NaturalHy Publishable Activity Report Final 1
NaturalHy Publishable Activity Report Final 1
NATURALHY
“Preparing for the hydrogen economy by using the existing natural gas system as a catalyst”
Integrated Project
Period covered from: 1 May 2004 up to 31 October 2009 Date of preparation: 25 March 2010
Final version
2
LIST OF CONTENT
2 INTRODUCTION ............................................................................................................................. 8
DISCLAIMER
The organizations taking part in the NaturalHy project ("the Organizations")
have taken all reasonable steps to ensure that all the information in this
document is correct at the time of publication. However, the Organizations
accept no liability whatsoever for losses of any kind arising out of the possible
errors or omissions in the document. Everyone who uses this document or its
contents does so entirely at their own risk.
3
OVERALL SUMMARY
Hydrogen is an important element of a sustainable energy society: it can be produced in many ways including
electrolysis of water, using electricity produced from wind or solar energy, or gasification of biomass and coal. It
can be an important part of the synthesis gas (syngas) produced in a coal or biomass gasifier, or of (waste) gases
of industrial processes. Pure hydrogen can be converted by fuel cells into electricity with high efficiencies. The
pollutant emissions from the controlled combustion of hydrogen are very low.
The first logical step towards a transitional delivery system suitable for hydrogen and hydrogen-containing gases
must be an investigation of the extent to which the existing assets, including the existing natural gas
infrastructure, can be used for hydrogen delivery.
Generally speaking, a network designed for natural gas cannot be used for pure hydrogen for a number of
reasons without modifications to network components or the way it is operated and maintained. However, the
existing natural gas transmission, distribution and end use systems could be used for mixtures of natural gas and
hydrogen given appropriate modifications. The mixture can be used as such and, if required, hydrogen
appliances could be fuelled with “pure” hydrogen by developing devices to extract hydrogen selectively from the
mixture.
Of course, for the accommodation of gases which contain a certain percentage of hydrogen it is important that
the physical and chemical characteristics related to the composition of the gas fit sufficiently with the
characteristics of natural gas, and do not initiate unacceptable risks for, for instance, the integrity of the gas
system. The physical and chemical properties of hydrogen differ significantly from those of natural gas and the
addition of a certain percentage of hydrogen to natural gas might have a direct impact on, for instance, the
combustion properties, the diffusion into materials and the behavior of the gas mixture in air. In particular, the
addition of hydrogen to natural gas may have an impact on, inter alia, the following aspects:
• Safety related to the transmission, distribution and use of gas.
• Integrity of pipelines.
• Gas quality management.
• The performance of end user appliances.
In order to determine the contribution the existing natural gas system could offer for hydrogen delivery, the
following main objectives of the NATURALHY project have been defined:
• To define the conditions under which hydrogen (pure, or as a part of a mixture with other gases) can be
added to natural gas in the existing natural gas system (transmission, distribution, end use, infrastructure
and appliances) with regard to acceptable safety risks, benefits, impact on the integrity of the system,
and consequences for gas quality management and for the end user.
• To develop technical options (particularly membranes) to separate hydrogen from hydrogen/natural gas
mixtures;
• To assess the socio-economic and life cycle aspects of the NATURALHY approach, thus illustrating
the real value of the NATURALHY project.
NATURALHY has been a significant project extending from May 2004 to end October 2009 to assess the
capability of the natural gas networks to deliver hydrogen with many hours dedicated to testing and production
of what is a vast array of data, much of it new. It is almost impossible to summarize the project in a short space
and, in fact, unfair to do so. Indeed care must be taken in looking at summary results from this project and
jumping to conclusions.
4
The data is often complex, with many provisos, given the immensity of what has been attempted and, for the
most part, achieved. The reader is therefore urged not to grasp at what looks like a favourable or even an
unfavourable result, without a deeper analysis of their own specific system.
1. Nevertheless, some attempt must be made to display the key findings of NATURALHY and they are
presented below, but should be read while bearing in mind the remarks above.
• With regard to durability of the materials used in the existing gas infrastructures, the obtained results
show that addition of hydrogen gas in methane (main component of the natural gas) does not
dramatically damage the studied materials in the foreseen range of hydrogen portion which is less than
the half of H2 in natural gas.
• Both cases of steels, representative of the old generation of steels (X52) and the new one (X70), for
transmission pipes, can sustain some hydrogen addition without decreasing either the fracture toughness
below the current threshold of design, or the fatigue crack growth resistance below the common
standard values (BS 7910). The limit of hydrogen addition could even reach 50 %vol. according to the
steel type and the operation conditions.
• The polymer material (polyethylene, PE) used for the modern distribution pipelines, is obviously
sensitive to hydrogen permeation through the pipe wall thickness; the hydrogen permeability is higher
than the permeability of methane in the same conditions of operation. But the effect of ageing of
hydrogen is not significant over the lifetime of PE pipes.
• At the end of the gas chain, the most common domestic gas meters with a polymeric membrane are not
show-stoppers and can reliably meter mixtures of hydrogen with NG up to 50 %vol. of H2.
• The effect of hydrogen on the tightness of the materials for inner grids was another durability and safety
concern. The range of materials used for these piping of gas installation in house is very wide. Among
the steels and polymers of different types of tested piping and connexion, the rubber hose only failed
the tightness tests.
2. Considering integrity, it is very important to know if additional measures regarding are needed to ensure a
reliability level comparable to the currently operated natural gas system if hydrogen is transported in the
existing pipelines. This is especially true for the inspection and repair of defects in particular for crack like
defects as they can change their growth behaviour significantly when hydrogen is added. The main findings
of the investigations performed on pipeline integrity and resource allocation are:
• Adopted inspection tools based on MFL and TRIAX technologies are capable to detect crack like
defects. EMAT technologies are even better suited to detect and size cracks and comparable defects.
The technologies needs to verify in field tests the promising results that were achieved in the project by
using pipe spools containing artificial and real defects.
• The repair technologies “Clock Spring”, “Metallic Sleeve” and “Weld Deposit” were assessed as
suitable for repairing hydrogen containing pipelines even though the performance was slightly reduced
in some cases.
• In a chosen example the effect of hydrogen on inspection and repair frequencies were calculated and the
corresponding cost were determined. A moderate increase of costs for inspection and repair activities
was observed as a consequence of hydrogen concentrations up to 50%, which is assessed as a very
promising result.
Summarising the results overall, it can be stated that appropriate pipeline integrity management can be put in
place for the transportation of natural gas and hydrogen mixtures by adopting existing systems especially in
the field of pipeline inspection and optimising repair intervals.
5
3. It was anticipated that adding hydrogen to the gas infrastructure may affect both the likelihood and severity
of untoward events and hence potentially increase the risk to the public. NATURALHY has established:
a. that escapes of natural gas/hydrogen mixtures within buildings behave in a similar way to natural gas, in
terms of the nature of the gas/air mixture produced. However, the gas concentration and volume of the
accumulation increases as hydrogen is added but these increases are slight for hydrogen addition up to
50% by volume;
b. within buildings, the severity of explosions is only slightly increased for hydrogen addition around 20%.
Analysis has suggested that the explosion frequency could increase by up to a factor of 2 as a result of
adding 20% by volume hydrogen to natural gas. However, the current risk is very low and even with a
2x increase the risk remains within generally acceptable limits;
c. from the point of view of the pipeline operator, the principal hazard posed by the failure of transmission
pipelines is that of a large fire. Project results suggest that the addition of hydrogen increases the risk to
an individual at locations near the pipeline but decreases the risk at locations further away, as the extent
of the hazardous region is reduced;
d. pipeline operators need to assess the background level of leakage from their pipeline networks, since
methane is greenhouse gas. A study of the expected background level of leakage has shown that the
level of leakage overall is very small and poses no hazard from a safety point of view. Indeed, the
addition of hydrogen results in a slight decrease in the level of methane emissions to the atmosphere
from the gas infrastructure, which is beneficial from an environmental perspective.
4. Regarding the end users of natural gas with hydrogen added, particular attention goes to domestic appliances
as personal health and home safety are at stake and tens of millions of appliances per country are involved.
It’s important to note that:
• the maximum hydrogen concentration for the domestic market in any country is determined by the safe
operation of properly adjusted conventional domestic appliances as well as by the local conditions of
natural gas quality (range and current value of Wobbe Index);
• for properly adjusted appliances and favourable conditions of natural gas quality, conventional domestic
appliances can accommodate up to 20% of hydrogen;
• for poorly adjusted appliances and/or unfavourable conditions of natural gas quality, no hydrogen
admixture is allowed;
• stationary gas engines and gas turbines need readjustment and/or modification;
• feedstock processing and industrial combustion applications require case by case consideration;
5. Gas quality issues have been considered, in the case of adding hydrogen to the natural gas network, as well
as the effect on downstream gas quality as hydrogen is selectively withdrawn by end-users. In a scenario
where end users at different points in the network may be taking out hydrogen at different quantities and
qualities, there will be an effect on the gas quality of the remaining natural gas mixture. However, analysis
shows that the downstream gas quality will not be adversely affected since the Wobbe index and heating
value can be assumed to still remain within the statutory requirements. But it should be noted that resulting
hydrogen concentration variations can be expected to pose problems to gas engines, gas turbines and
industrial applications.
6. Thin-film Palladium-based Membrane systems have been developed that generate a very good hydrogen
flux. These operate at around 300C. Carbon-based membranes operating at 30-90C have been optimised for
high flux and hydrogen recovery. These materials show better performance than current commercial
polymer membranes .Fibre spinning techniques have been employed to produce these membranes in the
form of hollow tubes which can be bundled into a membrane system.
6
7. The Decision Support Tool (DST) has two functions: to inform what is expected in material and device
behaviour at particular hydrogen percentages; and to simulate, using its ‘what-if’ analysis, the actual
pipeline degradation behaviour over certain periods of time.
The analysis comprises risk assessment, cost assessment, evaluation, and proposal of rules, guidelines and
procedures that will mitigate the expected increase of risk and/or costs when applying the gas mixture to the
pipeline network.
It also provides a comprehensive toolbox that enables the user to simulate a Gas Technology Network
(GTN) to enable comparisons between a GTN with or without hydrogen addition. The DST is extremely
flexible and is able to carry out GTN simulation and comparison of any two configurations over a period of
up to 50 years, yielding cost, safety and integrity calculations for all selected sections.
8. The potential benefits of adding hydrogen to the natural gas system have been addressed in a review of life
cycle and a socio-economic assessment and it has been possible to quantify benefits. However, the following
conclusions are, necessarily, qualitative:
• the addition of hydrogen to natural gas can make a significant reduction in total greenhouse gas
emissions if it is sourced from certain forms of biomass (forestry residues, straw and miscanthus), wind
power (both onshore and offshore) and nuclear power. Depending on circumstances, hydrogen
production from fossil fuels with carbon capture and storage (CCS) also offer some advantages.
However, reductions in total greenhouse gas emissions with these sources of hydrogen are generally
lower;
• potential benefits of selective extraction of hydrogen depend on the actual performance of the
separation technology and the subsequent use of the hydrogen (including its required purity) and the
residual gas (which still contains some hydrogen). However, overall air quality benefits (especially
lower sulphur dioxide, oxides of nitrogen and particulate emissions) can arise if hydrogen is
subsequently used in transportation and displaces conventional diesel fuel;
• the addition of hydrogen can be an effective means of "greening" natural gas so that the mixture is used
directly in existing appliances for heat production and electricity generation. With this option, the
potential benefits are mainly as a practical measure for mitigating global climate change and increasing
energy security, depending on the original source of the hydrogen.
In a few words and certainly not striving to be comprehensive, it can be concluded the results indicate that from
the safety, integrity and durability point of view (safety considering pipeline operations and pipeline integrity;
durability considering the life span of pipeline systems) the acceptable hydrogen level can be significant (several
tens of percent) depending on the mitigating measures taken by the operator. The safe use of a natural gas-
hydrogen mixture in buildings (severity of explosions) and the performance characteristics of some existing gas
appliances determine the ceiling. Safe use in buildings and with properly adjusted conventional appliances a
limit of approximately 20% hydrogen in the mixture is not leading to unacceptable consequences. However for
poorly adjusted appliances and/or unfavourable conditions of natural gas quality, no hydrogen admixture is
allowed without mitigating measures.
In all cases it might be possible to increase the maximum allowable percentage of hydrogen if additional
measures are taken. The feasibility of these additional measures will be addressed by the results of life cycle and
socio economic assessment as well as the Decision Support Tool (DST) that was developed to give pipeline
operators a tool in hands to determine the allowable hydrogen percentage in their grids. The costs associated
7
with additional measures need to be looked at in perspective of the very large investments needed to construct
extensive, new networks to transport hydrogen.
