Quantity Surveying and Contract Management Notes
Quantity Surveying and Contract Management Notes
Quantity Surveying and Contract Management Notes
INTRODUCTION
Actual cost: The actual cost of the work is known after the completion of the work.
Purpose of estimate
1. Probable cost to be made ready for taking a project.
2. To obtain administrative approval in case of public construction
3. To ascertain the qualities of the labour.
4. To fix up a construction schedule
5. To justify the benefit cost ratio
6. To invite tenders and prepare bills for payments
TYPES OF ESTIMATES
This estimate is prepared to decide financial aspect, policy and to give idea of the cost
of the proposal to the competent sanctioning authority. It should clearly show the necessity of
the proposal and how the cost has been arrived at
Department Of Civil Engineering, Dr.TTIT, Kgf. Page 1
Quantity Surveying and Contract Management – 15CV81
The calculations for approximate estimate can be done with the following data. The
data can be had from a similar construction already complete in the nearby area, excuted by
the department.
For example: To calculate approximate estimate for a Hospital, per bed cost is
calculated from the recent completed hospital and is multiplied with the number of beds
required. Similarly for a house, per square metre plinth area is calculated and is multiplied
with the proposed covered area. The specifications should also be same. For a road,
expenditure of per kilometre length is taken, width also plays the role.
a) Detailed report
b) Site plan of the proposal
c) It should also clearly mention about the acquisition of land, Provision of electric
and water supply etc.
Plinth area of a building means Length x Breadth ( roofed portion only ) excluding
plinth offsets. The estimates are prepared on the basis of plinth areas of the various buildings
proposed to be constructed. The rates are being arrived at the dividing the total cost of
construction with its plinth area. For example if total cost of a building is Rs. 2 lac and its
plinth area is 50 sq. m. then plinth area rate =2,00,000 = Rs.4000/- per 50 sq.m. Using this
rate as basis of the next construction, approximate or rough cost of the proposal can be
arrived at by multiplying the plinth area of the proposed building with this plinth area rate.
The cubic contents of a building means plinth area x height of the building. The
height is taken from top of floor level to top of roof.
The cubic contents of the proposed building are multiplied with cubic rates arrived at
for the similar construction i.e. total cost of construction divided by cubic contents = cost per
cubic metre.
4. Detailed Estimate
After getting Administrative approval on rough cost estimate, detailed estimates are
prepared.
In this, the estimate is divided in to sub-heads and quantities of various items are
calculated individually.
In the end of the detailed quantities, an abstract of cost giving quantities of each item
and rate of every item according to the sanctioned schedule of rates shall be attached. In case
of non-schedule rates i.e. rates which are not given in the sanctioned schedule of rates, proper
analysis of rates shall be attached. If however the work proposed to be constructed is located
in a remote place, the provision for the carriage of the material shall be added in the estimate
to avoid any excess over the administratively approved estimate later on. Detailed
specifications & report should also be attached with the estimate. Technical sanction is given
on detailed estimate.
The detailed estimate shall also provide for the cost of approach road, water supply,
electric installations and acquisition of land etc, so as to call it a comprehensive estimate.
In order to keep building and roads in perfect condition, annual repairs should be
carried out as follow:-
(i) In case of a building-white washing, oiling and painting of doors and windows,
cement plaster repairs (inside & outside), repairs of floors etc. In no case this annual repair
amount should increase more than 11/2% to 2% of the capital cost of the building.
7. Revised estimate
When the sanctioned estimate exceeds by 5% either due to the rate being found
insufficient or due to some other reasons, a fresh estimate is prepared which is called a
Revised Estimate. A comparative statement on the last page of the estimate is attached giving
there in the reasons of the increase of cost in case of each item.
8. Supplementary Estimate
This is fresh detailed estimate in addition to the original sanctioned estimate prepared
when additional works are deemed necessary during the progress of a work to supplement the
original works. The abstract of cost should show the amount of the original sanctioned
estimate as well as the supplementary amount of the original sanctioned estimate as well as
the supplementary amount for which sanction is required.
2. Crossing method.
5. Bay method.
This method is suitable only if the offsets are symmetrical and the building is more or
less rectangular in shape. The centre line of the building is determined carefully after doing
deductions for repeated measurements (as explained in the next problem). This centre line
acts as length for the complete calculations of the estimate. If the deduction is not cared for
the results of estimates may be wrong. All the walls should have the same section.
2. Crossing Method
In this method, lengths and breadths of the masonry walls at plinth level are taken
(internal dimension of the room + thickness of the walls) for calculating quantities. The
symmetrical offsets are a must as in the case of centreline method.
This method is most practicable under all circumstances and is generally followed in
the P.W.D. for computing the quantities of various items. The estimation in this book has
been done using this method.
4. Bay Method
This method is useful and is generally followed in case of building having several
bays. The cost of the one class room is worked out and then multiplied by the number of bays
in that building. The extra cost of the end walls and difference in framing. If there is any,
should be made, so as to arrive at the correct cost.
This method is followed in cases such as school building where there are so many
class rooms. The cost of one class room us worked out and then multiplied by the number of
class rooms to be construed. In case of Hospitals, the service unit is a bed, in case of Water
Tank, it is a litre and in case of Cinema Hall, the service unit is a seat.
Part A
METHOD OF ESTIMATING
Detailed estimate: Preparation of detailed estimate consists of working out the quantities of
different items of work and then working out the cost i.e. the estimate is prepared in two
stages
Height
Item Length, Breadth, or Quantity,
Particulars of items No. Explanation
No. m m depth, cu.m
m
2. Abstract of estimated cost: The cost under item of work is calculated from the
quantities already computed at workable rate, and the total cost is worked out in
prescribed form. A percentage of 3 to 5 percent is added for contingencies, to allow
for petty contingent expenditures, unforeseen expenditures, changes in design,
changes in rates, etc. which may occur during execution of the work.
Abstract of Estimate form -
SI Rate,
Particulars Quantity Unit Per Amount, Rs
No. Rs
Drawings: If the drawings are not clear and without complete dimensions the preparation of
estimation become very difficult. So, It is very essential before preparing an estimate
Specifications
a) General Specifications: This gives the nature, quality, class and work and materials in
general terms to be used in various parts of wok. It helps no form a general idea of building.
b) Detailed Specifications: These gives the detailed description of the various items of work
laying down the Quantities and qualities of materials, their proportions, the method of
preparation workmanship and execution of work.
Rates: For preparing the estimate the unit rates of each item of work are required.
1. Earthwork
2. Concrete in foundation
3. Soling
4. Damp proof course
5. Masonry
6. Arch Masonry work
7. Lintels over openings
8. R.C.C work
9. Flooring and roofing
10. Plastering and pointing
The principle for dimensions and measurements is to use millimetre (mm) for minute
dimensions, centimetre (cm) for small dimensions and metre (m) for big dimensions.
The dimensions, length, breadth and height of depth are to be taken out from the drawing-
plan, elevation and section. From the drawings, the dimensions are to be taken out correctly.
In this method, measure or find out the external length of walls running in the longitudinal
direction generally the long walls out-to-out, and the internal lengths of walls running in
transverse direction in-to-in. the same rule is applicable to the excavation in foundation, to
concrete in foundation and to masonry. Care should be taken to note the difference in
dimensions at different height due to offset or footings.
Long wall length out-to-out = centre to centre + half breadth on one side + half breadth on
other side = centre to centre length + one breadth
That is, in case of long wall add one breadth and in case of short wall subtract one breadth
from the centre length to get the corresponding lengths.
Example 1: The diagram represents the plan of the superstructure wall of a single room
building of 5m x 4m, and sections represent the cross-sections of the walls with foundation.
Estimate the quantities of – earthwork in excavation in foundation, concrete in foundation,
brickwork in foundation and plinth, brick work in superstructure.
Height
Item Length, Breadth, or Quantity,
Particulars of items Explanation
No. m m depth, cu.m
No. m
Earthwork in excavation in
1
foundation
L = 5.30 + 0.90 =
Long walls 2 6.20 0.90 0.90 10.04 6.20 m
S = 4.30- 0.90 =
Short walls 2 3.40 0.90 0.90 5.51 3.40 m
Total 15.55
cu.m
2 Concrete in foundation
L = 5.30 + 0.90 =
Long walls 2 6.20 0.90 0.30 3.35 6.20 m
S = 4.30- 0.90 =
Short walls 2 3.40 0.90 0.30 1.84 3.40 m
Total 5.18
cu.m
1st class brickwork in
3
foundation and plinth
Long walls
L = 5.30 + 0.60 =
1st footing 2 5.90 0.60 0.30 3.65 5.90 m
L = 5.30 + 0.50 =
2nd footing 2 5.80 0.50 0.30 1.74 5.80 m
L = 5.30 + 0.40 =
Plinth walls 2 5.70 0.40 0.60 2.74 5.70 m
Short walls
S = 4.30-0.60 = 3.70
1st footing 2 5.50 0.80 0.20 1.76 m
S = 4.30-0.50 = 3.80
2nd footing 2 5.60 0.70 0.10 0.78 m
S = 4.30-0.40 = 3.90
Plinth walls 2 5.90 0.40 0.80 3.78 m
Total 14.45
cu.m
4 Damp proof course
2.5 cm thick c.c
L = 10.60 + 0.40 =
Long walls 2 11.00 0.40 - 8.80 11.00 m
S = 6.30-0.40 = 5.90
Short walls 3 5.90 0.40 - 7.08 m
Total 15.88
sq.m
1st class brickwork in lime
5
mortar in superstructure
L = 5.30 + 0.30 =
Long walls 2 5.60 0.30 3.50 11.76 5.60 m
S = 4.30-0.30 = 4.00
Short walls 2 4.00 0.30 3.50 8.40 m
Total 20.16
cu.m
Example 2: Estimate the quantities of the following items of a two roomed building from the
given plan and section- Earthwork in excavation in foundation, Lime concrete in foundation,
1st class brickwork in cement mortar 1:6 in foundation and plinth, 2.5 cm c.c. damp proof
course and 1St class brickwork in lime mortar in superstructure.
