to an application system is a complex activity.
v. One Goal
Projects must have a single goal. However, very large or complex projects may be divided into
several subprojects, each of which is a project in its own right. This division allows better
management control. For example, subprojects can be defined at the department, division, or
geographic level. This artificial decomposition of a complex project into subprojects often
simplifies the scheduling of resources and reduces the need for unnecessary interdepartmental
communications while a specific activity is worked on. The downside is that the projects are now
interdependent. Even though interdependency adds another layer of complexity and
communication, it can be handled.
3
vii. Specified Time
Projects have a specified completion date. This date can be self-imposed by management or
externally specified by a customer or government agency. The deadline is beyond the control of
anyone working on the project. The project is over on the specified completion date whether or
not the project work has been completed.
Projects also have resource limits, such as a limited amount of people, money, or machines that
are dedicated to that particular project. Even though these resources can be adjusted up or down
by management, they are considered as fixed resources to the project manager.
The customer, or the recipient of the project’s deliverables, expects a certain level of
functionality and quality from the project. These expectations can be self-imposed, such as the
specification as to the project completion date, or customer-specified, such as producing the sales
report on a weekly basis.
Although the project manager treats the specification as fixed, the reality of the situation is that
any number of factors can cause the specification to change.
Some time, people confuse a project with a program and often use interchangeably, but the terms
are not the same. Unlike a project, a program is an ongoing development effort or plan.
The plan is the written explanation of goals, objectives, targets and means to achieve it.
A plan provides the steps to be carried out in both programs and projects. Thus, it establishes the
goals, deliverables, and the level of collaboration for both programs and projects.
A plan provides a comprehensive detailed course of action directed at achieving a specified end
result. A plan may be re-evaluated as goals and milestones are accomplished or as information or
circumstances change. There therefore may be some degree of flexibility to a plan.
4
A project is comprised of individual tasks that aim at specified outputs or deliverable products.
Milestones and goals are defined and measured against the output objective, costs and timetable.
Projects are well defined, short-term, with manageable risk, and resource needs that can be
estimated with reasonable accuracy. A project is defined as a temporary activity aimed at
achieving specific/narrow organization objectives.
Programs, on the other hand, are organization activities aimed at achieving broader organization
objectives by coordinating a group of projects. Thus, programs are much wider in scope
compared to projects. Objectives are comprehensive and encompass change within the
corporation such as in terms of a change in production capabilities or a change in organizational
structure or culture. Programs are defined in fluid terms, are long-term, with significant risks,
and resource costs.
The basic difference between plan, project and program is that a plan details a course of action;
a project is short-term and designed to deliver a specified output within time, cost and quality
parameters; and a program is a long-term managed portfolio of multiple projects designed to
produce outcomes.
The following comparisons may explain the difference between the two:
Meaning A project refers to the temporary activity, A program implies a set of projects
which is undertaken to create a distinct which are linked to one another, in a
product or service, which has certain sequential manner to attain the
objectives. combined benefits.
5
Tasks Technical in nature Strategic in nature
The similarities between the two sectors mainly refer to management functions, while the
differences focus on the conditions or constraints in which the management operates. In other
words project managers in the private and public sectors need the same skills and use the same
set of tools.
The main distinction between public and private organizations is their ownership. Unlike
private companies, owned by entrepreneurs or shareholders, public organizations are the
collective property of members of political communities.
Here are some additional differences between public and private organizations:
6
Absence of competitive pressures: public organizations generally have few competitors.
Even when competition is present, public managers often enjoy a dominant position in
the market, such as in education and healthcare.
It is also emphasized that the goals of public organizations are vaguer than those of their private
counterparts, because organizational goals are imposed through the political process, rather than
selected by the managers themselves.
Another feature of public organizations is that they usually have more formal procedures for
decision making and are less flexible and more risk averse.
Every project is constrained in different ways. Some project managers focus on scope, time, and
cost constraints. Other people focus on the quadruple constraint, which adds quality as a fourth
constraint. The scope, time, and cost limitations are sometimes referred to in project management
as the triple constraint.
To create a successful project, a project manager must consider scope, time, and cost and balance
these three often-competing goals:
1. Scope: What work will be done as part of the project? What unique product, service, or
result does the customer or sponsor expect from the project?
2. Time: How long should it take to complete the project? What is the project’s schedule?
3. Cost: What should it cost to complete the project? What is the project’s budget? What
resources are needed?
Other people focus on the quadruple constraint, which adds quality as a fourth constraint.
Quality: How good does the quality of the products or services need to be? What do we need to
do to satisfy the customer? Other also suggests these four constraints plus risk.
Risk: How much uncertainty are we willing to accept on the project?
Whatever its size, a project’s success is based on the three main criteria as shown by the
following triangle:
7
Scope
Time Budget
Project management is planning, scheduling, controlling and monitoring the complex non-
routine activities that must be completed to reach the predetermined objectives of the project. It
involves the coordination of a group activity, wherein the manager plans, organizes staffs,
directs, and controls to achieve an objective, with specified time, cost and performance of the
end product.
Planning is the process of preparing for the commitment of resources in the most economical
manner. Project planning deals with specified tasks and operations of activities, which must be
performed to achieve the project goals. Any project that we may consider has an objective and
has to be implemented within a given set of rules, regulations, constraints and restrictions.
Implementation of projects needs resources or inputs. Every project converts the given inputs
into output through a process of implementation. The outputs in the short run, lead to outcomes
which, in the long run, should result in impact. Thus, a project can be defined as complex set of
non-routine activities that must be completed with a set amount of resources and within a set of
time frame.
Project analysis in project management plays a key role in the economic development of a
country. Since the introduction of the concept of planning, countries of the world, especially,
8
developing countries, have been investing large amounts of money in projects related to industry,
minerals, power, transpiration, irrigation, education, etc with a view to improve the socio-
economic conditions of the people. The money invested both in industrial and social projects
keeps increasing. These projects are designed with the aim of earning adequate returns to
provide for future development. But, experience shows that there are several shortcomings in the
ultimate success of achieving the objectives of the proposed projects. One of the main reasons
for the failure of many projects in the developing countries is the inadequacy of managerial skill
for project implementation and imperfect planning and control of projects.
Controlling is the process of making events to conform to schedules by coordinating the action
of all parts of the project outlined to achieve its objectives.
Stakeholders are the people involved in or affected by project activities. These include the
project sponsor, the project team, the support staff, customers, users, suppliers and opponents to
the project. These stakeholders often have very different needs and expectations. For example,
there are several stakeholders involved in a home construction project.
The project sponsors would be the potential new homeowners. They would be the people
paying for the house and could be on a very tight budget, so they would expect the contractor to
provide accurate estimates of the costs involved in building the house. They would also need a
realistic idea of when they could move in and what type of home they could afford given their
budget constraints. The new homeowners would have to make important decisions to keep the
costs of the house within their budget. Can they afford to finish the basement right away? If they
can afford to finish the basement, will it affect the projected move-in date? In this example, the
project sponsors are also the customers and users for the product, which is the house.
The project manager in this example would normally be the general contractor responsible for
building the house. He or she needs to work with all the project stakeholders to meet their needs
and expectations.
The project team for building the house would include several construction workers,
electricians, carpenters, and so on. These stakeholders would need to know exactly what work
they must do and when they need to do it. They would need to know if the required materials and
9
equipment will be at the construction site or if they are expected to provide the materials and
equipment. Their work would need to be coordinated since there are many interrelated factors
involved. For example, the carpenter cannot put in kitchen cabinets until the walls are completed.
Support staff might include the employers of the homeowners, the general contractor’s
administrative assistant, and other people who support other stakeholders. The employers of the
homeowners might expect their employees to complete their work but allow some flexibility so
they can visit the building site or take phone calls related to building the house. Building a house
requires many suppliers. The suppliers would provide the wood, windows, flooring materials,
appliances, and other items. Suppliers would expect exact details on what items they need to
provide, where and when to deliver those items, and similar information. There are many
different stakeholders on projects, and they all have different interests. Stakeholders’ needs and
expectations are important in the beginning and throughout the life of a project. Successful
project managers develop good relationships with project stakeholders to understand and meet
their needs and expectations. Program managers often have review meetings with all their project
managers to share important information and coordinate important aspects of each project. Many
program managers worked as project managers earlier in their careers, and they enjoy sharing
their wisdom and expertise with their project managers. Effective program managers recognize
that managing a program is much more complex than managing a single project. They recognize
that technical and project management skills are not enough. In addition to skills required for
project managers, program managers must also possess strong business knowledge, leadership
capability, and communication skills.
10
CHAPTER TWO
Project cycle is referred to as the various stages through which project planning proceeds from
inception to implementation. It is the project’s life span through which a project advances
from infancy to maturity. Different guidelines, manuals and foreign authors have called project
phases by different names.
2.1. United Nations Industrial Development Organization (UNIDO) Project Life Cycle
UNIDO has divided project cycles into phases and stages as follows.
Pre-selection
Pre-feasibility study
Preparation
Identification
Feasibility Study
Opportunity study
Support Studies
Expansion Pre
Innovation investment
Operating
phase
Appraisal
phase Report
Replacement Investment
phase Negotiations and
Rehabilitation
contracting
Project Design
Commissioning and
startup
Construction
Pre-production marketing
Training
11
The delineation of each phase and each activity from the other is not clear cut/discrete line.
There are several activities undertaken in more than one phase and the transfer is very slow and
gradual. Activities are sequential but it is also possible to go back and revise some of the
activities after once passing that stage. All phases of the project cycle lend themselves to
important consultancy from different disciplines and expertise.
i) Opportunity Studies
The idea of the project that is generated from the opportunity studies must be elaborated in a
more detailed study. But, a feasibility study for a definite decision is expensive and time
12
consuming. So, before conducting a feasibility study, a further assessment of the project idea
might be made in pre-feasibility study. Such a study aims at determining whether:
1. All possible project alternatives have been examined,
2. The project concept justifies a detailed analysis by a feasibility study,
3. Any aspects of the project require support studies,
4. The project idea is attractive enough for a particular investor or investor group,
5. The environmental situation is in line with the national standards.
Support Studies
Support studies cover specific aspects of an investment project in support of pre feasibility or
feasibility studies. E.g. Market studies, Raw material studies, Laboratory tests, Location studies
etc.
iii) Feasibility Study
Feasibility study aims at providing all data necessary for an investment decision or against it.
Before the final decision is taken to commit resources, the technical, economical and commercial
justification has to be provided in comprehensive and authentic terms. These should be clarity
about the location, the plant size, the material and the major inputs. Proceeding from this base,
capital outlays, production costs, and expected sales revenues and return on investments have to
be ascertained. It assists in arriving at the final decision to invest. Feasibility study is an
essential document which spells out the economic viability and the prospects of the project.
Though the contents of pre feasibility and feasibility studies are the same, more accuracy is
expected in the feasibility study.
When the feasibility study is completed, the various parties involved in the project will carry out
their own appraisal of the investment project in accordance with their individual objectives. An
13
evaluation of expected risks, costs and gains of the project will be done. The project appraisal
should be considered as an independent stage of the pre- investment phase, marked by the final
investment and financing decision taken by the project promoters. Appraisal reports are
necessary for getting funds from the financial institutions. They reveal the health of the
company to be financed and the protection of its creditors.
14
sales revenues. These have a direct relationship with the projections made at the pre- investment
phase. If such projections prove faulty, remedial measures will not only be difficult but may
probe highly expensive.
Expansion Studies
Though the feasibility study aims at new projects, the same techniques can be applied to the
expansion of existing projects. The expansion may be in the form of increasing the quantity of
production, changing the production program or a combination of the two. Expansion should be
treated as a new project. In order to prepare a project proposal, the data of the expansion project
must be consolidated with those of the existing project. Any other changes in location,
administration etc. should be made clear. The financial impact may be expressed in terms of the
marginal costs and benefits.
Preparation
Identification Appraisal
Implementation
Evaluation
15
1.10.3. New Project Cycle (World Bank 1994)
UNIT TWO
GENERATION AND SCREENING OF PROJECT IDEAS
Introduction
The search for promising project ideas is the first step towards establishing a successful venture.
As the traditional adage goes, the key to success lies in getting into the right business at the right
time. While this advice is simple, its accomplishment is difficult because good business
opportunities tend to be elusive. Identification of such opportunities requires imagination,
sensitivity to environmental changes, and a realistic assessment to what the firm can do. The
task is partly structured, partly unstructured; partly dependent on convergent thinking, partly
16
dependent on divergent thinking; partly requiring objective analysis of quantifiable factors,
partly requiring subjective evaluation of qualitative factors; partly amenable to control, partly
dependent on fortuitous circumstances.
Identification is often the outcome of a triggering process rather than an analytical exercise.
While the notion of identification is simple, it is difficult to develop methods or procedures for
accomplishing it as there is no well defined theory to guide this task. And as Gordon and
Pinches observed: “These difficulties become more severe as one moves up the hierarchy of
organizational decision-making levels because of the relative uniqueness (non-routineness) of
higher level decisions as compared to lower level decisions.”
With this note of caution, this unit discusses certain broad consideration and guidelines helpful in
the generation and screening of project ideas. The objective is to identify investment
opportunities which are prima facie feasible and promising and which merit further examination
and appraisal. The discussion is divided into nine section as follows:
Generation of ideas
Monitoring the environment
Corporate appraisal
Profit potential of industries: porter model
Scouting for project ideas
Preliminary screening
Project rating index
Sources of positive net present value
On being an entrepreneur
Learning Objectives
17
services. The typical route may be described as follows: someone with specialized technical
knowledge or marketing expertise or some other competence feels that he can offer a product or
service which can cater to a presently unmet need or serve a market where demand exceeds
supply or effectively compete with similar product or services because of certain favorable
features like better quality or lower prices. His ideas are endorsed by his associates who
encourage him and even show willingness to collaborate with him on the proposal. Finally, he
receives support from investors (like venture capitalists and financial institutions) that approve
his project and show readiness to finance it.
SWOT Analysis. SWOT is an acronym for strengths, weaknesses, opportunities, and threats.
SWOT analysis represents a conscious, deliberate, and systematic effort by an organization to
identify opportunities that can be profitably exploited by it. Periodic SWOT analysis facilitates
the generation of ideas.
Clear Articulation of Objectives. The operational objectives of a firm may be one or more of the
following:
Cost reduction
Productivity improvement
Increase in capacity utilization
Improvement in contribution margin
Expansion into promising fields
A clear articulation and prioritization of objectives helps in channeling the efforts of employees
and prods them to think more imaginatively.
Fostering a Conducive Climate . To tap the creativity of people and to harness their
entrepreneurial urges, a conducive organizational climate has to be fostered. Two conspicuous
examples of organizations which have been exceptionally successful in tapping the creativity of
employees are the Bell Telephone Laboratory and the 3 M Corporation. While the former
succeeded in harnessing creativity by providing an unconstrained environment the latter
effectively nurtured the entrepreneurial urges of its employees. At a more mundane level, many
organizations (Hindustan Lever is a prominent example in India) have successfully used
suggestion schemes to motivate employees to think more creatively.
Can you mention some of the tools for identifying investment opportunities?
18
______________________________________________________________________________
__________________________________________________________________There are
several useful tools or frameworks that are helpful in identifying promising investment
opportunities. The more popular ones are the Porter model, life cycle approach, and experience
curve.
