Improving Cost Estimation in Construction Projects
Improving Cost Estimation in Construction Projects
net/publication/347361552
CITATIONS READS
18 1,559
3 authors:
Karim Eldash
Benha University
79 PUBLICATIONS 324 CITATIONS
SEE PROFILE
All content following this page was uploaded by Mohamed Abdelhamid on 16 September 2022.
To cite this article: Mohamed Sayed , Mohamed Abdel-Hamid & Karim El-Dash (2020): Improving
cost estimation in construction projects, International Journal of Construction Management, DOI:
10.1080/15623599.2020.1853657
ABSTRACT KEYWORDS
The accurate cost estimate is one of the success keys to construction projects. The influence of inaccurate Cost estimation;
cost estimation on construction projects is critical. There is no consensus among researchers about the questionnaire;
most important factors influencing the cost estimate accuracy. The study’s objective is to get an accurate Pareto technique
cost estimate because the precise cost estimate keeps all parties focused on delivering the project within
the budget. This objective is achieved by collecting the influential factors from the literature review and
creating a powerful arithmetical model of cost estimation. Twenty-nine factors were collected by review-
ing many researches. A questionnaire was prepared and then was examined by fourteen project manag-
ers. Pareto technique was conducted to get the foremost influential factors. Based on the Pareto
technique, the 29 factors were reduced to nine. Then, a powerful arithmetical model was created in this
study to get an accurate cost estimate. Finally, fourteen finished projects were selected to be case stud-
ies. The cost variance percentages were between 1% and 15% for each case study. By using the model,
the estimated contract value of each case study was recalculated and, the cost variance percentages
were between 0.5% and 0.8% for each case study.
important cost estimation factors from twenty-nine factors. The clarified that the cost information’s accuracy and reliability play
questionnaire form’s contents were based on the previous litera- an essential role in increasing the cost estimate precision.
ture review and consisted of twenty-nine factors investigated by On the other hand, cost estimating methodologies will be dis-
researchers. Then, the questionnaire was sent to 280 participants, cussed in detail to get the best methodology. That’s to use it in
and the total respondents are about 265. The respondents are civil the arithmetical model. The list of factors that affect the cost
engineers who consist of consultant and contractor engineers. estimation process will also be discussed in detail in the follow-
The Pareto technique is used to analyse all the collected data, ing sections.
allows seeing which 20% of factors cause 80% of the problems
and where efforts should be focused to get the most significant
improvement. This technique shows the foremost influential fac-
tors, which are reduced from twenty-nine to nine. The first three Cost estimating methodologies
factors are the market’s state, the estimating team’s experience
level, and site conditions. There are two cost estimating methodologies; conceptual and
The study provides a powerful arithmetical model, which is detailed. As the project definition level increases, the estimat-
created to estimate the construction project cost. This model is ing method will progress from conceptual methods to
developed by merging the nine factors inside the model and detailed methods.
selecting all techniques and procedures to get an accurate Early-stage cost estimation plays a vital role in backing up the
cost estimate. owners’ decision making (Zhi et al. 2014). When the project is
Fourteen finished construction projects were selected to be feasible, the owner proceeds by engagement of design firm to
case studies to validate the nine factors’ importance and the describe the project’s unique requirements and quality of con-
model’s effectiveness. These case studies had cost variance struction. The design team will prepare an approximate estimate
between the estimated cost and final actual contract value. There of the project at this stage (Akintoye 2000). This type of estima-
is a significant relationship between the nine factors and the cost tion is known as a conceptual estimation. After the owner has
variance reasons for each case study. That’s clarified the import- invited contractors to bid, the contractors make their detailed
ance of the nine factors, and the cost estimator must consider bid estimate. The contractor should present the lowest and the
the nine factors while conducting the cost estimation process. most accurate estimate because he aims to gain the project. The
On the other hand, the cost variance percentages were between contractor should use the detailed cost estimation methodology
1% and 15% for each case study, but after using the arithmetical because it is the most precise methodology to get a precise cost
model, the case studies’ cost variance percentages are between estimate. The detailed estimation aims to establish the real cost
0.5% and 0.8%. That’s clarified the model’s effectiveness. Hence, of executing the project (Phuwadol 2010). Detailed cost estimat-
the cost estimators should use the study’s model to get the most ing consists of the following seven steps:
accurate cost estimate for the construction projects.