Height
Item Length, Breadth, or Quantity,
Particulars of items No. Explanation
No. m m depth, cu.m
m
Earthwork in
1 excavation in
foundation
Long walls 2 11.70 1.10 1.00 25.74 L = 10.60 + 1.10 = 11.70 m
Short walls 3 5.20 1.10 1.00 17.16 S = 6.30 - 1.10 = 5.20 m
Total 42.90
cu.m
Lime Concrete in
2
foundation
Long walls 2 11.70 1.10 0.30 7.72 L = 10.60 + 1.10 = 11.70 m
Short walls 3 5.20 1.10 0.30 5.15 S = 6.30 - 1.10 = 5.20 m
Total 12.87
cu.m
1st class brickwork
3 in foundation and
plinth
Long walls
1st footing 2 11.40 0.80 0.20 3.65 L = 10.60 + 0.80 = 11.40 m
2nd footing 2 11.30 0.70 0.10 1.58 L = 10.60 + 0.70 = 11.30 m
3rd footing 2 11.20 0.60 0.10 1.34 L = 10.60 + 0.60 = 11.20 m
4th footing 2 11.10 0.50 0.10 1.11 L = 10.60 + 0.50 = 11.10 m
Plinth walls 2 11.00 0.40 0.80 7.04 L = 10.60 + 0.40 = 11.00 m
Short walls
1st footing 3 5.50 0.80 0.20 2.64 S = 6.30-0.80 = 5.50 m
2nd footing 3 5.60 0.70 0.10 1.18 S = 6.30-0.70 = 5.60 m
3rd footing 3 5.70 0.60 0.10 1.03 S = 6.30-0.60 = 5.70 m
4th footing 3 5.80 0.50 0.10 0.87 S = 6.30-0.50 = 5.80 m
Plinth walls 3 5.90 0.40 0.80 5.66 S = 6.30-0.40 = 5.90 m
Total 26.10
cu.m
4 Damp proof course
2.5 cm thick c.c
Long walls 2 11.00 0.40 - 8.80 L = 10.60 + 0.40 = 11.00 m
Short walls 3 5.90 0.40 - 7.08 S = 6.30-0.40 = 5.90m
Total 15.88
sq.m
1st class brickwork
5 in lime mortar in
superstructure
Department Of Civil Engineering, Dr.TTIT, Kgf. Page 13
Quantity Surveying and Contract Management – 15CV81
In this method the sum total length of centre lines of walls, long and short has to be found
out. Find the total length of centre lines of walls, of same type, long and short having same
type of foundation and footings and then find the quantities by multiplying the total centre
length by the respective breadth and the height.
In this method, the length of wall remains same for excavation in foundation, for concrete in
foundation, for all footings and for superstructure. This method is quick but requires special
attention and consideration at the junctions, meeting points of partition or cross walls, etc.
For buildings having cross or partition walls, for every junction of partition or cross wall with
the main walls, special considerations have to be made to find out the quantities accurately.
For each junction half breadth of the respective item should be deducted from the total centre
line length. Thus in the case of building having one partition wall, there are two junctions, for
earthwork in foundation trench and foundation concrete deduct one breadth of trench or
concrete from the total centre length (2 x ½ = one for two junctions).
For buildings having different types of walls, each et of walls shall have to be dealt
separately. Find the total centre length of all walls of one type and proceed in the same
manner as described above. Similarly find the total centre length of walls of second type and
deal this separately, and so on.
In the case of buildings having different types of walls, suppose the outer walls are of A type
and inner cross walls are of B type, then all the A type walls shall be taken jointly first and
then B type walls shall be taken together separately. In such cases no deduction of any kind
need to be made for A type walls, but where B type walls are taken, for each junction
deduction of half breadth of A type wall (main wall) shall have to be made from the total
centre length of walls.
It may be noted that at the corners of the building where two walls are meeting no subtraction
or addition is required.
If the total centre length is multiplied by the breadth and the depth we get the quantity of
earthwork in excavation.
Height
Item Length, Breadth, or Quantity,
Particulars of items No. Explanation
No. m m depth, cu.m
m
Total centre
Earthwork in excavation in
1 1 19.2 0.9 0.9 15.55 length of all walls
foundation = 19.20 m
cu.m
In this problem there are two junctions of the inner wall with the main wall
Total centre length of wall = 2 x c/c of long wall + 3 x c/c of short wall
Diagram
If the total centre length is multiplied by the breadth and depth, at the junction the portions A
and B shown by hatch lines come twice and we get the quantity in excess by these portions,
and these excesses shall have to be deducted. The deduction may be effected reducing the
centre length by half breadth for each junction
Height
Item Length, Breadth, m or Quantity,
No. Particulars of items No. m cu.m Explanation
depth,
m
total centre
length =
40.10m
Earthwork in excavation in L = 40.10 - 2 x
1 1 39.00 1.10 1.00 42.90 1.10/2 = 39.00 m
foundation
cu.m
Lime Concrete in
2 1 39.00 1.10 0.30 12.87
foundation
cu.m
1st class brickwork in
3
foundation and plinth
1st footing 1 39.30 0.80 0.20 6.29
2nd footing 1 39.40 0.70 0.10 2.76
3rd footing 1 39.50 0.60 0.10 2.37
4th footing 1 39.60 0.50 0.10 1.98
Plinth wall above footing 1 39.70 0.40 0.80 12.70
Total 26.10
L = 40.10 -
4 Damp proof course 1 39.70 0.40 15.88
2x0.40/2 = 39.70
Deduct door sill 2 1.20 0.40 0.96
Total 14.92
sq.m
1st class brickwork in lime L = 40.10- 2 x
5 1 39.80 0.30 4.20 50.15
mortar in superstructure 0.30/2 = 39.80 m
cu.m
Deduct
Door Opening 2 1.20 0.30 2.10 1.51
Window Opening 4 1.00 0.30 1.50 1.80
Shelves 0.60 Back of shelves 10
2 1.00 0.20 1.50 cm thick wall
Lintel over doors 2 1.50 0.30 0.15 0.14 Bearing 15 cm
Lintel over windows 4 1.30 0.30 0.15 0.23 Bearing 15 cm
Lintel over shelves 2 1.30 0.30 0.15 0.12 Bearing 15 cm
Total deduction 4.40
Net Total 45.75
cu.m
Example 5: The accompanying figure below shows the details of a two roomed building.
Estimate the quantities and cost of the following items of works: Earthwork in excavation for
the foundation in hard soil at Rs 14/m3, Lime concrete bed 1:2:4 for all walls at Rs. 1200/m3,
First class brick work (CM 1:4) in foundation and plinth at Rs. 2000/m3, First class brick
work (CM 1:4) in superstructure at Rs. 2200/m3, RCC 1:2:4 for roof slab
c/c length of long walls of rooms = 4.50 + 0.30 + 4.00 + 2 x 0.30/2 = 9.10 m
c/c length of front long wall of verandah = (4.5 + 0.3 = 4.0 + 2x0.30) – 2x0.20/2 = 9.20 m
Height
Item Length, Breadth, or Quantity,
Particulars of items No. Explanation
No. m m depth, cu.m
m
Earthwork in excavation in
1
foundation
9.1 + 2 x 0.9/2 =
Long Walls 2 10.00 0.90 0.90 16.20 10.00 m
3.9 - 2x0.90/2 = 3.00
Short walls 3 3.00 0.90 0.90 7.29 m
Verandah sides
Short walls
3.9 - 2x 0.6/2 = 3.30
1st footing 3 3.30 0.60 0.20 1.19 m
3.9 - 2x0.5/2 = 3.40
2nd footing 3 3.40 0.50 0.20 1.02 m
3.9 - 2x0.4/2 = 3.50
up to plinth 3 3.50 0.40 0.80 3.36 m
Total 15.90
cu.m
Steel Reinforcement
(1% of RCC= 5.64 x 0.001 x 7850) 0.5 ton
Abstract of Cost
SI
Particulars Quantity Unit Rate, Rs Per Amount, Rs
No.
1 Earthwork excavation in foundation 31.36 cu.m 140.00 cu.m 4390.40
2 Lime concrete bed 1:2:4 10.74 cu.m 1200.00 cu.m 12888.00
First Class brick work (1:4) in
3 15.90 cu.m 2000.00 cu.m 31800.00
foundation and plinth
First class brick work(1:6) in
4 27.65 cu.m 2200.00 cu.m 60830.00
superstructure
5 RCC 1:2:4 for roof slab 5.64 cu.m 3800.00 cu.m 21432.00
6 Steel reinforcement 0.50 ton 3800.00 ton 1900.00
133240.40
Taking 10% extra 13324.04
Total 146564.44
Example 6: The details of a residential building are shown in the below plan. Workout the
quantities and cost of the following items of work by centre line method
[0.30/2 + 2.5 + 0.30 + 1.0 +0.3 +3.5 + 0.30/2] x 2 + [0.30/2 + 3.5 + 0.3 + 5.0 + 0.30/2] x 2
+ [0.30/2 + 3.5 + 0.30 + 6.5 + 0.30 + 1.7 + 0.30/2] x 3 + [0.30/2 + 3.5 + 0.30/2] = 75.60 m
Height
Item Length, Breadth, or Quantity,
No. Particulars of items No. m m cu.m Explanation
depth,
m
Earthwork in excavation in
1 1 73.60 1.00 0.90 66.24 75.6 - 4(1.00/2)
foundation
cu.m
Total 56.81
cu.m
Abstract of Cost
SI Amount,
Particulars Quantity Unit Rate, Rs. Per
No. Rs.
1 Earthwork excavation in foundation 66.24 cu.m 102.00 cu.m 6756.48
2 Lime concrete bed 1:2:4 56.81 cu.m 2400.00 cu.m 136344.00
First Class brick work (1:4) in
3 63.61 cu.m 3650.00 cu.m 232176.50
foundation and plinth
375276.98
Taking 10% extra 37527.70
Total 412804.68
Example 7: Estimate by centre line method the quantities of the following items of a
residential building: 1) Earthwork in excavation in foundation, 2) Lime concrete in
foundation, 3) First class brickwork in 1:6 cement sand mortar in foundation and plinth, 4)
Damp proof course and 5) First class brickwork in lime mortar in superstructure.
Sol: Total centre length of all 30 cm walls of main rooms = Total centre length of walls of
drawing and left side bed room + Total centre length of walls of bed rooms right side.
= (2 x c/c length of long wall + 3 x c/c length of short wall) + (2 x c/c length of long wall + 2
x c/c length of short wall) = (2 x 10.60 + 3 x 5.30) + (2 x 9.60 + 2 x 4.80) = 65.90 m.
Total centre length of all 20 cm walls of front verandah, back verandah and bath room
= (c/c length of front wall + c/c length of side wall) + (c/c length of back verandah long wall
including bath + 2 x c/c length of cross walls of bath room) = (9.65 + 2.25) + (9.65 + 2 x
2.75) = 27.05 m.
