Tutorial

The document provides information about a project management tutorial, including two example projects with activity information and questions to draw activity on arrow networks, calculate early and late start/finish times, and draw bar charts for the projects.

Uploaded by

aderramo66
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
21 views

Tutorial

The document provides information about a project management tutorial, including two example projects with activity information and questions to draw activity on arrow networks, calculate early and late start/finish times, and draw bar charts for the projects.

Uploaded by

aderramo66
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

SCHOOL OF ENGINEERING & TECHNOLOGY

Department : Structural Engineering Program


Course : Project Management (CIV471)
Instructor : Assc.Prof. Ahmed Ehab
T. Assistant : E. Mostafa Ismael

Tutorial (3)
Activity on Arrow (A.O.N)
SCHOOL OF ENGINEERING & TECHNOLOGY
Department : Structural Engineering Program
Course : Project Management (CIV471)
Instructor : Assc.Prof. Ahmed Ehab
T. Assistant : E. Mostafa Ismael

Tutorial (3)
Activity on Arrow (A.O.N)

➢ For the Following project data, answer the following questions:

Activity Duration (days) Predecessor

A 2 --
B 6 A
C 3 A
D 1 B
E 6 B
F 3 C, D
G 2 E, F

Solution in Class

• Draw an AON network and perform forward and backward pass calculations?
• Draw a time-scaled diagram of the project?
• Tabulate activities ES, EF, LS, LF, TF, and FF.
• What is the effect of delaying activity D by 3 days?

➢ Draw (A.O.N) then Calculate (ES/LS/EF/LF/TF/FF) for each activity then draw Bar
Chart for this Project.

Activity Dur IPA REL LAG


A 2 -
B 4 -
C 5 -
D 6 A,B
E 8 A,C
F 2 D SF 2
E SS 4
G 3
E FF 3
H 4 D,E

Solution in Class
SCHOOL OF ENGINEERING & TECHNOLOGY
Department : Structural Engineering Program
Course : Project Management (CIV471)
Instructor : Assc.Prof. Ahmed Ehab
T. Assistant : E. Mostafa Ismael

Tutorial (3)
Activity on Arrow (A.O.N)

➢ Draw (A.O.N) then Calculate (ES/LS/EF/LF/TF/FF) for each activity then draw Bar
Chart for this Project.

Solution in Class

Solution in Class