CE244 Lab Report-1
CE244 Lab Report-1
CE244 Lab Report-1
CE 244
MATERIALS OF CONSTRUCTION
LAB REPORT-1
CEMENT PASTE
1|Page
TABLE OF CONTENTS
• Introduction
• Experimental
- Materials
- Apparatus
- Method/Procedure
• Results/Discussions
• Conclusion
• References
2|Page
1. INTRODUCTION
2. EXPERIMENTAL
I) Materials
3|Page
II) Apparatus
Figure 2.2)
electronic Vicat
apparatus
III) Methods/Procedures
3. The vicat ring is placed in the vicatronic and the surface is smoothed.
4. The plunger is removed from the vicat apparatus and was replaced by a 1mm
diameter needle for the purpose of penetration.
5. Lastly, the test starts approximately 15 minutes after placing the cement paste in the
vicat ring.
Figure 2.4)
Figure 2.3) vicat needle
vicat ring
4|Page
3. RESULTS/DISCUSSIONS
4. CONCLUSION
5|Page
also in accordance with the ASTM C 150 standard specification, thus no
major obstacles will occur due to settings. However, other obstacles might
occur during setting for various causes, obstacles that might occur are either
“Flash set” or “False set”. Flash test occurs when there is an insufficient
amount or no gypsum in the cement. While false test is the premature
stiffening of the paste after a few minutes of mixing. Furthermore, from this
experiment we also gained the knowledge of how a cement paste is
composed with the accordance of normal consisteny.in addition to, learning
the application of Vicat apparatus to find the setting times of different
materials.
5. REFERENCES
6|Page
ABDULLAH GÜL UNIVERSITY
DEPARTMENT OF CIVIL ENGINEERING
CE 244
MATERIALS OF CONSTRUCTION
LAB REPORT-1
DETERMINATION OF FLOW OF CEMENT
MORTAR
7|Page
TABLE OF CONTENTS
• Introduction
• Experimental
- Materials
- Apparatus
- Method/Procedure
• Results/Discussions
• Conclusion
• References
8|Page
9|Page
1. INTRODUCTION
2. EXPERIMENTAL
I) Materials
The materials used in this test/experiment where a cement mortar mix which
consists of:
1) cement
2) sand
3) water
Figure 2.1)
cement
10 | P a g e
II) apparatus
Mold
III) Methods/Procedures
1. Firstly, in the test the mold is placed in the middle of the table,
while the flow table was carefully cleaned and dried.
2. Secondly, a 25mm thick layer of mortar was placed in the mold, in the mean time
being tamped for about 20 times, where it should be just enough to make certain
of the uniform filling mold.
3. Thirdly, the mortar was filled in the mould while being tamped
4. The mortar was cut off to a plane surface by drawing the straight edge of the
trowel.
5. The mold is lifted from the mortar.
6. Dropping the table about 25 times in 15secs.
11 | P a g e
7. Finally, by the use of the ruler the final diameter is measured along the scribed
lines.
4. RESULTS/DISCUSSIONS
After preparing the cement mortar and implementing the experiment, it would
now be obtainable to measure and record the final diameters of the cement mortar.
After obtaining the diameter in two different perpendicular distances which where
“D1= 170(mm), and D2=180mm” respectively; The aim will be to find the net
increase from the original diameter (100mm) which in our case was 70mm for D1
and 80mm for D2. furthermore, we continued to find the average increase diameter
of both direction (75mm) as well as converting it into a percentage form as it will be
more clear for determining the flow of hydraulic cement mortar.
D1 D2 AVERAGE AVERAGE
INCREAS INCREAS INCREAS İNCREASE
E (MM) E E (MM) PERCENATAG
(MM) E (%)
70MM 80MM 75MM 75
5. CONCLUSION
To conclude, we found the net percentage increase of the diameter to be
about 75% nearest to +/- 5mm, we determined the percentage increase
because the flow of concrete is known to be the percentage increase in
12 | P a g e
average diameter of the spread of the concrete over the base of the mould.
From this lap experiment we gained new information about how a cement
mortar is made and the materials that are required. lastly, according to the
ASTM C1437 the percentage increase for the flow of the cement mortar
should be about 110% +/- 5%, what was obtained in this experiment was
not far from this value.
5. REFERENCES
13 | P a g e
ABDULLAH GÜL UNIVERSITY
DEPARTMENT OF CIVIL ENGINEERING
CE 244
MATERIALS OF CONSTRUCTION
LAB REPORT-1
DETERMINATION OF COMPRESSIVE STRENGTH
OF CEMENT MORTAR
14 | P a g e
Submitted to: Res. Assist. Hediye Yorulmaz
Date of Submission:
TABLE OF CONTENTS
• Introduction
• Experimental
- Materials
- Apparatus
- Method/Procedure
• Results/Discussions
• Conclusion
• References
15 | P a g e
1. INTRODUCTION
16 | P a g e
2. EXPERIMENTAL
I) Materials
1)500of cement
2)1375 g of sand
3)242 g of water
Figure 2.1)
cement
Figure 2.2)
cement
mortar
II) Apparatus
Figure 2.3)
A specimen mold
III) Methods/Procedures
17 | P a g e
1. the first procedure of the experiment is the preparation of the cement
mortar which was prepared by firstly drying the paddle and the bowel,
afterwards approximately 242 ml of water is added to the bowl with
adding about 500gr of cement into the water and mixing them together
with a slow speed for 30s.moreover, the preparation is continued with
gradually adding about 1375gr of sand into a mixer for a duration of 30s
with the same speed, the mixer is then stopped so the mixer can
continue with a more rapid speed then before for about 30 more
seconds, the preparation is finished with covering the bowl with a lid
and mixing for the last 60s in a high speed.
2. The specimen is then molded for roughly 2 and a half minutes, then a layer of
mortar which is about half the depth of the mold layer in all of the cube
compartments.
3. The procedure is continued with tamping the mortar for 32 times for 10s
in 4 rounds consisting of 8 adjoining strokes preferably over the surface
of the specimen.
4. The remaining mortar is used to fill the compartments in the meantime
continue tamping it. After the completion of the tamping it is necessary
for the tops of the cubes to extend slightly above the tops of the molds.
5. The mortar is cut to a near plane surface flush with the top of the mold
with the help of a sawing motion over the length of the mold
6. The molds is then covered with a wet cloth, a 24 hours’ wait is needed
to remove the molds and putting the samples in advance to the
experiment day in the curling pools
7. A press device is used to measure the compressive strength, then read
the maximum load at the moment where the specimen is fractured
8. Lastly 3 different samples must be crushed so we can have an accurate
value for the compression strength
18 | P a g e
Figure 2.4) test Figure 2.5) Figure 2.6) Order
specimen example of a press of Tamping in
device Molding of Test
Specimens
3. RESULTS/DISCUSSIONS
4. CONCLUSION
19 | P a g e
In conclusion, with accordance to the ASTM specification C 109 we
found the average compressive strength of the material to be about 0. 53866.
Mpa this test was conducted due to it being more simple and accurate than
other test such as the ASTM specifications C 349 where a Portland cement
is required for the preparation of the cement mortar. Lastly, from this lap
experiment we gained also new information about how a cement mortar is
made and the materials that are required.
5. REFERENCES
20 | P a g e