The study’s results are the nine factors deduced from the Separating the project into individual work items.
Pareto technique and the powerful arithmetical model. That’s to Determining labor, equipment, and material that are
get an accurate cost estimate. required to execute all work items.
The research methodology was chosen with the previous Defining the production rate.
sequence to show how the study’s objective is achieved and to Determining the cost of labor, equipment, and material.
provide more clarification for the reader. All the previous points Calculating the total cost for each work item by summing
will be discussed in detail in the following sections. all work item costs.
Determining taxes, overhead cost, and profit complete
the estimate.
Literature review Reviewing by the estimator is also required to determine if
This study is needed to get an accurate cost estimate for con- the assembly’s price seems reasonable for the amount of
struction projects. Previous studies and several researches have work that has to be completed (Phuwadol 2010).
been done to discuss the cost estimate’s precision and the influ- The estimators should depend on the detailed cost estimation
ential factors that affect the cost estimate’s accuracy in the con- methodology to get an accurate cost estimate, and also, this
struction projects. Azman et al. (2013) presented research to methodology is used in the study’s model.
enhance the cost estimate accuracy in Malaysia, selected eighty-
three projects as case studies and then, deduced that site condi-
tions and cost data are essential factors in preparing accurate
estimates. Mahamid (2015) determined forty-one factors affect List of factors
the accuracy of cost estimation for construction projects in the
West Bank in Palestine. He deduced that the estimating team’s Many studies were performed on the factors influencing the
experience level is an essential factor in improving construction accuracy of construction projects cost estimate. The researchers
projects’ cost estimate. Odusami and Onukwube (2008) discussed used different procedures to define the most influential factors
the factors that influenced the cost estimation process and identi- on the cost estimate’s accuracy. Table 1 shows some factors
fied the most influential factors. These factors are the estimating which were mentioned in previous literature.
team’s experience level and market condition. Hatamleh et al. Table 1 includes some factors affecting the cost estimate’s
(2018) mentioned that the equipment’s cost change affects the accuracy, the researcher names, and the published research year.
cost estimate’s accuracy in the construction projects. Qinghua Based on that, twenty-nine factors are collected in Table 3
(2019) stated that the estimator must consider the site conditions and are divided into three groups. The groups are project char-
because they cost overcharge, which might be missed while con- acteristics, financial issues, and estimation process. That will be
ducting the cost estimation process. Avinash et al. (2018) clarified in the questionnaire section.
INTERNATIONAL JOURNAL OF CONSTRUCTION MANAGEMENT 3
Table 1. Some factors affecting construction projects listed in the literature review.
No. Author Year Factors
1 Neufville et al, 1977 a. Level of competition
2 Taylor, 1977 a. Availability of productivity standards
b. Site conditions
3 Strandell, 1978 a. Productivity of labor & equipment
4 Smith and Jolly, 1985 a. Productivity of labor & equipment
b. Weather conditions
5 Skitmore, 1985 a. Experience of estimators
6 Koehn and Brown, 1985 a. Weather conditions
7 Azzaro et al, 1987 a. Estimating method
b. Available database
c. Market conditions
d. Site conditions
8 Loannou, 1988 a. Site condition
9 Akintoye, 2000 a. Project team requirement
b. Contract requirement
c. Project duration
d. Market requirement
10 Elhag et al, 2005 1-Location of the project
11 Odusami and Onukwube, 2008 a. Project team’s experience of the construction type
b. The tender period
c. Market condition
12 Aftab et al, 2010 a. Availability of management and finance plans
13 Enshassi et al, 2013 a. Location of the project
14 Alumbugu et al, 2014 a. Project teams experience on the
b. Specification
15 Arif et al, 2015 a. Inflation
b. Market condition
c. Location
16 Hatamleh et al, 2018 a. Market condition
b. Equipment (performance/cost)
17 Avinash et al, 2018 a. Inflation
18 Agyekum, 2018 a. Market condition
b. Site location and condition
respondent’s name, e-mail, experience years, and job occupied. measure assesses the intended concept of the study (Roberts
The second part includes the twenty-nine factors, which are split et al. 2006).