Micheal Porter has argued that the profit potential of an industry depends on the combined
strengths of the following five basic competitive forces:
Threat of new entrants
Rivalry among existing firms
Pressure from substitute products
Bargaining power of buyers
Bargaining power of sellers
a. Threat of New Entrants. New entrants add capacity, inflate costs, push prices down, and
reduce profitability. Hence, if an industry faces the threat of new entrants, its profit potential
would be limited. The threat from new entrants is low if the entry barriers confer an advantage
on existing firms and deter new entrants. Entry barriers are high when:
The new entrants have to invest substantial resources to enter the industry
Economies of scale are enjoyed by the industry.
Existing firms control the distribution channels, benefit from product differentiation in
the form of brand image and customer loyalty, and enjoy some kind of proprietary
experience curve.
Switching costs: Essentially one-time costs of switching from the products of one
supplier to another-are high.
The government policy limits or even prevents new entrants.
b. Rivalry between Existing Firms. Firms in an industry compete on the basis of price, quality,
promotion, service, warranties, and so on. Generally, a firm’s attempts to improve its
competitive position provoke retaliatory actions from others. If the rivalry between the firms in
an industry is strong, competitive moves and countermoves dampen the average profitability of
the industry. The intensity of rivalry in an industry tends to be high when:
The number of competitors in the industry is large
At least a few firms are relatively balanced and capable of engaging in a sustained
competitive battle.
The industry growth is sluggish, prodding firms to strive for a higher market share.
The level of fixed costs is high, generating strong pressures for all firms to achieve a
higher capacity utilization level.
There is chronic over capacity in the industry.
The industry’s product is regarded as a commodity or near-commodity, stimulating
strong price and service competition.
The industry confronts high exit barriers.
19
c. Pressure from Substitute Products. In a way, all firms in and industry face competition
from industries producing substitute products. Performing the same function as the original
product, substitute products may limit the profit potential of the industry by imposing a ceiling
on the prices that can be charged by the firms in the industry. The threat from substitute
products is high when:
The price-performance trade off offered by the substitute products is attractive.
The switching costs for prospective buyers are minimal.
The substitute products are being produced by industries earning superior profits.
d. Bargaining power of Buyers. Buyers are a competitive force. They can bargain for price cut,
ask for superior quality and better service, and induce rivalry among competitors. If they are
powerful, they can depress the profitability of the supplier industry. The bargaining power of a
buyer group is high when:
Its purchases are large relative to the sales of the seller.
Its switching costs are low.
It poses a strong threat of backward integration.
e. Bargaining power of Suppliers. Suppliers, like buyers, can exert a competitive force in an
industry as they can raise prices, lower quality, and curtail the range of free services that they
provide. Powerful suppliers can hurt the profitability of the buyer industry. Suppliers have
strong bargaining power when:
Few suppliers dominate and the supplier group is more concentrated than the buyer
group.
There are hardly any viable substitutes for the products supplied.
The switching costs for the buyers are high.
Suppliers present a real threat of forward integration.
Decline Stage. With the satiation of demand, encroachment of new products, and changes in
consumer preferences, the industry eventually enters the decline stage, relative to the economy as
20
a whole. In this stage, which may continue indefinitely, the industry may grow slightly during
prosperous periods, stagnate during normal periods, and decline during recessionary periods.
Each stage presents investment opportunities that exhibit different characteristics. Investment in
the pioneering stage, per se, many have a low return and negative NPV. However, it may
possibly create options for participating in the growth stage. Investment in the growth stage is
likely to earn a high return and generate positive NPV. Investment in the maturity stage may earn
average return and be NPV-neutral. Finally, investment in the decline stage may earn meager
returns and produce negative NPV.
Good project ideas key to success-are elusive. So a wide variety of sources should be tapped to
identify them. Here are some suggestions in this regard:
b. Examine the Inputs and Outputs of Various Industries. An analysis of the inputs required
for various industries may throw up project ideas. Opportunities exist when (i) material and
purchased parts for supplies are presently being procured from distant sources with attendant
time lag and transportation cost, and (ii) several firms produce internally some components/parts
which can be supplied at a lower cost by a single manufacturer who can enjoy economies of
scale. Similarly, a study of the output of the existing industries may reveal opportunities for
adding value through further processing of the main outputs, by-products, as well as waste
products. (Remember that one person’s trash can be another person’s treasure.)
c. Review Imports and Exports. An analysis of import statistics for a period of five to seven
years is helpful in understanding the trend of imports of various goods and the potential for
import substitution. Indigenous manufacture of goods currently imported is advantageous for
several reasons: (i) it improves the balance of payments situation, (ii) it generates employment,
and (iii) it provides a market for the supporting industries and services. Likewise, an examination
of export statistics is useful in learning about the export possibilities of various products.
21
d. Study Plan Outlays and Governmental Guidelines. The government plays a very important
role in the economy of a country. Its proposed outlays in different sectors provide useful pointers
toward investment opportunities. They indicate the potential demand for goods and services
required by different sectors of the economy.
A very valuable source of information to estimate the scope for further investment is the
Guidelines to Industries published annually by the Development Ministry Agency, Government
of India. This publication provides information about the structure and location, production
performance, licensed and installed capacity, exports, and future scope of various industries.
While the government projections are often a good starting point, they must be viewed with
some caution. Often they are not well-grounded. It is helpful to remember the words of Alvin
Hanson: “No one reading the plans can fail to be impressed by the frequent unrealism of these
assumptions. So much appears to be contingent on the realization of the unrealizable.”
f. Investigate Local Materials and Resources A search for project ideas may begin with an
investigation into local resources and skills. Various ways of adding value to locally available
materials may be examined. Similarly, the skills of local artisans may suggest products that may
be profitably produced and marketed.
The National Council of Applied Economic Research (NCAER) and other bodies publish
surveys of various regions showing the potential of industrial development in various regions.
These surveys assess the resources (human and material), infrastructural facilities, and markets
for various products.
g. Analyze Economic and Social Trends A study of economic and social trends is helpful in
projecting demand for various goods and services. Changing economic conditions and consumer
preferences provide new business opportunities. For example, a greater awareness of the value
of time is dawning on the public. Hence, the demand for time-saving products like prepared food
items, ovens, and powered vehicles has been increasing. Another change that can be seen is the
increasing desire for leisure and recreational activities. This has caused a growth in the market
for recreational products and services.
22
i. Draw Clues from Consumption Abroad. Entrepreneurs willing to take higher risks may
indentify projects for the manufacture of products or supply of services which are new to the
country but extensively used abroad. Automatic vending machines, entertainment parks, pre-
fabricated houses, and fast food restaurants are examples of projects belonging to this category.
j. Explore the Possibility or Reviving Sick Units. Industrial sickness is rampant in the
country. There are innumerable units which have been characterized as sick. These units are
either closed or face the prospect of closure. A significant proportion of sick units, however, can
be nursed back to health by sound management, infusion of further capital, and provision of
complementary inputs. Hence, there is a fairly good scope for investment in this area. Such
investments typically have a shorter gestation period because one does not have to begin from
scratch. Indeed, in many cases marginal efforts would suffice to revive such units.
l. Attend Trade Fairs. National and international trade fairs provide an excellent opportunity to
get to know about new products and developments.
m. Stimulate Creativity for Generating New product Ideas New product ideas may be
generated by thinking along the following lines: Modification, Rearrangement, Reversal,
Magnification, Reduction, Substitution, Adaptation, and Combination.
n. Chance. Hope that the chance factor will favor you. Identification of investment opportunity
may be influenced by the chance factor. Two examples may be given here.
23
Reasonableness of cost
Acceptability of risk level
The idea must be compatible with the interest, personality, and resources of the entrepreneur.
According to Murphy, a real opportunity has three characteristics: (i) It fits the personality of the
entrepreneur-it squares with his abilities, training , and proclivities. (ii) It is accessible to him.
(iii) It offers him the prospect of rapid growth and high return on the invested capital.
It may be noted here that Indian business has been traditionally faced with (i) shortages of certain
inputs like power, foreign exchange, and important raw materials, and (ii) fluctuating supplies of
agricultural raw materials like cotton, jute and seeds. Of course, in recent times, the situation has
improved in some ways :(i) power generation has increased significantly, (ii) foreign exchange is
now available more easily, and (iii) supplies of certain basic industrial raw materials have been
augmented substantially. However, the supply situation of power, coal, and transport facilities
still leaves much to be desired.
The size of the present market must offer the prospect of adequate sales volume. Further, there
should be a potential for growth and a reasonable return on investment. To judge the adequacy
of the market, the following factors have to be examined:
Total present domestic market
Competitors and their market shares
24
Export markets
Quality-price profile of the product vis-à-vis competitive products
Sales and distribution system
Projected increase in consumption
Barriers to the entry of new units
Economic, social, and demographic trends favorable to increased consumption
Patent protection
It may be emphasized here that barring recessionary aberrations, the demand for most of the
products in India has been growing secularly. This trend will continue because of the low levels
of per capita consumption in India. Fortunately, from the point of view of entrepreneurs, the
Indian economy unlike most developed, Western economies, is not a “share shift” economy
wherein the growth in demand for a product is likely to be at the expense of the demand for
others.
v. Reasonableness of Cost
The cost structure of the proposed project must enable it to realize an acceptable profit with a
price. The following should be examined in this regard:
Cost of material inputs
Labor cost
Factory overheads
General administration expenses
Selling and distribution costs
Service cost
Economies of scale
25
Rate the project proposal on various factors using a suitable rating scale. (typically a 5-
point scale or a 7-point scale is used for this purpose.)
For each factor, multiply the factor rating with the factor weight to get the factor score.
Add all the factor scores to get the overall project rating index.
Table 2.1. illustrates the determination of the project rating index. Once the project rating index
is determined, it is compared with a pre-determined hurdle value to judge whether the project is
prima facie worthwhile or not.
Table 2.1. Project Rating Index
Factor Factor V G A P VP Factor
Weight G 4 3 2 1 Score
5
Input availability 0.25 x 0.75
Technical Know-how 0.10 x 0.40
Reasonableness of cost 0.05 x 0.20
Adequacy of market 0.15 x 0.75
Complementary relationship with 0.05 x 0.20
other products
Stability 0.10 x 0.40
Dependence on firm’s strength 0.20 x 1.00
Consistency with government 0.10 x 0.30
priorities
Rating Index = 4.00
After the project rating index is determined it will be compared with the predetermined hurdle
number. Assume the predetermined hurdle number is 3. The project under consideration
worthwhile as the rating index is greater than the predetermined hurdle number, otherwise it will
be not worthwhile.
26
barriers is helpful in identifying positive NPV projects. It appears that there are six main entry
barriers that result in positive NPV projects. They are as follows:
i. Economies of Scale. Economies of scale means that an increase in the scale of production,
marketing, or distribution results in a decline in the cost per unit.. when substantial economies of
scale are present, the existing firms are likely to be large in size. The more pronounced the
economies of scale, the greater the cost advantage of the existing firms. In order to exploit the
economies of scale, new entrants require a substantial investment in plant and machinery,
research and development, and market development. Such capital needs serve as an entry barrier.
The greater the capital requirement, the higher the barrier to entry. This seems to be especially
true in industries like petroleum refining , mineral extraction, iron and steel, and aluminium.
ii. Product Differentiation. A firm can create an entry barrier by successfully differentiating its
products form those of its rivals. The basis for differentiation may be one or more of the
following:
Effective advertising and superior marketing
Exceptional service
Innovative product features
High quality and dependability
iii. Cost Advantage. If a firm can enjoy cost advantages vis-à-vis its competitors, it can be
reasonably assured of earning superior returns. Cost advantage may stem from one or more of
the following:
Accumulated experience and comparative edge on the learning curve
Monopolistic access to low cost materials
A favorable location
More effective cost control and cost reduction
27
Reddy’s Laboratory and Hero Honda have performed well because of their technological
strength.
vi. Government Policy. A government policy which shelters a firm from the onslaught of
competition enables it to earn superior returns. Government policies that create entry barriers,
partial or absolute, include the following:
Restrictive licensing
Import restrictions
High tariff walls
Environmental controls
Special tax reliefs
A number of firms in India benefited substantially from restrictive government policies which
offered considerable protection to them from potential competition, domestic as well as foreign,
for many years. The liberalization measures of recent years have, of course, dismantled, partly or
substantially entry barriers stemming from earlier government policies. Remember that what the
government can give, it can also take away.
[
Activity 3.
1. What are the tools for identifying investment opportunities?
__________________________________________________________
________________________________________________________
2. What are some of the suggestions to identify some of project ideas?
__________________________________________________________
________________________________________________________
3. What are the aspects we need to look into in the preliminary selection of
projects?
__________________________________________________________
________________________________________________________
4. What are the sources of positive NPV?
__________________________________________________________
________________________________________________________
2.5. On Being an Entrepreneur
28
(i) Are my goals well defined?
Personal aspirations
Business sustainability and size
Tolerance for risk
(ii) Do I have the right strategy?
Clear definition
Profitability and potential for growth
Durability
Rate of growth
(iii) Can I execute the strategy
Resources
Organizational infrastructure
The founder’s role
Willingness to Make Sacrifices. A new venture is often plagued with numerous difficulties
and unanticipated problems. To nurture it in such an inhospitable environment, the entrepreneur
has to be prepared to sacrifice his time, energy, and resources. He must be willing to struggle,
sacrificing personal comforts and conveniences, against seemingly endless odds. An
entrepreneurial job is not like a typical nine-to-five executive job. It tends to be far more
demanding, requiring total commitment and, sometimes, even obsessive preoccupation on the
part of the entrepreneur.
Leadership. Successful entrepreneurs generally have strong leadership qualities. They are able
to inspire ordinary persons to accomplish great feats. Even though outwardly they may show
bizarre signs (they may be whimsical, timid, or even cantankerous) they are able to fire people
with their zeal. They have the flair for galvanizing their team to successfully cope with the
challenges and frustrations inherent in a new venture.
29
enormous burden of decisions making. If he procrastinates, he may court disaster. If he dilly-
dallies, he may miss valuable opportunities. The fluid situation of a new enterprise calls not only
for an ability to decide quickly but also an ability to revise the decisions to adapt the enterprise to
an environment in which it has not established proper moorings.
Confidence in the project. An entrepreneur should have unbounded faith in his project. This
helps him in instilling confidence in supplier, creditors, costumers, employees, and others.
Without unflinching conviction in the project, it would be difficult for the entrepreneur to
withstand the failures and frustrations that form the new venture diet.
Strong Ego. Setting up a new enterprise is like riding an emotional roller coaster. There are
days which bring jubilation and there are days which cause despondency, as the enterprise is
buffeted by environmental forces, which tend to have a strong influence on the nascent venture.
The entrepreneur needs a strong ego to bear with such ups and downs. To endure periods of
adversity and to maintain a proper perspective when events cast a shadow over the enterprise, the
entrepreneur needs a strong identify and self image.