NATURALHY has kept abreast of the developments in other hydrogen projects in Europe and the USA. Most
research is concentrated on hydrogen for automotive purposes, like fuel cells and light weight hydrogen storage
tanks. Only a very limited number of research project is dedicated to the examination of the existing natural gas
networks for transport of hydrogen or a hydrogen – natural gas mixture. Some materials research is taking place
in the USA under government contract (DOE).
The results obtained by NATURALHY are clarifying and elaborating the feasibility of using the existing gas
grid for the transmission of natural gas - hydrogen mixtures. At the completion of the project it can be concluded
that research performed within the framework of the NATURALHY project has not identified any major barriers
to the addition of hydrogen at a useful level in the existing natural gas networks. In addition to answering the
essential question of “what is the maximum allowable percentage of hydrogen”, it has also considered that the
option of “greening” natural gas may be more feasible and attractive than transporting a mixture for subsequent
separation of the hydrogen at the point of end use.
8
1 INTRODUCTION
Hydrogen is widely proposed as an important energy carrier in the future sustainable energy society, as a means
of increasing security of supply and reducing carbon dioxide and other emissions associated with pollution and
global warming. More particularly, it is believed that utilizing hydrogen and gases containing hydrogen will
make a significant contribution to security of supply by utilizing locally available primary energies like gasified
biomass; reducing CO2 emissions by replacement of fossil fuels with hydrogen from renewables, or from fossil
fuels with CO2 sequestration, or by the implementation of the process for removing carbon (as a solid) from
natural gas to produce "hydrogen-enriched natural gas". These options contribute to de-carbonisation and
greening of our energy economy.
As hydrogen can be converted into electricity and vice-versa with high efficiency, it has potential for the indirect
storage of electrical energy (e.g. in case electricity production from wind and solar energy exceeds the demand).
This technology also increases the option for utilizing (waste) gases that contain hydrogen and enable the
development of power plants based on coal and biomass gasification in combination with carbon capture and
storage (CCS) to reduce greenhouse gas emissions, in spite of the fact that the gasification process demands a
high load factor. Furthermore, hydrogen could improve local air quality by replacing petrol and diesel in cars and
buses.
Gas network operators are very interested in de-carbonising natural gas and in adding sustainable produced gases
to natural gas infrastructures since this leads to de-carbonising of their business operations, provides new
business opportunities as well as improves corporate image. Hydrogen can be used as a pure gas (for example in
fuel cells, internal combustion engines and turbines) and also as a mixture with natural gas in internal
combustion engines, stationary applications and in some fuel cells.
However, because of a lack of infrastructure, the transition towards large scale production, delivery and use of
hydrogen will be long-term, extremely costly and only achievable with a substantial research and development
effort over many years. The first logical step towards a transitional delivery system suitable for hydrogen and
hydrogen-containing gases must be an investigation of the extent to which the existing assets, including the
existing natural gas infrastructure, can be used for hydrogen delivery.
The NATURALHY project aims to support the transition towards widespread use of hydrogen by utilising
existing and highly developed European natural gas networks for the delivery of hydrogen to end-users. The
project focused on the transmission, distribution and use of mixtures of hydrogen and natural gas. Techniques to
separate hydrogen from said mixtures were investigated as well. This approach obviates the need to construct a
wholly new distribution infrastructure, which (like the natural gas network developed over decades) would
require an investment of presumably many hundreds of billions of Euro.
In general, it is not possible to simply replace natural gas by hydrogen in existing natural gas networks as the
physical and chemical properties of hydrogen differ significantly from natural gas. Safety and durability of the
natural gas grid, as well as the performance of end use appliances, would be fundamentally affected.
Nevertheless existing natural gas networks could be suitable for mixtures of natural gas and hydrogen and the
9
concept of transporting and using mixtures safely was the specific focus of investigation in the NATURALHY
project. The purpose of this project was to define the conditions under which the existing natural gas network
(transmission and distribution system, end user infrastructure and end user appliances) could be used for
mixtures of natural gas and hydrogen. In addition, within the scope of the NATURALHY project, innovative
membranes have been developed that allow the selective withdrawal of hydrogen from a mixed natural
gas/hydrogen stream. Such development offers a unique opportunity to connect hydrogen producers and end
users in the short term at relatively low cost. The concept which underpins the approach adopted by the
NATURALHY project, further catalyses developments in hydrogen production and end use and, during the
transitional phase, provides more time to define the future, including the role of hydrogen therein, in sufficient
detail.
The strategic aspects of the project and its relevance to current world-wide activities in introducing hydrogen
have been addressed in the Strategic Justification for the project and this can be found at the NATURALHY
website: http://NATURALHY.net/docs/Strategic_justification_NATURALHY.pdf
Thus the main aim of the NATURALHY project has been to define the conditions under which the existing
European wide natural gas network (transmission and distribution system, end-user infrastructure and end user
appliances) can be used for hydrogen - natural gas mixtures. Furthermore, the project aimed to further develop
techniques to separate hydrogen from said mixtures, and to determine the overall socio-economic and
environmental benefits of the NATURALHY approach. It should be emphasised that the NATURALHY project
focused on potential showstoppers.
The NATURALHY approach leads to two specific options depending on future development scenarios:
• The addition, distribution and end-use of mixtures of natural gas and hydrogen will be a significant
contribution to the “greening of gas” i.e. to reduce global warming impacts of natural gas operation and
use.
• The transmission and distribution of hydrogen in natural gas networks and then separation of the
hydrogen provides a real opportunity for end users to obtain pure, or nearly pure, hydrogen for a variety
of applications, thus helping to create “local hydrogen centres” and enabling the accelerated transition
towards a hydrogen energy society.
To realize these goals the effect of the addition of hydrogen on the operation of gas networks and end use
appliances have been assessed. For the second option low cost and efficient means for separating hydrogen from
the natural gas / hydrogen mixture have been developed.
The NATURALHY Project has been a world-wide forerunner in researching the detailed impacts hydrogen
addition has on the existing natural gas networks. This work has attracted interest from international gas
operators and gas research organisations. Strong links have been forged with European, US and Asian
organisations attaching great importance to delivering hydrogen to end users. In addition to the execution of the
agreed work programme within the NATURALHY project, which is overseen by the Project Executive
Committee, views were exchanged with a Strategic Advisory Committee consisting of a select group of
representatives from relevant national and international organisations such as the International Gas Union,
International Hydrogen Energy Association, the European Gas Research Group (GERG), the European
Commission and European Parliament, United States Department of Energy, and the United Kingdom Health
and Safety Executive.
10
1.5 NATURALHY OBJECTIVES
Principal technical and strategic project objectives of the project are listed below.
o To define the technical conditions under which hydrogen can be accommodated in the existing
natural gas system with acceptable risk and avoiding unacceptable leakage and significant degradation
of the system and consequences for the end users. Work Packages WP2, WP3, WP4, and WP5 have
focussed on their respective programmes of safety, integrity, durability and end use appliances to cover
the essential aspects of the existing natural gas network and end use.
o To carry out life cycle assessment (LCA) as a means of comparing the major resource inputs and
environmental outputs of current natural gas and related systems and transitional natural gas/hydrogen
systems including methods of hydrogen production.(WP1)
o To analyse the socio-economic aspects of transitional natural gas/hydrogen systems and compare
these with current natural gas and related systems with particular reference to job creation and
maintenance, capital investment and total internal costs.(WP1)
o To develop innovative devices (membranes) to separate hydrogen from natural gas - hydrogen
mixtures: these devices will enable an early establishment of hydrogen growth centres that will advance
a gradual transition to the full hydrogen economy. (WP5)
o To assess the current situation of standards and regulations regarding natural gas/hydrogen
mixtures and to identify necessary modifications and to initiate required changes.(WP7)
o To develop a Decision Support Tool for assessing the technical suitability of an existing natural gas
system (transmission, storage, distribution, end user infra structure and end user appliance) for mixtures
of natural gas/hydrogen and to develop models for determining the environmental, employment and
economic aspects of the whole chain from sustainable hydrogen production up to and including end
user appliances (WP1,WP2,WP3,WP4,WP5,WP6)
o To motivate all stakeholders in the whole chain from production up to and including end use to
welcome “hydrogen”. Such stakeholders consist of among others, the public, end users, manufacturers
of appliances, owners and operators of gas transmission grids, hydrogen producers, local, regional and
national authorities, manufacturers of all kinds of equipment and components for gas, etc. This
objective was met in cooperation with among others the HyWays Integrated Project and the HySafe
Network of Excellence (WP1,WP2,WP3,WP4,WP5,WP6,WP7):
The main technical deliverable of the project is an expert system, the “Decision Support Tool”, which can be
used to determine the maximum percentage of hydrogen that can be added to natural gas supplied in any given
section of a natural gas pipeline system and identify the factors that limit the percentage.
It should be noted that although the objectives of the NATURALHY project concern hydrogen-natural gas
mixtures, the outcomes are very relevant for defining the conditions under which the existing natural gas system
can be used for biogas, hydrogen produced from syngas, and other sustainable produced gases containing a
certain amount of hydrogen, including SNG. Moreover, the information gained in this project can be used to
determine to which extent the existing pipeline network can be used for the delivery of pure hydrogen. In this
specific case, changing the operational conditions, particularly the pressure regime, and some of the hardware
(e.g. compressors) would seem to be a necessity.
11
In order to meet the objectives mentioned in paragraph above, a set of coherent Work Packages, detailed below,
has been defined within the NATURALHY project. The way they cohere is indicated in the following diagram.
WP Durability
WP End Use
WP Dissemination
WP Project Coordination
Figure 2.1 Schematic overview of the main relations between the Work Packages defined
WP1 Life Cycle and Socio-economic Assessments comprises a comparison of the main natural resource
requirements, environmental impacts, employment consequences and economic costs over the complete life
cycle of current natural gas and related energy systems and the proposed transitional natural gas/hydrogen
systems from source to point of use.
WP2 Safety enables the risks presented by the transmission, distribution and use of a hydrogen/natural gas
mixture to be compared with those for natural gas. To ensure credibility amongst system operators, the major
hazard scenarios previously studied for natural gas and pure hydrogen are re-examined experimentally for
hydrogen/natural gas mixtures. Tests include investigation of explosions and build up of gas in confined/vented
enclosures and congested regions, high pressure jet fires and pipeline fires. Large scale experimental testing is
crucial to the NATURALHY project as fire and explosion phenomena are scale dependent. The results are used
to modify existing risk assessment methodologies, developed originally for natural gas. The modified risk
assessment methodologies are currently used to undertake risk assessments to compare with those completed for
the existing natural gas system.
WP3 Durability determines the effects of hydrogen on the durability of materials and components used in the
natural gas transmission and distribution networks and end user infrastructure. Existing defect assessment
criteria are adapted to take into account an increasing percentage of hydrogen in natural gas. The results are
being processed to produce durability lifetime models. This will enable the assessment of the ageing of materials
and components and to provide a practical way of evaluate the system lifetime given its characteristics and the
percentage of hydrogen.
WP4 Integrity provided a specification for an Integrity Management Tool (IMT). The specification developed
support the operators to modify the existing Integrity Management Systems (IMS) covering the needs raised by
the challenge to transport hydrogen-natural gas mixtures in the existing pipelines, which were constructed to
carry natural gas. The activities cover the identification of defects sensitive to hydrogen, their critical sizes as
12
well as inspection and repair technologies. Furthermore the effect of introducing hydrogen in natural gas on
the costs for operating the integrity management was investigated.
WP5 End Use examines the implications of providing distributed pipeline natural gas/hydrogen mixtures to end-
users and the effect on existing appliances. A survey and analysis of existing data has been undertaken to assess
the impact of added hydrogen on the performance characteristics of existing natural gas appliances including,
domestic and industrial burners, particularly industrial burners used for glass industry. This has led to an
understanding of the requirements for existing and new appliances to operate safely and efficiently with
increasing levels of hydrogen. A R&D programme was conducted to develop high efficiency membranes and to
provide options for separating hydrogen from the distributed hydrogen/natural gas stream for end-use
applications at various scales. Methods for ensuring the gas quality as hydrogen is progressively removed are
assessed.
WP6 Decision Support Tool develops an expert system to assess the suitability of an existing gas system
(including transmission and distribution pipelines, end user appliances and operational aspects) to cope with
whichever hydrogen/natural gas mixture is proposed. With this tool, NATURALHY deals with the fact that no
general, simplistic figures on acceptable hydrogen percentages to be added to natural gas can be determined. As
explained before, the determination of the suitability of a natural gas system for hydrogen must be made by a
rigorous examination of the specific conditions pertaining.
WP7 Dissemination ensures that the results of the NATURALHY project are made available to targeted
technical/scientific stakeholders and decision makers at various levels. It achieves this via a series of appropriate
actions, including publications, workshops, technology transfer activities and regular interfaces with government
bodies, safety authorities, standards bodies, consumer organisations, environmentalists and decision-makers at
both national and European levels.