Height
Item Length, Breadth, or Quantity,
No. Particulars of items No. m m cu.m Explanation
depth,
m
Earthwork in excavation in
1
foundation
Walls of main room (6 L = 65.90 -
1 63.20 0.90 1.00 56.88 6x0.90/2 = 63.20 m
junctions)
L = 27.05 -
Walls of verandah (5 and 1
1 24.50 0.60 0.50 7.35 5x0.90/2 -1x0.60/2
junctions) = 24.50 m
Total 64.23
cu.m
2 Lime Concrete in foundation
Walls of main rooms L = 65.90 -
1 63.20 0.90 0.30 17.06 6x0.90/2 = 63.20 m
Walls of verandah and bath L = 27.05 -
1 25.50 0.60 0.20 3.06 5x0.50/2 - 1x0.60/2
=225.50 m
Total 20.12
cu.m
1st class brickwork in
3 foundation and plinth in 1:6
cement mortar
Walls of main rooms
L = 65.90 -
1st footing 1 64.10 0.60 0.20 7.69 6x0.60/2 = 64.10 m
L = 65.90 -
2nd footing 1 64.40 0.50 0.20 6.44 6x0.50/2 = 64.40 m
L = 65.90 -
Plinth wall above footing 1 64.70 0.40 0.90 23.29 6x0.40/2 = 64.70 m
Part B
Example 1: Prepare an detailed estimate of a septic tank with soak pit for 25 users from the
given drawing
Septic tank shall be of first class brickwork in 1:4 cement mortar the foundation and floor
shall be of 1:3:6 cement concrete. Inside of septic tank shall be finished with 12mm cement
plaster and floor shall be finished with 20 mm cement plaster with 1:3 mortar mixed with
standard water proofing compound. Upper and lower portion of soak-pit shall be of second
class brickwork in 1:6 cement mortar and middle portion shall be dry brickwork. Roof
covering slabs and baffle wall shall be of precast RCC. The length of the connecting pipe
from latrine seat may be taken as 3 m. Assume suitable rates.
Height
Item Length, Breadth, or Quantity,
Particulars of items No. Explanation
No. m m depth, cu.m
m
1 Earthwork in excavation
H = 140 + 30 + 20
Septic tank 1 2.80 1.70 1.95 9.28 +5 = 1.95 m
Soak pit up to 3 m depth 1 3.13 3.00 9.39
Soak pit lower portion 1 1.53 0.20 0.31
Total 18.98
cu.m
2 Cement concrete 1:3:6
Floor and foundation 1 2.80 1.70 0.20 0.95
Sloping floor 1 2.00 0.90 0.05 0.09
Total 1.04
cu.m
First class brickwork in 1:4
3
CM in septic tank
Long walls
1st step 2 2.60 0.30 0.60 0.94
2nd step 2 2.40 0.20 1.15 1.10
Short walls
1st step 2 0.90 0.30 0.60 0.32
2nd step 2 0.90 0.20 1.15 0.41
Total 2.78
cu.m
2nd class brickwork in 1:6
4
cement mortar
Soak pit
Upper portion 1 3.77 0.20 0.50 0.38
Lower portion 1 3.77 0.20 0.20 0.15
Total 0.53
cu.m
Example 2: Prepare a detailed estimate of a manhole from the given drawing and general
specifications
General Specifications: Foundation and floor concrete shall be of 1:3:6 cement concrete with
brick ballast. Brickwork shall be of first class in 1:4 cement mortar and inner faces of wall
shall be ponted with 1:2 cement mortar. Inside channles and benching floor shall be finished
with 20 mm thick plastering with 1:3 cement mortar.
Height
Item Length, Breadth, or Quantity,
Particulars of items No. Explanation
No. m m depth, cu.m
m
1 Earthwork in excavation 2.80 1.90 2.90 15.43
cu.m
Cement concrete 1:3:6
2
with brick ballast
Foundation and bed 1 2.80 1.90 0.20 1.06
Benching 1 1.80 0.90 0.40 0.65
Total 1.71
cu.m
Deduct
Upper portion of main
1 1.80 0.64 0.15 0.17
channel
Upper portion of branch
1 0.30 0.20 0.15 0.01
channel
total deduction 0.18
Net Total 1.53
cu.m
I class brickwork in 1:4
3
cement mortar
Long walls 1st step 2 2.60 0.40 0.90 1.87
Long walls 2nd step 2 2.40 0.30 1.00 1.44
Long walls 3rd step 2 1.00 0.20 0.70 0.28
Short wall 1st step 2 0.90 0.40 0.90 0.65
Short wall 2nd step 2 0.90 0.30 1.00 0.54
Short wall 3rd step 2 0.90 0.20 0.70 0.25
Total 5.03
cu.m
4 Cement pointing 1:4
Long walls up tp slab 2 1.80 1.50 5.40
Short wall up to slab 2 0.90 1.50 2.70
Short-left face 1 0.90 0.82 0.74
Short-right face 1 0.90 0.70 0.63
Remaining face 2 0.60 0.82 0.98
Total 10.45
sq.m
20 mm thick cement
5 plaster 1:3 in floor and 1 1.80 1.20 2.16
channels
sq.m
RCC Slab including steel
6
complete work of
SPECIFICATIONS
Definition
Purpose of Specification
Specification should be clear and there should not be any issues. From the study of the
specifications one can easily understand the nature of the work and what the work shall be.
Drawings do not furnish the details of different items of work, the quantity of
materials, proportion of mortar and workmanship which are described in the specifications.
Thus, drawings and specifications form important parts of contract document.
Specifications depend on the nature of the work, the purpose for which the work is
required, strength of the materials, availability of materials, quality of materials etc.
Detailed Specification: It specifies the qualities and quantities of materials, the proportion of
mortar, workmanship, the method of preparation and execution and the method of
measurement. The detailed specification of different items of work are prepared separately
and describe what the works should be and how shall be executed and constructed.
GENERAL SPECIFICATIONS
General specifications give the idea and class of work in general terms and are generally
attached with the rough cost and detailed estimates.
Foundation and Plinth: - Shall be of first class burnt bricks in lime or cement
mortar(1:6)over a bed of cement concrete. (1:6:12 or 1:8:16)
Superstructure:- Shall be of first class burnt brick work in lime or cement mortar (1:6)
Damp Proof Course:- Shall be of a cm thick cement concrete (1:2:4) with on-layer of
bitumen laid hot or any other specified water proof material.
Roofing:- Shall be of R.C.C. slabs (1:2:4) covered with two coats of bitumen lalid hot and a
layer of lime or cement concrete 8 cm. thick over it with a tile flooring with cement flush
with cement flush pointed on the top.
Flooring:- Shall be of TERRAZO in drawing, dining, bath and W.C., 4 cm thick plain
conglomerate polished floors in bed rooms and in other rooms.
Doors and Windows:- Doors and windows shall be of teak wood, panelled or panelled and
glazed with gauze shutters to outer doors and fixed wire gauze to windows and ventilators
Fittings shall preferably of brass or good quality metal.
Finishing:- The inside and outside walls shall have 1.25 cm. thick cement plaster. Drawing,
dining and bed rooms inside of walls shall have 2 coats of distemper and other rooms shall
have three coats of white washing. The outside of the wall shall have two coats of colour
washing over one coat of white washing.
Painting:- Doors and windows shall be given three coats of white lead where exposed and
white zinc or cream or grey silicate paint elsewhere.
Miscellaneous:- First class buildings shall be provided with first class sanitary and water
supply fittings and electrical installations. A plinth protection 1.50 m. wide of bricks sloped
away from the building shall be provided all round the building. Plinth Area Rate Rs. 4500.00
to Rs. 5,500 per sq. meter. (Rates variable).
Foundation and Plinth:- All walls shall be built of first class burnt bricks laid in mud mortar
over a bed of lime concrete or cement concrete. Top course of the plinth shall be laid in
cement mortar(1:6)
Superstructure: - All walls shall be built of first class burnt bricks laid in mud mortar.
Damp proof Course: - Damp proof course 4 cm thick shall be of Portland cement concrete
(1:2:4) with one coat of bitumen laid hot.
Roofing:- All main rooms shall have R.B. roof or R.C. roof and first class or second class
mud roofs over other rooms.
Floors:- the main rooms shall have conglomerate floors and verandahs shall have flat or
brick on edge floors over cement concrete and sand.
Doors and Windows:- Interior and exterior surface of wall shall be cement plastered 1.25
cm thick, covered with three coats of white washing.
Painting: - Doors and windows shall be painted with three coats of chocolate paint or any
other approved paint.
Miscellaneous:- Roof drainage shall be carried by means of Gargolyes and khassi parnalas.
Plinth protection1.50 m. wide of bricks shall be provided all-round the building. Plinth Area
Rate: Rs. 2500 to Rs.3000 per sq.m
Department Of Civil Engineering, Dr.TTIT, Kgf. Page 35
Quantity Surveying and Contract Management – 15CV81
Foundations and Plinth: - All walls shall be built of second class burnt laid in mud mortar
over bed on lime concrete.
Superstructure: - All walls shall be built of second class burnt bricks laid in mud mortar.
Roofing:- All rooms shall have second class mud roof and the verandahs shall have G.I. sheet
roof.
Floors:- Floors everywhere shall be of brick over mid concrete and cement pointed.
Doors and Windows: - Doors and windows shall be of kail, Chir, Mango or any other soft
wood, ledged, battened and braced type.
Finishing: - Interior surface of walls shall be mud plastered and covered with three coats of
white washing. The outside surface shall be flush lime pointed.
Painting: - Doors and windows shall be give two coats of ordinary chocolate paint.
Foundation and Plinth:- All walls shall be built of se3cond class brick work laid in mud
mortar.
Superstructure: - All walls shall be built of sand moulded sun dried bricks laid in mud
mortar with the exception of the following which shall be built in second class brick work in
mud.
Roofing:- Third class mud roof. Floors: - Mud floors(2.5cm) mud plaster over the rammed
earth.
Doors and Windows:- Doors and windows shall be of kail, chir or any other soft wood
batten doors. Finishing:- mud and mud plaster inside and outside.
Painting: Two coats of ordinary paint.
Plint Area Rate:- Rs. 800.00 to Rs. 1000.00 per sq.m.
Detailed Specifications
Detailed specifications give the method of constructions and specify the nature of work.
EARTHWORK IN EXCAVATION/BACKFILL
1. General
All work shall be executed accurately to the dimensions indicated on the drawings or
as directed by the Engineer.
The contractor is responsible for inspecting, testing and making his own decision as to
the actual nature of the ground to the excavated and any available trail hole data must
not be Taken as a guarantee that similar conditions prevail on the site.
The contractor shall advice the Engineer when trail pits or trial hole data are available
for examination so as to determine the bearing ability of the ground for foundation.
The contractor shall report to the Engineer when excavations are ready to receive
foundation concrete and shall obtain consent before depositing concrete.
In the event of excavations being made larger than the sizes indicated on the drawings
or as directed by the Engineer. The contractor shall fill in the excavated void to the
correct profile with mass concrete at his own expenses and as directed by the
Engineer.
2. Site Clearance
The sites of structures shall be cleared of all trees, bushes, scrubs, crops and all other
vegetable growth including grubbing up all roots rubbish and grubbing matter shall be
burned or disposes of, off site at tips to the provided by the contractor and approved
by the Engineer. All combustible materials and excavated surface soil shall be spread
and followed for the disposal.