30
Basically, a promising investment ideas enable a firm (or the entrepreneur) to exploit
opportunities in the environment by drawing on its competitive strengths. Hence, the firm must
systematically monitor the environment and assess its competitive abilities. For purposes of
monitoring, the business environment may be divided into six broad sectors. The important
aspects studied in monitoring the key sectors of the environment are as follows:
Economic Sector
State of the economy
Overall rate of growth
Growth rate of primary, secondary, and tertiary sectors
Cyclical fluctuations
Linkage with the world economy
Trade surplus/ deficits
Balance of payment situation
Governmental Sector
Industrial policy
Government programmes and projects
Tax framework
Subsidies, incentives, and concessions
Import and export policies
Financing norms
Lending conditions of financial institutions and commercial banks
Technological Sector
Socio-Demographic Sector
Population trends
Age shifts in population
Income distribution
Education profile
Employment of women
Attitudes toward consumption and investment
Competition Sector
Number of firms in the industry and the market share of the top few (four or five)
Degree of homogeneity and differentiation among products
Entry barriers
Comparison with substitutes in terms of quality, price, appeal, and functional
performance
31
Marketing policies and practices
Supplier Sector
Availability and cost of raw materials and sub-assemblies
Availability and cost of energy
Availability and cost of money
Corporate Appraisal
A realistic appraisal of corporate strengths and weaknesses is essential for identifying investment
opportunities which can be profitably exploited. The broad areas of corporate appraisal and the
important aspects to be considered under them are as follows:
32
Cost of capital
Tax situation
Relations with shareholders and creditors
Accounting and control system
Cash flows and liquidity
UNIT THREE
PROJECT FEASIBILITY STUDY
Some investment proposals pass through a stage of checking out the feasibility. Large projects
usually need feasibility test to be carried out before a handsome amount is committed. A
feasibility study is part of the process of project identification, preparation and selection. This
process involves the appraising of projects or groups of projects and choosing to implement
some of them. Feasibility literally means whether some idea will work or not. It knows
beforehand whether there exists a sizeable market for the proposed product/service, what would
be the investment requirements and where to get the funding from, whether and wherefrom the
necessary technical know-how to convert the idea into a tangible product may be available, and
so on. In other words, feasibility study involves an examination of the operations, financial, HR
and marketing aspects of a business on ex ante (before the venture comes into existence) basis.
Feasibility is a multivariate concept; that is, a project has to be viable not only in technical terms
but also in economic and commercial terms too. Moreover, there always a possibility that a
33
project that is technically possible may not be economically viable. After the problems of an
organization or economy have been determined and objectives and strategies agreed, concrete
steps have to be taken. The main form this takes is that of formulating appropriate development
projects to achieve plan objectives and meet the development needs of the economy. Proposals
relating to them are then put to the plan authorities for consideration and inclusion in the plan.
These proposals as pointed out above take the following forms of feasibility studies:
1. Market/Commercial viability
2. Economic feasibility
3. Financial feasibility
4. Technical feasibility
5. Social Cost Benefit analysis
6. Other feasibility considerations like legal, administrative, ecological
When projects are evaluated by government or government agencies, economic and social
feasibility is also considered. Market feasibility is also emphasized, but technical and financial
feasibility is less emphasized. The scope for scrutiny under each of these five heads would
necessarily render their careful assessment and the examination of all possible alternative
approaches. The process almost invariably involves making decision relating to technology,
scale, location, costs and benefits, time of completion (gestation period), degree of risk and
uncertainty, financial viability, organization and management, availability of inputs, know-how,
labor etc. The detailed analysis is set down in what is called a feasibility report.
3.1Market feasibility
A market, whether a place or not, is the arena for interaction among buyers and sellers. From
seller’s point of view, market analysis is primarily concerned with the aggregate demand of the
proposed product/service in future and the market share expected to be captured. Success of the
proposed project clearly hinges on the continuing support of the customers. However, it is very
difficult to identify the market for one’s product/service. After all, the whole universe cannot be
your market. You have to carefully segment the market according to some criteria such as
geographic scope, demographic and psychological profile of the potential customers etc. It is a
study of knowing who all comprise your customers, for this you require information on
consumption trends, past and present supply position, production possibilities and constraints,
imports and exports, competition, cost structure, elasticity of demand, consumer behavior,
intentions, motivations, attitudes, preferences and requirements, distribution channels and
marketing policies in use, administrative, technical and legal constraints impinging on the
marketing of the product.
The exercise of project appraisal often begins with an estimation of the size of the market.
Before a detailed study of a project is undertaken, it is necessary to know, at least roughly, the
size of the market because the viability of the project depends critically on whether the
anticipated level of sales exceeds a certain volume. Many projects have been abandoned because
preliminary appraisal revealed a market of inadequate size.
34
Requirements for market and demand analysis
A. Information requirement
The principal types of information required for market and demand analysis relate to:
1. Effective demand: to gauge the effective demand in the past and present, the starting point
typically is apparent consumption which is defined as:
35
a) Demographic and sociological information-, information on: age, sex, income,
avocation, residence, religion, customs, beliefs, and social background, and
b) Attitudinal information- information on - preferences, intentions, attitudes, habits, and
responses.
E. Governmental policy: the role of government in influencing the demand and market for a
product may be significant. Governmental plans, policies, legislations, and fiats which have a
bearing on the market and demand of the product under examination should be studied.
These are reflected in: production targets in national plans, import and export trade controls,
import duties, export incentives, excise duties, sales tax, industrial licensing, preferential
purchases, credit controls, financial regulations, and subsidies/penalties of various kinds.
F. Supply and competition: it is necessary to know the existing sources of supply and whether
they are foreign or domestic. For domestic sources of supply information along the following
lines may be gathered: location, present production capacity, planned expansion, capacity
utilization level, bottlenecks in production, and cost structure. Competition from substitutes
and near-substitutes should be examined because almost any good may be replaced by some
other good as a result of changes in relative prices, quality, availability, promotional
strategies, consumer taste, and other factors.
Demand estimation
The first and most difficult step in market feasibility analysis is determining the potential
demand for the product or the service we are intending to produce/render. There are different
methods of estimation.
A. Market survey
The information sought in a market survey may relate to one or more of the following;
(i) Total demand and rate of growth of demand;
(ii) Demand in different segments of the market;
(iii) Income and price elasticity of demand;
(iv) Motives for buying;
(v) Purchasing plans and intentions;
(vi) Satisfaction with existing products;
(vii) Unsatisfied needs;
(viii) Attitudes toward various products
(ix) Distributive trade practices and preferences;
(x) Socio-economic characteristics of buyers.
36
B. Demand forecasting
After gathering information about various aspects of the market and demand from primary and
secondary sources, an attempt may be made to estimate future demand. Several methods are
available for demand forecasting. The important ones are qualitative and quantitative methods.
Qualitative Methods
Qualitative or judgmental forecasting does not rely on numbers to conclude forecast, but rather
on intangible factors. This method is especially common when sufficient historical data is not
available, i.e., for a new business or a less-established market environment. Groups whose
judgment is normally surveyed in preparing a qualitative forecast include the experts in the field,
the sales force and the customers. Combining historical data with the judgment of people or
groups presumed to have superior knowledge of sales only adds to the reliability and integrity of
a company's sales forecast. Some of the identified qualitative methods of sales forecasting are
Delphi method and Jury of Executives Opinion methods. These methods rely essentially on the
judgment of experts to translate qualitative information into quantitative estimates.
This method, which is very popular in practice, involves soliciting the opinions of a group of
managers on expected future sales and combining them into a sales estimate. The advantages of
this method are: (1) It is an expeditious method for developing sales forecast; (2) it permits a
variety of factors like economic climate, competitive environment, consumer preferences,
technological developments, and so on, to be included in the subjective estimates provided by the
experts and, (3). it has an immense appeal to managers who tend to prefer their judgment to
mechanistic forecasting procedures. The disadvantages of this method are: (1) the biases
underlying subjective estimates cannot be unearthed easily; (2) the reliability of this technique is
questionable.
This method is used for eliciting the opinions of a group of experts with the help of a mail
survey. The steps involved in this method are:
1. A group of experts is sent a questionnaire by mail and asked to express their views.
2. The responses received from the experts are summarized without disclosing the identity of
the experts, and sent back to them along with a questionnaire meant to probe further the
reasons for the extreme views expressed in the first round.
3. The process may be continued for one or more rounds till a reasonable agreement emerges
in the view of the experts.
Delphi method appeals too many organizations for the following reasons: (1) it is intelligible to
users; (2) it seems to be more accurate and less expensive than the traditional face-to-face group
meetings. While the Delphi method is appealing, there are certain questions it doesn’t answer.
37
What is the value of the expert opinion? What is the contribution of additional round and
feedback to accuracy?
Quantitative Methods
A. Time Series Methods: these methods generate forecasts on the basis of an analysis of the
historical time series. The important time series projection methods are trend projection methods,
exponential smoothing method and moving average method.
When the trend projection method is used, the most commonly employed relationship is the
linear relationship. Trend projection: it consists of determining the trend of consumption by
analyzing past consumption statistics, and projecting future consumption by extrapolating the
trend. The trend of consumption may be represented by one of the following relationships:
Linear Relationship: Yt = a + bt
Where; Yt = demand for year t,
t = the time variable,
a = intercept of the relationship
b = slope of the relationship
a, b and aj’s are constants.
This relationship may be estimated by using one of the following methods visual curve fitting
method and least squares method.
1. Consumption level method:
Useful for a product which is directly consumed, this method estimates consumption level on the
basis of elasticity coefficients, the important ones being the income elasticity of demand and the
price elasticity of demand.
a) Income elasticity of demand— The income elasticity of demand reflects the
responsiveness of demand to variations in income. It is measured as follows:
Q2−Q1
∗I 1+ I 2
I 2−I 1
Y=
Q 1+ Q2
38
Where; Y = income elasticity of demand
Q1 = quantity demanded in the base year
Q2 = quantity demanded in the following year
l1 = income level in the base year
l2 = income level in the following year
b) Price elasticity of demand - The price elasticity of demand measures the responsiveness
of demand to variations in price. It is defined as:
Q2−Q1
∗P 1+ P 2
P2−P1
Y=
Q 1+Q 2
Where, Ep = price elasticity of demand
Q1 = quantity demanded in the base year
Q2 quantity demanded in the following year
P1 = price per unit in the base year
P2 = price per unit in the following year
c) End use method
Suitable for estimating the demand for intermediate products, the end use method, also referred
to as the consumption coefficient method involves the following steps:
1. Identify the possible uses of the product.
2. Define the consumption coefficient of the product for various uses.
3. Project the output levels for the consuming industries.
4. Derive the demand for the product
d) Leading Indicator Method
Leading indicators are variables which change ahead of other variables, the lagging variables.
Hence, observed changes in leading indicators may be used to predict the changes in lagging
variables. For example, the change in the level of urbanization- a leading indicator may be used
to predict the change in the demand for air conditioners a lagging variable. Two basic steps are
involved in using the leading indicator method:
(i) First, identify the appropriate leading indicator(s).
(ii) (ii) Second, establish the relationship between the leading indicator(s) and the variable
to be forecast.
e) Market penetration for the product: once a reasonably good handle over the aggregate
demand is obtained, the next logical question is: What will be the likely demand for the
product of the project under examination? The answer to this question depends on ggregate
potential supply, nature of competition, consumer preferences and sales promotion efforts.
If the aggregate potential domestic supply is likely to be significantly less than the
aggregate potential domestic demand, the demand for the product of the project under
examination is likely to be very strong, provided liberal imports which may hurt domestic
manufacturers are not allowed.
The nature of competition and market-sharing arrangement (if any) has a bearing on the
demand for the product of the project under examination.
39
Consumer preferences for competing products and the sales promotional efforts of
various competitors obviously influence the relative market shares enjoyed by them.
The promoter should be capable of creating a profile of the organization’s ideal customer. The
promoter must ask themselves: Who is our target customer? Am I operating as a Business to
Customer or Business to Business enterprise? What are our ideal customers’ sex, age, income
level and interests? Is there a distinction between our buyer and our end user? What are the target
customer segments (geographic, demographic, psychographic and behavioral)? What
products/services are they already using? On what factors are buying decisions made?
Apart from the cost-benefit analysis as above, which we also refer to as private cost-benefit
analysis, it is also useful to do what is known as social- cost-benefit- analysis (SCBA). For
example, the entrepreneur may be getting subsidized electricity in which case private cost would
be less than social cost. Likewise, exporting units earn precious foreign exchange resulting into
social benefits being more than private earnings. Many a time, a project that is worthy on SCBA
may find greater favor with the support agencies. This tells us that there is a huge overlap
between economic feasibility for a private project and financial feasibility and social cost-benefit
analysis of a developmental project. Hence the specific considerations and technical issue of this
part of the analysis will be covered in the subsequent sub-sections.
40
project will satisfy the return expectations of those who provide the capital. Capital budgeting is
a required managerial tool for project appraisal. One duty of a financial manager is to choose
projects with satisfactory cash flows and rates of return. Therefore, a financial manager must be
able to decide whether a project is worth undertaking and be able to choose intelligently between
two or more alternatives. To do this, a sound procedure to evaluate, compare, and select projects
is needed. This procedure is called capital budgeting.
In the form of either debt or equity, capital is a very limited resource. There is a limit to the
volume of credit that the banking system can create in the economy. Commercial banks and
other lending institutions have limited deposits from which they can lend money to individuals,
corporations, and governments. In addition, the Federal Reserve System requires each bank to
maintain part of its deposits as reserves. Having limited resources to lend, lending institutions
are selective in extending loans to their customers. But even if a bank were to extend unlimited
loans to a company, the management of that company would need to consider the impact that
increasing loans would have on the overall cost of financing.
In reality, any firm has limited borrowing resources that should be allocated among the best
project alternatives. One might argue that a company can issue an almost unlimited amount of
common stock to raise capital. Increasing the number of shares of company stock, however, will
serve only to distribute the same amount of equity among a greater number of shareholders. In
other words, as the number of shares of a company increases, the company ownership of the
individual stockholder may proportionally decrease.
The argument that capital is a limited resource is true of any form of capital, whether debt or
equity (short-term or long-term, common stock) or retained earnings, accounts payable or notes
payable, and so on. Even the best-known firm in an industry or a community can increase its
borrowing up to a certain limit. Once this point has been reached, the firm will either be denied
more credit or be charged a higher interest rate, making borrowing a less desirable way to raise
capital. Faced with limited sources of capital, management should carefully decide whether a
particular project is economically acceptable. In the case of more than one project, management
must identify the projects that will contribute most to profits and, consequently, to the value (or
wealth) of the firm. This, in essence, is the basis of capital budgeting.
41
5 Accept the project if PV of inflows > costs. IRR > Hurdle Rate and/or payback < policy
Basic Data
Expected Net Cash Flow
Year Project L Project S
0 ($100) ($100)
1 10 90
2 60 30
3 80 50
Evaluation Techniques:
A. Payback period and discounted pay-back period
B. Net present value (NPV)
C. Internal rate of return (IRR)
D. Profitability index
Payback Period (PBP): Payback period refers to the length of time it takes to recover initial
investment of the project. Depending on the nature of net cash flows, payback period may be
computed in two ways.
a) When cash flow is in annuity form:Annuity refers to equal amount of cash flows that occur
every period over the life of the project
Initial Investment
PBP = Annual Net Cash Flows
b) When cash flows are not in annuity form
When net cash flows are not annuity, payback period is obtained by adding net cash flows for
successful years until the total is equal to initial investment.
Payback period = Expected number of years required to recover a project’s cost.
Expected Net Cash Flow
Year Project L Project S
0 ($100) ($100)
1 10 90
2 60 30
3 80 50
Since the payback period rule ignores the time value of money, some firms have modified it to
reflect the time value of money. This is the discounted payback period. This technique specifies
that the cash flow from each period has to be discounted appropriately by the firm’s cost of
capital (i.e. a risk-adjusted WACC).
42
Given a 10% weighted average cost of capital, the payback period will be:
Year Project L Project S
Cash flow Discounted cash flow Cash flow Discounted cash
0 ($100) ($100) ($100) flow
($100)
1 10 9.09 90 81.82
2 60 49.59 30 24.79
3 80 60.12 50 66.55
Net Present Value Method: The net present value of project is the difference between the
present value of net cash inflows and present value of initial investment.
n
CFt
NPV = ∑ (1 + k) t
t =0
0 1 2 3
100.00 10 60 80 Project L:
9.09
49.59
60.12
NPVL = $ 18.79
NPV-S = $73.16
Decision: If the projects are independent, accept both. If the projects are mutually exclusive,
accept Project S since NPVS > NPVL.
