SP-2376-Piping - Engineering & Layout Design Requirements
SP-2376-Piping - Engineering & Layout Design Requirements
Document ID SP-2376
Security Restricted
Revision 01
Keywords: This document is the property of Petroleum Development Oman, LLC. Neither the
whole nor any part of this document may be disclosed to others or reproduced, stored in a
retrieval system, or transmitted in any form by any means (electronic, mechanical, reprographic
recording or otherwise) without prior written consent of the owner.
Page 1 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.
Revision: 01
Petroleum Development Oman LLC Effective: Dec-2021
i Document Authorization
Authorised for Issue
ii Revision History
The following is a brief summary of most recent revisions to this document. Details of all revisions
prior to these are held on file by the issuing department.
Page 2 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.
Revision: 01
Petroleum Development Oman LLC Effective: Dec-2021
Table of Contents
1. INTRODUCTION ........................................................................................................ 5
PART I PIPING – ENGINEERING & LAYOUT REQUIREMENTS ....................................... 16
1 PIPING BASICS ....................................................................................................... 16
1.1 GENERAL ................................................................................................................ 16
1.2 DESIGN CONDITIONS ............................................................................................ 16
1.3 PIPING ABOVE GROUND LEVEL .......................................................................... 17
1.4 PIPING BELOW GROUND LEVEL.......................................................................... 19
1.5 SMALL BORE PIPING ............................................................................................. 20
1.6 INSTALLATION OF FLANGES ............................................................................... 22
1.7 INSTALLATION OF VALVES .................................................................................. 23
1.8 UTILITY, DRAIN AND VENT CONNECTIONS ........................................................ 24
1.9 CONNECTIONS FOR MANUAL SAMPLING .......................................................... 25
1.10 THERMOWELL CONNECTIONS ............................................................................ 26
1.11 ORIFICE FLANGES AND ORIFICE METER RUNS ................................................ 28
1.12 DISPLACER CHAMBERS ....................................................................................... 28
1.13 GALVANISED PIPING ............................................................................................. 28
1.14 PIPING IN VIBRATING SERVICE ........................................................................... 28
1.15 WELL CONDUCTORS, WELLHEADS, XMAS TREES AND FLOWLINES ON
DIRECT VERTICAL ACCESS WELLS .................................................................... 29
1.16 RETRIEVABLE PROBE, COUPON AND INJECTION QUILL SYSTEMS ............. 29
1.17 REQUIREMENTS FOR PIPING TIE-IN CONNECTIONS ........................................ 30
1.18 GROUNDING AND STATIC ELECTRICITY ............................................................ 31
1.19 IRON SULFIDE - PYROPHORIC SCALES ............................................................. 32
1.20 PIPING THROUGH WALLS, STRUCTURAL DECKS AND CONCRETE
FLOORS OF BUILDINGS ........................................................................................ 32
1.21 DISTANCE BETWEEN PIPES ................................................................................. 32
1.22 OFFSITE PIPING SYSTEMS ................................................................................... 32
2 PIPING ADJACENT TO EQUIPMENT .................................................................... 33
2.1 GENERAL ................................................................................................................ 33
2.2 PUMP, STEAM TURBINE AND COMPRESSOR PIPING....................................... 33
2.3 HEAT EXCHANGER PIPING ................................................................................... 35
2.4 FURNACE AND BOILER PIPING............................................................................ 36
2.5 PRESSURE VESSEL PIPING.................................................................................. 36
2.6 RELIEF SYSTEMS ................................................................................................... 37
2.7 LEVEL GAUGES ...................................................................................................... 37
2.8 INSTRUMENTATION ............................................................................................... 39
2.9 PACKAGED EQUIPMENT PIPING.......................................................................... 40
2.10 VESSEL TRIM .......................................................................................................... 40
3 UTILITY PIPING ....................................................................................................... 40
3.1 GENERAL ................................................................................................................ 40
3.2 FIRE WATER............................................................................................................ 40
3.3 WATER FOR PURPOSES OTHER THAN FIRE WATER ....................................... 40
3.4 STEAM ..................................................................................................................... 40
3.5 UTILITY HOSE STATIONS ...................................................................................... 41
4 TANK FARM PIPING ............................................................................................... 41
5 PIPING COMPONENTS ........................................................................................... 42
5.1 GENERAL ................................................................................................................ 42
5.2 PIPE .......................................................................................................................... 42
5.3 PIPE JOINTS ............................................................................................................ 43
5.4 FITTINGS.................................................................................................................. 46
5.5 BRANCH FITTINGS ................................................................................................. 46
5.6 FLANGES AND FLANGE ISOLATION SETS ......................................................... 47
5.7 PIPING AND EQUIPMENT ISOLATION .................................................................. 48
Page 3 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.