All attempts must be made to maintain those trees and shrubs which are identified and
instructed by the Engineer as the ones to be retained and to disturb plant life as little
as possible. Where large shrubs and trees are positioned at our very near the location
of a building, fence or any alternative structures or positions for structures considered.
3. Site Excavation
The contractor shall excavate the site throughout the area shown on the site layouts.
Foundations Levels: The contractor shall determine the levels of the foundations in
relation to the structural drawing and the excavated site level. Where undulations
occur the contractor must place the top of the foundation at a level where surface
water will not undermine the foundation.
Poor Ground: Top soil, loose soil, bad ground or cavities met within any part of the
excavations for foundations and floor slabs of structures shall be excavated to a solid
formation and filled to foundation level with hard-core or other approved materials
properly compacted to the Engineer’s approval. Beneath all strip footings, the excess
excavated materials shall be replaced with concrete.
3.1 Excavation in Rock
Any excavation where chiselling or blasting is necessary will be classified as
excavation in rock, Removal of boulders of sizes up to approx. 0.5m3 shall not be
classified as rock excavation.
The contractor shall notify the Engineer on each occasion he considers he is entitled
or payment for excavation in rock and shall not fill any excavation concerned until it
has been inspected by the Engineer. No payment or excavation in rock shall be made
unless the Engineer has inspected the excavation and certified in writing the quantity
involved. Engineer’s decision shall be final and binding.
In the event of use of explosives being permitted the contractor shall obtain prior
approval of all relevant authorities and shall conform to safety standards and shall be
fully responsible for storage and usage.
4. Shoring Excavations
The contractor shall, to the satisfaction of the Engineer shore the sides of excavations
foe structures. Trenches and pits to prevent them from slipping or failing. Should any
slips, falls or settlement nevertheless occur they shall be made good by the contractor
at his own expense with selected ill or with mass concrete as may be directed by the
Engineer. Excavation shall be kept intact without backfilling for required period in
case of basement retaining walls etc.
In removing shoring from the sides of excavations, care shall be taken to avoid
bringing loads on to any concrete until it has hardened sufficiently to carry loads.
Timber or other materials used for shoring the sides of excavations shall be removed
as the work proceeds except when ordered to be left in by the Engineer.
5. Backfilling
Backfilling for retaining walls, basement, etc. shall be done only after the supported
slab is cast, cured and de-shuttered and given lateral stability to walls, Backfilling
shall start only after the approval of Engineer.
Retaining walls, foundations, trenches, column, bases and the like are to be backfield
with selected excavation materials or imported filling, well rammed and consolidated
to the satisfaction of the Engineer, in lavers as directed but not exceeding 150mm
thick and sufficiently watered during consolidating to achieve maximum
consolidation. The maximum size of the material shall not be greater than 50mm, not
more than 15% shall pass the 200 Sieve and it shall be free of all debris, vegetable
matter and like. The density after compaction shall not be less than maximum dry
density obtained in Test II of B.S. 1377.
6. Disposal of surplus excavated materials
Surplus excavated material shall be removed from the site and disposed off to a site to be
approved by the Engineer. All necessary permits and approvals of local authorities shall
be the responsibility of the contractor.
7. Trimming of slopes
The slopes of cutting and embankments shall be trimmed by hands or by approved
mechanical means to uniform batters of maximum 33 degrees as directed by the Engineer. A
tolerance of plus or minus 100mm measured at right angles to the batter will
be permitted. A channel 600mm wide x 300 mm deep shall be formed at the base of slopes to
divert rainwater.
Any rock or boulder appearing in the face of a cutting shall trimmed back to ithin the
tolerance specified above and in addition any rock or boulder which in the opinion of
the Engineer is unstable shall be completely removed and the resulting void filled
with compacted materials to the approval of the Engineer.
8. Keeping Excavations free from water
The contractor shall be responsible foe keeping all excavations free from water from
whatever cause arising and shall provide such pumping capacity and other temporary
works as may be necessary for this purpose.
The contractor shall make good as his own expense any damage that may result from
his failure to keep the excavations free from water.
9. Compacted fill, Granular fill Beneath Slabs, footings etc.
The fill is to be non-plastic granular material, well graded strong, with maximum
particle with size of 50mm with no more than 15% passing a 200 sieve, free of all
debris, vegetable mater and the like.
The fill is to be compacted using a vibrating compactor of not less than 1.5 tones. The
fill is to be thoroughly compacted in layers as directed but not more than 150mm
thick. Adequate water is to use for compaction and the density after compaction shall
not be less than maximum dry density obtained in Test II of B.S.1377.
BRICK WORK
1. Scope
This specification covers the construction of brick masonry in foundations, arches,
walls, etc. at all elevations. Only masonry with first class burnt clay brick is dealt
with in this Section.
The provision of the latest revision of IS: 2212 shall be complied with unless
permitted otherwise and any other I.S Codes (latest revision) shall form a part of this
specification to the extent it has been referred to or applicable with this specification.
2. Materials
Bricks shall conform to the requirements of I.S. 1077. Specification for common
burnt clay building bricks, and shall be of the first class quality. Bricks shall be of
uniform deep red, cherry or copper colour, thoroughly burnt. Without being vitrified,
regular in shape and size and shall have sharp and square sides, edges and parallel
faces to ensure uniformity in the thickness of the courses of brickwork.
Bricks shall be sound, hard, and homogenous in texture and omit a clear ringing
sound on being struck.
Brick shall be of the local standard size. Any other similar size may be accepted, but
no dimension shall vary more than 3 mm from the accepted size.
All bricks which absorb water more than 20% of their own dry weight after being
immersed in water for 24 hours shall be rejected.
All bricks shall have to be approved by the Engineer. Any lot of bricks found not up
to the specification, must be removed from the site immediately at Contractor’s own
cost.
Representative samples of bricks to be used shall be submitted to the Engineer and his
approval taken before bulk purchase.
The samples shall be kept sealed with the Engineer for future reference and
comparisons. All bricks supplied shall conform to these approved to these approved
samples in all respects.
Bricks shall be carefully and systematically stacked at locations an directed in an approved
manner. East stack shall contain equal numbers of bricks preferably not more than 3000.
Water
Water shall be clean and free from deleterious matter such as oil, acid, alkali, salt and
vegetable growth.
Cement
Portland cement conforming to Indian standard specification IS: 269 shall be used. Cement
shall be stored in weatherproof sheds on dry platforms and protected from rain and moisture.
Cement which has partially set shall not be used.
Sand
Sand shall conform to IS: 383, 100% of the sand shall pass through IS. Sieve No. 240 and not
more than 15% to 35% through I.S. sieve No. 30. Sand shall have a fineness modulus
between 2.1 and 2.5. Sand shall be clean and free from dirt, clay or other impurities.
Percentage of clay or total impurities shall not be more than 5% by weight.
3. Mortar
Mortar for brickwork except for half brick or lower thickness walls shall be 1 part
cement and 6 parts sand by volume.
Mortar for half brick and lower thickness brick walls shall be 1 part cement and 4
parts sand by volume.
The unit of measurement for cement shall be a bag of cement weighing 50 Kg. and
this shall be taken as 0.035 cu. Meter. Other ingredients in specified proportions shall
be measured in boxes of suitable size. Sand shall be measured on the basis of its dry
volume. In case of damp sand, its quality shall be increased suitably to allow for
bulkage.
Cement and sand shall be mixed dry thoroughly on clean approved platform and
water shall then be added to obtain a mortar of the consistency of a stiff paste, care
being taken to add just sufficient water for the purpose.
Mortar shall be used as soon as possible after mixing and within 2 hours after the
cement is mixed wet.
Mortar unused for more than 2 hours shall be rejected and removed from the site of
work.
Mixture of lime putty and sand can be kept for a period of 72 hours, provided it is
kept damp and not allowed to dry.
4. Workmanship
All workmanship shall be of best standard as approved by the Engineer.
Laying
Bricks shall be soaked in water before use for at least six (6) hours. The contractor
shall provide tanks of sufficient capacity to allow the specified immersion. Bricks
shall be laid in water by hand and not thrown. The bricks shall not be too wet at the
time of use, as they are likely to slip on the mortar bed and there will be difficulty in
plumbness of the wall.
Bricks shall be laid with a shore joint in full mortar beds and thoroughly slushed up
with mortar at every course. Face bricks shall be laid on full mortar beds and have all
vertical joints completely filled with mortar. All brick work shall be plumb, square
and true to dimensions shown on drawings and in approved bond.
All brick work shall be built tightly against columns, floor slabs or other structural
parts, around window and door frames with proper distance to permit caulked joint.
Where drawings indicated that structural Steel column and spandrel beams are to be
partly or wholly covered with brick work, the bricks shall be built closely against all
flange and webs with all spaces between the steel and the brickwork filled solid with
setting mortar with not less than 10 mm in the thickness.
Bricks shall be laid in joints not more than 12 mm thick, where stucco finish is
specified, the joints of brickwork shall be raked to a minimum depth of 10 mm to
ensure good bond of stucco with brick work.
Racking out joints
Joint of brick work shall be raked out to a depth of 12 mm at time of laying and face of
brick work shall be kept clear of all mortar.
Double scaffolding having two sets of vertical supports shall be provided except in
case of building upto two storeys where single scaffolding may be used if permitted by the
Engineer. The supports shall be sound and strong and of steal tubular construction unless
otherwise permitted by the Engineer. The vertical posts shall be tied together with horizontal
pieces over which the scaffolding planks shall be fixed. In cases where single scaffolding has
been allowed by the Engineer, the inner ends of horizontal. Scaffolding poles shall rest in a
hole provided in the header course only. One header for each hole shall be left out. Such
holes, however, shall not be allowed in pillars under one matter in width, or immediately near
the skew backs or arches. The holes left in masonry work for supporting the scaffoldings
shall be immediately filed and made good before plastering.
8. Methods of Measurement
a) Wall thickness shall be measured in terms of nominal brick size which shall be deemed to
be inclusive of mortar joints.
b) Actual volume of work done shall be measured in cu.m. and deductions for openings,
lintels, sills, conduits, ducts, pipes, etc. shall be made, but no deduction shall be made for
openings upto 0.1 .SQ.M. in area each. No deduction shall be made for inserts and embedded
fixtures nor any extra be made for the mortar used for fixing or for necessary cutting of
bricks.
c) For encasing of steel beams, columns, etc. the sizes as shown on drawings shall be
measured, and no deduction shall be made for the volume of steel beams, columns, etc.
d) No extra payment shall be made for any cutting of bricks for encasing of beams, columns
etc. and/or bricks cut for any other purposes.
e) Half brick thick walls shall be measured in Sq.M. and deductions made for all openings,
lintels, sills, conduits, ducts, pipes, etc. but no deduction shall be made for openings up to 0.1
sq.m. in area each. No additions or deductions shall be made for embedded fixtures.