Each Work Package is led by a Work Package leader (WP-leader), which are indicated below.
WP1 Life Cycle and Socio- University of Loughborough*), Nigel Mortimer, +44 1904 410 643,
Economic Assessment [email protected]
WP3 Durability GDF SUEZ (previously Gaz de France), Isabelle Alliat, +33 149225871,
[email protected]
WP6 Decision Support Tool Instituto de Soldadura e Qualidade (ISQ), Peter Bartlam, +35 1214229014,
[email protected]
13
WP7 Dissemination 1 Exergia, George Vlondakis, +302106996185, [email protected]
WP8 Project management N.V. Nederlandse Gasunie, Onno Florisson, +31 50 700 9732,
[email protected]
*) at the start of the project, University of Warwick (UK) was leading these two Work Packages; on its request
Warwick was discharged and as from November 2006 the partners mentioned in the table took over.
**) at the start of the project Netherlands Organisation for Applied Scientific Research (TNO) was leading this
Work Package: on its request TNO was discharged, and from May 2006 DBI-GUT took over this task;
1
The NATURALHY project website can be found at: www.NATURALHY.net
14
2 LIFE CYCLE AND SOCIO-ECONOMIC ASSESSMENT – WORK PACKAGE 1
2.1 OBJECTIVES
The main objectives of Work Package 1 of the NATURALHY Project consist of providing the means to conduct
life cycle assessment of the major natural resource inputs and environmental outputs, and socio-economic
assessments of economic costs and employment (or job creation) for current natural gas and related energy
systems, and transitional natural gas/hydrogen systems. For this purpose, life cycle assessment concentrates on
primary energy inputs relevant to energy resource depletion, greenhouse gas emissions, including carbon
dioxide, methane and nitrous oxide, associated with global climate change, hydrogen emissions (when known),
air quality pollutants, consisting of sulphur dioxide, oxides of nitrogen and particulates, and ionising radiation
(when determined). Socio-economic assessments focus on internal economic costs and estimates of direct and
indirect employment. A modular approach is necessary to ensure that all components of the systems under
investigation can be evaluated in a coherent and effective manner. Meaningful and persuasive comparison of the
relative benefits of current natural gas and related energy systems, and transitional natural gas/hydrogen systems
is based on recording the information and presenting calculations in a standard and transparent format.
2.2 CONTRACTORS
The contractors involved in this Work Package were Loughborough University (leader), COGEN Europe, ECN
– Energy Research Centre of the Netherlands, ISQ - Instituto de Soldadura e Qualidade, PLANET –
Planungsgruppe Energie und Technik GbR, SAVIKO Consultants ApS, and Technische Universität Berlin.
In order to achieve these objectives, it was necessary to develop a series of electronic workbooks which could
represent the relevant technologies adequately, provide a transparent means of documenting calculations, data
and sources, and present results in a clear and understandable form. Using previous experience, it was decided to
use MS Excel as a basis for these workbooks. A standard structure was devised for these workbooks so that they
consist of a series of the following specific worksheets:
• Version worksheet; documenting the author, date and main modifications of the latest version of the
workbook
• Input/Output worksheet; a table for entering values of the key parameters for the technology being
evaluated with their details and default values
• Unit Flow Chart worksheet; a visual representation of the process stages which constitute the
technology being evaluated with details of parameters which specify these stages
• Life Flow Chart worksheet; a visual representation of the phases of the technology being evaluated with
details of parameters which specify these stages
• Allocation worksheet; a means of partitioning environmental impacts, employment implications and
economic costs between multiple outputs from the technology being evaluated
• Global Warming Potentials worksheet; a means of specifying global warming potentials for greenhouse
gases
• Time Profile worksheet; a specification of the phases of the technology being evaluated mainly
consisting of construction, operation and maintenance, and decommissioning
• Summary worksheet; a tabular and graphic summary of results from the evaluation of environmental
impacts, employment implications and economic costs for the technology in question
• Process Stage worksheets; a collection of calculation worksheets which represent the individual process
stages of the technology being evaluated
• Reference worksheet; a record of the sources of data used in the workbook
15
Natural G as Input
C OMP R E S S OR S TATIONS
S TOR AG E F AC IL ITIE S
Natural G as Out-of-
S ystem
Natural G as Input (R egional Distribution)
Amongst the most important components of the workbook are the Unit Flow worksheet, as this describes and
specifies the essential components of any given technology, the individual Process Stage worksheets, as these
contain the basic calculations for environmental impacts, economic costs and employment implications, and the
Summary worksheet, as this presents the results of all calculations. A simplified representation of the Unit Flow
Chart (Figure 3.1) for a natural gas network shows that the technology is composed of a series of specified
processes, or components.
The individual Process Stage worksheets all have the same regular layout to assist data entry, analysis and
presentation. An example of part of a Process Stage worksheet (Figure 3.2) indicates that the basic features of
the process under consideration, such as its nature (functional unit), its units of measurement, relevant location
and period, the author of the worksheet and when it was last modified, are summarised in Rows 1 to 6 of the
worksheet. Descriptions of the inputs to a process are described briefly in Column A, units of measurement in
the Column B, with data values and ranges in Columns C and D, respectively, and supporting notes, including
references, in Column E. The multipliers used to convert these into environmental impacts, economic costs and
employment effects, and estimated results are then recorded, in subsequent columns. In this example, the units of
the primary energy multipliers are specified in Column F, their values and ranges with supporting notes are
provided in Columns G, H and I, respectively, and results, in the form of the estimated values and ranges of the
primary energy inputs, are presented in Columns J and K, respectively. This layout is repeated across the
workbook for other multipliers and results.
16
A B C D E F G H I J K
1 Description of Functional Unit: Storage Facility Operation
2 Final Unit of Measurement: 1 m3 of total gas storage capacity over a year
3 Relevant Location: European Union
4 Relevant Period: 2000
5 Author/Date: ISQ / February 2008
6 Last modification: TUB June 2009
7
8 Input Notes Primary Energy Multiplier Notes Primary Energy Input (MJ/m3)
9 Units Value Range +/- Units Value Range +/- Value Range +/-
Electricity Consumption MWh/m3 of total gas 0.0000124 0.0000019 Electricity consumption per cubic MWh/MWh 1.110 0.000 Primary energy input 0.0494 0.0074
storage capacity over metre of natural gas over a year per MWh electricity
a year based on the assumption that 30% of (Ref. 29).
the total storage volume is injected
10 and withdrawn over the course of a
year (Ref. 48), a typical pressure
increase for injection from 85 bar to
300 bar (Ref. 49) and a compressor
efficiency of 85%.
Maintenance t steel/m3 of total gas 0.000 0.000 Replacement of steel over the life of MWh/t 6.783 0.000 Total energy 0.0000 0.0000
11 storage capacity over storage facilities assumed to be requirement for cold-
a year negligible. rolled steel (Ref. 1).
The complete series of Process Stage worksheets for any given technology supplies relevant data to the
Summary worksheet where final results are derived and presented. As each Process Stage worksheet provides
results in units relevant to the process under consideration, these results are converted to appropriate units for the
entire technology, as a collection of processes, specified by the Unit Flow Chart worksheet. Such results are
detailed in tabular form and presented in graphical form. An example of the graphical presentation of results
(Figure 3.3) shows the contributions of different aspects of natural gas network operation to the delivery of
natural gas to large users.
100%
SOIL RESTORATION
70%
PIPELINE TESTS
60%
PIPE REPAIRS
50% DIGGING THE TRENCH
INTERNAL INSPECTIONS
30%
STORAGE FACILITY OPERATION
20%
COMPRESSOR STATION OPERATION
10% AERIAL PATROL
0% ROAD PATROL
Figure 3.3 An example of the graphical presentation of results showing the contributions of different aspects of
natural gas network operation to the delivery of natural gas to large users.
17
During the NATURALHY Project, workbooks were produced for a number of relevant technologies.
However, essential workbooks, which were required for the Decision Support Tool (DST developed by Work
Package 6, represent the following technologies:
• Natural gas supply
• Natural gas network construction
• Natural gas network operation
• Natural gas network decommissioning
• Natural gas hydrogen network operation
Whilst such workbooks could not address the exhaustive engineering complexity and detail of actual natural gas
networks, parameters were selected to ensure necessary functionality which would enable results to represent
specified networks appropriately. For this purpose, the main parameters for the user to specify any given natural
gas network consist of:
• Natural gas flow rates (m3/h):
o Out-of-system users (to other natural gas networks)
o Large users (to industrial consumers)
o Local users (to commercial and domestic consumers)
• Transmission pipes (head stations):
o Length (km), diameter (mm) and wall thickness (mm)
o Repair frequency (number/km.a)
• Transmission pipes (high pressure):
o Natural gas losses (%)
o Pipes (16 possible options) defined by total length (km), diameter (mm), wall thickness (mm)
and material (steel)
o Road, aerial and internal inspection frequencies (fraction of pipeline inspected/a)
o Repair frequencies (number/km.a)
o Length of pipe removed during decommissioning (km)
• Compressor stations:
o Total number of reciprocating engine and turbine compressor stations
o Land area (ha/station)
o Compression ratios for reciprocating engine and turbine compressor stations (m 3/m3)
o Annual maintenance and repair costs (% of initial capital costs)
o Material recycled during decommissioning (%)
• Storage facilities:
o Number of injection/withdrawal wells
o Well volume (m3)
o Annual maintenance and repair costs (% of initial capital costs)
• Regional distribution pipes (medium pressure):
o Natural gas losses (%)
o Pipes (16 possible options) defined by total length (km), diameter (mm), wall thickness (mm)
and material (steel, polyvinylchloride, polyethylene and iron)
o Road and aerial inspection frequencies (fraction of pipeline inspected/a)
o Repair frequencies (number/km.a)
o Length of pipe removed during decommissioning (km)
• Pressure reduction facilities (large):
o Number
o Natural gas capacity (m3/h)
o Annual maintenance and repair costs (% of initial capital costs)
18
o Material recycled during decommissioning (%)
• Local distribution pipes (low pressure):
o Natural gas losses (%)
o Pipes (16 possible options) defined by total length (km), diameter (mm), wall thickness (mm)
and material (steel, polyvinylchloride, polyethylene, iron and copper)
o Repair frequencies (number/km.a)
o Length of pipe removed during decommissioning (km)
2.4 RESULTS
Various results can be generated using the natural gas workbooks produced from the NATURALHY Project. For
example, the relative contributions to total primary energy, emissions and economic costs of the natural gas
delivered by the network to out-of-system users, large users and local users can be evaluated (Figure 3.4).
Local Users
Network Construction
Network Operation
Out-of-System
Network
Decommissioning
-50 0 50 100
Figure 3.4 For example, the relative contributions to total primary energy, emissions and economic costs of the
natural gas delivered by the network to out-of-system users, large users and local users
Apparent differences are due to the proportions of natural gas flowing through different parts of the network and
the significance of different components in the network (leakages, compressor station and storage operations,
etc.). Similarly, the breakdown of total greenhouse gas emissions for natural gas delivered to different users by
phase of development (natural gas supply, and network construction, operation and decommissioning) can be
determined (Figure 3.5). From this example, it can be seen that network construction and decommissioning are
relatively insignificant contributions to the total greenhouse gas emissions of natural gas delivery to end users.
The contributions of network operation varies depending on the nature of the user and extent to which they rely
on different parts of the network to obtain natural gas; only part of the transmission network is used to supply
out-of-system users, parts of the transmission and regional distribution networks are used to supply large users,
and parts of the transmission and regional distribution networks and all the local distribution network are used to
supply local users.
19
100%
90%
80%
70%
60%
50%
40%
30%
20% Local Users
10% Large Users
0%
Out-of-System Users
Figure 3.5 The breakdown of total greenhouse gas emissions for natural gas delivered to different users by phase
of development (natural gas supply, and network construction, operation and decommissioning)
The workbook for natural gas network operation provided the basis of developing the essential workbook which
represents the operation of an existing network with the addition of hydrogen. This consists of the injection of
hydrogen from given sources, its transport as a mixture with natural gas through the network, its possible
removal using specified separation technologies, and its eventual use (as hydrogen or in a mixture with natural
gas). The original source of hydrogen is one of a number of important factors which determine the relative
advantages or disadvantages of transporting this energy carrier with natural gas in existing networks. Hence, it
was necessary to assemble representative results for the generation of hydrogen from different sources as well as
conventional energy technologies and a variety of relevant end use applications. For ease of use, these results
were incorporated into a Library of Results which represents 97 technology options. Significant differences in
results are apparent, as demonstrated by the example of total greenhouse gas emissions (Figure 3.6) for hydrogen
generation. These results can be compared with the total greenhouse gas emissions for the conventional supply,
delivery and combustion of natural gas (indicated by the red dashed lines).