Revision: 01
Petroleum Development Oman LLC Effective: Dec-2021
APPENDICES
APPENDIX A ADDITIONAL REQUIREMENTS FOR SPECIFIC SERVICES ....................... 73
APPENDIX B PIPING SYSTEM DEVELOPMENT BASED ON CONSTRUCTION
CLASSES ................................................................................................................. 75
APPENDIX C DEVIATIONS APPROVAL WITH APPLICABLE MITIGATIONS .................. 78
APPENDIX D SHALL [PS] STATEMENTs FOR DEP 31.38.01.24 (VER.44) AND DEP
31.38.01.25 (VER.45) ............................................................................................... 81
APPENDIX E SKETCH OF ALUMINIUM CLADDING FOR CRA PIPE PROTECTION
FROM MOLTEN ZINC ............................................................................................. 82
Page 4 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.
Revision: 01
Petroleum Development Oman LLC Effective: Dec-2021
1. INTRODUCTION
1.1 SCOPE
This SP specifies requirements and gives recommendations for engineering and layout of
piping systems built in accordance with ASME B31.3 and pipeline facilities (pump stations,
compressor stations, valve stations, pig stations) built in accordance with pipeline codes
such as ISO 13623, ASME B31.4, ASME B31.8, NEN 3650 and PD 8010. It applies to
piping for all types of process fluids (including fluidised solids), and all utility fluids.
Piping covered under equipment design codes is excluded from the scope of this SP.
Oil and gas risers, hull piping subjected to Classification Society rules (except for piping
associated with topsides process systems), subsea piping systems, utility piping in living
quarters and plant buildings are excluded from the scope of this SP.
Cross-country sections of pipelines - with the exception of pipeline facilities - designed in
accordance with codes such as ISO 13623, ASME B31.4, ASME B31.8, NEN 3650 and PD
8010 are excluded from the scope of this DEP. Sketches of the interface between pipelines
and other equipment are included in ASME B31.8 and ISO 13623.
Piping fabrication requirements are covered SP 2404.
Piping systems of “boiler proper piping” as referenced in ASME B31.1, Section 100.1.1 are
covered by ASME Section I.
Piping systems of “boiler external piping” (steam, feed water and blow down piping
systems) as referenced in ASME B31.1, Section 100.1.1 are covered by ASME B31.1.
Refer to Appendix-D. for SHALL[PS] requirements applicable to both DEM1 DEP
31.38.01.24 & DEP 31.38.01.25.
This SP excluding process design requirements which shall be referred to DEP 31.38.01.24
and SP 2373 which is in place of DEP 31.38.01.25. in addition, this SP contains piping
design requirements as per DEP 31.38.01.24 and DEP 31.38.01.25.
This SP addresses piping design requirements excluding process design requirements
referred from DEP 31.38.01.24 & DEP 31.38.01.25. SP-2373 addresses the process
requirements referred from DEP 31.38.01.25.
Page 5 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.
Revision: 01
Petroleum Development Oman LLC Effective: Dec-2021
1.2 DEFINITIONS
1.2.1 General definitions
Contractor A party that carries out all or part of the design, engineering,
procurement, construction, commissioning or management of a
project or operation of a facility. The Principal may undertake all or
part of the duties of the Contractor.
Page 6 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.
Revision: 01
Petroleum Development Oman LLC Effective: Dec-2021
Term Definition
flashing fluid Fluids listed in Energy Institute IP 15 as Class 0, I, II (2) and III (2).
Where warm/hot surfaces are within the distances defined in API RP
505:2018, section 14.3, fluids listed as Class II (1) and III (1) also are
included.
