This document provides instructions for creating a periodic invoicing plan purchase order in SAP to generate scheduled monthly lease payments for multiple year equipment leases without requiring monthly goods receipts. It describes entering vendor, contract, and item details to set up the purchase order, and updating delivery information to trigger payments according to the invoicing plan schedule. Multiple purchase orders may be needed to cover the lease period for each piece of equipment. The document emphasizes important dates and provides examples.

Uploaded by

José Robles
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
25 views16 pages

CreatePeriodicInvoicingPlan PDF

This document provides instructions for creating a periodic invoicing plan purchase order in SAP to generate scheduled monthly lease payments for multiple year equipment leases without requiring monthly goods receipts. It describes entering vendor, contract, and item details to set up the purchase order, and updating delivery information to trigger payments according to the invoicing plan schedule. Multiple purchase orders may be needed to cover the lease period for each piece of equipment. The document emphasizes important dates and provides examples.

Uploaded by

José Robles
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 16

Create Periodic Invoicing Plan Purchase Order (ME21N)

Use this procedure to create the SAP purchase order transaction type
Periodic Invoicing Plan (IP) for MFD Leases under multiple contracts:

VENDOR
CONTRACT NUMBER NUMBER VENDOR NAME
Konica Minolta Business Solutions
4600015235 102519 USA, Inc.
4600015237 172615 Kyocera MITA America Inc.
4600015250 172181 Hewlett Packard Co
4600015251 102545 Sharp Electronics Corporation
4600015253 104274 Xerox Corporation
4600015254 102592 Canon USA Inc
4600015713 116604 Ricoh USA, Inc.

This IP will generate scheduled monthly lease payments and does not
require monthly input of a goods receipt.

Part 1: Creating and Issuing the Purchase Order

1. Select ME21N Create Purchase Order from the SAP menu

(the Create Purchase Order data entry screen displays)

2. Select the ITEM LIST icon in the Order type field; choose Periodic
Inv. Plan from the resulting list

3. Enter vendor number in the Vendor field

Upon the entry, you will be prompted to choose 1) an Ordering Address first,
and 2) Invoice Presented by.
The Ordering Address (OA) defaults , and can be accepted by pressing the
Enter key or selecting the green checkmark. To choose an alternate OA,
place the cursor on the appropriate number and Enter.

The Invoice Presented by defaults correctly to and should not be changed.


Accept this number by pressing the Enter key or selecting the green
checkmark.
4. Select the EXPAND HEADER icon

(the Header data tabs are visible for selection, as shown below)

5. Select the Org. data tab and complete the required fields, as
shown below, substituting your own Purchasing Group number for 279 (DGS
Central)
6. Select the Texts tab and enter information in the applicable text
areas

7. Select the Additional data tab and populate the validity


date fields with a start and end for the plan period

Note: The Validity start and end dates are being used as start and
end dates for the invoicing plan, and are not to be confused with the
validity dates in the statewide MFD Lease contract

IMPORTANT: The Validity start date on the PO should always be the first
day of the month after the copier is (or will be) received

Examples:

Copier received on: Validity start:


May 5, 2014 June 1, 2014
July 15, 2014 August 1, 2014
August 1, 2014 September 1, 2014
IMPORTANT: The Validity end date on the PO may not extend beyond June
30th – the end of every fiscal year

Examples:

May 1, 2014 through June 30, 2014


July 1, 2014 through June 30, 2014
Special note regarding Purchase Orders where Federal funds are
used:

 When Federal funds are used, additional rules related to the


Validity end date on the PO will apply

 The PO also may not extend beyond September 30th – the end
of the Federal fiscal year

Examples:

May 1, 2014 through June 30, 2014


July 1, 2014 through September 30, 2014
October 1, 2014 through June 30, 2010
July 1, 2010 through September 30, 2010
8. Enter line item information, beginning with the Outline Agreement field:

a. Enter Outline Agreement

b. Enter applicable Agreement Item (contract line item)

c. Select the ENTER icon to pull the contract item details into the
Purchase Order

(Scroll to the right to access the Outline Agreement field)

d. Enter the PO (line item) quantity *


*Limit of one copier base unit per Purchase Order

e. Enter the applicable Account assignment category

f. Enter the net price per line item (should be the same as the quoted
price received from the contractor).

g. Allow the remaining default line item information to remain

Repeat Step #8, as necessary, until all line items (optional


accessories) have been entered

9. Select the EXPAND ITEM DETAILS icon

(the Item data tabs are visible for selection, as shown below)
10. Select the Account Assignment tab and enter the
applicable account code information

a. To distribute costs among multiple account assignments, please


reference the separate instructional document “IP with Multiple Account
Assignment”

