Reasons for performing high-voltage tests and diagnostic measurements and their benefits
Insulation diagnosis (such as a partial discharge measurement) will typically be carried out on GIS
in the following cases: :
When a new system is commissioned (as part of the voltage testing)
Due to extensions
When systems are extended – after accidents
Following activation of partial discharge monitoring systems (in-service measurements in
some cases)
After weak points have been identified
To determine the condition of the insulation (old systems, in-service measurements)
Fault types
The application of test methods is merely one aspect of testing. When diagnosing dielectric faults
(especially during a partial discharge measurement), the test engineer's experience plays a
critical part in ensuring an efficient and effective test procedure. Expert assessment of partial
discharge occurrences, elimination of the partial discharge source and consideration of the need
for further investigations may all be decisive factors in preventing future GIS failures.
Multi-channel UHF partial discharge analyser Voltage test with UHF partial discharge measurement
on a 123 kV GIS S
High-voltage test and partial discharge
measurement on a medium-voltage GIS
FKH Head Office FKH Insulating Oil Laboratory FKH Experimental Station
Hagenholzstrasse 81 4658 Däniken 4658 Däniken
8050 Zurich