Flowline Piping which carries well fluid from wellhead to manifold or first process
vessel
HP steam Typically steam between 40 barg and 100 barg (580 psig and
1450 psig)
MP steam Typically steam between 12 barg and 18 barg (175 psig and 260 psig)
pipe track Piping route typically consisting of multiple pipes, where pipes are
routed at grade level using concrete sleepers as pipe supports
pipe trench Piping route typically consisting of multiple pipes, where pipes are
routed below grade and uncovered using concrete sleepers or
pedestals as pipe supports.
Pipeline System of pipes and other components used for the transportation of
fluids between (but not within) plants. A pipeline typically extends from
pig trap to pig trap (including the pig traps). If no pig trap is fitted, the
pipeline extends to the first isolation valve within the plant boundaries.
Page 7 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.
Revision: 01
Petroleum Development Oman LLC Effective: Dec-2021
Term Definition
Piping Assembly of straight and bent pipes, fittings, flanges, gaskets, valves
and other components (e.g., expansion joints, swivel joints, strainers,
devices for mixing, separating, distributing, metering and flow control). It
also includes pipe supporting elements and insulation.
Piping does not include supporting structures (such as frames of
buildings, stanchions or foundations) or equipment (e.g., heat
exchangers, vessels, columns, pumps) or instrument impulse pipes.
Instrument specifications apply downstream the last joint of the last
process to instrument valve or valve assembly, defined for the
instrument connection in the mechanical piping class. This can include
the 5 mm restriction nipple where applicable.
Piping class Assembly of piping components, suitable for a defined service and
design limits, in a piping system.
spec break Physical location as a single point dividing one piping class from
another.
Standard Piping components which are covered under DEP piping classes with
Piping corresponding MESC numbers.
Components
long-run Piping with length more than one pipe support span
piping
pipe stress Engineer approved by the Principal to undertake pipe stress analysis for
engineer a project. The engineer is responsible for obtaining data from disciplines
as appropriate, creation, maintenance and issue of the pertinent pipe
stress analysis documentation detailed within this standard, analysis
and approval of all stress critical lines and the timely dissemination of
pipe support/restraint information
Piping class Assembly of piping components, suitable for a defined service and
design limits, in a piping system. The piping classes are contained in
the following DEP binders:
DEP 31.38.01.14-Gen. - Piping classes
DEP 31.38.01.23-Gen. - Piping classes developed primarily for use in
the oil, multi-phase, water and gas pipeline systems from a wellhead to
a plant facility administered primarily to the CSA Z662 standard.
Very Toxic Includes very toxic – acute / very toxic – chronic / very toxic –
environment. For details, see SP-1125 & DEP 01.00.01.30-Gen.
Page 8 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.
Revision: 01
Petroleum Development Oman LLC Effective: Dec-2021
Term Definition
back seat A feature within linear motion valves, where an integral seat within the
stem can be back seated against the bonnet. This arrangement allows
for safer packing adjustment or emergency sealing of the stem in the
fully open position.
bellows Type of seal that utilizes bellows for providing positive metallic sealing.
sealed The ends of the bellows are fastened to the bonnet and closure
member/stem. The bellows expands and contracts with stem travel.
closure Moving part of the valve which closes off the seat, e.g., ball, disc, gate.
member
cost of Total lifetime cost, associated with purchasing, installing, operating and
ownership maintaining.
dirty service Fluids with solids that can deposit, compact, solidify, erode, scour and
seriously impair the performance of valves unless the correct type is
selected.
double block Arrangement of valves, which includes two valves in series and has a
and bleed bleed valve between. Total isolation of the pipework is achieved when
both valves are closed, and the bleed is open. Special integral DBB
units are available to reduce weight and to give minimal joints. The
valve ends can be flanged, hub type or butt weld.
extended Extension used when the media is at high or low temperatures. Its
bonnet function can be to isolate the gland from the high or low temperature
zone so as to maintain integrity of the stem seal and the operation of
the valve. The extension can also be required to locate the gland
outside the insulation.
floating ball Ball valve in which the ball is not rigidly held on its rotational axis and so
is free to float between the seat rings.
flow capacity- Different valve types have relatively higher/lower flow capacities, due to
resistance their inherent resistance to flow, this is measured as a Cv.
fouling/ Liquids or slurries, carrying suspended particles that can form a deposit
scaling on surfaces or build up in pockets within a valve. These can seriously
service impair the performance of valves unless the correct type is selected.