Natural gas steam reforming without carbon capture and storage 348
Hydro power plant, centralised atmospheric electrolyser 315
Geothermal power plant, centralised atmospheric electrolyser 259
Solar PV power plant, onsite atmospheric electrolyser 202
Short rotation coppice power plant, onsite atmospheric electrolyser 182
Natural gas steam reforming with carbon capture and storage 146
Miscanthus power plant, onsite atmospheric electrolyser 137
Forest residue power plant, onsite atmospheric electrolyser 134
Straw power plant, onsite atmospheric electrolyser 107
Wind power plant, onshore, onsite atmospheric electrolyser 37
Wind power plant, offshore, onsite atmospheric electrolyser 35
Nuclear power plant, centralised atmospheric electrolyser 13
Forest residue gasification 5
kg eq. CO2/MWh H2
Figure 3.6 Total greenhouse gas emissions for different scenarios of hydrogen generation
Complete analysis can be undertaken with the natural gas hydrogen network operation workbook which
incorporates the following key parameters:
20
• Amount of hydrogen injected (% by volume)
• Relative contributions of hydrogen from different sources (%)
• Injection point (start of transmission or regional distribution network)
• Separation point (end of transmission or regional distribution network)
• Hydrogen separation technology (pressure swing absorption, carbon membrane, palladium membrane,
or hybrid system):
o Purity of separated hydrogen (%)
o Hydrogen content of residual gas (%)
o Heat requirements of separation technology (MJ/kg H 2)
o Electricity requirement of separation technology (kWh/kg H 2)
• Hydrogen re-compression (for direct use or transport filling station supply):
o Inlet and outlet pressures (kPa)
o Single unit output rating (Nm3/h)
o Number of single units
o Load factor (%), annual operating time (h/a) and lifetime (a)
21
3 SAFETY – WORK PACKAGE 2
3.1 OBJECTIVES
The key objective of the Safety Work package was to compare the hazards and risks presented to the public by
the existing infrastructure conveying natural gas with the hazards and risks presented by the same infrastructure
assuming that a natural gas/hydrogen mixture is conveyed.
3.2 CONTRACTORS
The contractors involved in this Work Package were Loughborough University (leader), Leeds University, CEA,
Shell Hydrogen, National Grid and the UK Health and Safety Executive.
In order to be able to achieve this objective, it was necessary to modify the risk assessment methodologies used
for the natural gas infrastructure to enable them to be used for natural gas/hydrogen mixtures. Risk is
combination of the likelihood of an adverse event and the consequences of that event. Hence, in order to modify
the risk assessment for natural gas/hydrogen mixtures, it is necessary to consider both the likelihood and
consequences of releases of such natural gas/hydrogen mixtures. Specific aspects that have required modification
include:
• The probability of an accidental release from different parts of the gas infrastructure and the probability
of ignition of the gas mixture
• The assessment of the consequences of gas dispersion, fires and explosions involving natural
gas/hydrogen mixtures
• The data on the properties of natural gas/hydrogen mixtures particularly in relation to the turbulent
combustion of such mixtures in air and ignition energy
Determining the failure probability involved using information from the literature and results of work performed
within Work Packages 3 (Durability) and 4 (Integrity) of the NATURALHY project. Modelling the
consequences of gas dispersion, fire and explosions has been achieved using ‘engineering type’ models which
are often used for risk assessment purposes and through the use of more complex Computational Fluid Dymanic
(CFD) approaches. In order to develop and validate the mathematical models, experimental data on gas
dispersion, fire and explosion phenomena for natural gas-hydrogen-air mixtures was required. As such
phenomena are strongly scale dependent, large scale experiments have been performed as part of the Safety
Work Package to study gas build up, fire and explosions. Laboratory scale experiments have also been
conducted to obtaining specialised data on the turbulent combustion parameters (such as turbulent burning
velocity) which are important when modelling explosion events. Ignition energy of methane/hydrogen mixtures
was also determined through laboratory scale experiments.
The purpose of the gas industry is to provide energy to the population for use in their homes and also for
commercial and industrial premises. By its very nature, the gas infrastructure comes into close contact with the
public. Clearly pipelines are needed to convey the gas to the areas where people live and hence pipelines will be
located near people’s homes. From the gas meter onwards, the gas is in very close proximity with people and
how they care for and maintain their own internal gas pipework and appliances can affect their safety. For these
reasons, in considering the risk to the population and how this may change if hydrogen is added to the network,
two key areas have been considered:
1. The risk posed by a failure on the high pressure pipeline system and
22
2. The risk posed by an escape of gas from the low pressure pipelines close to buildings or from
pipework and appliances internal to the property which could lead to gas accumulation within the
property and a gas explosion.
In addition to the above hazard and risk assessments, the Safety Work package was also requested to review the
incidental low level of leakage from the pipeline system due to minor imperfections. For the system operating
with natural gas, this is not a safety issue (although it is important from an environmental perspective since
methane is a strong greenhouse gas). The purpose of the review was to ensure that the addition of hydrogen does
not result in this leakage creating an additional hazard and to reassess the level of leakage of methane.
3.4 RESULTS
Incidental Leakage
Incidental leakage from the gas pipeline infrastructure arises mostly as a result of poor or damaged joints or
minor defects in the pipe wall. The vast majority of this leakage occurs on the lower pressure parts of the system,
especially where older materials, such as cast iron mains, are used. The level of leakage is very low typically less
than 1% of the gas conveyed and presents no safety hazard. A theoretical assessment of the effect on leakage of
adding hydrogen to a pipeline system was undertaken. This included both low and high pressure pipelines. Using
information gathered within Work Package 3 (Durability) on the permeability of polymer pipelines to methane
and hydrogen (which showed that polymers were more permeable to hydrogen than to methane), the losses
through polymer pipe wall permeation were also considered.
It was found that the addition of hydrogen to the pipeline system reduced the mass leakage rate slightly, for the
level of hydrogen addition envisaged by NATURALHY. For example, for 20% (by vol) hydrogen addition, the
total mass leakage reduced by a factor of 0.91 and the methane mass leakage by 0.89. However, the addition of
hydrogen to natural gas would result in a reduction in the rate of energy delivery if the system continued to
operate at the same pressures. One option is to slightly increase the delivery pressure to maintain the energy
delivery rate, but the increased pressure would increase the leakage. For a system with 20% (by vol) hydrogen
addition, operating at slightly higher pressure to achieve the same energy delivery rate, the total mass leakage
would reduce by a factor of 0.96 and the methane mass leakage by 0.93.
In conclusion, it was found that following the introduction of hydrogen the incidental leakage is not a safety
issue and that overall the mass leakage reduces slightly. In particular, the methane leakage reduces, which is
beneficial since methane is a greenhouse gas. Despite the increased permeability of plastic pipelines to hydrogen,
the leakage from this mechanism is negligible and there is insufficient residence time of the gas in the pipelines
for any noticeable change in gas composition to arise as a result of preferential loss of hydrogen through polymer
pipe walls.
Large scale experiments to study high pressure jet fires and fires following the rupture of an underground
transmission pipeline were undertaken (Figure 4.1). During the experiments the flame length and thermal
characteristics were measured and used to develop and validate engineering models of the fire event. It was
found that the addition of 25% (by vol) hydrogen made little difference to the fire characteristics, however, the
mass outflow was reduced and the pipeline depressurised more quickly for the mixture. This results in a slightly
reduced extent of the hazardous region for the natural gas/hydrogen mixture. For the jet fires, a slight increase in
the heat loading to an engulfed obstacle was measured during tests involving the natural gas/hydrogen mixture,
most likely associated with an increase in the convective heat transfer from the high velocity flame.
The severity of explosions was studied at large scale during 3 experimental programmes, one studied confined
vented explosions in a large enclosure and the other two programmes studied vapour cloud explosions in
congested regions of pipework. Mathematical modelling using both engineering type models and CFD models
was undertaken. The explosion models also required information on the laminar and turbulent burning velocity
of methane/hydrogen mixtures and this was achieved through an extensive programme of laboratory experiments
in a specialised test facility (Figure 4.2).
Figure 4.1 a large scale rupture from an underground Figure 4.2 Laboratory experiment to study the laminar
transmission pipeline and turbulent burning velocity of methane/hydrogen
mixtures
For confined vented explosions, the results showed that the severity of explosions increased as hydrogen was
added but the increase was slight for 20% (by vol) hydrogen addition but more significant for 50% addition. A
modified version of the Shell model SCOPE was used to model the explosions satisfactorily. A CFD model was
also developed and used to explore the impact of varying hydrogen addition and this suggested that a more
significant rate of increase in overpressure could be expected for hydrogen additions over 45% (by vol).
Vapour cloud explosions (VCEs) in a compact cubical region of pipework, with gas compositions ranging from
100% methane to 100% hydrogen with 3 mixtures in between, also showed that the addition of 50% (by vol)
hydrogen increased pressures significantly and a transition to detonation was observed for 100% hydrogen.
VCEs in a long congested region (Figure 4.3), which provided a longer path length for flame acceleration
showed that for 40% (by vol) or more addition of hydrogen would give rise to accelerating flames and potential
24
for a transition to detonation. In circumstances involving high levels of congestion and a high speed flame
venting into the congestion, continued flame acceleration and damaging pressure levels could also be
experienced for lower levels of hydrogen addition. However, reduced congestion levels had a significant impact
on reducing overpressures. Engineering and CFD models were also applied to model these VCEs.
Figure 4.3 Site to study Vapour Cloud Explosions in a long congested region
Overall it was concluded that the severity of explosions increases as hydrogen is added to natural gas, but the
increase is small for hydrogen addition up to 30% (by vol). For 40% (by vol) or more, a significant increase in
explosion severity can be expected.
The failure frequency of natural gas pipelines can be determined based on historical information available in
incident databases. This information is included within LURAP as a function of the pipeline parameters (such as
diameter, wall thickness etc). Additionally, a correlation based method for calculating failure frequency due to
third party damage was also included in LURAP and this approximates the results of a structural reliability
approach. The advantage of this method is that mitigating measures, such as the use of increased depth of cover
or concrete slabbing can be assessed. For use with natural gas/hydrogen mixtures, it was essential to consider if
any of the failure mechanisms might be affected by the introduction of hydrogen. In collaboration with partners
from Work Package 3 and 4 it was concluded that the only failure mechanism which would be affected by the
introduction of hydrogen was that of failures arising from fatigue crack growth of sharp crack-like defects, where
disassociation of hydrogen molecules into atomic hydrogen could detrimentally affect the material properties of
the steel. Using a methodology developed within Work Package 4, and data obtained by Work Package 3 to
describe the rate of crack growth, the impact on failure frequency was considered for realistic initial crack sizes.
It was found that, for mixtures containing up to 50% (by vol), provided that an appropriate integrity management
25
strategy was adopted, the failure frequency for crack-like defects should not increase above that already
experienced for natural gas.
Incident database information was also used to provide 3 different approaches to assessing the ignition
probability of natural gas pipeline failures. Conservative estimates of the ignition probability of hydrogen
pipeline failures were made and a method developed to determine the ignition probability of mixtures. The
resulting ignition probabilities for mixtures depend to some extent on the approach adopted for natural gas, but
always increase as hydrogen is added.
A model of the thermal characteristics of the pipeline fire was developed and validated against the large scale
data described above. However, the effect of thermal radiation on people is a function of both the level of
radiation and the time of exposure – termed the ‘thermal dose’ measured in thermal dose units (tdu =
(kW m-2)4/3 s ). Typically a level of 1800 tdu would result in 50% fatalities and 1050 tdu corresponds to a 1%
chance of becoming a fatality. It was also assumed that persons in the vicinity will attempt to escape and are
likely to find shelter within 30 seconds. To provide a conservative approach, LURAP determines the distance to
1050 tdu over a 30 second period and uses this as a criteria for fatalities. In reality the outflow and fire event
following rupture of a pipeline is a highly transient event and so the radiation will vary with time and distance
following the rupture. However, prediction of the outflow is complex, so the approach taken by LURAP is to
approximate the transient event by a steady outflow. The determination of the steady outflow level includes
factors which are a function of the gas composition and so take into account the different mass outflow and more
rapid depressurisation expected for pipelines which include some hydrogen. The approach was validated against
the experimental data and against benchmark exercises for natural gas and found to predict the extent of the
hazard region within ±10%.
Using LURAP, predictions of individual and societal risk have been made for typical pipelines. The addition of
up to 50% (by vol) hydrogen slightly increases the risk to an individual close to a pipeline, but reduces the risk at
locations further away, associated with the reduced extent of the hazardous region. Similarly, for societal risk,
the frequency of low consequence events (small number of casualties) is expected to rise but high consequence
events (involving large number of casualties) are expected to involve fewer casualties and be less frequent.