STONE MASONRY
1. Scope
This section covers the layout and construction of stone masonry in foundations
superstructures, wall, arches, etc. at all elevations. Only masonry with good quality of quarry
stones is dealt with in this section.
2. Materials
Stone
All stone used for this work should be hard, uniform in texture, locally the best
available from the nearest quarry or elsewhere approved by the site engineer/supervisor.
Samples, which are not similar to the samples supplied shall be rejected . No round stone
shall be used unless broken. Stones shall be fairly regular in size and every stone shall be
fitted to the adjacent stones. No stone shall be less than 15 cm in size.
Face stones shall be comparatively larger and uniform in size and colour to given a
good appearance, and breadth of face stones shall be grater than the height. Face stones
should tail into wall to a sufficient depth to bound well. Stones shall be broken and faces of
wall shall be truly in plumb. Corner stones or quoins should be a good stone and dressed
correct to angle and laid as headers and stretches.
Mud
Mud to be used shall be of approved quality, obtained from foundation cuttings or
borrow pits at least 1 M. below ground level. It shall be free from gravel or other foreign
bodies. Soil so brought up from cuttings shall be collected first and allowed to dry
completely, after which it shall be beaten down into smaller particles before being passed
through a standard 20 gauge wire mesh to remove course material.
The fine sieved portion shall then be collected in a pit of appropriate size before
addition of water as required to produce a homogeneous mass. The mud shall be thoroughly
kneaded according to local practice being taken to area of work.
Water
Water shall be clean and free from deleterious matter such as oil, acid, alkali, salt and
vegetable growth
Cement
Portland cement conforming to Indian standard specification IS: 269 shall be used.
Cement shall be stored in weatherproof sheds on dry platforms and protected from rain and
moisture. Cement which has partially set shall not be used.
Sand
Sand shall conform to IS: 383, 100% of the sand shall pass through IS. Sieve No. 240
and not more than 15% to 35% through I.S. sieve No. 30. Sand shall have a fineness modulus
between 2.1 and 2.5. Sand shall be clean and free from dirt, clay or other impurities.
Percentage of clay or total impurities shall not be more than 5% by weight.
3. Mortar
Mud Mortar
The mud mortar shall be made by thoroughly mixing clay with water . The quality of
clay is to be used as mentioned above and must be approved by the site engineer. The
ingredient clay shall be checked thoroughly for aggregate etc. and evenly mixed, care being
taken not to add more water than is required.
Cement Mortar
Cement mortar shall be of proportions of 1:6 ( 1 cement; 6 course sand). The
ingredient shall be accurately gauged by measure and shall be well and evenly mixed together
in a mechanical pan mixer, care being taken not to add more water than is required. No
mortar that has begun to set shall be used. Not more than one bag of cement shall be mixed
one time, which shall be consumed within half an hour of its mixing. The work shall be well
watered for a fortnight.
4. Construction
Random Rubble Masonry ( Uncoursed )
The stones shall be dressed rough to approximate shape and size before use. The
Maximum bushing for unplastered faces for stones shall be limited to 25 mm. On the surface
to be plastered this shall not exceed 10 mm so as to incorporate lime plastering thickness
within a margin of 5 mm. stones used on facing shall be to the possible extend equal in
texture. The gaps between the stones should be properly filled up by spalls. The gaps should
not exceed 50 mm either way and they should never be left hollow. The joints should be well
packed with mortar with a porker. In no case water should be allowed to be poured into
joints. Only mortar to the required consistency shall be permitted. Bond stones shall be
provided to the full width of the wall or to the tailed length of such stones. Quoins and corner
stones are to be provided properly dressed to angles. The length of quoins shall be to full wall
width and size suitably selected to match the courses. Care should be taken to see that joints
of adjacent coursed are not in one vertical line. The mortar joints shall not exceed 25 mm in
any case. Mortar used for the masonry shall be generally mud mortar unless otherwise
specified. The stones to be used in jambs, reveals, sills and other places of such nature should
be properly selected and dressed. All the joints should be raked out to depth 15 mm to enable
pointing or lime plastering or cement plastering.
Coursed Rubble Masonry
The stones for such works shall be properly selected and each course shall be of same
height. Stones should be semi-dressed at quarry and the final dressing shall be done at site of
work by chisel and hammer. The bushings shall not exceed 20 mm. Corner stones should be
properly dressed to angles. The bond stones shall be spaced 1.5 meters apart. The height of
quoins should not exceed the height of the course. Vertical joints should be avoided. The joints
should be raked out to a depth of 15 mm to enable pointing or lime plaster washing or cement
plastering.
Ashlar Masonry
The stones shall be hard, tough and durable from a approved quarry. Stones shall be
chisel-dressed on all edges to have perfectly square or rectangular faces so that they may be
laid in perfect horizontal and vertical joints. Minimum height of stones shall be 20 cm and
breadth not less than 1.5 times height. Stones shall be laid alternate headers and streachers
with breadth joints in two consecutive layers. Each course shall be truly horizontal and each
stone shall be laid on its natural bed. The wall shall be truly in plumb. No joint shall he
thicker than 3.5 mm. Not more than 60 mm height of masonry shall be constructed at a time.
Mortar shall be mud mixed thoroughly to get a uniform workable consistency. If
mortar specified as cement mortar is used it shall first have water added slowly and gradually
and mixed thoroughly to get a uniform mortar of workable consistency. Fresh mortar shall be
used. At the end of day’s work the masonry shall be flooded with 25 mm water at the upper
surface in case of cement mortar. All stones shall be the roughed before use. Usually,
exposed faces of stones are rough chiselled.
5. Workmanship
General construction techniques shall be in accordance with the best local traditions.
The contractor shall ensure that only the most experienced of local masons are
employed on random rubble works in foundation.
The selection of stone or blocks for foundation shall be convenient, placing them in
position to obtain a good bond while restriction in cutting of the stones to removal of
inconvenient corners only. The stones shall be laid on their natural beds as nearly as
possible at right angles to the direction of the load or thrust.
Wetting of stones shall be necessary only in the case of very dry porous stones.
Impervious stones, however, do not have to be wetted before being laid. Water
absorbing natures of the various stones shall first be ascertained on samples and as far
as is practicable only stones of approximately the same porosity shall be used
throughout any length of walling.
Quoins shall be built up in advance of the main body of the wall to a height of 50 cm
and adjacent wall on both sides stepped down. Quoins stones shall be more regular in
shap than the main wall and shall be selected and set out on the ground before
hand.They shall be carefully dressed to produce regular corners. The masonry shall be
brought to courses at every 50 cm intervals. Method of wall construction shall be as per the
best local traditions, using as far as possible stones that are broad on the bed and which tail-in
well with adjacent stones. Void spaces shall be filled with hearting stones selected to bond in
with the rest. Stones chips shall be used only to fill voids between hearting stones and to
avoid use of excessive mortar. All stones shall however, be solidly and well bedded in mortar,
all voids being packed with mortar.
The random rubble wall shall be brought to courses at convenient heights but not
exceeding 50 cm. The course height shall correspond with the quoin stones or their
multiples, as necessary. All projecting stones at levels where width of footings change
shall be headers, with the long side tailing under the footing. Stones for face walling
inside and outside has to be minimum dressed in order to receive evenly joints on all
four sides.
Bonds shall be both transverse (across the thickness of the wall) and longitudinal.
Transverse bonds shall be achieved by use of bond stones of lengths extending the full
width of the wall. These shall be placed at approximately 60 cm. Vertical and
horizontal intervals, staggering the stones between the two faces.
Joints in the wall shall be not less than 6 mm thick in to any part of the bed and shall
be thick enough throughout to take up any irregularities of the stones without making
a stone-too stone contact. Interior wall of 30 mm thickness shall have stones
extending to the full thickness of the wall. It should be break joints with stones at least
half the thickness of the wall.
At ground level, the wall shall be brought to course and the top finished off level with
a thick layer of cement mortar (1:4) not less than 20mm thick. In the case of sloping
grounds, random rubble work shall be coursed and finished level as above at the
lower. Levels at the corners of the top most course shall be checked for uniformity
before proceeding with further works.
Protective measures consisting of covering by sacking, tarpaulins or other material
shall be taken during rains to prevent mortar being washed out of the joints before it
has set.
6. Measurements
The measurement shall be in cubic meter of product of length, breadth or thickness
and depth ot height. All thickness of stone walls shall be measured and will be as per
drawings. Deductions for floors, windows, and other openings including lintels shall be made
to arrive at the net quantity of work. Nothing shall be paid extra for forming such openings.
Stone work covering to R.C.C. structures and in continuation of the main wall shall be
measured in thickness nearest to the figures shown in the drawing. Unless otherwise specified
nothing extra shall be admissible for cutting in stone works to suit R.C.C. structure, wall in
any shape other than straight, any cutting necessary for shaping the walls to structural design.
Rate shall be inclusive of all necessary scaffolding, materials, labour, curing, etc.
CEMENT CONCRETE
1. Ingredients: Cement, sand, brick or stone aggregate, gravel or shingle and water
Cement
Cement shall be Portland cement of the Indian standard Specifications as perIS: 269.
All cement shall be brought to the site of work in bags with the seals in tack. Fresh and from
moisture. All cement shall be gauged by weight and shall be added at the mixture in whole
50kg.bags.
Fine Aggregate (Sand)
It shall consist of clean, hard, uncoated grains of natural sand or crushed stone sand
rushed gravel sand or combination of any of these free clay, loam, silt, organic or other
deleterious substances. The sand shall be washed before using trough for washing sand.
Coarse Aggregate
It shall consist of good hard tough and clear water worn bajri obtained from natural
streams. The girl shall be free from dirt, clay, leaves or other organic matter and soft or
decayed stone and shall be of the gauge specified according to the nature of the work.
Water
Water used in construction shall be clean, free from earthly, vegetable or organic
impurities: like alkalis, salts etc. which cause efflorescence and affect setting time of mortar.
2. Mixing
In all proportions of cement concrete except 1:1½:3, 1:2:4 and 1:3:6, the measured
quantity of cement is to be placed on top of the measured quantity of the aggregate (fine and
coarse) and the whole mass mixed three or four times so that it shall be thoroughly
incorporated. The required quantity of water (clean, rather drinking water) shall then be
added and the entire wet mass shall be turned over unto the homogeneous mixture of the
required consistency is obtained.
10 Expansion Joints
In every long lengths of slab work, expansion joints shall be provided at intervals of
about 9 m. to 12m.
11 Measurement
Measurements are taken in cubic meters.