Page 9 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.
Revision: 01
Petroleum Development Oman LLC Effective: Dec-2021
Term Definition
full bore Valve in which the bore (port) is equal to the bore of the connecting
pipe.
linear motion Valve that has a sliding stem that pushes the obturator closed or pulls it
valve open. They are capable of being adapted to bellows sealed. See also
rising stem.
needle valve Manual flow-regulating valve which gives a small aperture change
relative to the stem travel.
non-operable Valves which do not require to be operable below -29 °C (-20 °F).
at low
temperature
non-return Valve that allows fluid flow in only one direction. Also known as check
valve valve.
on-off valve Basic operation of a valve to start or stop the flow of a fluid, also
referred to as isolating or stop valves.
outside screw Non-rotating, linear motion stem, where the threads are outside the
and yoke valve body and not subjected to possible negative effects of the process
(OSY) fluid.
positive body Dedicated feature within a double seated valve which gives an actual
cavity relief connection of the close valve cavity with either the high pressure or low
pressure side of the valve.
pressure seal Design of bonnet/cover where the body to bonnet/cover seal is pressure
bonnet/ cover assisted.
quarter turn Valve (such as ball, plug, butterfly) which requires a 90-degree
valve operation of the stem to move from the fully open to the fully closed
position. They will readily accept any type of actuation (pneumatic,
hydraulic, electric).
reduced bore Valve in which the bore (port) is smaller than the bore of the connecting
pipe.
retainerless Check valve without drilled holes through the body to facilitate the
check valve assembly of the valve.
rising stem Non-rotating, linear motion stem, where the threads are outside the
valve body and not subjected to possible negative effects of the process
fluid.
Page 10 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.
Revision: 01
Petroleum Development Oman LLC Effective: Dec-2021
Term Definition
seat Part of a valve against which a closure member effects a tight shut-off,
or a rate of shut-off, the material can be soft (polymeric/ elastomeric) or
metallic, or a combination of both.
shut-off A valves ability to give leak tight shut-off when closed for different types
capability of fluid.
torque seated Valves where the operator can apply more torque to seat the valve.
valve These are preferred by operators particularly for dirty service.
trunnion Part of a ball valve which holds the ball on a fixed axis and which allows
the ball to turn.
Term Definition
MESC Materials and Equipment Standards and Code. The MESC codes are
contained in the Catalogue Management Tool (CMT) system
NPS Nominal Pipe Size. The NPS prefix indicates the nominal diameter of a
piping system component in inches
Page 11 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.
Revision: 01
Petroleum Development Oman LLC Effective: Dec-2021
COMPANY STANDARDS
SP-2170 Specification for Shell & Tube Heat Exchangers
SP-2070 Specification for Air Cooled Heat Exchangers
SP-2069 Specification for Pressure Vessels
SP-1201 Procurement Specification for Pipeline Ball Valves
SP-2187 Specification for Storage Tanks (Suppliment to API 650 13th edition March 2020)
SP-2279 Specification for Flare systems
SP-2342 Specification for Standard Piping Bulk MESC Items
SP-2385 Plate & Frame Heat Exchangers- Amendments/Supplements to ISO15547-1
SP-2374 Tank Repair Methods Based on API 653 Mar 20
SP-1188 Specification for Chemical Injection Skids
SP-2376 Piping – Engineering, Layout & Process design Requirements
SP-2373 Piping – Process Design Requirements
SP-2390 Piping Stress Analysis Specification
SP-2411 Pipe Supports
SP-2404 Shop and field fabrication of piping
SP-2051 Specification for Flushing, Pressure Testing, Pickling and Sensitive Leak Testing
SP-2342 Specification for standard piping items
SP 1127 Layout of Onshore Facilities
SP-2215-1 Human factors engineering in projects
SP-2215-2 Human factors engineering – control room design
SP-2215-3 Human factors engineering – physical workspace design
SP-2215-4 Human factors engineering –human machine interface design for situation awareness
SHELL STANDARDS
Wet H2S requirements for downstream pressure vessels and piping DEP 30.10.02.17-Gen.
Page 12 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.