Having detected a gas escape, many residents will take action to mitigate the consequences, such as isolation of
the gas supply and/or opening windows/doors, thereby preventing an explosion occurring. In most cases, the
residents will also report the escape to the gas company and an engineer will be dispatched to take mitigating
action if not already taken by the resident.
26
However, all of the above events take time, and the time intervals between commencement of a release and its
detection, or between detection and reporting, or between reporting and arrival of the engineer, may vary in
length according to the time of day and the behaviour of the resident, and these variations are included by
assigning probabilities to each of the alternatives at each step of the process.
During all the time from the moment that the gas release commences until mitigating actions are taken, there is
the potential that a flammable accumulation could be ignited. Hence at all steps along the process, the possibility
of ignition is considered. Ignition could arise as a result of household appliances such as refrigerators or boilers
which activate automatically, or could occur due to the actions of the occupants of the property – such as light
switches or striking matches. The estimation of ignition probability was assisted by laboratory scale data
obtained to determine the minimum ignition energy of methane/hydrogen mixtures across the flammable range.
By evaluating the probabilities of each step of this process, it is possible to determine the probability of an
explosion given that an escape of gas has occurred. Using historical data on the number of gas escapes per year,
it is then possible to determine the number of explosions per year. Taking pessimistic assumptions about the
ignition probability, it was found that the addition of 20% hydrogen (by vol) could result in a 2-fold increase in
explosion frequency whereas for 50% the increase could be up to 4-fold. However, the current risk is very low
and even with this increase, the risk remains within generally acceptable limits.
3.5 CONCLUSIONS
The Safety Work Package has considered the change in the risks presented to the public following the addition
of hydrogen to the natural gas infrastructure, particularly focussed on levels of hydrogen up to 50% by volume.
The nature and characteristics of gas releases, build up, fire and explosions have been studied for natural
gas/hydrogen mixtures and the failure frequency and ignition probability of accidental releases have been re-
assessed.
The extensive body of large scale and laboratory scale data generated by the Safety Work Package provides a
valuable resource to research workers and gas industry safety engineers, which can be used to develop and
validate modelling approaches to hazard assessment and inform decisions about the potential for introducing
hydrogen into pipeline networks. The mathematical modelling undertaken within the project demonstrated this
capability and has shown how the level of hydrogen introduced affects the severity of the hazard and hence the
level of risk.
The overall conclusion from the Safety Work Package is that up to 30% by volume of hydrogen could be added
to the natural gas within the current gas infrastructure without adversely affecting the risk to the public
significantly and without any additional mitigation measures.
The addition of 40 to 50% by volume of hydrogen would probably also be achievable without unacceptably
increasing the risk to the public from the pipeline system or from explosions in properties. However, it is
recognised that in some circumstances the increase in the severity of the explosions may be undesirable and pose
an additional hazard. Therefore, it would be prudent to consider the adoption of mitigation measures in situations
where the explosion severity could be increased.
27
4.1 OBJECTIVES
The existing natural gas system has been designed for natural gas. The physical properties of hydrogen differ
substantially from natural gas and consequently the impact of hydrogen added to natural gas on the durability of
the materials of the grids should be studied. Durability of pipeline materials is an important issue concerning the
technical/economic lifetime of the transmission system and it is also a key aspect regarding safety risks. Work
Package 3 aims to establish the acceptable percentage of hydrogen that can be mixed with natural gas, given its
effects on the characteristics of the component parts and materials employed in the existing natural gas
infrastructure, including transmission, distribution (including domestic gas meters) and inner grids, taking into
account the requirement to maintain safe operation.
Considering the huge amount of materials forming the existing pipeline networks over Europe and the inner
grids, a dedicated selection of few materials was decided and focused on the materials for pipelines themselves.
The other major equipment studied were domestic gas meters and the materials used for inner grids. Therefore
WP3 provides answers on the selected materials regarding their ability to delivery mixtures of NG+H2, and the
method for assessing the durability of materials.
4.2 CONTRACTORS
The contractors involved in this Work Package were GDF SUEZ (leader), CEA, CMI-Beasy, CSM, DBI-GUT,
DESFA (DEPA), ENIM, GASUNIE, IFP, IGDAS, ISQ, STATOIL, TNO, TOTAL.
Transmission pipes in the existing natural gas grids operate under high pressures, for example from 40 bar up to
100 bar. The low carbon steels used for building the transmission grids have been developed with increasingly
higher mechanical strength; the steel X42 is one of the oldest, used in the 1960’s while today operators have
started to use the X80. However, the higher the yield strength, the lower is the resistance to crack growth. This
risk is well managed for natural gas, but should be assessed for hydrogen.
Although the interaction of hydrogen with steels has been largely studied, the aim of using the steel grids
designed for natural gas for transporting hydrogen requires extended studies about the effect of hydrogen on the
properties of these steels (mechanical strength and fracture behaviour) as well as an understanding of the
mechanisms.
Tests on 2 steels currently used in existing pipeline grids (X52 and X70) were executed on laboratory samples, to
quantify the effect of hydrogen on their fracture toughness and fatigue crack growth resistance. Some
demonstrative tests were carried on at full-scale under hydrogen pressure; burst tests were performed on parts of
pipes with well-controlled defects (cracks). The special case of the rapid propagation of crack, following rupture
of the gas pipe, was studied by numerical modelling. It is expected that due to their different thermo-dynamical
properties, the crack arrest will happen sooner in case where hydrogen is present in the gas pipe.
X52 and X70 base metal in 100% H2, compared to literature data + BS 7910
X52, Naturalhy
0,1
X80, literature
0,01
< 0.01um/cycle
= acceptable
P = 66 bar
0,001
1 10 100
stress intensity factor range DK [MPa√m]
Figure 5.1 Fatigue crack growth of X52 and X70 base materials in 100% H 2.
Before injecting H2 in the existing NG transmission grids, the other devices along the transmission grids have to
be investigated. In addition, the effect of H2 on compression stations needs clarification, which like storage were
outside the scope of the NATURALHY project.
29
4.4 DURABILITY OF POLYMERS FOR DISTRIBUTION PIPES WITH HYDROGEN
The poly-ethylene (PE) is the mostly used polymer material for local distribution of natural gas at low pressures,
from 16 bar down to few mbar. The main concern about pipes made of polymers like polyethylene is its
permeability to hydrogen which may induce leakage of gaseous H2 and therefore a dangerous situation, un-
reliable metering, and potential damage due to ageing.
The aim of this study was to be able to compare the gas losses of the natural gas service in comparison to the
transportation of hydrogen rich gases depending on the hydrogen concentration. Three different polymers were
studied ; PE80, PE100 and PVC-HI (ductile PVC), and electro-fusion welds.
Amount H (cm )
6
Thermoregulated environment
4
5 0.8
2
4
0.6
3
3
Gas collector
0.2
Thermoregulated pipe 1
0 0
4 4 4 4 4
0 1 10 2 10 3 10 4 10 5 10
Time (s)
Figure 5.2 Testing facility for permeation (IFP) Figure 5.3 Example of measurement of gas
permeates.
It was noticed that for a given temperature, each gas (either H 2 or CH4) keeps its intrinsic permeability
coefficient whatever the composition of the feed mixture is. No particular interaction could be noticed, that is to
say, no mixture effect occurs. From the experimental results, it is possible to extrapolate and to obtain the
permeability coefficients values at lower temperatures such as 10°C or 0°C.
By comparing the behaviour of the two single gases, one can see that the permeability of H2 is larger than those
of CH4 whatever the temperature. The activation energy of the permeability phenomenon through PE 80 for
hydrogen is weaker than that for methane. As a consequence, the decrease of permeability with temperature is
slower with hydrogen than with methane.
Permeation results were used for calculating the potential leakages on distribution. Below is an example of
theoretical calculation of gas leakages due to permeation for the case of a PE pipe distributing at 4 bar a mixture
of 80% NG + 20% H2 :
• Permeation leakage of H2 = 2,3 litre/ km / day,
• Permeation leakage of CH4 = 1,1 litre / km / day.
For comparison, the gas leakage for the same PE pipe distributing only CH 4 would be :
• Permeation leakage of CH4 = 1,4 litre / km / day.
30
Permeation results were also used for assessing the consequences on safety. According to the assessment
performed by the University of Loughborough within the WP2 Safety, it was concluded that the H 2 losses due to
permeation is extremely small compared to the leakage from small defects in the pipe wall and that the leakage
rates are insignificant from a safety perspective.
From the results obtained it can be concluded that the transport of hydrogen through polymers is significantly
elevated in comparison to methane. In particular the transport of hydrogen through PE pipes turned out to be 6 to
7 times higher than for methane.
Examples of H2 leakages due to gas permeation are given below for the case of a 110 mm-pipe distributing H2 at
200 mbar ;
• Permeation leakage of H2 of a PE100 pipe = 5,0 liter / km / day,
• Permeation leakage of H2 of a PVC-HI pipe (including joints) = 13,2 liter / km / day.
Depending on the ageing conditions, significant variations have been measured despite the discrepancy inherent
in the samples themselves. Taking into account the corresponding discrepancies, neither a major nor catastrophic
influence of ageing (in the range studied) has been identified. However, a small increase in permeation
coefficients was observed which is essentially linked to the increase of solubility in the material.
As a conclusion, the change in tightness performance with age remains small with respect to industrial use of
these PE materials.
Leakages due to gas permeation through the wall of pipes were taken into account in economics (loss of fuel)
and environment (GHG emission) assessments in the WP1.
The most common domestic gas meters are membrane meters, made with a polymeric membrane which is
sensitive to hydrogen permeation. Several potential effects of hydrogen were expected, for example, influence on
metering accuracy and safety due to leakages, and on durability (physical damage).
31
Hence, domestic meters from 3 European manufacturers (Gallus (France), Dresser (Italy), Elster (Germany))
were tested regarding their reliability for hydrogen metering of the membrane in presence of hydrogen. The
meters were tested with 2 different mixtures (100% CH4, 50% H2 – 50% CH4). Using a flow of 50-50 CH4-H2
mixture produced little difference in metering (<2%), and the lower the flow rate, the lower the difference with
the CH4 reference performance.
In order to evaluate the suitability for hydrogen service (up to 50% hydrogen), connection types (i.e. connection
between end-using devices and house installation ) and gas-valve combinations of end use devices, both
designed for applications in houses, have been investigated. Specimens were chosen which were believed to
have a significant market share in the future.
The test samples were investigated according to the guidelines DVGW VP 614, DIN EN 161 and DIN EN 13611
and DIN 3387. In part, the test criteria were enhanced, in particular the pressure of impact by test gas
investigation. This pressure was enhanced, compared to the DIN 3387, for most of the connection tests to ensure
sufficient gas capacity for the gas analysis after the test period. This was an additional investigation not foreseen
by the guidelines but important in order to determine the difference between the hydrogen and methane gas loss
through the connections.
The gas-valve combinations EUROSIT 630 by SIT la Precisa Padova and the compact assembly CG10 by
Kromschröder were tested according to the guidelines DIN EN 161 and DIN EN 13611. Both samples passed the
tests successfully with the methane-hydrogen mixture (50 % H2 - 50 % CH4).
32
The investigated in-house connections passed both the static bending test and the subsequent leakage test with
the hydrogen-methane mixture (8 of the 9 specimens passed the test performed with the CH 4-H2 gas mixture).
One specimen, a flexible rubber hose, failed the test.
5.1 OBJECTIVES
The main objective of the Integrity Work package was to provide support to pipeline operators on when and how
to inspect and repair pipelines that convey natural gas and hydrogen mixtures.
5.2 CONTRACTORS
The contractors involved in this Work Package were TNO Science & Industry, Computational Mechanics
BEASY, GDF SUEZ, PII Ltd. (A member of GE Energy Group), Istanbul Gas Distribution Co. Inc. (IGDAS),
N.V. Nederlandse Gasunie, Instituto de Soldadura e Qualidade (ISQ), Turkish Scientific and Technical Research
Council (TUBITAK), StatoilHydro and Total.
In order to support the pipeline operators to maintain a proper pipeline integrity management (IM) for pipelines
that conveys mixtures of natural gas and hydrogen the main components of the IM have been investigated. The
investigations comprises the expected effect of hydrogen on the existing defects, a comprehensive sensitivity
analysis, the estimation/calculation of the probability that a pipeline will fail as well as the inspection and repair
technologies of pipelines. The results have been summarised in reports and are used in the Decision Support
Tool of WP6.
5.4 RESULTS
Defect criticality
As well as the defect type, it is very important to know the critical size of defects. Cracks can grow over time
(cracks are time dependent defects) so knowledge of the crack growth rate in a certain timeframe can provide the
critical initial defect size by back-calculation assuming a particular design life. The critical initial defect size
should not be exceeded at the beginning of the period under review. Sensitivity analyses show that, under the
selected assumptions, the effect of hydrogen on materials considered to be sensitive, is minor up to
concentrations of 50% (by volume) compared to the effect of pure hydrogen. Nevertheless a clear impact on the
acceptable initial crack size was observed especially for axial defects (Figure 6.1).