into three main areas. These areas are project characteristics, Cronbach’s a coefficient test is used for appraisal of the reli-
financial issues, and estimation process. The respondents have ability. The measure is considered to be reliable if the value of
five options for each factor. These are ‘very major effects’, ‘major Cronbach’s a coefficient equals or exceeds 70 percent (Cronbach
effects’, ‘minor effects’, ‘very minor effects’ and ‘no effect’. and Shavelson 2004). In this study, the values of Cronbach’s a
Choosing the participators who are participating in the ques- Coefficient for each group ranged from 0.75 to 0.90. Since these
tionnaire. Hence, sending the questionnaire to them and then values were more than 0.7, the instrument of the questionnaire
collecting all questionnaires after filling them out to get opinions. was stable and reliable.
Finally, putting all opinions in Table 3, which contains all Two statistical tests were conducted to ensure the question-
respondents’ selections. naire’s validity. The first Spearman test was conducted to ensure
The questionnaire’s main objective is to get opinions in the last criterion validity. Thus, the Spearman coefficient and p-value
column from Table 3 and then conduct the Pareto technique. were calculated between each item in one group and the whole
Table 3 includes all respondents’ opinions for each factor, and group. The obtained results of the p-values are less than 0.05.
each respondent has five choices for selecting between them in Therefore, the correlation coefficients of the trait are statistically
each factor. significant, which means that the tools used are valid to measure
what is intended to be measured.
Reliability and validity The second Spearman test is conducted for validity. The
Spearman coefficient and p-value are calculated for each of the
The tool’s reliability means that the study’s findings are stable three groups. The p-values are less than 0.05. Therefore, the cor-
and can be replicated for another case; validity implies that the relation coefficients of the trait are statistically significant; this
means that the tools used are valid.
Table 2. Respondents’ information.
Respondents’ information Frequency Percent %
A) Type of respondents’ occupation
Consultant engineers 60 22.6
Pareto technique
Contractors’ engineers 205 77.4
Pareto technique is a statistical technique in decision-making
B) Respondents’ experience years in the construction industry
<2 years 35 13 used to choose a limited number of tasks that produce a signifi-
2 to 5 years 55 21 cant overall effect. After collecting all respondents’ opinions in
5 to 10 years 40 15 the previous section, the Pareto technique is selected to deduce
10 to 20 years 65 24.5
>20 years 70 26.5 the most influencing factors from the twenty-nine factors; the
Pareto technique is used to sort the factors in descending order.
Table 3. The results for factors influencing the accuracy of cost estimation.