Revision: 01
Petroleum Development Oman LLC Effective: Dec-2021
Assessment and design of the fire safety of onshore installations DEP 80.47.10.30-Gen
INTERNATIONAL STANDARDS
Pipe flanges and flanged fittings, NPS 1/2 through NPS 24 metric/inch standard ASME B16.5
Metallic gaskets for pipe flanges - ring-joint, spiral-wound and jacketed ASME B16.20
Cast copper alloy pipe flanges and flanged fittings Classes 150, 300, 600, 900, 1500, ASME B16.24
and 2500
Large diameter steel flanges NPS 26 through NPS 60 metric/inch standard ASME B16.47
Petroleum and natural gas industries — Materials for use in H2S-containing NACE MR0175
environments in oil and gas production
Petroleum and natural gas industries. Drilling and production equipment. Wellhead and ISO 10423
Page 13 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.
Revision: 01
Petroleum Development Oman LLC Effective: Dec-2021
Bolted bonnet steel gate valves for the petroleum, petrochemical and allied industries ISO 10434
Petroleum and natural gas industries - Pipeline transportation systems ISO 13623
Petroleum and natural gas industries - Pipeline transportation systems - Pipeline valves ISO 14313
Petroleum and natural gas industries - Materials for use in H2S-containing environments ISO 15156
in oil and gas production
Metal ball valves for petroleum, petrochemical and allied industries ISO 17292
STANDARDS DRAWINGS
Sample cabinets with inlet on top - Material: carbon steel or low-alloy steel S 38.037
Overall dimensions of plate-type level gauges, through-vision and reflex type S 38.059
Orifice flanges, raised face, with flange tappings. ANSI classes 300 to 2500 incl., S 38.130
Nom. size DN 50 to DN 600 incl.
Orifice flanges, raised face, with corner tappings. ASME classes 300 and 600, S 38.131
Nom. size DN 50 to DN 600 incl.
Orifice flanges, raised face, with parallel flange tappings. ASME classes 300 to S 38.132
2500 incl. nom. size DN50 to DN 600 incl.
Orifice meter runs with flanged ends, ASME classes 150 to 1500 incl., Nom. size S 38.134
DN 15 to DN 40 incl.
Page 14 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.
Revision: 01
Petroleum Development Oman LLC Effective: Dec-2021
Steam ring to horizontal flanges of DN 150 (NPS 6) and above in hydrogen service S 38.141
Two steam rings to horizontal flange of DN 150 (NPS 6) and above (with spectacle S 38.142
blind, spade, spacer or orifice)
Steam ring to vertical flange of DN 150 (NPS 6) and above in hydrogen service S 38.143
Two steam rings to vertical flange of DN 150 (NPS 6) and above in hydrogen S 38.144
service (with spectacle blind, spade or spacer)
Pressure connection assemblies with flanged isolation valves and fittings S 38.156 (all sheets)
Orifice flange connection assemblies with flanged valves and fittings S 38.158 (all sheets)
Orifice meter run connection assemblies with flanged valves and fittings S 38.159 (all sheets)
Typical bracings for small bore branches of piping (e.g., drain/vent point) S 44.030
Typical bracings for small bore branches of piping (e.g., orifice instrument S 44.031
connection)
Typical bracings for small bore branches of piping (e.g., pressure instrument S 44.032
connection)
Page 15 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.
Revision: 01
Petroleum Development Oman LLC Effective: Dec-2021
1 PIPING BASICS
1.1 GENERAL
1. Refer to the following DEPs and MESCs for the selection of piping construction:
a. DEP 31.38.01.10-Gen.;
b. DEP 31.38.01.14-Gen.;
c. Standard form DEP 31.38.01.84-Gen.;
d. MESC Group 74 (pipe);
e. MESC Group 76 (fittings and flanges);
f. MESC Group 77 (valves);
g. MESC Group 81 (bolting);
h. MESC Group 85 (gaskets and packing).
2. Refer to (Appendix B) for the requirements for the piping system development of all
piping systems.
3. Project modifications to piping classes should be minimized.
4. Refer to SP-2411 for the requirements for pipe supports.
5. Piping layouts having dead legs where any of the following can happen shall be
subject to the review and approval of the Principal:
a. water can accumulate and freeze;
b. materials of construction are affected by corrosive fluids;
c. particles or bulk solids can accumulate;
d. stagnant flow can lead to polymer growth (e.g., ethylene oxide service).