Note: NPV declines as k increases, and NPV rises as k decreases.
Internal Rate of Return (IRR)
Internal Rate of Return is the discount rate which equates the project NPV equal to zero. It is the
discount rate at which the present value of Net cash flows is equal to the present value of initial
43
investment. In other words, IRR is the rate of return on investments in the project. The
determination of IRR is purely based on project cash flows. Mathematically, at IRR,
n Ct
∑ ( 1+ r )t = Initial investment
i=1
IRR is determined using trial and error: the complexity of determining IRR is greater if net cash
flows are not in annuity form. This section illustrates the determination of net cash flows when
cash flows are annuity as well as non-annuity.
n
CFt
IRR: ∑ ( 1 + IRR ) t = $0 = NPV
t=0
0 1 2 3
-100.00 10 60 80
18.1% Project L:
8.47 18.1%
43.02
48.57 18
$ 0.06 $0
IRRL = 18.1%
IRRS = 38%
Decision: If the projects are independent, accept both because IRR > k. If the projects are
mutually exclusive, accept Project S since IRRS > IRRL. Also Note also that IRR is independent
of the cost of capital.
Advantages and Disadvantages of IRR AND NPV
Advantages
A number of surveys have shown that, in practice, the IRR method is more popular than the NPV
approach. The reason may be that the IRR is straightforward, and it uses cash flows and
recognizes the time value of money, like the NPV. In other words, while the IRR method is easy
and understandable, it does not have the drawbacks of the ARR and the payback period, both of
which ignore the time value of money.
Disadvantages
The main problem with the IRR method is that it often gives unrealistic rates of return. Suppose
the cutoff rate is 11% and the IRR is calculated as 40%. Does this means that the management
should immediately accept the project because its IRR is 40%.? The answer is no! An IRR of
44
40% assumes that a firm has the opportunity to reinvest future cash flows at 40%.If past
experience and the economy indicate that 40% is an unrealistic rate for future projects, an IRR of
40% is suspect. Simply speaking, an IRR of 40% is too good to be true! So unless the
calculated IRR is a reasonable rate for project of future cash flows, it should not be used as a
yardstick to accept or reject a project.
Another problem with the IRR method is that it may give different rates of return. Suppose there
are two discount rates (two IRRs) that make the present value equal to the initial project. In this
case, which rate should be used for comparison with the cutoff rate? The purpose of this
question is not to resolve the cases where there are different IRRs. The purpose is to let you
know that the IRR method, despite its popularity in the business world, entails more problems
than a practitioner may think.
IRR Vs NPV k NPVL NPVS
NPV 0% $50 $40
($) 5 33 29
50 10 19 20
15 7 12
20 (4) 5
40
20 IRRS = 23.6%
10
0
5 10 15 20 25 k(%)
[ PI =
PV of Cash Flows
Initial Investment ]
45
In this method, a project with a PI greater than 1 is accepted, but a project is rejected when its PI
is less than 1. Note that the PI method is closely related to the NPV approach. In fact, if the net
present value of a project is positive, the PI will be greater than 1. On the other hand, if the net
present value is negative, the project will have a PI of less than 1. The same conclusion is
reached, therefore, whether the net present value or the PI is used. In other words, if the present
value of cash flows exceeds the initial project, there is a positive net present value and a PI
greater than 1, indicating that the project is acceptable. PI is also known as a benefit/cash ratio.
Project L
0 10% 1 2 3
-100.00 10 60 80
PV1 9.09
PV249.59
PV360.11
118.79
[ PI =
PV of cash flows
initial coast ]
118. 79
= = 1.10
100
Focus on incremental cash flows. The point of the whole analytical exercise is to judge
whether the firm will be better off or worse off if it undertakes the project. Thus one wants to
focus on the changes in cash flows affected by the project.
The analysis may require some careful thought: a project decision identified as a simple go/no-go
question may hide a subtle substitution or choice among alternatives. For instance, a proposal to
invest in an automated machine should trigger many questions: Will the machine expand
capacity (and thus permit us to exploit demand beyond our current limits)? Will the machine
reduce costs (at the current level of demand) and thus permit us to operate more efficiently than
before we had the machine? Will the machine create other benefits (e.g., higher quality, more
46
operational flexibility)? The key economic question asked of project proposals should be, “How
will things change (i.e., be better or worse) if we undertake the project?”
Account for time. Time is money. We prefer to receive cash sooner rather than later. Use NPV
as the technique to summarize the quantitative attractiveness of the project. Quite simply, NPV
can be interpreted as the amount by which the market value of the firm’s equity will change as a
result of undertaking the project.
Account for risk. Not all projects present the same level or risk. One wants to be compensated
with a higher return for taking more risk. The way to control for variations in risk from project
to project is to use a discount rate to value a flow of cash that is consistent with the risk of that
flow. These 4 precepts summarize a great amount of economic theory that has stood the test of
time. Organizations using these precepts make better project decisions than organizations that do
not use these precepts.
CAPITAL RATIONING
Exists whenever enterprises cannot, or choose not to, accept all value-creating project projects.
Possible causes may be: banks and investors say “NO” and managerial conservatism. Analysis is
required. One must consider sets of projects, or “bundles”, rather than individual projects. The
goal should be to identify the value-maximizing bundle of projects. The danger is that the
capital-rationing constraint heightens the influence of nonfinancial considerations, such as the
following:
Competition among alternative strategies
Corporate politics
Bargaining games and psychology
The outcome could be a sub-optimal capital budget, or, worse, one that destroys value!
Some remedies are the following: Relax and eliminate the budget constraint; Manage the process
rather than the outcomes; Develop a corporate culture committed to value creation.
The technical aspects of a typical project idea can be scrutinized in detail to evaluate its technical
feasibility, as distinct from commercial, financial, economic and managerial feasibility. For the
sake of comprehensiveness we will cover Environmental Impact Analysis (EIA) also, as a part of
this analysis. While the various aspects to be examined will obviously vary from project to
project, the following summary covers the more common ones briefly.
3.4.1. Objectives:
First, the project proposal must fall within the ambit of the stated mission of the sponsor(s).
Next, the proposal must be able to further the objectives and priorities of the sponsor(s). These
must therefore be ascertained and clearly recorded, along with detailed specifications for the
output which constitute the basic frame of reference for all future decisions. The private sector
would usually expect a project to earn a high enough profit, i.e. a stated level of return on
47
investment. Only for core projects (which are intended to basically support other highly
profitable projects) may this requirement be relaxed. The public sector generally has multiple
objectives and profitability normally takes a back seat. In either case, it is essential for the project
analyst to keep the organization’s objectives - a along with their interest priorities - in sharp
focus, to ensure that his/her efforts follow the correct direction.
3.4.2. Location and site
Initially, as many locations as possible should be identified which meet the most fundamental
operational requirements of the proposed project. These should then be evaluated and an
optimum location selected using the criteria of material versus market orientation, quality
standards, infrastructural status, local laws, and socio-economic and living conditions.
Within the geographical location so selected, alternative sites are similarly identified and the
most optimal one selected after considering factors like terrain, local climate land its impact on
plant & equipment and their operation, availability and cost of land (plus its development), local
infrastructural facilities and their costs (power; water: road/ air/water transport;
telecommunications; etc.), socio-economic conditions, availability and quality of labour and
construction equipment, valid waste disposal alternatives and their costs, local living conditions,
public policies, local law, and taxes, etc.
Note: Resource-oriented projects like mining of minerals involve items like geological analysis
covering geological structure, hydrological conditions, characteristics of the resource, resource
reserves, prospecting status, and expected geological problems.
The location decision should be made after giving due consideration to various benefits and
incentives offered by governments or local bodies for setting up production or service facilities
in certain specified areas. These may include assistance in the form of or in respect of capital
loans and grants, tax, concessions, clearances, subsidies, infrastructure, etc. One way to do
this is to evolve (or use available). Location Cost Indices (LCI) for different sites. If the cost (in a
specified currency) of setting up a plant is CA at location A and CB at location B, the LCI for
location A is defined as 100 x CA/CB. If reliable values of LCI for different locations, whether
within one or more countries, are available, the selection of an appropriate location becomes a bit
easier. Such valuable information is however kept a closely guarded secret by a consulting
company and is therefore difficult to come by.
Plant Size
Determination of an optimum plant size is critical to the success of a project. A plant represents
sunk costs and any under utilization of its capacity means either reduced profits or, for levels
below the Break-Even Point, losses. The adverse impact of an extra-large capacity is felt all the
more keenly during the early years when profits are all the more important for survival. It is
therefore normally better to err on the lower side and to build a plant having a capacity that is
likely to be fully utilized quickly, rather than to go in for a large capacity in the fond hope of a
growing share of the market. In a feasibility study, one-begins by looking 'at projections of the
demand-supply gap in the market and anticipated arrives' at the possible range of project sizes
after considering various constants like availability of materials, technology, equipment, public
48
policy (for example, a large company may be precluded from setting up capacities beyond a size)
and finances, etc.. The best possible size of plant & equipment is then recommended after
analyzing the availability, economics, and practicability of different size options.
Technology
The same product or service can generally be obtained using quite different technologies.
Electricity, for example, can be generated using solar panels, coal (thermal plants), hydraulic
power plants, and nuclear power plants and so on. Basic telephone Sol-vices can similarly be
provided using manual, semiautomatic, or automatic exchanges. And, even the last-named
category is available if] various technological versions like Stronger, Crossbar, Analogue
electronic and Digital electronic. Needless to say, the latest technologies usually represent many
improvements over the existing or older ones. They may also offer certain unique features.
However, newly emerging technologies may have some inherent dangers as well.
What is important for formulating a successful project is to weigh available alternative
technologies and select the one that is most appropriate in the prevailing situation, rather than
blindly adopt the latest, state-of-the-art technology assuming that it will work since it works
elsewhere. A technology is considered appropriate only if it is assessed to be satisfactory, and
relevant, vis-à-vis the following aspects in lie specific situation of the project.
Specifications of the task/product
Task uncertainties and interdependence
[Especially for public sector] Developmental imperatives (e.g. growth of employment;
maximizing use of local resources; reduction of disparities in income levels)
Required gestation period versus the time actually available of the project.
Source(s) and ease of availability.
Indigenous availability of comparable technology
Field validation status in comparable situations. If necessary, field trials may have to be set
up.
Adaptability to the qualitative characteristics of the locally (or indigenously) available
resources including energy and efficiency in their usage
Dependence on nonrenewable sources of energy
Capacity of the organization to absorb/adopt the technology
Timely availability of manpower with requisite skills for installation, operation and
maintenance
Cost of' acquisition, installation, repairs and maintenance versus availability of funds
(local/foreign)
Safety characteristics
Requirement or availability of R & D facilities • Environmental and sociocultural
sensitivities
Likelihood, and time frame, of obsolescence
49
various facilities and list out all the major equipments needed, with key specifications and
available source(s) of supply. Moreover, it should consider, and evaluate alternative equipments
as well and give reasoned recommendations about them. The importance of thoroughness of
planning at this stage of the feasibility study can hardly be overemphasized. Many delays, cost
overruns, and even failures of projects can be avoided provided the design and physical
formulation of the project are based on a sufficiently deep analysis and have the support of the
owner at the highest level. Otherwise, the project is likely to encounter mid-steam changes, with
untoward consequences. There is a general impression that "minor" midstream changes would
not pose much of a problem. This is not so. A project is a multi-task entity with complex
linkages and interrelationships between its various constituents, and even "small" changes, which
may result in certain made-to-order procured equipments being rendered unsuitable and thus
throw the project schedule and costs haywire. The aim of all the efforts at this stage is to design a
viable operating entity which not only works, but works harmoniously (and with minimum costs)
in relation to the stipulated inputs and local environment. Apparent as well as latent and
relatively infrequent factors having a bearing on the effectiveness of the project must therefore
be identified and considered. Neglect of climatic and geographical aspects (e.g. monsoons,
floods, snowstorms, dust-storms, heat/cold-waves, earthquakes, typhoons, etc.) at this stage can
prove quite costly later on. It is equally important to ascertain and give due consideration to local
industrial and safety standards.
Construction Process
This needs to be tackled in the feasibility study in terms of its five aspects,
First, the methodology to be followed - viz., capital intensive or otherwise and its feasibility
under prevailing conditions. Second, whether the construction or installation is to be done in-
house, or on a turnkey basis, or by farming out a number of contracts for different work
packages, and their feasibility. A recommendation may also be made whether any special agency
(ies) should be engaged as a part of backup or contingency arrangements for critical activity
(ies). Third, the determination of such construction equipments, materials and other essential
inputs (like cement, sand, steel, stores etc.) as are to be arranged by the owner, along with their
alternatives, availability, source of supply (local/foreign), lead-times, and infra-structural
requirements (like uninterrupted supply of power, clean water, gas, steam, etc). Fourthly, the
recommended sequence and time schedule of different activities in the form of a bar-chart/PERT
network. Lastly, assessment of the financial implications of this phase based on the latest
available unit costs and with provision for inflation and contingencies.
Inputs
These relate to the operation phase of the project, but need to be identified at this stage of the
feasibility study to examine the technical feasibility of the proposed system(s). For this,
classification of the inputs into following categories will be found useful.
raw materials,
processed materials,
components & sub-assemblies,
spares and wear & tear parts,
water & steam,
50
gas, fuels and electricity.
Next, their qualitative and quantitative requirements (including buffer stocks, where applicable),
availability, feasibility alternatives and reliable sources of supply should be carefully ascertained
and record. The problems involved in their storage and handling should be also assessed.
Infrastructural Facilities
Availability and characteristics of roads, bridges, railway facilities (like station, yards), air
transportation, waterways, ports, etc. depending upon their relevance to the assessed
requirements of the project at both implementation and operation stages need to be studied. After
studying the appropriateness of the infrastructure existing around the project location, the
infrastructural requirements at the project site itself. A large part of the land area is normally
required to be reserved for service roads, storm water mains, railways, over-ground or overhead
gas, steam, and air pipelines, water reservoirs, and even harbors for certain large-scale industrial
projects. A detailed study of all such requirements and of their implications in terms of time,
resources, and approximate costs is necessary to avoid surprises later on.
Manpower
The availability in needed numbers, of manpower of requisite skills where and when required,
has to be studied. This covers both the project implementation and the operation (&
maintenance) phases. In case imparting of training is also involved, timely availability, and costs,
of the training facilities have also to be assessed.
For each of these, the resulting impacts, whether beneficial or otherwise, are then identified and a
detailed Environmental Management Plan (EMP) prepared for such mitigation, protection and/or
enhancement measures, as are considered necessary,
51
the costs, benefits, and effects of a project. Such appraisal is preformed for development and
infrastructure projects usually by emphasizing the economic, technical, operational, institutional,
and financial factors to ensure that the selected project meets all necessary requirements and is
implementable.
SCBA focuses on the following objectives:
To contribute effectively to GDP of an economy;
To aid in economic development;
To justify the utilization of economy’s scare of growth;
To maintain and protect environment from pollution;
To educate new lines of functioning that are simple and cost effective;
To benefit the rural poor and reduce regional imbalances;
To justify the risks undertaken to implement and the sacrifices made in the process.