11. Select the Delivery tab

a. Remove the check mark from the Goods Receipt box in the Delivery
tab, as shown below.
12. Select the Invoice tab

a. Ensure that the GR-based IV box is unchecked, as shown above

b. Select the Invoicing Plan button

c. In the Specify Invoicing Plan box, select


MFD Lease from the menu, as shown below

Note: Based upon the Invoicing Plan type that was chosen, payment
dates and amounts are automatically populated between the Validity
start and end dates; the data screen is for viewing only – do NOT
change any of the defaulted information

13. Select the CHECK icon to see if the PO contains any errors

(an error message dialog box displays)


14. At the message prompt, hold the PO by selecting the HOLD
button

15. Save the PO by selecting the SAVE icon

16. Select the CHANGE icon to edit (continue working in) the PO

17. Add any necessary attachments by selecting the Services for Object
icon, as shown below

a. Select Create

b. Select Create attachment

18. Select (highlight) the applicable document from the directory folder

19. Select the OPEN button

20. Continue the process


until all attachments have
been added, as shown below
21. Select either “X” to exit the Service Attachment list

22. Re-save the PO by selecting the SAVE icon

23. Upon approval, issue the PO to Ikon to order your MFD


IMPORTANT:

 As noted in Step 7, the validity periods for each Purchase


Order are specifically defined

 As noted in step 8.d., each Purchase Order has a limit of one


MFD (copier) base unit

Therefore, continue creating and issuing additional Purchase Orders,


as necessary, for each copier needed and the subsequent validity
periods

Sample Scenario

The Purchaser needs to lease three copiers for their office through
the end of the MFD lease contract

Copier #1 6/1/2014 to 6/30/2014 PO 4500700001


7/1/2014 to 6/30/2015 PO 4500700002
7/1/2015 to 6/30/2016 PO 4500700003
Copier #2 6/1/2014 to 6/30/2014 PO 4500700004
7/1/2014 to 6/30/2015 PO 4500700005
7/1/2015 to 6/30/2016 PO 4500700006
Copier #3 6/1/2014 to 6/30/2014 PO 4500700007
7/1/2014 to 6/30/2015 PO 4500700008
7/1/2015 to 6/30/2016 PO 4500700009

As the above sample scenario indicates, multiple Purchase Orders are


necessary to meet the Purchaser’s requirement of three copiers over the
length of the MFD lease contract
Part 2: Commencing Payments

The steps outlined below should be completed, as necessary, for


each Purchase Order once the machine has been delivered.

1. Select ME22N Change Purchase Order from the SAP menu

2. Select the Customer data tab at the header level and


insert the Serial number for your newly delivered copier into the Invoice
Reference field, as shown below

Do not use any spaces or special characters such as #, $, @, etc.

Note: The machine delivery packing slip must reference the serial
number to be applied to the Invoice Reference field. The machine
delivery packing slip must also identify the purchase order # for the
first fiscal year.

3. Select the Delivery tab at the item level and select the
Delivery complete check-box, as shown below

Note: The Invoicing Plan is triggered by the start date in the Invoicing Plan
box, as well as the selection of the Delivery completed box in the Delivery
tab

Repeat Step #3, as necessary, for all line items


4. Re-save the PO by selecting the SAVE icon
Sample Scenario, cont’d

Copier #1 6/1/2014 to 6/30/2014 PO 4500700001


7/1/2014 to 6/30/2010 PO 4500700002
7/1/2010 to 6/30/2011 PO 4500700003
Copier #2 6/1/2014 to 6/30/2014 PO 4500700004
7/1/2014 to 6/30/2010 PO 4500700005
7/1/2010 to 6/30/2011 PO 4500700006
Copier #3 6/1/2014 to 6/30/2014 PO 4500700007
7/1/2014 to 6/30/2010 PO 4500700008
7/1/2010 to 6/30/2011 PO 4500700009

Using our previous example (shown above), serial numbers would be


inserted for:

Copier #1 into PO 4500700001, 002, and 003


– Copier #2 into PO 4500700004, 005, and 006
– Copier #3 into PO 4500700007, 008, and 009

The Delivery Completed checkboxes should be selected for all PO’s, including
those for future fiscal years
IMPORTANT: If any issues arise with MFD’s leased
through these contracts, contact Amy McFadden
([email protected]) , 717-346- 3828 with the Bureau of
IT Procurement in OA.

Amy will work with the contractors to resolve these issues

 DO NOT suspend or discontinue payment on your


Purchase Order(s)!

You might also like