6. Design reviews shall be performed in stages to verify the proposed physical or
3D CAD models to confirm that the optimum piping layout is achieved in terms of
process requirements, HFE, commissioning, operation, inspection and maintenance.
a. Refer to DEP 30.10.05.11-Gen for the requirements for model reviews.
b. Proposed physical or computer piping 3D CAD models shall be subject to
approval by the Principal before proceeding for construction of piping systems.
7. Valves shall not be installed above roads.
Page 16 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.
Revision: 01
Petroleum Development Oman LLC Effective: Dec-2021
Page 17 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.
Revision: 01
Petroleum Development Oman LLC Effective: Dec-2021
at the same elevation as the bottom of adjacent lines without pipe shoe or reinforcing
pads.
9. The difference in elevation between lines running in plane north or south and lines
running in plane east or west should be a minimum of 1 m (3.3 ft).
10. Piping should be routed to provide a simple, shortest-possible run, allowing easy
support and with the minimum number of fittings adequate for expansion and flexibility.
11. Piping shall be routed such that overhead clearance (headroom) or stumbling hazards
such as obstruction to walkways and other paths of travel or equipment movement are
avoided.
12. Diagonal and skewed angles of piping layout in horizontal plane should be avoided.
13. Piping connected to more than one piece of equipment (e.g., a pump and its spare)
shall be designed and supported in accordance with the following:
a. excessive loads on equipment do not occur when one branch of the pipe is
disconnected (e.g., during maintenance operations);
b. if multiple nozzles are applied, (e.g., on air cooler banks) the connecting piping is
designed so that small dimensional errors in construction can be accommodated;
c. the piping itself is adequately designed to compensate for any thermal expansion
due to differential temperatures between operating equipment and spare
equipment.
14. Pipe sizes that require support spacing closer than 6m shall have intermediate beams
installed between main pipe rack stanchions.
Rationale: The distance between the stanchions for pipe racks is typically 6m but
will be optimised based on pipe rack loading and the distribution of pipe sizes.
15. The pipe rack width depends on the number of lines and future expansion where
generally is kept about 5 m with a height from grade of 3 m to first tier bottom. This
elevation should be optimised based on the crossing road, crane approach, vehicle
access anticipated and headroom clearance.
The number of tiers and clearence between the various tiers should be determined
based on the number of pipes / size / pipe entry dimension/ cable routing etc. In
general, the clearance between the various tiers shall be maintained common space
across each tiers.
The utility lines are to be placed on the top level and process lines on the bottom level
if possible. For minimum pipe size for pipe rack and pipe track refer to part II of this
SP.
16. If a pipe rack forms part of a structure, or is located next to a structure, the stanchions
of the pipe rack should be in line with the columns of the structure, to make optimal
use of space for incoming and outgoing pipes.
17. In a pipe rack, piping arrangements with complicated crossings should be avoided,
e.g., by not installing pipe rack spurs opposite each other.
18. Piping or components of austenitic stainless steel, duplex stainless steel, nickel alloy
or 9 % nickel steel SHALL [PS] be designed such that they are protected from
contamination with molten zinc due to fire. This SHALL [PS] is mitigated as per sketch
in Appendix-E or alternative arrangements can be followed e.g using painted structural
material in place of galvanized structures which needs to be approved by PDO TA.
19. For design requirements of fire water piping, refer to DEP 80.47.10.30-Gen.
Page 18 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.
Revision: 01
Petroleum Development Oman LLC Effective: Dec-2021
Local regulations might require larger minimum soil cover. The soil cover depth can also increase
due to outside temperature or permeability of the soil.
9. The load on pipe crossing roads should be equalised by means of pipe sleeves or a
culvert.
a. The pipe should be centered in the sleeves by use of distance pieces welded to
the pipe, or distance pieces fixed to the sheeting if the pipe is insulated for low-
temperature service.
10. Insulated pipe should not be buried.
11. For buried pipe operating ≤ 60 °C (140 °F), there shall be a clear distance of at least
0.3 m (12 in) between the pipe and any electrical or instrument cables.
Page 19 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.
Revision: 01
Petroleum Development Oman LLC Effective: Dec-2021
12. For buried pipe operating above 60 °C (140 °F), there shall a clear distance of at least
0.6 m (24 in) between the pipe and any electrical or instrument cables.