No Very minor Minor Major Very major
No. Factors effect (1) effect (2) effect (3) effect (4) effect (5)
A) Project characteristics
1 Weather conditions 14 88 74 52 37
2 Transportation problems 15 0 29 15 206
3 Availability of power & Water in site 22 0 29 15 199
4 Site conditions 0 0 15 29 221
5 Vandalism and site security 44 81 118 7 15
6 Project schedule and shelf-life 15 7 22 44 177
7 Type of contract 45 81 88 29 22
8 Specification 44 37 140 29 15
9 Experience of field staff 0 51 103 74 37
10 Labor and equipment required 7 8 22 15 213
11 Use old equipment 7 37 74 37 110
12 Equipment maintenance 30 7 0 37 191
13 Productivity of labor and Equipment (the effect of learning theory) 37 74 147 7 0
14 Adoption of material from the owner 15 14 15 52 169
15 Control the wastage 29 59 96 52 29
B) Financial Issues
16 State of market 0 1 7 29 228
17 Currency exchange fluctuation average 52 51 133 29 0
18 Uncertainty of taxes 52 0 147 66 0
19 Inflation factor 7 133 37 59 29
20 Availability of management and finance plans 29 0 22 15 199
21 periodical payments 0 15 15 29 206
22 Insurance required 36 59 133 37 0
C) Estimation Process
23 Method used in determining contingency 30 140 59 29 7
24 Availability of productivity standards 15 7 0 37 206
25 Availability of cost indexes average 16 66 29 110 44
26 Experience of estimating team 1 0 7 29 228
27 Estimate notes and (questions & answers) 66 140 59 0 0
28 Time between project announcement and bid opening average 37 81 59 81 7
29 Number of competitors 15 81 140 29 0
INTERNATIONAL JOURNAL OF CONSTRUCTION MANAGEMENT 5
Pareto calculations Figure 1 shows the most significant factors, which are the first
nine factors in the chart. The foremost influential factors are: the
The last column in Table 3 is rearranged in descending order
market’s state, the estimating team’s experience level, site condi-
and then put in Table 4, then calculates the cumulative fre-
tions, labor and equipment required, transportation problems,
quency for each factor and then gets the percentage of cumula- periodical payments, availability of productivity standards, avail-
tive frequency by dividing each the cumulative frequency value ability of power & water in site, and availability of management
by the total. and finance plans.
Table 4 shows the cumulative calculation for each factor and
the cumulative percentage by dividing each the cumulative num-
ber by the total (2,797) for each factor. Analytical model
An analytical model is provided in this study. This model’s main
Pareto chart objective is to get an accurate cost estimate and reduce the vari-
ance between the estimated cost and final cost in the construc-
The value of the Pareto Principle is that it reminds us to focus tion projects. This model consists of inputs and outputs. All
on 20% of the issues that matter. Identify, and focus on those inputs consist of three parts that will be clarified in the inputs
things first, but don’t entirely ignore the remaining 80%. section. This model introduces many reports, which are the
model’s outputs. Reports are the sheets that present information
Results from the Pareto technique in an organized format for the users. The content of these
reports will be clarified in the outputs section. There are some
As a result of the Pareto technique in Figure 1, the authors constraints in this model, such as the project type is the con-
deduce issues: the first nine factors in Figure 1. Not taking the struction project, and the measured quantities of all items in the
nine factors into account during the cost estimation process project must be specific and precise.
leads to inaccuracy of this process’s results and causing a vari- On the other hand, this model is developed by merging the
ance between the estimated cost and the project’s final cost. nine factors inside it and also, selecting all techniques and proce-
Then, the impact of these factors will be verified through a dures are led to the most accurate cost estimation. That’s clari-
review of case studies. fied in the following points:
6 M. SAYED ET AL.
Figure 1. Pareto chart for factors affecting the accuracy of cost estimation.
Three costs estimated probability for each activity (pessimis- merge the market state factor into the model. Typical out-
tic, most likely, and optimistic) are calculated in the report puts include a histogram that shows the number of itera-
of ‘Monte Carlo simulation for estimated cost’. That’s to tions where a particular outcome resulted from the
INTERNATIONAL JOURNAL OF CONSTRUCTION MANAGEMENT 7
simulation or a cumulative probability distribution (S-curve) ‘Aggregate demand plan for the material report’. Using this
that shows the probability of achieving any specific product report, the user can know monthly quantities and monthly
or less. estimated costs for every project’s material.