TILE FLOORING
Consists of first class burnt bricks or tiles laid flat or on edge over a bed of 10cm,
thick lime concrete or cement (1:6:18) and 10cm. thick sand.
Laying: All bricks or tiles or tiles shall be laid in lime or cement mortar with bed and vertical
joints full of mortar1:4 simple “lipping” at the edge shall not be permitted. The laying shall
be in plain, diagonal, herring bone or other pattern as desired by the Engineer-in-charge. The
work shall be protected from the effect of sun, frost and rain during construction.
Soaking: Before use, all bricks or tiles shall be soaked in clean water in tanks for at least one
hour.
Joints: The joints shall not exceed 6mm in thickness. The mortar in the joints shall be struck
off flush with s trowel. Care shall be taken that no mortar shall spreed over the edge of the
bricks or tiles.
Curing: The floor must be kept wet for seven days after laying. If cement pointing is done, it
shall be kept moist for at least 15days after the pointing has been done.
TERRAZO FLOORING
A rough foundation of ordinary cement concrete 1:2:4 to within 29mm below the
required finish grade shall first be provide. The material of the terrazzo consisting of 1½ parts
of very small marble chips machine crushed and free from marble dust and foreign matter, 6
to 13 mm, to one part cement shall then be laid and floated over the rough surface, so that flat
sides of the chips lay evenly at the top if the marble chips do not show up sufficiently, the
defective parts may be filled up by hand.
After the terrazzo concrete has hardened enough to prevent dislodgement of
aggregate, it shall be ground down with an approved type of grinding machine shod with free
rapid cutting carborundum stones to expose the coarse aggregate. The floor to be kept wet
during grinding process. After this the finish shall be scrubbed with warm water and soft soap
and mopped dry.
MARBLE FLOORS
The marble flooring shall consists of marble tiles laid on 12mm thick mortar bed over
the usual base courses of 10cm base concrete 1:8:16 and 10cm said or stone filling in case of
ground floor or over R.C.C slabs. In case of upper floors the mortar bed shall be of 1:3
cement sand mortar.
The marble slabs should be of approved quality and thickness 20mm to 25mm with
truly plane surface. The size of marble slab shall be slightly oversize to permit cutting to
actual size of tiles at the site of work.
Curing: During the progress of work and for 10days after laying, each section of floor shall
be kept flooded. Three clear days shall be allowed for setting before the pavement is walked
over and no weight should be rested upon the surface, until 7days after laying is completed,
Polishing is done, as in case of Terrazzo flooring and no first cutting is usually needed.
6. Measurements
Measurements are taken in square metres.
DOORS & WINDOWS
Doors and windows may range from the humble ledged and braced doors and
windows which are usually, fitted to out houses, to the multiple, panelled and panelled and
fitted with ornate moulding and panelled, and which are usually associated with the entrances
to important buildings.
In all cases the construction shall be such as to ensure that the door shall be
satisfactory in service.
1. Timber
All doors, windows, clerestory windows and all almirahs with their chowkats shall be
made of well-seasoned deodar wood or any other food timber free from sapwood, large knots,
shakes cracks and other serious defects.
2. Panels
In case of panelled doors, the panels shall not be less than 13 mm thick.
3. Sash
Bars In case of glazed doors, Sash Bars shall be of the full thickness of the leaf and 38
mm. in width and shall be moulded and metered on the outside and rebated from inside. The
width of the rebate shall be 13 mm.
2. Installation
Materials
Materials shall be highest grade products of well-known approved manufacturer and
shall be delivered to the site in original sealed containers, bearing brand name,
manufacturer’s name and colour shade, with labels intact and seals unbroken. All materials
shall be subject to inspection, approval by the Engineer. It is desired that materials of one
manufacturer only shall be used as far as possible and paint of one shade be obtained from
the same manufacturing batch.
All paint shall be subjected to analysis from random samples taken at site from
painters bucket, if so desired by the Engineer. All prime coats shall be compatible to the
material of the surface to be finished as well as to the finishing coats to be applied.
All specified materials such as shellac, turpentine or linseed oil shall be of the highest
quality available and shall, conform to the latest I.S. standards. All such materials shall be
made by reputable recognized manufacturers and shall be approved by the Engineer.
All colours shall be as per painting schedule and tinting and matching shall be done to
the satisfaction of the Engineer. In such cases, where sampled are required, they shall be
eccicuted in advance with specified materials for the approved of the Engineer.
White Washing
Shall be done from pure shall lime or fat lime, or a mixture of both as instructed by
the Engineer and shall conform to IS : 712 latest edition. Samples of lime shall be submitted
to the Engineer for approval and lime as per approved sample shall be brought to site in
unslaked condition. After slaking, it shall be allowed to remain in unslaked condition.
After slaking, it shall be allowed to remain in a tank of water for two days and then
stirred up with a pole. Until it attains the consistency of thin cream. 100 grams of gum to 6
litres of white wash water and a little quantity of indigo or synthetic ultramarine blue shall be
added to the lime.
Water-proof cement paint
Shall be made from best quality white cement add lime resistant colours with
accelerations, water proofing agents and fungicides. The paint shall conform to IS : 5410.
Synthetic Enamel Paint
Shall be made from synthetic resins and drying oil with rutiletitanius dioxide and
other selected pigments to give a smooth, hard, durable and glossy finish to all exterior
surfaces. White and pastel shade shall resist yellowing and darkening with ageing. The
3 Storage
The contractor shall arrange for safe and proper storage of all materials and tools.
Paints shall be kept covered at all times aqnd mixing shall be done in suitable containers. All
necessary precaution shall be taken by the contractor to prevent fire.
4 Preparation of Surface
Before starting the work the contractor shall obtain the approval of the Engineer regarding the
soundness and readiness of the surface to be painted on.
Masonry, Concrete and Plastered Surface
Surface shall be free from all oil, grease efflorescence, mildew, loose paint or other
foreign and loose materials. Masonry cracks shall be cleaned out and patch filled with mortar
similar to the original surface and uniformly textured. Where this type of resurfacing may
lead to the finishing paint being different in shade from the original surface, the resurfaced
area shall be treated with minimum one coat of cement primer which should be continued to
the surrounding area from a distance of minimum 100 mm.
Surface with mildew or efflorescence shall be treated as below :
a) Mildew: All mildewed surface shall be treated with an approved fungicide such as
ammonia cal wash consisting of 7 gm., of copper carbonate dissolved in 80 ml liquid
ammonia and diluted to 1 litre with water, or 2.5 per cent magnesium silicofluoride
solution and allowed to dry thoroughly before paint is applied.
b) Efflorescence: All efflorescence shall be removed by scrubbing affected surface
with a solution of muriatic acid in water (1:6 to !:8) and washed fully with clear and
allowed to dry thoroughly.
Metal
All metal surface shall be absolutely clean, dry and free from was, grease or dried
soap films. All steel and iron surface in addition shall be free from rust. All galvanized iron
surface shall be pretreated with a compatible primer according to the manufacturer’s
direction. Any abrasion in shop coat shall be touched up with the same quality of paint as the
original coat.
5 Applications
General
The method of application shall be as recommended by the manufacturer. In case of selection
of special shades and colour (not available in standard shades) the contractor shall mix
different shades and prepare test panels of minimum size 1 meter square as per instruction of
the Engineer and obtain his approval prior to application of finishing paint. Proper tools and
implements shall be used. Scaffoldings if used shall be independent of the surface to be
painted to avoid shade differences of the freshly repaired anchor holes.
Painting shall be done by skilled labours in an workmanlike manner. All materials
shall be evenly applied, so as to be free of sags, runs, crawls or other defects. All coats shall
be of proper consistency. In case of application by brush, no brush marks shall be visible.
The brushes shall be clean and in good condition before application of paint.
All priming undercoats for painting shall be applied by brush only and rollers , spray
equipment etc. shall not be used.
No work shall be done under conditions that are unsuitable for production of good
results. No painting shall be done when plastering is in progress or is drying. Application
of paint which seals the surface to moisture shall onlu be done after the moisture on and
below the surface has dried out.
All coats shall be thoroughly dry before being sand papered or before the succeeding
coat is applied. Coats of painting as specified are intended to cover surface. Perfectly. in case
the surface is not covered properly by applying the specifying number
of coats, further coats shall be applied by the Contractor when so directed by the Engineer.
All primers and undercoats shall be tinted to approximate the colour of the finishing
coats. Finished coats shall be of exact colour and shade as per approved samples and all
finish shall be uniform in colour and texture. All parts of moulding and ornaments shall be
left clean and true to finish.
White Washing
The surface where white washing is to be applied shall be cleaned of all loose
materials and dirt. All holes and irregularities of the surface shall be filled up with lime putty
and shall be allowed to dry up before application of the lime solution.
One coat of white wash shall consist of one stroke from top downwards, another from
bottom upwards over the first stroke and another from left to right before the previous one
dries up. Second coat shall be applied after the first coat dries up completely and similarly
third coat shall be applied and in case the Engineer feels that one or more coats are required
the Contractor shall do so without any extra coat to the Owner. No brush marks shall show on
the finished surface. The inner plastered surfaces of walls shall be given 3 or more coats of
white washing.
Water-proof paint
Surface to be coated with cement paint shall be washed and brushed down. As soon as
the moisture has disappeared, the surface shall be given one coat of paint. Care shall be taken
so that the paint does not dry out too rapidly. After 4 to 6 hours, the water shall be sprinkled
over the surface to assist ouring and prevent creaking. After the first coat has dried (24 to 48
hours), the second coat shall be applied in a similar manner. The finished surface shall be
kept moist by occasional sprinkling with water for seven days after painting.
Synthetic Enamel Paint
Shall be applied on properly premiered surface. Subsequent coat shall not be applied
till the previous coat is dry. The previous coat shall be lightly sand papered for better
adhesion of subsequent coats.
6 Cleaning Up
The Contractor shall, upon completion of painting, etc. remove all marks and make
good surfaces, where paint has been spilled, splashed or splattered, including all equipment,
fixtures, glass, furniture, fittings etc. to the satisfaction of the Engineer.
Part C
ANALYSIS OF RATES
1. Lime Concrete in Foundation with 40 mm gauge Stone Ballast, White lime and Sand
(Proportion 1:2:4) unit 1 cu.m
Quantity Cost,
Particulars Unit Rate, Rs. Per
or Nos Rs.