Therefore, it is important to identify the major economic, environmental, social and other factors
a project may influence directly or indirectly. For instance, introducing a coal-fired power plant
in a location previously supplied with power over long transmission lines at great cost would
introduce economic benefits in terms of lower power costs, higher supply reliability and local
employment at the power plant and support activities. Similarly, economic costs might include
the use of local land for use of the power plant and coal handling or storage activities, air
pollution from both the plant and coal handling, ground water and soil pollution from both the
plant and coal handling, ground or storage activities, air pollution from coal washing and run-off,
temperature (heat) pollution from heat rejection of cooling water, congestion of roads and or rail
corridors, reduction of investment capital for other projects, commitment of local consumption,
and various other indirect costs. Some of the local costs are usually hidden under various
concessions given to public development projects, such as capital generation by use of tax-free
bonds, use of public land subsidizing local development constructions, etc.
The net benefits equation can be written as:
NB = α ( βγδ X −βM−γδ d )
Where α = weighing factor for exchange rate stability;
β = weighing factor for impact of protective practices;
γ = weighting factor for labor availability
δ = weighting factor for adequacy of support services
UNIDO - Guidelines for Project Evaluations released during early 70s
Fundamental focus of these guidelines is net increase in the aggregate consumption of an
economy due to the project output. Other subsidiary objectives are noted as:
Changes in the distribution of domestic income;
Changes in the savings and investment levels of a community;
Change in the labor market due to project implementation, etc.
Therefore, to survey the above objectives, the guidelines advocate the following steps for the
appraiser.
Identification of direct and indirect costs and benefits that affect the aggregate
consumption of an economy;
52
The consumption of the shadow prices of labor, foreign exchange, and investment;
The estimation of the social rate of discount, and also of relative weights to be attached to
the net benefits accruing to various groups in the economy if redistribution of income is
considered as separate objectives.
In a nutshell, the UNIDO guidelines base its arguments on:
The financial profitability of a project;
The net effect of costs and benefits on the economic situation of a country;
The opportunity cost of the investment;
The financial profitability which is similar to that used in normal commercial ventures based on
Discounted Cash Flow techniques and other standard financial management tools;
The concept of shadow prices that are associated with various types of goods and services dealt
in the project.
Diamond – Mirrleess Approach
Little and Mirrlees, through their pioneering efforts, interpret the problem of Least Developed
Countries (LDCs) as follows:
In an LDC, the foreign trade sector is considered as the public sector program. The public sector
projects are to be efficient by setting their prices equal to marginal costs. (P = MC – leaving to
room for loss). Under such a threshold pricing level only world prices should be used as ‘shadow
prices’. Distribution and efficiency be the twin important objectives of a government policy that
affects project performance. Therefore, shadow prices give risk to effect on social welfare of a
small change in quantity of an input or output. Its value depends on the welfare function being
used and the constraints imposed.
53
Ecological Feasibility
We have discussed Environmental Impact Analysis under the Technical analysis. When there are
serious ecological implications, it is worthwhile to have a separate and full-fledged ecological
feasibility. Ecological consideration is another issue to be covered in feasibility study. In recent
years, environmental concerns have assumed a great deal of significance especially for projects,
which have significant ecological implications like power plants and irrigation schemes, and for
environment polluting industries (like bulk drugs, chemicals and leather processing). The
concerns that are usually addressed include the following: What is the likely damage caused by
the project to the environment? What is the cost of restoration measures required to ensure that
the damage to the environment is contained within acceptable limits?
Legal and Administrative Feasibility
Legal and administrative feasibility is another element of the study. Clearances and Approvals:
Setting up of an industrial unit requires the entrepreneur to obtain a number of clearances and
approvals regarding land use, pollution control and safety. In this regard, you would be required
to interact with the local government authorities. Certain products may require specific
clearances from the relevant departments/authorities. Those are the issues we address under legal
and administrative clearance.
UNIT FOUR
PROJECT PLANNING
Introduction
Project Planning is foreseeing with blue print towards some predicated goals or ends. Project
plan is a skeleton which consists of bundle of activities with its future prospects; it is a guided
activity. It is a plan for which resources are allocated and efforts are being made to commence
the project with great amount of preplanning, project is a way of defining what we are hoping to
do about certain issue. The project alone is not responsible for what happens during the course of
a planning. Project is a final form of written documents that guides us as to what steps need to be
taken next.
54
4.1 Nature of project planning
One cannot conceive a project in a linear manner. It involves for activities, resources, constraints
and interrelationships which can be visualized easily by the human mind and planned informally.
However, when a project crosses a certain threshold level of size and complexities, informal
planning has to be substituted by formal planning. Besides that it is an open system oriented
planned change attempt which has certain parameters and dimension. So, the need for formal
planning is indeed much greater for project work than for normal operations. The pre-defined
and outlined in detail plan of action helps those manners to perform their task more effectively
and efficiently. There are always competing demands on the resources available in a region or a
country because of the limited availability and ever expanding human needs. Planning for the
optimum utilization of available resources becomes a pre requisite for rapid economic
development of a country or a region. Project planning makes a possible to list out the priorities
and promising projects with a view to exercising national choice among various alternatives
available. It is a tool by which a planner can identify a good project and to make sound
investments decisions.
4.2. Need for project planning
One of the objectives of project planning is to completely define all work requested so that it will
be readily identifiable to each project participant. Besides that there are four basic reasons for
project planning: To eliminate or reduce uncertainty, to improve efficiency of the operation, to
obtain a better understanding of the objectives, to provide a basis for monitoring and controlling
work.
4.3. Functions of project planning
The following functions are to be performed carefully in the Project Planning process. It should
provide a basis for organizing the work on the project and allocating responsibilities to
individuals. It is a means of communication and co-ordination between all those involved in the
project. It induces the people to look ahead. It instills a sense of urgency and time consciousness
It establishes the basis for monitoring and control. In planning a project, the project manager
must structure the work into small elements that are: Manageable, Independent, Integrated and
Measurable in terms of progress. Project planning must be systematic and flexible enough to
handle unique activities, disciplined through reviews and control and capable of accepting
multifunctional inputs.
55
subordinates. Planning is a systematic attempt to achieve a set of goals within the specified time
limit under the constraints of available resource restrictions involving the least sacrifice. Broadly
speaking planning involves two differences methodologies:
56
Planning the manpower and organizations: The manpower required for the project must
be estimated and the responsibility for carrying out the project work must be allocated.
Planning the money: the expenditure of money in a time-phased manner must be budgeted
Planning the information system: The information required for monitoring the project must
be defined
Standing plans: Standing plans are those plans which include policies, standard methods and
standard operation, procedures. They are designed to deal with recurring problems. It may be
treated as standard document to be used in different plans to deal with a set of problems. The
design procedure and steps are already described. It may require adjustment considering the unit
of operation.
Project planning begins with the end result, the goal and works backward. Often the focus of
project planning is on questions like who does what and when before such operational planning
is done, the objectives and policies guiding the project planning exercising must be articulated. If
the project team lacks a clear goal, even excellent skills and the best equipment will not enable
the team to do a good job. Well defined objectives and policies serve as the framework for the
decisions to be made by the project manager. Throughout the life of the project, he has to seek a
compromise between the conflicting goals of technical performance, cost standard and time
target. A clear articulation of the priorities of management will enable the project manager to
take expeditious actions.
An effective project goal has the following characteristics. These characteristics are captured in
the term SMART, an acronym for the aspects of a goal commitment. These characteristics of a
project goal are specific, measurable, agreed upon, realistic and time framed. The objectives of a
project may be: Technical objectives, Performance objectives, Time and cost goals. Policies are
the general guide for decision making on individual actions. Some of the policies of a project
are: Extent of work given to outside contractors, Number of contracts to be employed and Terms
of the contract etc. Project policies must be formulated on the basis of following principles:
It must be used upon the known principles in the operating areas;
It should be complementary for co-ordination
It should be definite, understandable and preferably in writing,
It should be flexible and stable,
57
It should be reasonably comprehensive in scope.
The project review dates are indicated by a vertical dotted line and at this time a horizontal line is
drawn beneath each bar to indicate the progress actually made up to that date. The length of the
progress line is then drawn to represent the percentage of the job that has been completed at the
review date. The merits and demerits of Gantt are below:
MERITS: 1. It is simple to understand
2. Is can be used to show progress
3. It can be used for manpower planning
58
4.10.2. Network techniques
The foundation of the approach came from the Special Projects Office of the US Navy in 1958. It
developed a technique for evaluating the performance of large development projects, which
became known as PERT - Project Evaluation and Review Technique. Other variations of the
same approach are known as the critical path method (CPM) or critical path analysis (CPA). The
heart of any chart is a network of tasks needed to complete a project, showing the order in which
the tasks need to be completed and the dependencies between them. This is represented
graphically:
The slack time or Total float for an activity is the time between its earliest and latest start time,
or between its earliest and latest finish time. Slack is the amount of time that an activity can be
delayed past its earliest start or earliest finish without delaying the project. The critical path is the
path through the project network in which none of the activities have slack, that is, the path for
which ES=LS and EF=LF for all activities in the path. A delay in the critical path delays the
project. Similarly, to accelerate the project it is necessary to reduce the total time required for the
activities in the critical path. Activity is an individual task needed for the completion of a
project. Duration is the length of time (hours, days, weeks, months) needed to complete an
activity. Float is the amount of time that an activity can slip past its duration without delaying
59
the rest of the project. Free float is the excess time available before the start of the following
activity.
Diagram Symbols
Dummy Activity: An imaginary activity that requires no time and is used to correctly maintain
the appropriate precedence relationships.
60
Critical path is the longest-duration path through the network. The significance of the critical
path is that the activities that lie on it cannot be delayed without delaying the project. Because of
its impact on the entire project, critical path analysis is an important aspect of project planning.
The critical path can be identified by determining the following four parameters for each activity:
Earliest Start time (ES): the earliest time at which the activity can start given that its precedent
activities must be completed first.
Earliest Finish time (EF), equal to the earliest start time for the activity plus the time required
completing the activity.
Latest Finish time (LF): the latest time at which the activity can be completed without delaying
the project.
Latest Start time (LS), equal to the latest finish time minus the time required to complete the
activity.Worked Example
61
Preceding
Activity Duration Calculated ET
ET
2 5 3 5 8
1 4 0 6 8
3 4 3 2 5
So the earliest start time for event 4 is day 8 (by this time all the preceding activities will have
been completed). What is the earliest time for event 5? If you are unsure, the answer is explained
4 5 8 6 14
So the earliest start time for event 5 is day 14 (by this time all the preceding activities will have
been completed).
Calculation of Latest Time:
Use the instructions presented above and the following diagram.
62
Solution to Calculation of Earliest Start Time for Event 5
This solution builds on the previous one - the earliest start time for event 4 was day 8 therefore...
Activity Preceding ET Duration Calculated ET
2 5 3 9 12
4 5 8 6 14
So the earliest start time for event 5 is day 14 (by this time all the preceding activities will have
been completed).
What is the latest time of event 1? If you are unsure, the answer is explained
Solution to Calculation of Earliest Start Time for Event 5
This solution builds on the previous one - the earliest start time for event 4 was day 8 therefore.
Analysis of the network allows the 'float' to be calculated, this is essentially the amount of time
an action can be delayed without delaying the overall project. Activities on the critical path must
be monitored very carefully.
63
4.4.1 Overview of the logical framework approach
Logic is a science that deals with the rules and tests of sound thinking and proof by reasoning
The Logical Framework is a simple tool for organizing thinking, elating Activities to expected
results, separating means from ends, setting performance indicators, allocating responsibilities,
communicating concisely & unambiguously. The Logical Framework or Log Frame Matrix is
one tool, amongst others, used for project planning & management (M&E). The Log Frame
Matrix (LFM) displays the casual relationship between the project inputs & outputs and
demonstrates how the outputs will lead to attainment of objectives and then contribute toward the
ultimate goal. A useful tool for planning more complicated projects is the logical framework
approach. The idea of this tool is that you identify all the main elements of a new proposal, and
examine how they fit together. The logical framework requires that you write down the planned
activities in a certain order that helps you to check whether one step will lead to the next, note
any assumptions that you are making, and examine whether or not they are true, identify
indicators of progress.
By Using LFM project designers/planners, managers and evaluators can define a project
hierarchy of objectives and the necessary and sufficient conditions required to achieve the next
higher-level objective/s/. The standard model log frame is a 4×4 matrix which vertically and
horizontally summarizes what the project intended to achieve, from the level of goal down to
specific activities, the performance questions and indicators that will be used to monitor progress
and evaluate overall achievements, how these indicators will be monitored or where the data can
be found, the assumptions behind the logic of how activities will eventually contribute to the
goal, plus associated risks for the project if assumptions turn out to be incorrect.
The Vertical Logic (Project Logic) is a set of means and ends interrelated in a logical fashion and
intended to define the way the project inputs are transformed into development goals. It is based
on the assumption that the achievement of ultimate project objectives (goal) proceeds through a
hierarchy of sub-objectives linked by a set of hypotheses: If we provide the following inputs and
carry out the following activities, then we produce the required outputs, If we produce those
outputs (product &/or service), then the purpose will be achieved. If the purpose is achieved,
then the goal will be realized. The statement of goal, purpose, outputs & activities (inputs)
frequently are subject to different interpretations by those involved with the project. Hence, the
HL enables to state the evidence that will signal success or failure, and the means it can be
verified. It lists the Objectively Verifiable Indicators of progress (OVIs), the Means of
Verification (MOV) and the Important Assumptions.
64
Example: Emergency Project
GOAL Communities and individuals who are better able to prepare and
respond to local disasters
OBJECTIVE Widely disseminated and heeded public information campaign on how to
locally prepare and respond to disasters
OUTPUTS work-plan reflecting roles, responsibilities and a time line for action
4.4.5 Budgets
The next step in resource allocation is the development of a budget for each important element of
the program. Simple, accurate systems that improve budgeting and cost control are crucial.
Whatever approach is used, a budget must be flexible and anticipate inflation of costs. Many
projects experience difficulty with monetary control and have trouble accounting for funds.
Usually this is because the project has not specified the accounting system to be used from the
outset or the system chosen is not adaptable to the project situation. For example, during disaster
times, good field accounting requires a simple system that is easy to use, easy to carry, and
places the emphasis of trust on the user. It also requires training in how to use the system before
disaster strikes. Field representatives, especially in the emergency, must have an accounting
system that recognises the need for flexibility and simplicity. Several agencies have recently
begun to use simplified field-account books that have built-in impression pads, so that duplicate
or triplicate records can be prepared and maintained. This innovation reflects the agencies'
awareness that a disaster creates special accounting needs. There is a close relationship between
budgeting as a planning technique and budgeting as a control technique. In this section we are
concerned only with the preparation of budgets prior to operations. From this perspective,
budgeting is a part of planning. With the passage of time and as the organization engages in its
activities, however, the actual results will be compared with the budgeted (planned) results. This
analysis may lead to corrective action. Thus, budgeting can also be viewed as a method for
evaluating and coordinating the efforts of the organization.
65
Assumptions: The mere fact that inputs are available, however, and that activities are performed
does not guarantee the production of outputs. The resources must be properly managed to
perform the right activities. Furthermore, management could be prevented from producing the
outputs if uncontrollable circumstances prevailed. Similarly, producing the outputs does not
ensure that the desired effect will follow. This relationship is based on the best judgment of the
planners and it may not be right. Besides, if this judgment was right, extraordinary
circumstances may prevent the production of the desired effect. Good project design requires that
project hypotheses and relevant assumptions must be clearly identified.
UNIT FIVE
Time for action now! You will now hold a formal kick-off meeting to start the execution phase
of your project during which you will direct your team’s activities in order to produce the agreed
upon deliverables as detailed in the project plan.
There are two systems for the management of project and they are: Project work system and
Project control system. Project work system can be designed by developing and preparing the
following tools: Work breakdown structure, Project execution plan and Project procedure manual
66
etc. Similarly for effective project control system it is essential to design the tools such as project
planning, project scheduling and project monitoring.