In the wages & salaries calculation sheet, transportation cost ‘Detailed cost estimation for mobilization, excavation, and
is calculated as a part of the indirect cost. backfilling works report’; ‘detailed direct cost estimation for
In a detailed calculation sheet for mobilization cost, all site concrete works report’; ‘detailed direct cost estimation for
requirements are calculated. finishing & MEP works report’; and ‘detailed indirect cost
The model includes productivity standards, which is an estimation report’. These reports produced all detailed esti-
input in this model. mated costs and expected working hours for each item and
This model contains a monthly allocating cost estimate to all projects. These reports help in making control during the
know what financial value should be provided each month project life cycle and decreasing cost variance.
to complete the project. This model also includes the esti- ‘Estimated cash flow & net cash flow report’. From this
mated cash flow and net cash flow for the project that pro- report, the user can know monthly and cumulative esti-
vides more effective management and financial plans. mated cash flow. That will help the user to determine
finance plans for the project.
Based on the previous, the merging of the nine factors into ‘Equipment ownership cost report’. This report’s outputs are
the arithmetical model and using Mont Carlo simulation techni- salvage value after the end of the default age of equipment,
ques help decrease the cost variance between the estimated cost book value every year, and total depreciation cost.
and final project cost. The next two sections clarify the inputs ‘Break-even point report’. This report for comparison
and the outputs of this model. between owned & rental equipment. (3) Results from the
Pareto technique.
Table 7. Cost variance percentage without using the model and with using model.
Estimated contract Estimated contract Actual CV% without CV% with
value without using value with using contract using the using the
No. Project name the model (EGP) the model (EGP) value (EGP) model model
1 Bank of Housing and Development Branch of Burj Al Arab 63,000,000 63,917,320 64,247,400 2% 0.5%
2 Villa Ghazal 23,277,997 23,610,046 23,776,146 2% 0.7%
3 Belt one Financial New Head Office Smart Village 88,999,332 89,410,116 89,889,326 1% 0.5%
4 Al Bustan Mall 224,759,440 236,035,124 237,235,384 6% 0.5%
5 Core & Shell Offices - Smart Village 38,034,000 40,816,020 41,076,720 8% 0.6%
6 Local Popular Council in Luxor 4,500,000 4,703,000 4,734,000 5% 0.7%
7 Al-Rehab Building 57,788,945 60,317,111 60,747,739 5% 0.7%
8 Bloom Bank Head Quarter 121,530,978 135,153,580 136,053,930 12% 0.7%
9 Madkour quotas primary School in Dakahlyah 1,824,409 2,081,285 2,098,070 15% 0.8%
10 Odeer Al Hadydy secondary industrial school in Dakahlyah 5,409,552 6,127,161 6,172,840 14% 0.7%
11 Rayah building Smart Village 49,000,000 53,706,411 53,998,000 10% 0.5%
12 EFG Hermes New Headquarter - Smart Village 190,687,009 192,018,290 193,547,314 1% 0.8%
13 Piraeus Bank Egypt, Smart Village 190,212,739 196,831,113 198,019,228 4% 0.6%
14 Ekhnatoon School-New Cairo 65,700,000 70,328,828 70,824,600 8% 0.7%
approach for every case study. This table’s information was col- studies’ cost variance percentage is between 0.5% and 0.8% after
lected from communication with project managers and lessons using the model. All these values are in Table 7.
learned registers for every project. Table 7 contains fourteen case studies, estimated contract
The cost variance is the difference between the actual project value without using the model, estimated contract value with
contract value and the estimated project cost. Also, the cost vari- using the model, cost variance percentage without using the
ance percentage (% CV) is considered an indicator of the cost model, and cost variance percentage with using the model.
estimating accuracy. The cost variance reasons show in Table 6
for each case study. All cost variance reasons were collected to
clarify all inaccurate cost estimates reasons. Results of case studies
Table 6 contains the cost variance reasons for each case study. There is a significant similarity between the cost variance reasons,
This table’s information is collected from communication with
which were mentioned in Table 6 for each case study, and the
project managers, from the lesson learned registers, and issue
nine factors deduced from the Pareto chart. That’s clarified
logs for every project.
the nine factors’ importance. The cost estimator must consider the
There is a significant similarity between these cost variance
nine factors while conducting cost estimation calculations. If the
reasons, which were mentioned in Table 6, and the previously
nine factors are considered, the cost variance reasons will decrease.
mentioned nine factors that were deduced from the Pareto chart.
