Assignment
Assignment
Assignment (3)
Example (1)
1. The free float is defined as:
a. The amount of time an activity can be delayed without affecting the following activity.
b. The amount of time an activity can be delayed without affecting total project duration.
a. The critical activities can be determined easily when using the bar chart.
b. The network must have definite points of beginning and end.
c. The network must be continuous from start to end.
d. There’s no dummy activities in the arrow networks,
e. A forward pass is used to determine late start and late finish times.
f. The time for completing a project is equal to the sum of the individual activity times.
Example (2)
For the Following project data, answer the following questions:
A 2 --
B 6 A
C 3 A
D 1 B
E 6 B
F 3 C, D
G 2 E, F
• Draw an AON network and perform forward and backward pass calculations?
• Draw a time-scaled diagram of the project?
• Tabulate activities ES, EF, LS, LF, TF, and FF.
• What is the effect of delaying activity D by 3 days?
SCHOOL OF ENGINEERING & TECHNOLOGY
Department : Structural Engineering Program
Course : Project Management (CIV471)
Instructor : Assc.Prof. Ahmed Ehab
T. Assistant : E. Mostafa Ismael
Assignment (3)
Example (3)
Example (4)
Draw an (A.O.N) Network for the shown project Activities
and determine Activity IPA Dur
A 4
1- The Total Duration of this Project B 2
2- The Critical Path/s of this Project C A 5
3- The Most Critical Activity D A 3
4- Draw the Bar Chart for this Project E C 3
F C,D,G 4
G B 3
H G 5
I G 6
J E 4
K H 4
L K 5
M K,I 2
N F,J 9
O L,M 4
P L,M 6
SCHOOL OF ENGINEERING & TECHNOLOGY
Department : Structural Engineering Program
Course : Project Management (CIV471)
Instructor : Assc.Prof. Ahmed Ehab
T. Assistant : E. Mostafa Ismael
Example (6)
Draw (A.O.N) then Calculate (ES/LS/EF/LF/TF/FF) for each activity then draw Bar Chart for
this Project.
Assignment (3)
Example (7)
Draw (A.O.N) then Calculate (ES/LS/EF/LF/TF/FF) for each activity then draw Bar Chart for
this Project.
Example (8)
Complete this project then Calculate (ES/LS/EF/LF/TF/FF) for each activity then draw Bar Chart
for this Project.