Furthermore, a tool (POF tool) able to calculate the probability that a pipeline or a defect (crack and corrosion)
will fail or lead to failure and the failure rate was developed.
34
Resource allocation
The costs for modifying the IM-systems in place are strongly dependent on the individual situation especially on
the hydrogen concentration, defect distribution, material properties, loads and integrity targets. Therefore an
example was performed using material data provided by WP3, defect distributions which reflect pipes in a
medium condition with a maximum operation pressure of 66 bars and aiming to meet a Probability Of Failure
(POF) integrity target for corrosion and for cracks after 50 years of operation, which is in line with the failure
statistics of European transmission pipelines for natural gas. For the example, it can be concluded that for high
concentrations of hydrogen (50%) in natural gas pipelines a slight effect on the inspection and repair frequency
is expected. Within the chosen example an increase of total costs (inspection and repair for corrosion and cracks)
of the order less than 10% was calculated.
Work on the pipeline integrity management performed within the project show that when hydrogen is added to
the pipelines constructed to convey natural gas crack like defect are most critical. Corresponding defect sizes
have been determined and candidate inspection technologies have been selected and tested leading to promising
results. Furthermore repair technologies were proven to be suitable when hydrogen is added to the existing
system. The effect on the costs has been calculated for an example and comprehensive guidance is given for:
• calculating of the probability that a pipeline will fail within a given time (POF software tool)
• developing modified integrity management systems suitable to cover the effect of hydrogen and
• determining the corresponding cost for the adapted integrity management systems
It can be concluded that from the integrity management point of view, hydrogen can be transported by the
existing natural gas system providing small adaptions of the existing IM are executed. The necessary adaptions
are strongly linked with the hydrogen concentration and the conditions of the grids to be considered. The
necessary modifications are not significant up to about 50% hydrogen for the considered cases but a detailed
investigation for every case is mandatory and can possibly lead to lower limitations on the hydrogen
concentration permissible.
37
6 END USE- WORK PACKAGE 5
6.1 OBJECTIVES
The End-Use work package focussed on the potential impacts of adding hydrogen to natural gas networks on end
use applications, and the possibility to withdraw hydrogen from the mixture for differing applications, and
consequent impact on gas quality as a result of hydrogen withdrawal.
The efficient separation of hydrogen is a key component of initiating a hydrogen infrastructure while
development of highly efficient membranes offers the potential to obtain hydrogen of different purities at low
cost and at a range of scales.
6.2 CONTRACTORS
The partners involved are University of Oxford, NTNU, CETH, Gasunie, DGC and Midt-Nord
Figure 7.1 Screen shots of testing domestic boilers with hydrogen/natural gas mixtures
38
Figure 7.2 H-band-like distribution, the working area for domestic appliances
Thus, for fuel rich appliances (worst case scenario), avoiding light-back will limit hydrogen addition to:
~28% hydrogen addition to a natural gas at the maximum of the H-band
~23% hydrogen addition to a gas equivalent to pure methane
~18% hydrogen addition for a gas where the resulting Wobbe index of the mixture is kept at the minimum of the
H-band.
It is important to note that for poorly adjusted domestic appliances and/or unfavourable conditions of natural gas
quality, no hydrogen admixture is allowed.
Stationary gas engines, gas turbines, natural gas feedstock processing and industrial combustion applications
require consideration from case to case.
39
Development of membranes for hydrogen separation
In addressing objective 2, parallel developments of two types of membrane materials were undertaken:
development of selective carbon based membranes, and, development of ultra-thin Palladium based membranes
for producing pure hydrogen. Substantial progress was achieved in both research programmes. Highly efficient
carbon molecular sieve membranes were prepared by special routes designed to control and optimise controlled
pore structure. These materials showed high selectivity and permeability of hydrogen. Some progress was also
made in forming the membranes into hollow tubes by special spinning techniques, suitable for packaging into a
practical membrane module.
Ultra- thin, 3micron Palladium based membranes were prepared by a range of techniques including electroless
plating and magnetron sputtering. Electroless plating of Palladium onto a porous alumina substrate has given
membranes that meet the 2010 DOE targets for hydrogen flux at 400C. Similar routes to palladium alloyed with
silver and copper have not given successful membranes. Manufacturing defects in the ceramic supports have
been shown to give rise to pin-hole leaks and mechanical problems. The application of a fine pore (20nm)
surface coating smoothes out most substrate defects, but improved substrates are still required.
Figure 7.3 8 µm Pd membrane supported on Figure 7.4 Ceramic substrate with 10 µm alumina sol gel
ceramic substrate coating
A series of membranes were prepared by Magnetron vacuum sputtering by a specialist company using a
77%Pd/23%Ag source. The Pd alloy was deposited on silicon, porous steel and polymer supports. These were
3micron thickness, and required chemical, peeling using potassium hydroxide, to remove them from the support
surface. Although initially it proved difficult to obtain pin-hole free membranes, in the final stages of the project
a new method was employed that gave coherent Pd/Ag membranes supported on porous supports.
Process development has been directed towards a conceptual process for producing PEM fuel cell grade
hydrogen in a 2 stage process utilising a first stage carbon based membrane followed by a Pd based membrane to
40
deliver 100 m3/hour of hydrogen; this scale represents a small refuelling station for hydrogen vehicles. The
first stage effectively increases the hydrogen partial pressure of hydrogen that improves substantially the
performance of the Pd membrane in the second stage. The process is shown in Figure 7.5.
Figure 7.5 Conceptual scheme for separation of hydrogen from hydrogen/natural gas mixtures
This process has been optimised and analysed to derive performance and cost factors. Manufacturers and
engineering contractors have been approached in an effort to obtain current costs for alternative separation
options, principally pressure swing adsorption (PSA) plants. Although it proved very difficult to obtain real costs
from commercial suppliers, some estimated costs were provided and these, together with existing literature data
were used to compare likely costs of PSA with membranes.
Following this work, the technical and economic performance of membranes and the options for hydrogen
separation have been assessed. In particular, membranes have been compared with pressure swing adsorption
(PSA) route in terms of efficiency, and capital and operating costs for three scales:
• Small scale separation to deliver <50 m3/hr hydrogen suitable for fuel cells
• Intermediate scale (refuelling station) delivering 100 m 3/hr hydrogen
• Large scale separation (1000 m3/hr) of hydrogen suitable for gas turbines
Overall, the work on separation indicates that NATURALHY membranes can deliver 98% hydrogen using
carbon membranes alone at low cost, or with the palladium membrane in series, high purity hydrogen at lower
capital costs compared to PSA.
The quality of Supply to downstream hydrogen users as hydrogen is withdrawn along the network will depend
on a number of factors.
• Rate of hydrogen extraction is roughly proportional to the hydrogen partial pressure
41
• Users’ capital and running costs are very dependent on the partial pressure of H 2
• Local domestic supply could be subject to considerable variation in hydrogen concentration as domestic
hydrogen extraction becomes more common
• Larger users will probably be located at higher pressure sources and have a more predictable effect on
local hydrogen depletion
• The increasing separation and use of hydrogen will most likely result in a requirement for a unified
standard for acceptable variation in hydrogen concentration
Results from the WP relating to the performance and costs of the membranes relative to commercial PSA have
been derived and provided to the Socio-economic analysis Work Package and as input into the Decision Support
Tool.
A number of papers and presentations relating to the above work have been published (see chapter 11).
42
7 DECISION SUPPORT TOOL – WORK PACKAGE 6
7.1 OBJECTIVES
The main objective of the Decision Support Tool (DST) Work Package was to develop a software tool to enable
a Natural Gas Company to perform a what-if analysis on what happens to a specific Gas Transport Network
(GTN) when specific hydrogen percentages are transported. The DST is a PC based software tool enabling a
company to introduce a configuration layout of a specific gas transport network or section and evaluate what are
the consequences of carrying hydrogen and compare it with any other configuration over a number of active
years.
7.2 CONTRACTORS
The contractors involved in this Work Package were Instituto de Soldadura e Qualidade (WP Leader), DESFA,
Gasunie, GDF Suez, National Technical University of Athens, SQS Portugal, The Open Group, University
College of Borås and University of Oxford.
The Work Packages of the NATURALHY project have delivered a massive amount of information on the
economics, societal and environmental aspects of transporting hydrogen over a natural gas transmission network
and on a wide range of materials’ properties and behaviour, on separation membranes performance and costs for
several end user applications, such as industries, filling stations, etc., on pipeline integrity and on gas transport
network safety performance when carrying hythane – the mixture of hydrogen and natural gas.
It must be stressed that the DST is focused on an overall and general type of analysis and not on replacing, for
instance, commercially available pipeline integrity management systems which carry integrity analysis to a much
more detailed level. In addition, the massive amount of detailed information on actual pipeline conditions and
behaviour that is required in order to enable a more thorough analysis is either simply not available at gas
company level or requires a data collection cost that is not acceptable for the obtainable increase in accuracy.
The DST has two main uses: firstly to inform, through its Information Repository, what is expected in material
and device behaviour when certain hydrogen loads/percentages are applied and secondly to simulate, using its
what-if analysis capabilities, the actual pipeline degradation behaviour over certain periods of time being also
able to apply, on the pipeline model, mitigation measures. Thus, the NATURALHY-DST key goals are to (i)
enable editing, analysis and annotation of a pipeline network, so relevant information may be found and
extracted at later stages, (ii) to allow comparison of parameters and measures amongst several pipeline network
trunks and terminal points and (iii) to compute, from the information included by the operational Work
Packages, a parameter set condensate which will yield a comprehensive what if analysis of applying different
load balances of hydrogen and natural gas of different subsections of the network;
The above-mentioned analysis comprises risk assessment, cost assessment, evaluation, and proposal of rules,
guidelines and procedures that will mitigate the expected increase of risk when applying the gas mixture to the
pipeline network.
The methodology adopted throughout the duration of the project has been to work in a highly integrated way
with the 5 technical Work Packages in order to determine the type of project results that would be produced and
to develop a consensus on the use and presentation of the results to be finally included in the DST. This included
determining which results would be implemented in the network simulation what-if analysis and which results
would simply be implemented in the Information Repository for access by the end user.
In particular the following Work Packages presented their key results for use in the DST.
43
• WP1 (Life Cycle and Socio-economic Assessment). Baseline and Intermediate Scenario EXCEL
workbooks, integrated in the DST for network analysis.
• WP2 (Safety). LURAP risk assessment tool, integrated in the DST for network analysis
• WP4 (Integrity). Probability of failure tool, integrated in the DST for network analysis
• WP5 (End Use). Membrane hydrogen separation options. Effects on gas quality and appliances.
Based on the preliminary discussions and inputs from the Work Packages the first stage of WP6 was completed
with the generation of the DST Concept Document. The software development stages adopted the Dynamic
Systems Development Methodology – DSDM which is an internationally recognised software development
framework. The significant development steps included the development of a functional prototype, system
architecture definition, Global Data Model and Final Specification of User Requirements. Finally as the final
data and results became available from the Work Packages the main software development proceeded with the
construction of the DST. The testing stages of the DST consisted of two parts. The first part included the testing
of the network layout simulation functionality with the verification of analysis results based on a Benchmark
Configuration consisting of a fictional network with 12 different pipe sections. The final deployment and
validation testing stage consisted of the simulation and analysis of real natural gas networks using data for
sections of the Portuguese and Greek gas transmission networks.
7.4 RESULTS
The DST follows the generally adopted software interface behaviour for MS/Windows systems. The tool
interaction itself is organised around a number of tab selected forms, a toolbox and a control toolbar and the DST
is focused on enabling effective what-if analysis, thus making it very simple:
• to establish/modify H2 load conditions;
• to modify pipeline layouts;
• to compare risk, integrity and cost results derived from the several H 2 Load conditions;
• to compute and simulate the pipeline behaviour over a period of time and, finally
• to keep a track record of the user interactions and results of analyses.
The DST works on a local database that contains a selected number of data fields from the Gas Company
mainstream PIM system; these data fields are complemented with specific DST fields, namely the ones carrying
H2 related information. The tool is able to export some data elements through its reporting facility.
Thus, a DST Configuration is a Gas Transport Network (GTN) topology able to be analysed and compared; it is
an abstract description of the gas infrastructure which is the basis for simulation purposes. An energy
infrastructure generally covers the whole supply chain, from energy source to end use. The Decision Support
Tool (DST) covers the mid- and downstream part of the energy chain. The network representation covers the
midstream, i.e. the transmission, distribution and end use parts of the network.