On the other hand, after using the model in all case studies,
That’s clarified the nine factors’ importance. Based on that, the
cost estimator must consider the nine factors while conducting the cost variance percentage decreased, as showed in Table 7.
cost estimation calculations. That proves the model’s accuracy and effectiveness. Hence, the
On the other hand, that’s important to validate the arithmet- estimators should use the study’s model.
ical model’s accuracy and effectiveness. Without using the model,
case studies’ cost variance percentages were between 1% and Summary and conclusions
15%. The estimated contract value for each case study is recalcu-
lated by using the model. The bill of quantity for each case study Estimating the cost of construction projects is highly complex
is the input in the mathematical model, and the new estimated and challenging for construction companies. This study’s sum-
contract value of each case study is the output. Hence, all case mary and conclusions are shown in the following paragraphs:
INTERNATIONAL JOURNAL OF CONSTRUCTION MANAGEMENT 9
Twenty-nine factors were collected from the previous Agyekum G. 2018. The degree of accuracy and factors that influence the
researches. The questionnaire technique was selected to collect uncertainty of SME cost estimates. Int J Constr Manage. 19(5):2–12.
Akintoye A. 2000. Analysis of factors influencing project cost estimating
opinions from participants who consisted of consultant and con- practice. J Constr Manage Econ. 18(1):77–89.
tractor engineers. The questionnaire was distributed to a sample Alumbugu P, Ola-Awo W, Saidu I, Abdullahi M, Abdulazeez A. 2014.
of 280 participants. The objective of this questionnaire is to get Assessment of the factors affecting accuracy of pre-tender cost estimate in
participants’ opinions on twenty-nine factors. Kaduna state, Nigeria. IOSRJ Environ Sci Toxicol Food Technol. 8(5):
Using the Pareto technique, the findings indicate that nine 19–27.
Arif F, Lodi S, Azhar N. 2015. Factors influencing accuracy of construction
factors should be considered during the cost estimation process. project cost estimates in Pakistan: perception and reality. Int J Constr
The first three factors from the nine factors are the market’s Manage. 15(1):59–61.
state, the estimating team’s experience level, and site conditions. Avinash RY, Swamy RM. 2018. Factors affecting cost and inflation of a pro-
A powerful arithmetical model is presented in this study to ject. Int Res J Eng Technol. 5(2):1713.
get an accurate cost estimate. Fourteen projects were selected as Azman M, Abdul-Samad Z, Ismail S. 2013. The accuracy of preliminary cost
estimates in public works department (PWD) of Peninsular Malaysia. Int
case studies to validate the nine factors’ importance and the J Project Manage. 31(7):994–1005.
model’s effectiveness. The cost variance reasons between the esti- Azzaro D, Hubbard J, Robertson D. 1987. Contractors’ estimating procedures –
mated cost and final cost were obtained by reviewing all lesson an overview. London (UK): Royal Institution of Chartered Surveyors; p. 2–12.
learned registers for each case study. There is considerable con- Barlett J, Kotrlik J, Higgins C. 2001. Organizational research: determining
vergence between the first nine factors in the Pareto chart and appropriate sample size in survey research. J Inf Technol Learn Perform.
19(1):43–50.
the cost variance reasons in all case studies. If the nine factors Cronbach L, Shavelson R. 2004. My current thoughts on coefficient alpha
are considered, the cost variance reasons will decrease. All case and successor procedures. J Educ Psychol Meas. 64(3):391–418.
studies’ cost variance percentage was 1% and 15%, but after Elhag TMS, Boussabaine A, Ballal TMA. 2005. Critical determinants of con-
using the model, these percentages changed between 0.5% and struction tendering costs: quantity surveyors’ standpoint. Int J Project
0.8% for each case study. Hence, the cost estimator should use Manage. 23(7):538–545.