Materials
Stone Ballast 40 mm gauge 8.80 cu.m 1800.00 cu.m 15840.00
Sand 4.40 cu.m 900.00 cu.m 3960.00
White lime Slaked 2.20 cu.m 800.00 cu.m 1760.00
Total 21560.00
Labour
Mistri (Head Mason) ½ no. 350.00 day 175.00
Mason 1 no. 300.00 day 300.00
Mazdoor 12 nos. 220.00 day 2640.00
Coolie 12 nos. 200.00 day 2400.00
Bhisthi 2 nos. 200.00 day 400.00
Miscellaneous Lump sum 100.00 100.00
Total 6015.00
Total of materials and labour 27575.00
Add 1.5% of Water charges 413.63
Add 10% Contractor's profit 2757.50
Grand Total for 10 cu.m 30746.13
Rate per cu.m = Rs. 30746.13/10 = Rs. 3074.50
Sand = 22 x 2 = 44 cu m
Stone aggregate = 22 x 4 = 88 cu m
2. Cement concrete 1:5:10 in foundation or floor with Brick Ballast 40 mm thick gauge-
unit 1cu m.
Sol: Take 10 cu m
Quantity
Particulars Unit Rate, Rs. Per Cost, Rs.
or Nos
Materials
Brick Ballast 40 mm gauge 9.50 cu.m 650.00 cu.m 6175.00
Sand 4.75 cu.m 700.00 cu.m 3325.00
White lime Slaked 0.95 cu.m 7650.00 cu.m 7267.50
Total 16767.50
Labour
Mistri (Head Mason) 1/2 no. 350.00 day 175.00
Mason 1.5 no. 300.00 day 450.00
Mazdoor 12 nos. 220.00 day 2640.00
Coolie 18 nos. 200.00 day 3600.00
Bhisthi 4 nos. 200.00 day 800.00
Miscellaneous Lump sum 100.00 100.00
Total 7765.00
Total of materials and labour 24532.50
Add 1.5% of Water charges 367.99
Add 10% Contractor's profit 2453.25
Grand Total for 10 cu m, Rs. 27353.74
Rate per cu m, Rs. 2735.37
Sol: Take 10 cu m
Quantity
Particulars Unit Rate, Rs. Per Cost, Rs.
or Nos
Materials
Stone Ballast 40 mm gauge 8.80 cu.m 1800.00 cu.m 15840.00
Sand 4.40 cu.m 1500.00 cu.m 6600.00
White lime Slaked 2.20 cu.m 7650.00 cu.m 16830.00
Total 39270.00
Labour
Mistri (Head Mason) no. 350.00 day 116.70
Mason 2 no. 300.00 day 600.00
Mazdoor 12 nos. 220.00 day 2640.00
Coolie 20 nos. 200.00 day 4000.00
Bhisthi 6 nos. 200.00 day 1200.00
Forms Lump sum 1300.00 1300.00
Department Of Civil Engineering, Dr.TTIT, Kgf. Page 59
Quantity Surveying and Contract Management – 15CV81
Quantity
Particulars Unit Rate, Rs. Per Cost, Rs.
or Nos
Materials
Stone Ballast 40 mm gauge 8.80 cu.m 1800.00 cu.m 15840.00
Sand 4.40 cu.m 1500.00 cu.m 6600.00
Cement 2.20 cu.m 7650.00 cu.m 16830.00
Steel, mild steel bars @ 1% =
1 cu m @ 78.5 q/cu m = 7.85 7.85 q 4400.00 q 34540.00
q
Binding wire 1.50 kg 65.00 kg 97.50
Total 73907.50
Labour
Mistri (Head Mason) ½ no. 350.00 day 175.00
Mason 3 no. 300.00 day 900.00
Mazdoor 12 nos. 220.00 day 2640.00
Coolie 20 nos. 200.00 day 4000.00
Bhisthi 6 nos. 200.00 day 1200.00
Miscelleneous Lump sum 150.00 150.00
Total 9065.00
Bending, Cranking and
binding steel bars in
Position
Blacksmith (II class) 8 nos. 280.00 day 2240.00
Mazdoor 8 nos. 220.00 day 1760.00
T. and P. Lump sum 90.00 90.00
Total 4090.00
Centring and shuttering
(both erection and
dismantling)
Timber planks and ballies Lump sum 1500.00 1500.00
Carpenter (II class) 10 nos. 280.00 day 2800.00
Mazdoor 10 nos. 220.00 day 2200.00
Nails Lump sum 200.00 200.00
T. and P. Lump sum 70.00 70.00
Department Of Civil Engineering, Dr.TTIT, Kgf. Page 60
Quantity Surveying and Contract Management – 15CV81
Total 6770.00
Total of materials and labour 93832.50
Add 1.5% of Water charges 1407.49
Add 10% Contractor's profit 9383.25
Grand Total for 10 cu m, Rs. 104623.24
Rate per cu m, Rs. 10462.32
Quantity Unit
Particulars or No Rate, Rs. Per Cost, Rs.
Materials
Stone Ballast 40 mm gauge 8.40 cu.m 1800.00 cu.m 15120.00
Sand 4.20 cu.m 1500.00 cu.m 6300.00
Cement 2.80 cu.m 7650.00 cu.m 21420.00
Steel, mild steel bars @ 2% =
.2 cu m @ 78.5 q/cu m = 15.7 15.70 q 4400.00 q 69080.00
Q
Binding wire 2.00 kg 65.00 kg 130.00
Total 112050.00
Labour
Mistri (Head Mason) ½ no. 350.00 day 175.00
Mason 3 no. 300.00 day 900.00
Mazdoor 12 nos. 220.00 day 2640.00
Coolie 20 nos. 200.00 day 4000.00
Bhisthi 6 nos. 200.00 day 1200.00
Miscellaneous Lump sum 150.00 150.00
Total 9065.00
Bending, Cranking and
binding steel bars in
Position
Blacksmith (II class) 12 nos. 280.00 day 3360.00
Mazdoor 12 nos. 220.00 day 2640.00
T. and P. Lump sum 90.00 90.00
Total 6090.00
Centring and shuttering
(both erection and
dismantling)
Timber planks and ballies Lump sum 1500.00 1500.00
Carpenter (II class) 10 nos. 280.00 day 2800.00
Mazdoor 10 nos. 220.00 day 2200.00
Nails Lump sum 200.00 200.00
T. and P. Lump sum 70.00 70.00
Total 6770.00
Quantity
Particulars Unit Rate, Rs. Per Cost, Rs.
or Nos
Materials
Cement (9 bags) 0.30 cu.m 7650.00 cu.m 2295.00
Sand 1.80 cu.m 700.00 cu.m 1260.00
Total 3555.00
Labour
Mistri (Head Mason) 1/3 no. 350.00 day 116.70
Mason 10 no. 300.00 day 3000.00
Mazdoor 15 nos. 220.00 day 3300.00
Bhisthi ¾ nos. 200.00 day 150.00
Miscellaneous Lump sum 150.00 150.00
Total 6716.70
Total of materials and labour 10271.70
Add 1.5% of Water charges 154.08
Add 10% Contractor's profit 1027.17
Grand Total for 10 cu m, Rs. 11452.95
Rate per cu m, Rs. 114.53
ROADWORK ESTIMATION
Cross section of road in banking and cutting is generally in the shape of trapezium.
A= Bd + sd2
Mean Area
Area Total Length Quantity
Station Depth depth of
of sectional between
or or or central
sides area, Bd stations
chainage height height portion Embankment Cutting
sd2 + sd2 L
d Bd
A2 = Bd2 + sd22
Cross-section at middle
Dm = (d1 + d2)/2
Am = Bdm + sdm2
= B(d1 + d2)/2 + s[(d1 + d2)/2] 2
Quantity = L/6 (A1 +A2 + 4Am)
4. Trapezoidal method
When a series of cross-sectional areas are calculated at equidistant points, the volume may be
worked out by trapezoidal formula
Where A0, A1, A2, A3…..An-1 and An are the areas of cross-sections,
Example 1 Estimate the quantity of earthwork for a road of 12m formation width with the
Chainage 14 15 16 17 18 19 20 21 22
RL of
108.6 109.25 109.4 108.9 108.5 107.25 106.8 107.2 107.2
Ground
following data using mid section formula.
The road is proposed at uniform falling gradient 1 in 200 passing through GL at chainage
14. Length of one chain = 30 m, side slope 1.5:1 in cutting and 2:1 in banking. The rate of
earthwork in filling and cutting are Rs 180/m3 and Rs 120/m3 respectively.
The road is at a falling gradient of 1 in 200 i.e. for every 200 m, there is 1 m fall for every 30
m
30
∗ 200 = 0.15 𝑚
1
The road passes from cutting to banking on between the chainage 18 and 19. The distance
where it passes through zero i.e. ground level is determined as
follows:
𝑥 30 − 𝑥
=
0.5 0.60
Therefore, x = 13.63 m
RL of RL of Mean
Chainage Depth
Ground Formation Depth
14.00 108.60 108.60 0.00
15.00 109.25 108.45 -0.80 -0.40
16.00 109.40 108.30 -1.10 -0.95
17.00 108.85 108.15 -0.70 -0.90
18.00 108.50 108.00 -0.50 -0.60
Passes from cutting to banking
108.60 108.60 0.00 -0.25
19.00 107.25 107.85 0.60 0.30
20.00 106.80 107.70 0.90 0.75
21.00 107.15 107.55 0.40 0.65
22.00 107.20 107.40 0.20 0.30
110.00
Ground Level
109.50
Formation level
109.00
108.50
108.00
107.50
107.00
106.50
14.00 15.00 16.00 17.00 18.00 19.00 20.00 21.00 22.00
Chainage
Area
Central Total Quantity, cu.m
Mean of Distance,
Chainage Depth Area, area,
Depth sides, m
sq.m sq.m Banking cutting
sq.m
14.00 0.00 - - - - 0
15.00 -0.80 -0.40 4.80 0.24 5.04 30 151.2
16.00 -1.10 -0.95 11.40 1.35 12.75 30 382.5
17.00 -0.70 -0.90 10.80 1.21 12.01 30 360.3
18.00 -0.50 -0.60 7.20 0.54 7.74 30 232.2
Passes from cutting to banking
0.00 -0.25 3.00 0.09 3.09 13.63 42.16
19.00 0.60 0.30 3.60 0.18 3.78 16.37 61.88
20.00 0.90 0.75 9.00 1.13 10.13 30 303.8
21.00 0.40 0.65 7.80 0.85 8.65 30 259.4
22.00 0.20 0.30 3.60 0.18 3.78 30 113.4
total 738.4 1168
cu.m cu.m
Example 2 Reduced level of a ground along the centre line of a proposed road from the
chainage 10 to chainage 20 are given below. The formation level at the 10th chainage is 107
and the road is downward gradient of 1 in 150 up to chainage 14 and then the gradient
changes to 1 in 100 downward. Formation width of the road is 10 m and side slope of
banking are 2:1, length of the chainage is 30m.
Draw longitudinal section of the road and the typical c/s and prepare an estimate of earthwork
at a rate of Rs 275 per cu.m
Chain
10 11 12 13 14 15 16 17 18 19 20
age
RL of
105.4 104. 104.