The DST Menu Bar
DST provides the user with a traditional Menu Bar, containing the commonly used options for opening and
editing Configurations. In the menu strip, the following options are available:
Configuration Edit Report Compare Window Help
The DST Desktop
Below in Figure 8.1 the Menu Bar, there is a grey empty area where all Configuration screens may be laid. It is
the DST desktop.
44
Distribution Valve
Network
Exit Blending
Station
Compressor
Station
Figure 8.5 The GTN Elements
47
Configuration Parameters
The user is able to specify specific parameters which appear in the Property Sheet area and are grouped in 3
main domains: Device specific. Miscellaneous and Operation Parameters. The Device parameters describe the
major characteristics of the Device, which can be any of the GTN elements. The Misc (Miscellaneous)
Parameters contain parameters that cannot be grouped in the two specific clusters.
Hydrogen Extraction
The Hydrogen extraction element enables the user to insert at any point an extraction of Hydrogen. In order to
facilitate the extraction parameterisation, the DST provides a number of possible generic applications and helps
the end user to select, according to its forecasts, the actual and detailed parameters.
The predefined Hydrogen applications include:
The User is then able to select the appropriate separation option from available membrane and PSA solutions and
the appropriate parameters such as purity.
Integrity Profile
The Integrity Profile form contains a total of seven charts plus a property sheet where all output values are
numerically displayed. The charts are organised in specific groups as defined below.
• Leakage Probability of Failure by Cracks/Corrosion/3rd Party Damage
• Rupture Probability of Failure by Cracks/Corrosion/3rd Party Damage
• Number of forecasted repairs
48
The Safety Profile
Opposite to the concept of addressing failure of only one pipeline at a time, the Safety Analysis performs
calculations both for a specific pipeline, yielding the Individual Risk which represents the risk of casualty of a
person living at specified distances from the pipeline and a global computed risk for the network, the Societal
Risk, yielding the risk of exceeding a number of fatalities.
These risks are presented in the two related charts presented in the Risk Profile form. A third chart plots the
Societal Risk over the years having pre-selected, by a button, the number of casualties.
Testing and Verification of the Tool
The testing and verification of the functionality of the DST has been undertaken by creating a Benchmark
Configuration of a fictional pipeline network. This consists of a network of 12 various pipe sections which is
based on the LURAP work carried out within WP2 by Loughborough University on risk assessment
methodology. For the testing and verification of LURAP all twelve pipe sections are analysed but for the testing
and verification of the POF Tool only two pipe sections are analysed. The results have been correlated against
the results produced by the Work Packages.
The GTN Layout of the Benchmark Configuration is shown in Figure 8.6 and typical results of the Safety Profile
(LURAP) and the Integrity Profile (POF Tool) are shown in Figure 8.7 and Figure 8.8 respectively.
The development of the DST has been successfully completed, tested and verified. In the verification testing the
DST has proven to be very user friendly in terms of setting up the simulation of network configurations and in
producing what-if analyses of the effects of hydrogen on a network using the LURAP and POF tools. However
the objectives have not been fully met in that user trials have been more limited than planned and will therefore
be ongoing beyond the project. Additionally some of the project results are not yet fully integrated into the DST
due to the delays in the Work Packages and in some cases the non-availability of results and reports within the
project timescale.
51
8 DISSEMINATION-WORK PACKAGE 7
The main objective of the Workpackage “Dissemination” was to disseminate effectively the results of the
NATURALHY project via a series of appropriate actions, including:
• publications, both printed and electronic;
• a series of workshops targeted at various user groups and stakeholders
• regular interfaces with government bodies, decision-makers at both national and European levels, safety
organisations, standards bodies, consumer organisations, etc.
In addition, the workpackage, included a subtask for investigating the situation regarding relevant standards and
for providing proposals regarding steps to be undertaken in the standardisation field.
The work package built on the results achieved by the other work packages in order to serve the aforementioned
objectives.
A project web site was established right after the commencement of the project work (www.naturalhy.net). The
web site became the main outlet for the distribution of information and results of the project work, including
sections such as: Reports, Presentations, Publications, News, etc. Towards the end of the project, the web site
was completely redesigned in order to freshen up its appearance and to obtain a more modern look and
functionality.
A series of 9, six-monthly Newsletters were prepared and published. The Newsletters were 4-pages, full colour
publications, including articles that presented results from the NATURALHY project activities, in various stages
of its development.
The Newsletters were distributed during the various events and conferences where NATURALHY participated.
They were also emailed to the members of the mailing list which was established during the course of the
project, and they were available for downloading through the project web site. More than 16,000 copies of the
newsletters were downloaded from the project web site during the project duration.
A series of four workshops were organised on an annual basis, starting from the second year of the project’s
duration, so as to reach a scientific audience and present and discuss the project findings. All workshops were
organised within international scientific events, so as to maximise the attention received on the project and the
audience size.
The workshops were organised at:
• Zaragosa, Spain, on November 22, 2005 during the 2nd European Hydrogen Energy Conference EHEC
2005
• Amsterdam, Netherlands, on May 30 within the Conference “Transmission of CO2, H2, and biogas:
exploring new uses for natural gas pipelines”
• Paris, France on October 9th, 2008 within the International Gas Research Conference, that was held on
October 7-10, 2008.
• Ajaccio, Corsica – France during the International Conference on Hydrogen Safety.
In total, more than 250 attendants participated in these events. Attendants included engineers, scientists and
decision makers from the gas sector from Europe, USA and Asia. Lively discussions followed the presentations
made by NATURALHY members in each event, thus providing a valuable insight to NATURALHY project
work
54
Figure 9.3 Impression of the 3rd NATURALHY Workshop (IGRC 2008, Paris)
Further to the above workshops, NATURALHY also participated in several other international events in order to
present and discuss its scientific findings. These events included mostly international conferences e.g. the 17th
World Hydrogen Energy Conference, the Forum Hydrogen Pipeline Transmission of the International Pipeline
Conference 2006, the World Gas Conference 2006, the European Hydrogen and Fuel Cell Technology Platform,
the 2nd European Hydrogen Energy Conference, (EHEC 2005), the International Conference on Hydrogen
Safety (ICHS 2005, 2007 and 2009), the 3rd GCC-EU Advanced Oil and Gas Technology Conference in
November 2005 in Kuwait, etc.
Particular notice should be made to the event which was organized for the presentation of the NATURALHY
Project to the Committee on Industry, Research and Energy (ITRE) of the European Parliament, on May 31,
2009.
Finally, the NATURALHY results were presented at the Final Public Presentation, which was dedicated to
NATURALHY and that took place at the headquarters of the project coordinator N.V. Nederlandse Gasunie, in
Groningen, the Netherlands on 19th November 2009.
A NATURALHY Brochure was prepared, in order to provide the ultimate dissemination publication of the
project and to provide an insight to the major findings of the project activities. The brochure is a 32, full color
A4 pages and includes articles on the role of hydrogen in the transition towards a sustainable energy society; the
NATURALHY approach and what can the natural gas system offer for the delivery of hydrogen; the impact of
adding hydrogen to natural gas on the durability of the network; the measures that should be taken to control and
monitor the condition of the network; the impact of adding hydrogen to natural gas on safety aspects; the impact
of adding hydrogen to natural gas on end user aspects; the separation of hydrogen from hydrogen/natural gas
mixture and its impact on the quality of the remaining gas; how to assess a specific network for the
NATURALHY concept; the overall benefits of adding hydrogen to natural gas and concluding remarks.
The brochure was made available in hardcopy format and in electronic format, available for downloading from
the project web site.
55
8.5 WORK ON STANDARDISATION
One of the objectives of the NATURALHY project is to assess the current situation of standards and regulations
regarding hydrogen/natural gas mixtures and to identify necessary modifications and eventually to initiate
required changes. It is understood that some aspect of the gas system will be affected more than others by the
injection of hydrogen. It can be expected that standards related to the chemical (gas) composition, performance
of end user appliances, safety distances (safety risks) have to be revised. Also, depending on the technique of
production, (standard) requirements for the entry point and the injection will be necessary.
Since the start of the NATURALHY project we have seen several developments in relation to the possible future
use of the (European) gas grid. Next to addition of hydrogen into the natural gas grid, the injection of other non-
conventional sources like methane rich gases were being considered and discussed more and more. In the
meantime CEN/TC 234 decided to install a new working group, CEN TC/234 WG9 Non conventional gas
injection into gas grids to start standardization development. Within this working group the development of a
CEN Technical report Gases from non-conventional sources — Injection into natural gas grids — Requirements
and recommendations started . It covers the state of the art in the treatment, injection, transportation, distribution
and utilization of gases from non-conventional sources, including hydrogen, in the natural gas system. It also
tries to foresee the possible developments in this field in the nearer future.
The scope of the CEN Technical Report covers the utilization of non-conventional sources like methane rich
gases from gasification or fermentation processes; hydrogen-rich gases from gasification or other chemical
processes and hydrogen produced by electrolysis (generally using renewable energy).
The main aspects to be covered by the CEN/TC 234/WG 9 are the technical, gas quality and most important
(long term) safety and integrity aspects related to the delivery of such gases by the existing natural gas networks,
and concern particularly the processes injection in the gas networks, metering and billing, transmission and
distribution, and end use. The production and upgrading processes will only be described as far as relevant for
the other processes.
For the moment the focus within this standards development will be mainly on the biogas but in the following
years this CEN document should be considered in addition to any existing National standards covering
installations for manufacture, extraction, treatment, injection, transport and utilization of non conventional gases.
It may also support any future directive or ordinance in this field.
The CEN/TC 234/WG 9 already is aware of the NATURALHY project and furthermore will take into account
the results of the NATURALHY project. Furthermore, CEN/TC 234/WG 9 will be the basis for relevant future
standardization initiatives related to the injection of hydrogen into the gas grid. The working group will only
work on standardization of main aspects and not on all individual aspects as discussed in this report. However,
they can and most probably will act as initiator to other working groups and Technical Committees and working
groups in and outside CEN.
To enable a market introduction of gas/hydrogen mixtures, all technical barriers should be taken away by
amending the existing relevant national and European standards and development of new European standards.
The impact of revision of standards should not be underestimated due to the huge number of standards involved.
Next to both the European and the national standards also branch codes do exist and next to that a lot of
companies do have their own companies standards which include by reference a mix of the above mentioned
codes and standards and additional company specific issues. Furthermore a lot of the standards are linked by
references to European and national legislation but also to for instance certification schemes and training plans.
56
The project management structure is based on highly linked team organization with assigned responsibilities and
roles (Figure2)
.
Overall
Project Executive Committee
management
European
delivery of Project Co-ordinator, Work Package Leaders, several key Commission
objectives, IPR, partners
finance,
knowledge
WP Leader WP Leader WP Leader
Deliverables 1 2 7
WP WP --- WP
members members members
Naturalhy Consortium
Integration
All partners
The Project Executive Committee (PEC), as the core group responsible for the successful completion and
delivery of the Project, was delegated by the full project Consortium to oversee the management of the project,
and the Committee reported to the full Consortium at the annual all-partner meetings. The Committee is a
management team that consisted of the Work Package leaders, the GERG representative and the project
coordinator. This Committee met at least every 6 months and at appropriate phases of the project
o Overall Project management: to approve the progress of the Project and to solve any bottlenecks. The
project coordinator prepared progress reports based on the information of the partners, compared the actual
progress with the planning and prepared appropriate proposals to deal with any discrepancies. The Work
Package leaders have prepared substantial contributions to the regular progress reports and the final reports.
The Committee tuned the programs and activities carried out within the Work Packages, solved bottlenecks
and took care of information exchange among and towards the partners. Particular effort has been paid to
project integration: if the output from one Work Package is aimed to be the input of another Work Package,
57
the type of data, the planning of the delivery, the format of the data, the conditions for which the data is
valid etc. has to be agreed in detail.
o Financial management: Administrative aspects of the financial management were carried out in compliance
with the EC contract and the Consortium Agreement by the project coordinator and his staff: project
finance needed the approval of the Executive Committee and the Party(ies) concerned.
o Management of knowledge resulting from the project and of legal issues: Knowledge management
concerns issues like ownership of results, access rights, commercialization of results, and was a basic
responsibility of the PEC. As a part of this, the Work Package leaders have paid particular attention to the
quality of reports prepared by the members of its Work Package.
o Information management: The Consortium Agreement determines that all information produced within the
project was confidential unless the PEC decided otherwise. The project coordinator took the lead for
requesting such approval. All documents relevant for the project have been made accessible for all partners
(supported by the project website). Communications with the Commission were also one of the
responsibilities of the project coordinator.
The 7 Work Package Committees defined comprise the partners that carried out the RTD programme for
NATURALHY. For the co-ordination of each Work Package, a dedicated Committee was established, that was
led by a well-experienced partner (the Work Package leader). The Work Package co-ordination was focussed on
progress obtained in the Tasks and on completion of the Work Programme by planning details of specific
activities, liaising with Work Package participants, checking milestones, organising deliverables, and assisting
integration with other related Work Packages. These Work Package Committees met regularly, at least every 6
months.