Factory design and layout of the factory are significant aspects of the factory organizations. They
have direct relationship with the process of manufacturing, productively and value of the
product. It also influences the operational costs of the enterprise. It also boosts the morale of
workers and ensures maximum supervision.
5.3. Factors affecting factory design
The following factors influence the design of a factory: Location
1. Nature of the manufacturing process
2. Plan Layout
3. Functional Smoothness
4. Material Handling and movement
5. Cost of Building
6. Lighting, Ventilation and Service Facilities
7. Nature of Product
8. Future expansion, modernization etc.
9. Projecting the image of a factory.
The factory design and layout should be flexible so that it may be adapted easily to technological
change, modernization, diversification and expansion with minimum cost and time. Any
planning exercise requires of the planner a good knowledge of what is involved in the activity
concerned, such as the nature of the materials to be handled, their quality and the quantity, the
processes they have to be subjected to, inspection and quality control at various stages, assemble
procedures, packing etc. He could also know the sequence of operations. He should look ahead
beyond the immediate future and anticipate changes, modifications, additions, deletions etc.,
which may be forced upon his organization as a result of expansion, obsolescence,
diversification or any other reasons. Having anticipated these, provision should be made to
accommodate such changes.
67
While working on factory layout plan, a very important aspect to be kept in mind is the fact that
the movement of materials from one stage of manufacture to the next should be minimal. For
this, this movement has to be streamlined. If this is not initiated, it will result in the wastage of
human effort and time, both of which have a telling effect on the efficiency of an organization
and the cost of production. In industrial life, the economic and efficient usage of all the factors of
production is the key to profitability and the ability to compete in the market.
a. Plant layout
A plant layout is “a floor plan for determining and arranging the desired machinery and
equipment of a plant, whether established or contemplated, in the one best place to permit the
quickest flow of material at the lowest cost and with the least amount of handling in processing
the product from the receipt of the raw materials to the shipment of the finished products”.
During the course of appraisal, considerable emphasis is laid on a proper and scientific plant
layout as once the plant and equipment are erected, it becomes difficult and costly to change at a
later stage. The following aspect is kept in view while evaluating the plant layout: Production
technology and product – mix, Efficient, economic and uninterrupted flow if human and
materials resources, Proper space for maintenance, Future expansion/diversification of the
project, Safety precautions particularly when explosive or bulky material is required to be
handled, Proper lighting and ventilation, Proper layout of utilities and services and provisions for
effluent disposal, where necessary, Effective supervision of work, and Proper storage and
stacking space, where required. The success of an enterprise to a greater extent depends upon the
factory design and layout. The location, layout, amenities will influence productivity and
facilitate better management. More importantly, the efficiency of the production flow depends
largely on how well the various machines, production facilities and employee amenities are
located in a plant.
b. Project design
Project design is the first stage in the execution of the project. Project design is concerned with
developing project scheduling techniques and also drawing the schedule for implementation of
the project. This is more or less a time frame for each phase in the project development. It
includes major items of project implementation such as finding of location, construction of
building, procuring plant and machinery and finally executing the production program. Project
design along with network analysis helps to develop work plan of the project and present it in the
form of diagrams representing duration of time for each work and adjustment of the time
schedule framed with reference to the problems that usually arise in the project execution.
Project design is useful to the entrepreneurs in the following ways:
It gives a comprehensive idea about the entire project – described in every phase along with
the time schedule within which it has to be completed.
It is a diagrammatic representation of work plan devised to execute the project, after
adjusting the usual delays that may arise4 in the implementation fo the project.
The various constituent continent activities of the project are narrated in sequence to
highlight the various phases of the project.
68
It defines the individual activities which go into the corpus of the project and their
interrelationship with each other.
It enables to identify and know of events which must take place for the successful
completion.
It helps entrepreneurs in coordinating project activities.
It serves as an effective tool of planning and implementation of a project
It helps managers to plan the project economically.
With the advent of the computer and large-scale introduction of computer based planning and
control, network analysis can considerably enhance managerial effectiveness in the context of
any time bound action programs. Computer-based network analysis can handle these problems
economically and efficiently. The binding condition is, however, that management is serious in
effecting economies in different areas of activities; and activities and events are closely watched
for initiating corrective action in proper time. The main task of a project manager is to design
systems and manage through them. A business system refers to the total picture of men, machine,
materials and paperwork involved in the implementation of any phase of a project. System has a
planned sequence of operations for carrying out a recurring work involved in a system with
family and consistently which is called a procedure. The first step in system design for project
management is to conceive the total physical system and its natural modules. In the next step, the
connection between these modules has to be identified. Finally, a control system using
information as the media has to be developed for self control as well as forced control of the total
project. Project management system is mainly constituted by project work system and project
control system.
If the project is organized on the lines of process units or technological systems, coordination
will be extremely simplified and cooperation would be almost assured. Therefore, better result
can be obtained if the design of work is systematized. The process of systematization starts with
the development of a work breakdown structure.
Work breakdown structure, WBS in short, is a technique which breaks down a work into its
components and at the same time establishes the connections between the components on the
lines of a family tree. The work breakdown structure represents a systematic and logical
breakdown of the project into its components parts. It is constructed by dividing the project into
its major parts, with each or these being further divided into sub-parts. This is continued till a
breakdown is done in terms of manageable units of work for which responsibility can be defined.
Thus the work breakdown structure helps in: Effective planning by dividing the work into
manageable elements which can be planned, budgeted, and controlled. Assignment of
responsibility for work elements to project personnel and outside agencies. Development of
control and information system. Work breakdown structure and Project organization. The project
organization represents formally how the project personnel and outside agencies are going to
work. The work breakdown structure defines what work is to be done in a detailed manner. To
69
assign responsibility for the tasks to be done, the work breakdown structure has to be integrated
with the project organization structure.
Work packing plan will be the next important step in the preparation of the project execution
plan. A work package in a project is the smallest division of work where it still retains the
characteristics of a project. This when a project is progressively divided into systems and the
system into subsystems, a stage is ultimately reached where further division into components
will strip it of its multi-disciplinary character – the work at that stage can be consideration these
packages, grouping them or keeping them as they are, in order to from viable contracts. Work
packaging enables better organization and management of projects. A work package or several
work packages may be assigned to one individual who could serve as a mini project manager.
This enables prioritization of the entire project execution effort which, in turn, ensures the closest
possible adherence to time, cost and technical performance targets. Work packaging can also
ensure that all agencies in a project think and channel their effort in one direction, i.e. towards
the completion of the packages only. Thus, design engineers, procurement engineers and
construction engineers will then give priority to their work in relation to a work package and not
according to functional convenience. Fulfillment of the requirements of a work package will
alone be considered and achievement and not the mere volume of work completed. This will lead
to a well-coordinated completion of the project. Thus, the contracting plan and work packaging
plan together produce a list of contracts with the scope of work defined in terms of self-contained
work packages.
70
iii.Organization plan
Having decided the number of contracts and their scope, the owner is now in a position to set his
own house in order. The owner can deliberate on the form of organization to be adopted so that
the interest of the project is best served. Several standard organizational arrangements are
possible, ranging from pure functional organization to pure project zed organization and an
owner has to choose his own arrangement depending on the project size, location, complexity,
work packages, type and number of contacts. It should be however, noted that an organization
can become more self-regulation if it is on taskforce or project zed. The participants in such
cases fully identify themselves with the project objectives and would regulate their behaviors on
their own, as the situation may demand.
iv. System and procedure plan
The last section of the project execution plan deals with system and procedure. A heavy
emphasis has to be placed on routine system and procedure so that no intervention is required in
the day –to-day operation of a system. There are at least eight routine sub-system of project
management for which appropriate procedures can be conceived right at the start of the project
implementation. These eight sub-systems are:
1. Contract management
2. Configuration management
3. Time management
4. Cost management
5. Fund management
6. Materials management
7. Communications management
a) Project direction
Project direction refers to the use of authority to channel the activities of the project on desired
lines. During the initiation of start-up period of the project this direction shall be provides by
the project manager. But once the project inters the production period direction will be exercised
71
by other members of the project organization of else the project will stall. Project
initiation/start-up: The need for project direction, as mentioned before, is maximum at the time
of start-up of implementation. The project manager during this period needs to provide directions
relating to: Scope of work, Specification of results of completed work, Basis of work, Division
of work – imported vs. indigenous, departmental Vs. contract etc., Schedule of work, Budget of
work, Systems and procedure for work, Co-ordination of work, Authority and accountability for
work, Control of work. The success of a project is heavily dependent on team work. All the items
from 1 to 10 are finalized with the involvement of project participants or else the directives will
appear authoritarian, and will unnecessarily invite opposition. If the directions can be formulated
through a participative approach, the some can be issued formally in the name of a project
manual with instructions for strict adherence to the same. Direction, during the project initiation
period, means not simply giving a push to the project; the direction issued at this stage will, in
fact, shape the destiny of the project.
Direction during production stage: Direction after the initiation period can be considered to be of
the administrative variety. Invariably, after the start-up period, direction is provided of a case-to-
case basis through formal documents or personal contacts. A group meeting may also be used for
this purpose. On-going directions may refer to approval of work schedules, detailed budgets,
specification, purchase orders, work orders, construction drawings, travels, miscellaneous
expenses, changes in baseline etc.
Ongoing direction
Project start-up, design review, purchase order and work orders are on-time directions. But a
project will require only when unforeseen events occur, directors otherwise will require to be
provided when problems occur during project execution. In either case, a decision has to be
made as to what should be done and the same should be authorizing for implementation. Thus,
decision making and direction are part of every-day function of any manager. Routine directions
involve five steps: Understanding the decision environment, Establishing the decision
alternatives, Evaluation of the alternatives and selection of course of action, Communication the
decision to the individual or agency who is to implement the decision and Checking up if the
decision is working so that the decision could e steered by the consequences.
b) Communication in a project
For ongoing direction a two-way communications system is essential. For that matter, the entire
process of direction, co-ordination and control in a project revolves around communication. It is
often concluded that projects are run by communications. In fact, most of management problems
are caused in whole or in part by faulty management communications. Communication has two
dimensions physical and mental, passing a memo, drawing, data, instruction, information, etc.
are the physical aspects of communication; understanding the same in the light of role
expectation, empathy, preconceived notion, language barriers, listening skills etc., are the mental
aspects of communication. While physical aspects of communication can be easily achieved, the
mental aspects often present barriers to communication. Prefer communication requires a
72
conscious and determined effort. Affective communication in a project would require a
communication oriented action plan. The actions that may be taken in this regard are as below:
Time and cost over-runs of projects are very common in practice, particularly in the public
sector. Due to such time and cost over-runs, projects tend to become uneconomical, resources are
not available to support other projects, and economic development is adversely affected. This
helps to minimize time and cost over-runs and thereby improve the prospects of successful
completion of projects. A lot of things can be done to achieve this goal; the most important ones
appear to be as follows: adequate formulation, sound project organization, proper
73
implementation planning, advance action, timely availability of funds, judicious equipment
tendering and procurement, Better contract management and Effective monitoring.
a. Adequate formulation
Often project formulation is deficient because of one or more of the following shortcomings:
Superficial field investigation, cursory assessment of input requirements, slip-shod methods used
for estimation costs and benefits, omission of project linkages, flawed judgments because of lack
of experience and expertise, undue hurry to get started and deliberate over-estimation of benefits
and under-estimation of costs. Care must be taken to avoid the above deficiencies so that the
appraisal and formulation of the project is through, adequate and meaningful.
A sound organization for implementing the project is critical to its success. The characteristics of
such an organization are: It is led by a competent leader who is accountable for the project
performance. The authority of the project leader and his team is commensurate with their
responsibility. Adequate attention is paid to the human side of the project. Systems and methods
are clearly defined. Rewards and penalties to individuals are related to performance.
Once the investment decision is taken – and often even while the formulation and appraisal are
being done – it is necessary to do detailed implementation planning before commencing the
actual implementation. Such planning should inter alia, seek to: develop a comprehensive time
plan for various activities like land acquisition, tender evaluation, recruitment of personnel,
construction of building, erection of plant, arrangement for utilities, trial production run, etc.
estimate meticulously the resource requirements (manpower, material, money, etc) for each
period to realize the time plan; define properly the inter-linkages between various activities of
the project; specify cost standards.
d. Advance action
When the project appears prima facie to be viable and desirable, advance action on the following
activities may be initiated: (i) acquisition of land, (ii) securing essential clearances, (iii)
identifying technical collaborators / consultants, (iv) arranging for infrastructure facilities, (v)
preliminary design and engineering, and (vi) calling of tenders
e. Timely availability of funds
Once a project is approved, adequate funds must be made available to meet its requirements as
per the plan of implementation – it would be highly desirable if funds are provided even before
the final approval to initiate advance action. Piecemeal, ad-hoc, and niggardly allocation, with
undue rigidities, can impair the maneuverability of the project team. It is a common observation
that firms which have a comfortable liquidity position are, in general, able to implement projects
expeditiously and economically. Such firms can initiate advance actins vigorously, negotiate
with suppliers and contractors aggressively, organize input supplies quickly, take advantages of
74
opportunities to effect economies, support suppliers in resolving their problems so that they can
in turn redound to the successful completion of projects, and sustain the morale of project-related
personnel at a high level.
To minimize time over-runs, it may appear that a turnkey contract has obvious advantages. Since
these contracts are likely to be gagged be foreign suppliers, when global tenders are floated, a
very important question arises. How much should we rely on foreign suppliers and how much
should we depend on indigenous suppliers? Over-dependence on foreign suppliers, even though
seemingly advantageous from the point of view of time and cost, may mean considerable
outflow of foreign exchange and inadequate incentive for the development of indigenous
technology and capability. Over-reliance on indigenous suppliers may mean delays and higher
uncertainty about the technical performance of the project. A judicious balance must be sought
which moderates the outflow of foreign exchange and provides reasonable fillip to the
development of indigenous technology.
Since a substantial portion of a project is typically executed through contracts, the proper
management of contracts should be done. The competence and capability of all the contractors
must be ensured–one weak link can jeopardize the timely performance of the contract. Proper
discipline must be inculcated among contractors and suppliers by insisting that they should
develop realistic and detailed resource and time plans which are congruent with the project plan.
Penalties – which may be graduated–must be imposed for failure to meet contractual obligations.
Likewise, incentive may be offered for good performance. Help should be extended to
contractors and suppliers when they have genuine problems–they should be regarded as partners
in a common pursuit. Project authorities must retain latitude to off-load contracts (partially or
wholly) to other parties well in time where delays are anticipated.
h. Effective monitoring
In order to keep a tab on the progress of the project, a system of monitoring must by established.
This help in anticipating deviations from the implementation plan, analyzing emerging problems,
taking corrective action. In developing a system of monitoring, the following points must be
borne in mind: It should focus sharply on the critical aspects of projects implementation. It must
lay more emphasis on physical milestones and not on financial targets. It must be kept relatively
simple. If made over-complicated, it may lead to redundant paper work and diversion of
resources. Even worse, monitoring may be viewed as an end in itself rather than as a means to
implement the project successfully.
75
that the project management is an extremely important problem area for a developing country
such as ours. Unfortunately many projects experience schedule slippage and cost overruns due to
a number of reasons. To remedy the situation, projects ought to be meticulously planned,
scrupulously implemented and professionally managed to achieve the objective of time, cost and
performance. Modern technique of project management can play a major role in streamlining the
management of projects. Projects management is a complex process bristling with a number of
variables contributing to success in a project. It is not a facile task to ensure overall effectiveness
of the project. Several factors contribute to its success. The project determinants are plenty and
many success of the projects interalia include factors which little or no management control is
possible. Discretionary factors can be controlled either within the project itself or in the larger
system, and the end products serve as the basis for the determination of degree of success.