Enshassi A, Mohamed S, Abdel-Hadi M. 2013. Factors affecting the accuracy
this model to increase the cost estimation accuracy. of pre-tender cost estimates in the Gaza strip. J Constr Dev Countries.
The implications are that the study is not limited to construc- 24(1):2–17.
tion projects only but may be generalized to other types of proj- Hatamleh MT, Hiyassat M, Sweis GJ, Sweis RJ. 2018. Factors affecting the
ects, the findings of this study supply useful information for accuracy of cost estimate: case of Jordan. Eng Constr Architect Manage.
future studies associated with the construction industry. 25(1):113–653.
Koehn E, Brown G. 1985. Climatic effects on construction. J Constr Eng
Finally, the study’s results are the nine factors and the power-
Manage. 111(2):129–137.
ful arithmetical model. That’s to get an accurate cost estimate. Loannou P. 1988. Geologic exploration and risk reduction in under-ground
The nine factors are: the market’s state, the estimating team’s construction. J Constr Eng Manage. 114(4):532–547.
experience level, site conditions, labor and equipment required, Mahamid I. 2015. Factors affecting cost estimate accuracy: evidence from
transportation problems, periodical payments, availability of Palestinian construction projects. Int J Manage Sci Eng Manage. 10(2):
117–125.
productivity standards, availability of power & water in site, and Matel E, Vahdatikhaki F, Hosseinyalamdary S, Evers T, Voordijk H. 2019.
availability of management and finance plans. On the other An artificial neural network approach for cost estimation of engineering
hand, the arithmetical model was verified from its effectiveness services. Int J Constr Manage. 37(5):1–14.
by recalculating the cost estimate for each case study. The cost Neufville R, Hani E, Lesage Y. 1977. Bidding models effects of bidders’ risk
variance percentage after using the model was between 0.5% aversion. J Constr Div. 103(1):57–65.
Odusami K, Onukwube H. 2008. Factors affecting the accuracy of a pre ten-
and 0.8%.
der cost estimate in Nigeria. J Cost Eng. 50(9):32–35.
Hence, the cost estimator must consider the nine factors and Phuwadol S. 2010. A visual approach to construction cost estimating. Thesis
use the arithmetical model while conducting the construction (M.Sc.). Marquette University; p. 2–55.
projects’ cost estimation process. By implementing the study’s Qinghua J. 2019. Estimation of construction project building cost by back-
results, all the previously mentioned gaps in the cost estimation propagation neural network. J Eng Des Technol. 18(3):601–604.
Roberts P, Priest H, Traynor M. 2006. Reliability and validity in research.
process will be addressed. Nurs Standard. 20(36):41–45.
Skitmore R. 1985. The influence of professional expertise in construction
price forecasts. Salford, UK: University of Salford, British Cataloging
Disclosure statement Library Publishing; p. 12
Smith G, Jolly P. 1985. Estimating for building and civil engineering works
No potential conflict of interest was reported by the authors. England: Butterworth’s. 10.
Strandell M. 1978. Productivity in the construction industry. AACE Bull.
20(2):18.
References Taylor T. 1977. How certain area you about the uncertainty of your esti-
mates. AACE Bull. 12(2):30–31.
Aftab H, Ismail A, Mohd A, Ade A. 2010. Factors affecting construction cost Zhi R, Han S, Hyun C, Kim J. 2014. Improving accuracy of early stage cost
in mara large construction project: perspective of project management estimation by revising categorical variables in a case-based reasoning
consultant. Int J Sustain Constr Eng Technol. 1(2):42–54. model. J Constr Eng Manage. 140(7):04014025.