The Full Project Consortium of partners met annually (including at the kick-off meeting). These meetings took
take place over two days and had agreed timetable and agenda to ensure all business were completed and that all
partners were well informed. The agendas were dedicated to project business aspects including the status of the
project, specific results obtained and problems surmounted, updates from the Commission, financial issues, IPR
and dissemination issues. Furthermore, there was room for partners to interact, discuss detail project
developments, discuss project plans etc (Integration). Any major changes to the Project needed the approval of
the Full Project Consortium.
The Strategic Advisory Committee (SAC) was aimed at addressing the strategic aspects of the project and to
establish a platform for dissemination and for promoting public understanding and acceptance. It comprised
selected representatives and advisors of European decision makers, regulators, authorities and policy groups in
the fields of energy, environment and legislation, together with the members of the NATURALHY Project
Executive Committee. Among others, the following entities have participated in this Committee: US DOE (US),
International Gas Union (Global), Naturgas Energia (ES), TPAO (TR), Health & Safety Executive (UK), EON-
Ruhrgas (DE), DVGW (DE), Alliander (NL), Air Liquide (FR), AKZO NOBEL (NL), IEA GHG(UK) ,
HYSAFE (DE), Roads2Hycom (UK), Wuppertal Institute (DE), Bellona (NO), European Natural Gas Vehicle
Association (ENGVA, NL), European Commission, ENI (IT), Linde (NL), Gordon Adams (former MEP, UK).
This Committee has discussed the strategic aspects of the project and it was the ‘vehicle’ by which the
NATURALHY-members informed the Committee of the vision and results of the Project, so that these were
taken into account in their own processes. In return, the NATURALHY members were informed about the
current relevant developments in politics, legislation, other projects etc. The resulting advices and guidance from
this Advisory Committee have been taken into account by the PEC very seriously, and several of them have led
to adjustments of the NATURALHY project program. So, this Committee had a critical role in ensuring a perfect
match between the Project objectives and the real long term (political) needs; moreover, the Committee was a
58
platform for the dissemination of results on an international and global level and for promoting public
understanding, awareness and acceptance of the introduction of hydrogen energy into EU society.
The Project coordinator and his staff formed a dedicated team for the co-ordination activities: The main
management activities of the project coordinator and his staff involved
• Co-ordination at consortium level of the technical activities of the project by informal contacts and formal
meetings;
• Focal point of information and collaboration with related projects and initiatives;
• Close liaison with the EC-representative, both formally and informally, to ensure the EC is closely informed
of developments;
• The overall legal, contractual, ethical, financial and administrative management of the consortium;
• Preparing, updating and managing the Consortium Agreement between the participants;
• Examination of the progress and the quality of the execution of the work, and motivating and encouraging
Parties;
• Preparation of progress and final reports on the basis of contributions from the Parties;
• Co-ordination at consortium level of knowledge management and other innovation-related activities;
• The implementation of competitive calls by the consortium to find new participants;
• Overseeing science and society issues, related to the research activities conducted within the project.
At the completion of the Project, it can be concluded that the management structure defined at the start worked
out very well for this project. It turned out to be efficient and effective. Nevertheless, the effort initially planned
by the PEC-members for the project management has been exceeded by far: the effort demanded for a proper
project management was significantly underestimated at the start of the project.
The communication with stakeholders and other on-going research projects is essential to ensure that:
• The NATURALHY project maintains an awareness of, and takes into account, developments in the
fields relevant to the project;
• The NATURALHY results find a broad acceptance;
• The NATURALHY results establish a benchmark and, hence, are integrated into other research
projects.
Therefore, the following arrangements have been made in addition to the comprehensive dissemination
programme executed in the framework of Work Package 7:
• The NATURALHY Strategic Advisory Committee (SAC) was established as described above.
• The NATURALHY project has been recognised as a project in the International Partnership for the
Hydrogen Economy, and aims at worldwide collaboration with other projects and organisations.
Finally, several NATURALHY partners participated in various national and international platforms, forums,
working groups etc. in which NATURALHY results were introduced. In return, these partners also gathered
relevant information and views which were fed back into the project.
59
10 FURTHER INFORMATION ABOUT NATURALHY
The NATURALHY project included a comprehensive dissemination programme to inform all stakeholders
including the general interested public as well as for experts in the different fields of expertise, of the results (and
during the project execution, the progress). The public part of the project website www. NATURALHY.net
includes copies of for instance scientific papers, presentations, newsletters, the NATURALHY brochure, the
NATURALHY Workshop presentations, the presentations at the NATURALHY Final Public Presentation and
the public final report.
The table below shows the presentations given as congresses and the papers published, ordered by work
package. Most of these papers and presentations are available on the project website www. NATURALHY.net
NATURALHY IN GENERAL
NATURALHY, using the existing Presentation Onno Florisson (N.V. DOE Workshop
natural gas network for hydrogen Nederlandse Gasunie) Hydrogen Pipeline
delivery: final results Working Group
Meeting, Boulder US,
26+27 Aug. 2009
“NATURALHY”: Assessing the Presentation Onno Florisson (N.V. IEA workshop “Large-
potential of the existing natural gas Nederlandse Gasunie) scale Hydrogen
network for hydrogen delivery Infrastructure and Mass
Storage”, Amsterdam,
12-13 Feb. 2009
NATURALHY: The first step in Presentation Gjalt Tiekstra (N.V. PWG meeting organised
assessing the potential of the Nederlandse Gasunie) by the US DOE, Sandia
European natural gas network for Laboratories, CA, USA,
Hydrogen delivery 20-21 February 2008
Preparing for the hydrogen Presentation Onno Florisson (N.V. European Hydrogen and
economy by using the existing Nederlandse Gasunie) Fuel Cell Technology
natural gas system as a catalyst Platform, Brussels, 6-9
(NATURALHY) Dec. 2006
The value of the existing natural Paper Isabelle Alliat (Gaz de World Gas Conference
gas system for hydrogen, the France) Onno Florisson 2006
sustainable future energy carrier (N.V. Nederlandse
(progress obtained in the Gasunie), Dr. Barbara
NATURALHY-project) Lowesmith & prof. Geoff
Hankinson
(Loughborough
University),
The NATURALHY-project: The Paper Onno Florisson (N.V. 2nd European Hydrogen
potential of the existing natural gas Nederlandse Gasunie) Energy Conference
system for hydrogen (EHEC 2005),
Zaragoza, 22-25 Nov.
2005
Preparing for the hydrogen Presentation Rolinda Huizing (N.V. 3rd European Forum
economy by using the existing Nederlandse Gasunie) Gas, Warsaw, Poland,
natural gas system as a catalyst-an Dave Pinchbeck (GERG) September 2005
overview of the NATURALHY
project
Natural gas, hydrogen and Article Onno Florisson (N.V. Petroleum Economist,
sustainability Nederlandse Gasunie) Fundamentals of the
World Gas Industry,
Bob Harris (Broadfern
2005
Consultants)
A step towards the hydrogen Presentation Onno Florisson (N.V. Conference “Natural
economy by using the existing Nederlandse Gasunie) gas: a reliable and
natural gas grid versatile source”, Milan,
14 Dec. 2004
61
A practical step towards Paper Onno Florisson (N.V. International Gas
“hydrogen”: The conditions under Nederlandse Gasunie) Research Conference,
which the existing natural gas Vancouver, Nov. 2004
system can be used for mixtures of
hydrogen and natural gas (the
NATURALHY -project)
Natural gas, the bridge to Presentation Onno Florisson (N.V. International Workshop
sustainability (including the Nederlandse Gasunie) “EU-Russian
NATURALHY-project”) cooperation on research
for hydrogen and fuel
cells”, Moscow, 29-30
Sept. 2004
Life Cycle and Socio-Economic Paper Nigel Mortimer 17th World Hydrogen
Assessment of the Natural Gas (Loughborough Energy Conference, 15-
System in Transition to Hydrogen University) 19 June 2008, Brisbane ,
Australia
62
Supplying Energy to a changing Presentation Technische Universiät 17th World Hydrogen
World Berlin Energy Conference, 15-
19 June 2008, Brisbane ,
Australia
Life Cycle Assessment of Natural Paper Nigel Mortimer International Gas Union
Gas Systems (Loughborough Research Conference,
University) Oct 2008, Paris
Grids for the Future – Natural Gas Article G. Tiekstra (NV DVGW Energie/ Wasser
Todday, Hydrogen Tomorrow Nederlandse Gasunie) Praxis, 2008
and Nigel Mortimer
(Loughborough
University)
Two-Parameter Approach : (Kρ – Presentation Hadj Meliani, Z. Azari, CAM 2009, Alger
Tρ) Constraints Effects Estimation Y. Matvienko and G. (2009)
in Pipelines with notches Pluvinage
Gouge assessment for pipes and Presentation Pluvinage, J. Capelle NT2F8 , Slovénie,
associated transferability problem And M. Hadj Meliani Octobre, (2008).
Durability of existing Natural Gas Presentation Isabelle Alliat (Gaz de PWG meeting organised
Infrastructures France) by the US DOE, Sandia
Laboratories, CA, USA,
20-21 February 2008
Comparison of methods to measure Presentation J. Capelle, J. Gilgert, Yu. ICF Fracture Mechanics
the resistance to fracture emanating G. Matvienko G. in Design of Fracture
from scrathes in gas pipes Pluvinage Resistant Materials and
Structures, Moscow,
july (2007).
Comparison of methods to measure Presentation J. Capelle, J. Gilgert, Yu. New trends in Fatigue
the resistance to fracture emanating G. Matvienko G. and Fracture NT2F7
from scratches in gas pipes Pluvinage Miskolc ,May (2007).
Hydrogen effect on fatigue life of a Presentation J Capelle, J . Gilgert G Kiev XIII International
pipe steel Pluvinage Colloquium
“Mechanical Fatigue of
Metals” Kiev
66
(Ukrainia) September 25
to 28, (2006).
Adib-Ramezani , J. Jeong,
Structural integrity evaluation of Paper International Journal of
G. Pluvinage
X52 gas pipes subjected to external Pressure Vessels and
corrosion defects using the Piping pp1–13,(2006)
SINTAP procedure
Electrocor Conference,
Computational modelling of CP Paper A. Peratta, J. Baynham, May 2009, Bologna, Italy
systems for pipelines in multi layer R. Adey; CMI Beasy Ltd
soil
ICHS Conference,
Prediction of Third Party Damage Paper L. Zhang, R.A. Adey, September 2009, Ajaccio,
Failure Frequency for Pipelines Beasy Corsica, France
Transporting Mixtures of Natural
Gas and Hydrogen'
International Gas Union
Reliability Analysis of Pipelines Paper Lie Zhang and Robert Research Conference,
Containing Cracks and Corrosion Adey, Beasy Paris, 2008
Defects
ICHS 2007 Conference,
Predicting the Probability of Failure Paper L. Zhang, R.A. Adey, September 2007, St.
of Gas Pipelines Including Inspection Beasy Sebastian Spain
and Repair Procedures
The recovery by carbon molecular Article Grainger, DR and Hägg, Int J Hydr Energy 33
sieve membranes of hydrogen M-B (2008) 2379-2388
transmitted in natural gas networks,
Application of carbon molecular Abstract Jon Arvid Lie, David European Congress of
sieve membranes in a mixed Grainger, May-Britt Chemical Engineering
hydrogen natural gas distribution Hägg, NTNU (ECCE-6) Copenhagen,
network 16-20 September 2007
Safe operation of Natural gas Paper De Vries, H., Florisson, HYSAFE conference,
appliances fuelled with O, Tiekstra, G, September 2007
hydrogen/natural gas mixtures N.V.Nederlandse
(progress obtained in the Gasunie
NATURALHY project)
Injection of hydrogen into the Abstract May-Britt Hägg, NTNU North American
European gas network- and
68
recovering the same from the gas Membrane Society 2007
mix by use of CMS-membranes at
the end-user.
Investigation of using the existing Paper Jon Arvid Lie, May-Britt Journal of Membrane
gas network for transport of Hägg, NTNU Science 284 (2006) 79–
hydrogen-and using membranes at 86
the end user for separation of H2-
natural gas
Carbon membranes from metal Abstract Jon Arvid Lie, May-Britt 9th International
loaded cellulose, and the Hägg, NTNU Conference on Inorganic
application of an external field for Membranes,
improved performance June 25-29, 2006,
Lillehammer, Norway
Hydrogen recovery in a combined Paper David Grainger, Jon WHEC 16 / 13-16 June
natural gas-hydrogen distribution Arvid Lie, May-Britt 2006 – Lyon France
network using carbon molecular Hägg, NTNU
sieve membranes