Grou 105 105.6 105.9 105.42 104.3 105 104 103.3
4 1 6
nd
107.50
107.00 Ground Level
106.50 Formation level
106.00
105.50
105.00
104.50
104.00
103.50
103.00
102.50
10.00 11.00 12.00 13.00 14.00 15.00 16.00 17.00 18.00 19.00 20.00
Chainage
RL of RL of
Chainage Depth
Ground Formation
10.00 105.00 107.00 2.00
11.00 105.60 106.80 1.20
12.00 105.44 106.60 1.16
13.00 105.90 106.40 0.50
14.00 105.43 106.20 0.77
15.00 104.30 105.90 1.60
16.00 105.00 105.60 0.60
17.00 104.10 105.30 1.20
18.00 104.60 105.00 0.40
19.00 104.00 104.70 0.70
20.00 103.03 104.40 1.37
B = 10 m and s = 2
Area
Central Total Quantity, cu.m
of Mean Distance
Chainage Depth Area, area,
sides, Area ,m
sq.m sq.m Banking cutting
sq.m
10 2.00 20.00 8.00 28.00
11 1.20 12.00 2.88 14.88 21.44 30 643.20
12 1.16 11.60 2.69 14.29 14.59 30 437.57
13 0.50 5.00 0.50 5.50 9.90 30 296.87
14 0.78 7.80 1.22 9.02 7.26 30 217.75
15 1.60 16.00 5.12 21.12 15.07 30 452.05
16 0.60 6.00 0.72 6.72 13.92 30 417.60
17 1.20 12.00 2.88 14.88 10.80 30 324.00
18 0.38 3.80 0.29 4.09 9.48 30 284.53
19 0.70 7.00 0.98 7.98 6.03 30 181.03
20 0.10 1.00 0.02 1.02 4.50 30 135.00
Total 3389.60
cu.m
Formation width of the road is 10 m. Side slopes are 2:1 in banking and 1.5:1 in cutting
R.L of
Station Distance R.L of
in m Ground foramtion
25 1000 51.00 52.00
26 1040 50.90 Downward
Department Of Civil Engineering, Dr.TTIT, Kgf. Page 70
Quantity Surveying and Contract Management – 15CV81
𝑥 40 − 𝑥
0.3 =
0.4
Therefore, length of banking portion is 17 m and the length of cutting portion is 40 – 17 = 23 m.
B = 10 m, s = 2 for banking and s = 1.5 for cutting
Area Quantity
Area Total Length
Station Depth of
Distance, Mean of sectional between
or or central Embank Cutti
m depth sides area, Bd stations
chainage height portion ment ng
sd2 + sd2 L
Bd
25 1000 1.00 - - - - - - -
26 1040 0.90 0.95 9.50 1.81 11.31 40.00 452.20
27 1080 1.10 1.00 10.00 2.00 12.00 40.00 480.00
Whenever there is a vertical drop in the ground at any point, there will be two reduced levels
of the ground at that point. In calculating the earthwork the portions on the either side of the
vertical drop should be dealt in two operations one by taking the mean of the consecutive
heights or depths up to the point and the other by taking the mean of the two consecutive
heights or depths beyond the point.
Example 4 Estimate the quantity of earthwork for a portion of a road taking a constant
formation level of 49.50. Length of the chain is 50 m.
The Formation width of the road is 8 m and side slope in banking is 1.5:1 and in cutting is 1:1
R.L of
Station Distance R.L of Ground
foramtion
in m
10 500 50.00
11 550 50.60
50.30
12 600
48.50 49.50
13 650 47.90
14 700 48.20
15 750 48.00
51.00
RL. of Ground
50.50
50.00
49.50
49.00
48.50
48.00
47.50
10 11 12Chainage13 14 15
Definition
A written or spoken agreement, especially one concerning employment, sales, or tenancy that is
intended to be enforceable by law.
Types of contracts
specifications.
d) Through rate contract: In some cases, the contract quotes the rates at some
percentage above or below the through rates.
2) Lump sum contract: In this contract, the contractor agrees to execute the complete work
in all respects for the specified amount in specified time. The plans, drawings and
specifications of all the items of the work are supplied to the contractor but the details of
the quantities and schedule of items will not be given and the contractor will have to
complete the work as per the plan and specification within the contract period.
3) Combination of both Item rate and Lump sum contract: In those contracts, fixed sum
is agreed upon the completion of a particular work of a contractor. In case of any
additions or alterations the payment is made or deducted on the basis of schedule of rates.
4) Piece work contract: The contractor agrees to execute the different items of work on
mutually agreed rates. The agreement contains different items of work carried out with
proper description and rates for unit quantity of work. Small works which do not require
engineering skills for execution like earthwork excavation, patch work, maintenance work
and white washing etc., may be carried through piecework contract.
Qualifications of Contractor
There are no fixed norms of qualifications of a contractor. There are some essentials which a
contractor is expected to have. Such as:
Quotation: The rates quoted by a contractor in response to tender call are called “quotations”
Earnest money deposit: When a contract submits a tender for a work, he has to deposit some
amount usually about 2% of the estimated cost to the department as a guarantee of the
tender. When the tender is accepted, the contractor shall not refuse to accept the work. If the
contractor rejects to do the job, then his earnest money will be forfeited, but the EMDs of the
other contractors whose tenders are not accepted are returned back. The earnest money may
be in cash or fixed deposits in banks, bank guarantee and National saving certificate.
Security deposit: Once the tender is accepted, the contractor deposits 10% of the estimated
amount as security with the department. The amount includes earnest money deposited
earlier. The contractor should fulfil all the requirements of the department and carryout the
work satisfactorily as per the specification. If the contractor fails to satisfy the conditions of
the agreement, then the complete amount of SD shall be forfeited fully or partially by the
department. If the contractor completes the work as per the agreement within the specified
time, then the security money is refunded to the contractor.
Administrative sanction: Administrative approval indicates that the proposal has been
formally accepted by the competent authority. Only after obtaining this administrative
sanction, PWD offers detailed design plans, necessary drawings, estimates etc. The
department prepares approximate estimates and preliminary plans and submit the same for
administrative sanction
Technical sanction: It means the sanction of the detailed estimate, design calculations,
quantities of works, rate and cost of the work by the competent authority of the Engineering
department. This work is started only after obtaining the technical sanction. This sanction
guarantees that the proposal are structurally sound, and the estimate is accurately calculated
based on the adequate data.
Tender notice: Tender for a work or supply are invited by issuing tender notice in prescribed
form. The following particulars are given in the tender notice:
Tender notice is posted in the notice board of the department and for major work the tender
notice in brief is also given in the newspaper.
Measurement Book: Measurement book is a record in original of all kinds of the work
which are susceptible to measurements. All the works of construction or maintenance and
repair or supplies of the materials in connection with the work to be executed are recorded in
the measurement book.
The total quantities are calculated and the payments are made on this basis. The
measurement books are very important account records.
All the measurement books are numbered serially and a register is maintained in the
divisional office showing the serial number of each book, the names of the sub division or the
officer to whom issued, the date of issue and return and remark.
Schedule of Rates: It is a list of rates of various items of work. It helps in the preparation of
the estimates also serves as guide in setting rates in connection with the contract agreements.
The schedule of rates is prepared on the basis of analysis of rates. As the rates vary slightly
from year to year, the rates are increased or decreased by the percentage on the schedule of
rates. Rate per unit of various items of works and materials, rates of wages of labour and rates
of transport are given in the schedule.
Nominal Muster Roll: Nominal muster roll is the daily attendance which is recorded. In this
part there are columns and spaces for the names of the labours, designation, father’s name,
dates of attendances, rates, total amount due to each, total amount due to whole, signature of
the person taking attendance, signature of officer making payments etc and these columns are
duly filled up. Fines, if any on the labourer is also recorded. Muster roll should never be
made duplicate and entries should be made in duplicate and entries should be made in such
manner that it may not be possible to interpolate or to alter them.
Valuation
Necessity of Valuation
Role of an Engineer
The roll of an Engineer in valuation is felt when an Engineering structure is to be valued, if
and when it is:-
(a) To e acquired
(b) To be divide
(c) To be allotted to a claim holder.
Obsolescence:- The value of property decreases if its style and design are outdated i.e. rooms
not properly set, thick walls, poor ventilation etc. the reasons of this is fast changing
techniques of construction, design, ideas leading to more comfort etc.
Free hold Property:- Any property which is in complete possession f the owner is known as
free hold property. The owner can use the property in an way he likes. But he will have to
follow constraints fixed by town planners or Municipality before doing any construction.
Department Of Civil Engineering, Dr.TTIT, Kgf. Page 80
Quantity Surveying and Contract Management – 15CV81
Lease hold:- If a property is given to some person on yearly payment basis by the free
holder, then the property is called „lease hold property‟ and the person who take s the
property is called Lease-holder. In case of building, the lease is for 99 years to 9 years.
Easement:- An owner getting over the property of another person, the following faculties is
known as easements.
(i) Facility of running water and sewer pipes through other’s land.
(ii) Facility of air and light.
(iii) Facility of drainage of rain water. (iv) Facility of access.
The owner who gives facilities is known as Servant owner and who enjoys facilities is
called Dominant owner.
Scrap Value:- If a building is to be dismantled after the period of its utility is over, some
amount can be fetched from the sale of old materials. The amount is known as Scrap Value of
a building. If varies from 8% to 10% of the cost of construction according to the availability
of the material.
In case where Wood & Steel are available, the scrap value is more than as R.C.C
structure, as in the latter case, the material has less reuse value.
Salvage Value:- If property after being discarded at the end of the utility period is sold
without being broken into pieces, the amount thus realized by sale is known as its Salvage
Value.
For example, railway sleepers can be re-used as posts and even old iron rails taken out
can be used as beams in a roof or sheds of a building.
Building Cost Index: A building cost index indicates the increase and decrease of the cost
above the cost above the cost at a certain base year and is expressed by a percentage rise &
fall. For instance taking 1960 as a base year, the present 1980 as Building Cost Index may be
taken 1.25% to 150% above the cost during the year 1960.
Capitalized value:- It is defined as the amount of money whose annual interest at the highest
prevailing rate will be equal to the net income received from the property. To calculate the
capitalized value, it is necessary to know highest rate of interest prevailing on such properties
and net income form the property.
Sinking Fund:- A fund which is gradually accumulated and aside to reconstruct the property
after the expiry of the period of utility is known as sinking Fund. The sinking funds may be
found out by taking a sinking fund policy with any insurance company or depositing some
amount in the bank. Generally while calculating the sinking fund, life of the building is
considered. 90% of cost of construction is used for calculations & 10% is left out as scrap
value.