Factor (Determinants) for effective project Management
The study of factors for effective projects management comprising both internal and external
determinant factors are taken into account. The internal factors are project managers, project
team, project management techniques, project organization structure, project monitor and
evaluation system, use of computers, detailed project engineering know how, management
reporting system, etc.
1. Internal Factors
a. Project Managers:
The project manager is the crux of the coordinating authority with various functional heads.
He/she is the seminal coordinating authority forging a lasting rapport with the financial
institutions, government and statutory bodies, etc. He/she is the main plank and fulcrum of the
project and he is a person who has been associated with the project right from the scratch to the
completion of the project. He play role like a lynch-pin. He/she encompasses into his fold the
whole gamut of the project team and also entire spectrum of clientele contractors and turnkey
consultants. The foremost aim and motto of the project manager is to accomplish the project cost
within the stipulated amount. Hence, it can be observed that the project manager plays a vital
role in the firmament of industrial project.
b. Project Team:
The project team comprises of section heads of production, electrical and mechanical who are
looking after the activities of their respective wings. The project team is a la cricket team where
we could find players adept in bowling, batting and fielding with the result al the players would
put their unstinted and indefatigable effort to translate their action of accomplishing the objective
of the team. For any project, success could be attributed to the able support of all the players and
the project manager would don the role of a captain of the cricket team or of a captain of ship.
c. Project Managerial Techniques:
The project organization structure should be in consonance with the nature of the project, its
complexity, and type of process technologies developed. Centralized policy formulation with
decentralized implementation appears best suited for project management. The organizational
structure should provide for scheduling and monitoring, contract management, materials and
76
equipment procurement, on site co-ordination and control and information processing, etc.
Adequate powers should be delegated to enable on the spot decisions and thereby minimize
avoidable delays. The well designed and established project organization structure will effective
project implementation and improve project management performance tremendously.
A well designed and in built project monitoring and evaluation system will minimize project
slippage. A project management information system with the help of computer net works and
methods would enable project monitoring and control at various levels and that would naturally
enhance the project management performance.
e. Use of Computers:
Project management software package are used to meet deadlines, to reduce costs and ultimately
to optimal utilization of resources. They offer services like planning, coordinate and monitor
product launches, plant commissioning, and erection, maintenance, and construction activities.
They also identify crucial problematic areas and sound warnings on possible delays and
contingencies and also to take instant and remedial measures to arrest the lapses before assuming
hiatus in the project management. They generate instant reports in project status, keep track of
project progress and trends to achieve targets and also allocate the resources in order to achieve
realistic goals. Undoubtedly, the usage of computers saves precious time and money. The
application of computers will enhance and uplift the overall project management effectiveness.
The management information and reporting systems ensures monitoring or the project progress
and also identifies the specific information requirement of the project. To achieve this objective
every project should develop requisite reporting formats for input and output of data, proper
information flow and communication systems and setting up adequate date processing and
storage systems necessary for the purpose. The well knit management reporting system will go a
long way I assisting speedy implementation of projects’ performance.
2. External Factors
a. Support from financial institutions:
77
The simplification of bureaucratic rigmarole and red-tapism of the government departments in
project approval and sanctioning for public sector projects and liberalization of industrial
licensing, foreign exchange regulation provision, MRTP clearance, environmental clearance etc.
for private and joint sector projects would minimize and reduce the time delay in clearing such
approvals thus ensuring early implementation of industrial projects so as to trigger fillip to the
project management success.
Construction management plays a unique part in the matter of industrial project management.
The construction management includes under its fold the construction of factory and office
buildings and erection and construction of factory sheds and plant commissioning etc. These
ought to be constructed according to the project schedule so as to minimize project delays.
e. Project Consultants:
Project management consultants are professionally qualified who are fully equipped to perform
services to the project management organization in the entire gamut of erection, commissioning
and implementing the industrial projects. A delay in project consultant’s performance of his hob
would mean procrastination of the project, for which ultimately client suffers more than the
consultants pay a vital role in the various stages of the project right from the stage of
commissioning of the project. He is also abundantly responsible for closely monitoring the
progress of the project. He is also abundantly responsible for closely monitoring the progress of
the project at every phase of the project. The unstinted and unflappable support of the project
consultants would naturally brighten the project’s success.
Expenses incurred for identifying the project, conducting the market survey, preparing the
feasibility report, drafting the memorandum and articles of association and incorporating the
company are referred to as preliminary expenses. Expenses borne in connection with the raising
of capital from the public are referred to as capital issue expenses. The major components of
capital issue expenses are underwriting commission, brokerage, fees to managers and registrars,
printing and postage expenses, advertising and publicity expenses, listing fees, and stamp duty.
Pre-operative Expenses
Expenses of the following types incurred till the commencement of commercial production are
referred to as pre-operative expenses these include (i) establishment expenses, (ii) rent, and
78
taxes, (iii) traveling expenses, (iv) interest and commitment charges on borrowings, (v) insurance
charges, (vi) mortgage expenses, (vii) interest on deferred payments, (viii) start-up expenses, and
(ix) miscellaneous expenses. Pre-operative expenses are directly related to the project
implementation schedule. So, delays in project implementation, which are fairly common, tend
to push up these expenses. Pre-operative expenses incurred up to the point of time the plant and
machinery are set up may be capitalized by apportioning them to fixed assets on some acceptable
basis. Pre-operative expenses incurred from the point of time the plant and machinery are set up
are treated as revenue expenditure. The firm may, however, treat them as deferred revenue
expenditure and write them off over a period of time.
The principal support for working capital is provided by commercial banks and trade creditors.
However, a certain part of the working capital requirement has to come from long-term sources
of finance. Referred to as the ‘margin money for working capital’ this is an important element of
the project cost. The margin money for working capital is sometimes utilized for meeting over-
runs in capital cost. This leads to a working capital problem (and sometimes a crisis) when the
project is commissioned. To mitigate this problem, financial institutions stipulate that a portion
of the loan amount, equal to the margin money for working capital, be blocked initially so that it
can be released when the project is completed.
Initial Cash Losses: Most of the projects incur cash losses in the initial years. Yet, promoters
typically do not disclose the initial cash losses because they want the project to appear attractive
to the financial institutions and the investing public. Failure to make a provision for such cash
losses in the project cost generally effects the liquidity position and impairs the operations.
Hence prudence calls for making a provision, overt or covert, for the estimated initial cash
losses.
Means of Finance: To meet the cost of the project, the means of finance that are available
include Share capital, Term loans, Bonds, Deferred credit, Incentive sources, and Miscellaneous
sources.
79
1. Share Capital. There are two types of share capital; namely, equity capital (through the
issuance of common stock) and preference capital (through the issuance of preferred stock).
Equity capital represents the contribution made by the owners of the business, the equity
shareholders, who enjoy the rewards and bear the risks of ownership. Equity capital being a risk
capital carries no fixed rate of dividend. Preference capital represents the contribution made by
preference shareholders and the dividend paid on it is generally fixed.
2. Term Loans. They are provided by financial institutions and commercial banks. Term loans
represent secured borrowings which are a very important source (and often the major source) for
financing new projects as well as for the expansion, modernization, and renovation schemes of
existing firms.
3. Bond capital. Bonds are instruments for raising debt capital. The typical example of bonds is
debentures. There are two broad types of debentures; namely, non-convertible debentures and
convertible debentures. Non-convertible debentures are straight debt instruments. Typically they
carry a fixed rate of interest. Convertible debentures, as the name implies, are debentures, which
are convertible, wholly or partly, into equity shares. The conversion period and price are
announced in advance.
4. Deferred Credit. Many a time the suppliers of the plant and machinery offer a deferred credit
facility under which payment for the purchase of the plant and machinery can be made over a
period of time.
5. Incentive Sources. The government and its agencies may provide financial support as an
incentive to certain types of promoters or for setting up industrial units in certain locations.
These incentives may take the form of seed capital assistance (provided at a nominal rate of
interest to enable the promoter to meet his contribution to the project), or capital subsidy (to
attract industries to certain locations), or tax deferment or exemption for a certain period.
6. Miscellaneous Sources. A small portion of the project finance may come from miscellaneous
sources like unsecured loans, public deposits, and leasing and hire purchase finance. Unsecured
loans are typically provided by the promoters to bridge the gap between the promoters’
contribution (as required by the financial institutions) and the equity capital the promoters can
subscribe to. Public deposits represent unsecured borrowings from the public at large. Leasing
and hire purchase finance represent a form of borrowing different from the conventional term
loans and debenture capital.
1. Norms of Regulatory Bodies and Financial Institutions. In some countries, the proposed
means of finance for a project must either be approved by a regulatory agency or conform to
certain norms laid down by the government or financial institutions in this regard. The primary
purpose of such regulations is to impart prudence to project financing decisions and provide a
80
measure of protection to investors. In addition, the norms of financial institutions, which often
provide substantial assistance to projects significantly shape and circumscribe project financing
decisions.
2. Key Business Considerations. The key business considerations which are relevant for the
project financing decision are cost, risk, control, and flexibility.
a. Cost. In general, the cost of debt funds is lower than the cost of equity funds. Why? The
primary reason is that the interest payable on debt capital is a tax-deductible expense whereas the
dividend payable on equity capital is not.
b. Risk. The two main sources of risk for a firm (or project) are business risk and financial risk.
Business risk refers to the variability of earnings before interest and taxes and arises mainly from
fluctuations in demand and variability of prices and costs. Financial risk represents the risk
arising from financial leverage. It must be emphasized that while debt capital is cheap it is also
risky because of the fixed financial burden associated with it. Generally the affairs of the firm
are, or should be, managed in such a way that the total risk borne by equity shareholders, which
consists of business risk and financial risk, is not unduly high. This implies that if the firm is
exposed to a high degree of business risk, its financial risk should be kept low. On the other
hand, if the firm has a low business risk profile, it can assume a high degree of financial risk.
c. Control. From the point of view of the promoters of the project, the issue of control is
important. They would ordinarily prefer a scheme of financing which enables them to maximize
their control, current as well as potential, over the affairs of the firm, given their commitment of
funds to the project.
d. Flexibility. This refers to the ability of a firm (or project) to raise further capital from any
source it wishes to tap to meet the future financing needs. This provides maneuverability to the
firm. In most practical situations, flexibility means that the firm does not fully exhaust its debt
capacity. Put differently, it maintains reserve-borrowing powers to enable it to raise debt capital
to meet largely unforeseen future needs.
Production Costs: There are three major categories of manufacturing costs. These are
1. Direct materials cost: - The acquisition costs of all materials that are identified as part of the
cost object and that may be traced to the cost object in an economically feasible way.
Acquisition costs of direct materials include inward delivery charges, tax, and custom duties.
Direct material often does not include minor items such as glue or tacks. Why? because the
cost of tracing insignificant items do not seem worth the possible benefits of having more
accurate product costs. Such items are called supplies or indirect materials and are classified
as part of the indirect manufacturing costs.
2. Direct labor. The compensation of all labor that can be identified in an economically
feasible way with a cost object. Examples are the labor of machine operators and assembler.
Indirect labor costs are all factory labor compensation other than direct labor compensation.
These are labour costs that are impossible or impractical to trace to a specific product. They
81
are classified as part of the indirect manufacturing cost. Examples include wages of janitors,
and plant guards.
3. Indirect manufacturing costs (manufacturing overhead). All manufacturing costs that
cannot be identified specifically with or traced to the cost object in an economically feasible
way. Other terms used are factory overhead, factory burden, manufacturing overhead, and
manufacturing expenses. Examples of factory overhead (when products are cost object)
include power, supplies, indirect labour, factory rent, insurance, property taxes, and
depreciation.
Project human resource management includes the processes required to make the most effective
use of the people involved with a project. Project Human Resource Management includes the
processes that are important to organize and manage the project team. The Project team is
comprised of the people who have assigned roles and responsibilities of completing the project.
The type and number of project team members can often change as the project progresses. In
projects, HRM has some peculiarities and problems. These include Project staffing problems
(e.g. diversity, availability), Performance appraisal problems, Motivation problems and Job
Description etc… Managing people under projects is more difficult because of the following.
Dual responsibility, Split Authority, Imbalance of authority and responsibility, The temporary
nature of projects and Lack of managerial capacity. In addition to technical capacity, project
managers need to have managerial capacity. This includes: Efficiency combined with
effectiveness, Non mechanistic approach to problem solving, Conflict management, Team
Building, Interpersonal skills, Motivation and leadership, Time Management, Change
Management, and Diversity Management. Generally a project contains both the technical staff
the support staff. The structure of the staff depends on the three types of the project structure. A
project manager is expected to manage not only the core and support teams but also other
stakeholders. These include: Sponsors, End users, Sub-contractors, Suppliers and Other line
departments.
5.3.1 Managing People in Projects
A. Looking inwards and downwards: this is managing yourself and your team to maximize your
and their contribution. This includes: Providing SMART project goals, Creating a supportive
culture, Celebrating success and Providing purpose and direction.
82
B. Looking Upwards and Outwards: this refers to managing the project sponsor, clients or any
other external stakeholders to ensure their commitment and fulfill their expectations. This
involves: Building credibility, Networking, Securing stakeholders’ agreement and Marketing
the project.
C. Looking Forwards and Backwards: is about proper planning and continuous planning of the
future and monitoring and evaluation of the past. This involves: continuous planning and
review, keeping the whole team involved, Seeking and providing feedback and anticipating.
5.3.2. Project Staffing Problems: Anxieties about the possible loss of employment ,
Frustration due to authority ambiguity problems, Conflicts when there are no formal procedures,
role definitions and job descriptions, Conflicts are perceived more seriously by project staff ,
Project personnel feel abandoned from both sides (from the project and mother organization).
Project Human Resource Processes: Project Human resource planning, acquiring the
project team, developing the project team, managing the team.
Planning: Define Human Resource requirements of project (Number and Kind)
Identifying and documenting project roles, responsibilities, and reporting relationships
Planning Issues: Project interfaces: Organizational /formal and informal relationships among
different units/. Technical /formal and informal relationships among different technical
disciplines/. Interpersonal /formal and informal relationships among different individuals
working in the project/. Staffing Requirements: Kinds of competencies needed, Kinds of
individuals or groups needed, Time frames, Constraints - factors that limit team’s options,
Organizational constraints: e.g. Matrix strength, Collective bargaining agreements, Template -
Previous projects, Staffing management plan, How resources will be brought onto and taken off
the team, Appropriate reassignment procedures may, Reduce costs by eliminating “fill in” work,
Improve morale by reducing employment uncertainties.
83
Acquiring the Project Team: Acquiring qualified people for teams is crucial. The project
manager has to work hard in recruiting the best . Staffing plans and good hiring procedures are
important, as are incentives for recruiting and retention
Acquisition Issues: Staffing pool description: Team must consider characteristics of potential
staff, such as… Previous experience, personal interests, personal characteristics, availability,
competencies and proficiency. Negotiations, with… Functional managers, other project
management teams Pre assignment, Specific staff promised in proposal, Internal service project,
staff assigned in charter
Development: The main goal of team development is to help people work together more
effectively to improve project performance. It takes teamwork to successfully complete most
projects
Project Management: Project managers must lead their teams in performing various project
activities. Regular performance assessment is also needed. After assessing team performance and
related information, the project manager must decide: If changes should be requested to the
project: if corrective or preventive actions should be recommended; if updates are needed to the
project management plan or organizational process assets.
