(4). What’s SWEBOK? How many KAs (knowledge areas) in SWEBOK V3? List the first 5 KAs in SWEBOK V3.
(1). When we talk about managing people in project management, different personality types should be taken into account. Please list three kinds
of “Personality types”. What should you consider personality types when selecting staff?
(2). What are the two aspects you should consider when you conduct 'Risk analysis'? You can get a list of risks after 'Risk identification' and 'Risk
analysis', respectively, what's the difference between the two lists?
(5). A number of design choices have to be made to develop integrated application systems. What are these choices?
Ⅲ. Case analysis(20points)
Assume that you are working in a company that develops Intelligent Terminal systems. The company wishes to enter the growing market of
Mobile Application to help people live conveniently, e.g. for helping elderly and disabled people live independently.
You are appointed to be the project manager and lead a team of 6-8 developers to develop a new product which mainly includes wearable
equipment (Hardware) as well as some Mobile Apps (Software).
Please describe it in detail on how to carry out your project in a systematic and organized way based on theories and practice of software
engineering, especially ‘Project Management’ concerns(individual motivation, team spirit, group composition) you have learned in this course.
(1) (6points) What are the three types of component composition? Describe them in graphical ways.
(2) (6points) What are the two kinds of related interfaces for a component? Please draw a diagram expressed in UML notation, and these two
kinds of interfaces can be fitted with each other.
(3) (6points)
The following diagram describes Estimate uncertainty for project planning. Horizontal axis means project progresses(stage), Vertical axis means
the range of the actual effort as measured.
(a) (3points) If the initial estimate of effort required is x months of effort, what’s the range of the actual effort as measured when the system was
delivered according to the above diagram?
(b) (3points) During development planning, what’s the change trend of estimates as the project progresses(goes on)?
1/2
Final Test Paper
(4) (12points)
A hypothetical set of tasks is created as shown in the following table, it shows tasks estimated effort, duration, and task interdependencies.
Effort
Task Duration (days) Dependencies
(person-days)
T1 15 10
T2 8 15
T3 20 15 T1 (M1)
T4 5 10
T5 5 10 T2, T4 (M3)
T6 10 5 T1, T2 (M4)
T7 25 20 T1 (M1)
T8 75 25 T4 (M2)
T9 10 15 T3, T6 (M5)
T10 20 15 T7, T8 (M6)
T11 10 10 T9 (M7)
T12 20 10 T10, T11 (M8)