We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1
PMP®/CAPM® Formulas Cheat Sheet
Earned Value Management Earned Value Management
BAC No Formula. Project % Σ BAC Budget At Completion CPI Cost Performance Index 100 No Formula. It is sometimes expressed as a Complete PV Planned Value CPIC Cumulative Cost Performance Index PV %age of BAC. ETC = (BAC – EV) / CPI EV Earned Value CPIP Projected Future CPI No Formula. It is sometimes shown as a ETC = (BAC – EV) EV %age of BAC or PV. ETC ETC = (BAC – EV) / CPIp AC Actual Cost ETC Estimate To Complete AC No Formula. EAC = AC + ETC SV Schedule Variance EAC Estimate At Completion SV SV = EV – PV EAC = AC + (BAC – EV) CV Cost Variance VAC Variance At Completion CV CV = EV – AC EAC = AC + (BAC – EV) / CPI SPI Schedule Performance Index TCPI To Complete Performance Index SPI SPI = EV / PV EAC = BAC / CPI SPIC Cumulative Schedule Performance Index SPIC SPIC =∑EV / ∑PV EAC EAC = AC + [(BAC – EV) / (CPI * SPI)] Network Diagram CPI CPI = EV / AC VAC VAC = BAC – EAC Earned Schedule Management CPIC CPIC = ∑EV / ∑AC TCPI = (BAC – EV) / (BAC – AC) TF Total Float SVT Schedule Variance (Time) Budget % Σ TCPI TCPI = (BAC – EV) / (EAC – AC) FF Free Float 100 SPIT Schedule Performance Index (Time) Spent ES Early Start ES Earned Schedule Estimation AT Actual Time LS Late Start Earned Schedule Management E = (O + P + M) / 3 EF Early Finish LF Late Finish SVT ES - AT Triangular − + − − Estimation SPIT ES / AT = √ Dur Duration Dist. 18 E Expected Value PERT E = (O + P + 4*M) / 6 O Optimistic Value Network Diagram σ = (P – O) / 6 P Pessimistic Value Project Selection Methods TF = LS – ES Range Est. R = E ± (n * σ) M Most Likely Value PV Present Value Total Float TF = LF – EF Var. Var = σ2 SD or σ Standard Deviation or Sigma DCF Discounted Cash Flow Free Float FF = ESSuccessor – ESPresent – DurPresent Path Var. VarPath = ∑(Var) Var Variance of an Activity FV Future Value Path St. VarPath Variance of a Network Path r Discount Rate = √ Project Selection Methods Deviation n Sigma multiplication Factor n Number of years n PV = FV / (1 + r) 1σ = 68.27% DF Discount Factor PV / DCF PV = FV * DF 2σ = 95.45% Expected Monetary Value NPV Net Present Value NPV NPV = ∑PV Sigma 3σ = 99.73% EMVR Expected Monetary Value for Risk ROI Return on Investment ROI ROI = Return / Investment Values 4σ - 99.994% P Probability BCR Benefit Cost Ratio BCR BCR = Benefits / Costs 5σ = 99.99994% I Impact (Monetary Value) CBR Cost Benefit Ratio CBR CBR = Costs / Benefits 6σ = 99.999999% EMVP Expected Monetary Value for Project IRR Internal Rate of Return IRR Formula not needed. Higher is better. PP No formula. Lesser the better. Communication Channels PP Payback Period Opp Cost No formula. C = n*(n – 1) / 2 Procurement Opp. Cost Opportunity Cost Expected Monetary Value PTA Point of Total Assumption EMVR EMVR = P * I Procurement CP Ceiling Price Communication Channels EMVP EMVP = ∑EMVR Pt. of Total − TP Target Price C Number of Communication Channels = + Net Benefit Net Benefit = EMVP – Cost Assumption !ℎ #$%& TC Target Cost n Number of Stakeholders