Project Team Building: A team is a group of people working together towards a common
goal”. A team is two or more people working together, encouraging and supporting each other,
achieve in an efficient way, mutually agreed up on and appropriate goals. Team building is
deliberate action focusing on encouragement of effective working practices and diminishing of
difficulties among team members. Team members share a common goal or goals. Team
members have individual tasks and roles that help to achieve group goals. Team members co-
operate with and respect one another, and tolerate individual differences. In team, seek
consensus, accept different points of view, work together and support one another. The team
leader is facilitator of the collective style.
Behavioral aims of team building: Reticent, communicative, Secretive & reserved, open,
conflict, cooperation, Apprehensive, trusting, Impersonal, mutual concern, Avoidance of
84
responsibility, self- responsibility, Sterility, creativity, alienation, commitment, Role confusion,
Individual centered, role clarity, team centered.
Communication in Project Teams: Follow these principles when you communicate in Team
(they are called the 7 Cs)-Clarity, Completeness, Conciseness, Concreteness, Correctness,
Consideration, Courtesy.
UNIT SIX
Once the project has been launched, it is essential to control the projects to achieve the desired
results. In this process the control becomes closely inter-wined in an integrated managerial
process. Project control involves a regular comparison of performance against targets, a search
for the causes of deviation and a commitment to check adverse variances.
6.1. Introduction to Project control
Project control serves two major functions: It ensures regular monitoring of performance. It
motives project Personnel to strike for achieving projects objectives steps in Projects Control.
There are two important steps in the project control; Establishment of controls and On-going
controlling activities using above controls. It is nothing but controlling a project when it enters
the production period using the controls established during the initiation period.
85
Control during the production period involves four steps, there are
1. Setting targets for what should be achieved,
2. Measuring of what is happening including anticipation of what may happen.
3. Comparison between what should happen and what is happening or likely to happen.
4. Taking corrective actions to make things happen, as they should these four steps should
fellow each other till the work is completed.
Let us consider a specific example. A piece of equipment is made of two parts A and B which
are to be assembled together before they are dispatched. Part A is of cast steel, which requires a
pattern and a mould. Part B is a machined item made on special machine M which needs to be
purchased and installed. Parts A requires special hear-treatment before assembly. The assembly
needs to be tested with a specially constructed rig before dispatch.
The time scale for each activity is as follows:
Preparing a pattern for casting 4 Weeks
Preparing a mould 2 Weeks
Costing the cleaning operation of A 1 Weeks
Heat-treatment of A 2 Weeks
86
Obtaining and installing machine M 7 Weeks
Machine part B 5 Weeks
Assembling part A and B 3 Weeks
Preparing the test rig 4 Weeks
Testing the assembly 2 Weeks
Packing for dispatch 1 Weeks
The various activities are shown along the ordinate or the vertical axis and the time elapsed along
the horizontal axis.
In a program where there are a large number of activities that can be started with a certain degree
of concurrency, the bar chart cannot show clearly the interdependent among the various efforts
or activities. This is a serious deficiency. The mere fact to or more activities are scheduled for
simultaneous or overlapping times does not necessarily make them related or interdependent, or
completely independent. Such activities as preparing a pattern, preparing a mould, costing and
cleaning, and heat-treating have to run sequentially, i.e., one activity must be completed before
the other can begin. The bars representing these activities are not allowed to overlap. On the
other hand, installing machine M and preparing the test rig can proceed simultaneously because
they are completely independent activities and hence the bars representing them can run parallel
to each other. However, this is exactly the weakness of the bar chart, because two parallel bars
need not necessarily stand for independent activities, as the following example will show.
Suppose a project involves digging foundation, erecting side boards or shuttering, and pouring
concrete. The time consumed is shown against each activity:
Digging foundation 20 Weeks
Erecting side boards 14 Weeks
Pouring concrete 16 Weeks
If the activities are not allowed to run in parallel but in strict sequence, the total time taken for
the completion of the project is 50 weeks. As we can easily see, erection of the sideboards can
start after the completion of, say, one-half of foundation digging. Similarly, poring of concrete
can start, say, 5 Weeks after the erection of side boards. According to this plan, the side board
erectors still have 4 weeks of work after the excavation job is over. However, if due to certain
unexpected difficulties the excavation is delayed by 1 or 2 weeks, how will reflect on the
sideboard erection or the concrete pouring job? This is not revealed by the bar chart.
Project progress:
A bar chart cannot be used as a control device since it does not show the progress of work.
Knowledge of the amount of work in progress or jobs completed is absolutely necessary in a
dynamic program. Changes in plans are a necessary part of a large project and a bar does not
offer much assistance under such circumstances. However, a conventional bar chart can be
modified to give this additional information.. Suppose 16 weeks have elapsed after he project
87
started: be the progress made in the project can be depicted by partially filling in the blank bars.
Foundation digging, is weeks behind schedule.
Uncertainties
One of the most important deficiencies of the bar chart is its inability to reflect the uncertainty or
tolerances in the duration times estimated for various activities. The modern day space system
programs or other complex projects are largely characterized by extensive research, development
and technological progress. The traditional knowledge or practices play a very insignificant role.
In such situations, the completion of various stages or jobs cannot be forecast with exactness.
Uncertainty about a test becoming successful or a sudden break though in technology to know-
how will always provide situations which will make rescheduling of various events a necessary
part of the project and give it a dynamic character which is not reflected in a bar chart.
Milestone Charts
Because of the shortcomings or the inadequacies of the chart in meeting the requirements of the
modern day management, efforts have been made to modify it by adding new elements. One
such modification is milestone chart. Another important modification, relatively successful, has
formed a link in the evolution of the Gantt chart into the PERT or CPM network. This
modification is called the milestone system. Milestones are key events or point time, which can
be identified when, completed as the project progresses. In the Gantt chart a bar which represents
a long-term job is broken down to several pieces, each of which stands for an identifiable major
event. Each event is numbered and an explanatory table given identifying the number with the
event. These are specific event (points in time) which management has identifies as important
reference points during the completion of the project. This work breakdown increases the
awareness of the interdependent between tasks. While the milestone chart was definitely an
improvement on the bar chart, it still had one great deficiency, i.e., it did not clearly show the
interdependent between events. In a milestone chart the events are in chronological, but not
logical, sequence. A natural extension of the milestone chart was the network where the events
are connected by arrows in a logical sequence.
88
Critical path method (CPM)
The critical path analysis is an important tool in production planning and scheduling. Gantt
charts are also one of the tools of scheduling but they have one disadvantage for which they are
found to be unsuitable. The problem with Gantt chart is that the sequence of operation of a
project or the earliest possible date for the completion of the project as a whole cannot be
ascertained. This problem is overcome by this method of Critical Path Analysis. CPM is used for
scheduling special projects where the relationship between the different parts of project is more
complicated than of a simple chain of task to be completed on after the other. This method
(CPM) can be used at one extreme for the very simple job and at other extreme for the most
complicated tasks. A CPM is a route between two or more operations which minimizes (or
maximizes) some measures of performance. This can also be defined as the sequence of
activities, which will require greatest normal time to accomplish. It means that the sequences of
activities, which require longest duration, are singled out. It is called at critical path because
longest duration is singled out. It is called as critical path because any delay in performing the
activities should be taken should be taken up first.
According to John L. Burbidge, “One of the purposes of critical path analysis to find the
sequence of activities with the largest sum of duration times, and thus find the minimum time
necessary to complete the project. This critical series of activities is known as the ‘Critical path”.
Under CPM, the project is analyzed into different operation or activities and their relationship
are determined and shown on the network diagram. So, first of all a network diagram is drawn.
After this the required time or some other measure of then combined to develop a schedule
which minimizes or maximizes the measure of performance for each operation. Thus CPM
89
marks critical activities in a project and concentrates on them. It is based on the assumption that
the expected time is actually the time taken to complete the object.
Main objects of CPM
The main objects of CPM are: to find difficulties and obstacles in the course of production
process, to assign time for each operation, to ascertain the starting and finishing times of the
work, to find the critical path and the minimum duration time for the project as a whole.
Situation where CPM can be effectively used: CPM techniques can be used effectively in the
following situation: In production planning, location of and deliveries from a warehouse, road
systems and traffic schedules and communication network.
Advantages of CPM
The application of CPM leads to the following advantages: It provides an analytical approach to
the achievement of project objective which are defined clearly. It identifies most critical
elements and pays more attention to these activities. It assists avoiding waste of time, energy and
money on unimportant activities. It provides a standard method for communicating project
plains, schedules and cost. Thus CPM technique is a very useful analysis in production planning
of very large project. There are so many modern techniques that have developed recently for the
planning and control of large projects in various industries especially in defense, Chemical and
construction industries. Perhaps, the PERT is the best known of such techniques. PERT is a time-
event network analysis technique designed to watch how the parts of a program fit together
during passage of time and events. The special project office of the U.S. Navy developed the
technique in 1958. It involves the expected of any operation can never by determined expected
time of any operation can never by determined exactly.
Major feature of PERT or Procedure or Requirement for PERT
The following are the main feature of PERT: All individual tasks should be shown in a network.
Events are shown by circles. Each circle representation event a subsidiary plans whose
completion can be measured at a given time. Each arrow represents and activity the time
consuming element of a program, the effort that must be made between events. Activity time is
the elapsed time required to accomplish element an event. In the original PERT, three-time
values are used as follows: Is
t1 (Optimistic time) : It is the best estimate of time if everything goes exceptionally well
t2 (Most likely time): It is an estimated time what the project engineer believes necessary
to do the job or it is the time which most often is required if the activity is repeated a
number of times.
t3 (Pessimistic time) : It is also an activity of under adverse conditions. It is the longest
time and rather is more difficult to ascertain.
The experiences have shown that the best estimate of time out of several estimates made by the
projects engineer is:
90
t1 + 4t2 + t3
t=
6
and the variance of t is given by-
t3 t1
V (t )=
6
Here it is assumed that the time estimate follows the Beta distribution.
The next step is the compute the critical path and the slack time. A critical path or critical
sequence of activities is one, which takes the longest time to accomplish the work and the least
slack time.
Advantage of PERT
PERT is a very important of managerial planning and control at the top level concerned
with overall responsibility of a project. PERT has the following merits.
Pert forces managers and subordinate manger’s to make a plan for production because
time event analysis is quite impossible without planning and seeing how the pieces fit
together.
PERT encourage management control by exception. It concentrates attentions on critical
element that may need correction.
It enables forwards-working control, as a delay will affect the succeeding events and
possibly the whole project. The production manager can somehow make up the time by
shortening that of some other time.
The network system with its sub-systems creates a pressure for action at the right spot and
level and at the right event.
PERT can be effectively used for re-scheduling the activities.
91
assumes that he duration of every activity is constant and therefore every activity is
critical or not.
PERT is concerned with events, which are the beginning or ending points of operation
while CPM is concerned with activities.
PERT is suitable for non-repetitive projects while CPM is designed for repetitive
projects.
PERT can be analyzed statistically whereas CPM not.
PERT is not concerned with the relationship between time and cost, whereas CPM
established a relationship between time and cost is proportionate to time.
The last major phase of a project's life cycle is the close-out. Closing a project should be a fairly
routine process.
Key elements
The key elements to project close-out are: accepting the project's products indicated by user sign-
off, completing the Post Implementation Evaluation Report (PIER), disbursing the resources—
staff, facilities, and automated systems, conducting a lessons learned session, completing and
archiving project records, recognizing outstanding achievement, celebrating project completion.
These activities are particularly important on large projects with extensive records and resources.
This section does not address processes for transitioning the technical support into maintenance
and operation. These tasks are diverse and unique to the specific development environment of a
project. The first step of the close-out process is the user's acceptance of the system. This is a
critical and important step, as the user decides when the project is completed. Acceptance is
based upon the success criteria defined in the very early concept and planning stages of the
project. This acceptance should be formal, meaning that user sign-offs should be obtained.
92
Financial data
Recommendations to future project managers
Lessons Learned (from lessons learned session)
Identifying and Addressing Success
Be certain that successes as well as problems on the project are identified in the PIER. Be certain
to include new ideas that were very successful on the project. Make recommendations on how
these processes might be adapted for other projects. Share the project successes with other
organizations. In the same way that problem identification can lead to improvements, successes
must be shared so they can be repeated. Where possible, successes should be translated into
procedures that will be followed by future projects.
The project manager has responsibility for preparing the report. The project manager gets input
from the entire project team, the users, and other major stakeholders. People performing
different functions on the project will have a different outlook on the successes and failures and
on possible solutions. If every project member cannot be consulted, at least ensure that a
representative from each major area of the project participates. The users’ overall view of the
project and its final product is also a major focus of the project. It is this view, along with the
view of the major stakeholders that lives on after closure has been completed.
Collecting Project Data
Following preparation of the Post Implementation Evaluation Report, the project database is
archived. Historic project data is an important source of information to help improve future
projects. Typically, the following project data is archived: Project identification and evaluation
report, project plan and project Management Control Documents (correspondence, relevant
meeting notes, status reports, and contract files), technical documents, and information that had
been placed under configuration management
All the hard copy records should be stored following standard guidelines. Many of the technical
records and automated versions will be turned over to stakeholders responsible for maintenance
and operation of the system. Summary technical information should be electronically stored for
historical access. The project archive includes a description of the files being submitted, the
application (including version) used to create the archived materials, and a point of contact if
further information is needed.
93
data is collected over time, the state may be able to develop an experience database that will help
to make strong estimates and develop realistic project plans.
Recognition of Success
Celebrate the success of completing a project!
There is fairly universal recognition that positive reinforcement, or rewarding behavior, is an
effective management tool. Since it is a goal within the project promoters to execute all projects
successfully, it is important to recognize teams that have met this goal. When success in a project
is achieved, be certain to provide some recognition to the team. If individuals are singled out for
significant achievements, don’t forget to recognize the entire team as well.
What is Success?
Success is defined at the early stages of planning the project. In this project management
methodology, success factors are developed as part of the concept phase. Success is not tied only
to budget and schedule. Many projects can be considered a tremendous success even though the
project did ultimately cost more than had been anticipated.
Some key questions that determine success are:
Were the success factors achieved?
Do the stakeholders and end-users view in a positive manner the project product?
Was the project well-managed?
Did the team work well together and know what was going right and wrong?
Informal Recognition
There are many ways to reward people for a job well done. The reward might be an informal
after work gathering or a lunch-time celebration. If people are willing to chip in, you could
provide mugs that commemorate the event.
Formal Recognition
Management may also want to express recognition of a successful team effort by praising the
team at a key meeting or a large gathering of staff. People are proud to have senior management
appreciation stated, and such recognition sets the stage for future successful work. Formal
recognition can also be achieved through coordination with the Kansas Information Technology
Office for articles in industry periodicals and by updating the project data that is circulated to the
legislature.
94
public recognition and offers an opportunity to discuss ways to improve future processes and
procedures.
One purpose of the PIER is to document lessons learned. This means that problems encountered
by the project team are openly presented. Problem identification on completed projects provides
a method to discuss the issue in hopes of eliminating its occurrence in future endeavors. It is
important, however, that the problem discussions do not merely point a finger away from the
project team. Responsibility and ownership for problem areas are critical to developing useful
recommendations for future processes. Problems that were encountered should be prioritized
with focus on the top five to ten problems. One should not document every problem. Since
problems or sensitive issues may be discussed in the PIER and Lessons Learned, it is helpful to
have all contributing parties review the materials prior to formally submitting the document. It is
useful to have the reviews in an interactive forum where all parties can discuss their
recommendations for improvement. The PIER can then present a complete view of the project.
95
76