13. For buried pipe systems where the emission or leakage of aromatic hydrocarbons or
very toxic fluids is a HSE concern (e.g., pollution of ground water or saturation of the
soil), the following shall apply:
a. no bolted joints;
b. valves installed in pits.
14. In case of any constraints to maintain the min soil cover due to existing under ground
facilities, additional sort of protection shall be provided like concrete slab, channel,
sleeve, culvert etc. subject to approval of the company with design calculation to
prove the imposed stress is within allowable limit.
1.4.2 Pipe tracks and pipe trenches
1. Piping outside process units (e.g., piping between process units and storage facilities)
should be supported on sleepers, at ground level in pipe tracks or below ground level
in pipe trenches.
a. The choice between pipe tracks or pipe trenches should be dictated by technical
and economic considerations, e.g., the number of road or rail crossings, the
ground water level and the length of the required trench.
b. Pipe racks may be used if space at ground level is limited or if the use of culverts
or buried piping is uneconomical.
2. The distance between sleepers in pipe tracks and in pipe trenches shall be based on
the maximum allowed free span of the majority of pipes in accordance with SP-2390
a. Smaller pipe requiring a shorter supporting distance shall be grouped together
and be supported on additional supports.
3. The elevation of sleepers shall meet all of the following:
a. provide a minimum vertical clearance of 0.3 m (12 in) underneath the bottom of
carbon steel pipe in culverts or concrete trenches, to facilitate inspection and
coating maintenance;
b. allow access for maintenance and for operation of valves, drains and
instrumentation;
c. ensure that pipes and insulation will remain above the highest expected storm
water levels;
d. ensure that pipes and insulation will remain above the highest expected
accumulation levels of snow.
4. Flanged connections shall not be installed in trenches where the emission of aromatic
hydrocarbons or very toxic fluids is a HSE concern (e.g., pollution of ground water).
Page 20 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.
Revision: 01
Petroleum Development Oman LLC Effective: Dec-2021
2. For direct mounted instrument connections, the minimum size of branch connections
to run pipes shall be in accordance with Table 2.
a The mechanical strength of instrument connections shall be improved by using
the bracing of these branches to the run-pipe (see Standard Drawings S 44.030,
S 44.031, and S 44.032) if such connections are causing Longitudinal
/ Circumferential bending moments on the run pipe of (Refer to figure-1 as an
example- Note that applicable cases are not limited to this figure):
b. Non-direct-mounted instrument-connections should be kept as simple as possible.
c. The length of the branch should be minimised (fitting-to-fitting), with isolation
valve(s) as per latest piping classes:
i. with monoflange/slimline (DB&B) valves where design temperature is lower
than 150 °C (300 °F);
ii. with only tubing or a pressure gauge connected to the isolation valve.
3. Larger piping should be used instead of using support bracing (attachments) to small
bore piping for situations where increased mechanical strength is required.
4. For critical situations (e.g., where vibration of piping is expected), the mechanical
strength of instrument connections may be improved by using reducing nozzles, e.g.,
weldolet DN 40 (NPS 1 ½) – reducer DN 40/15 (NPS 1 ½ / ½) – welding neck flange
DN15 (NPS ½).
5. In branches with flanged valves, branch fittings with flanged outlets shall be used in
order to reduce the number of welds.
6. The branch size shall be restricted to minimum 2’’ for the following cases:
i. High H2S concentration/ toxity level as per SP-1190.
ii. For Waxy/ sand service, highly viscous fluid or where ice is anticipated,
pressure transimitter where diaphragm seal type is recommended by C&A.
iii. Internally coated / lined branches where it is restricted by coating limitiations
such as, Roto/ PEliner, FBE, Glass Flakes pipes etc.
7. Refer to DEP 32.31.00.32-Gen. for the requirements for level connections.
8. Pressure points should be as short as possible.
Page 21 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.
Revision: 01
Petroleum Development Oman LLC Effective: Dec-2021
9. In case of any branch connections fitted with unsupported valve causing Longitudinal
/ Circumferential bending moments (Ref.figure-1) on the run pipe of cases mentioned
above on this section clause 2a shall be braced (see Standard Drawings S 44.030,
S 44.031 and S 44.032).
a. In cases of long connection or vibrating service, the pressure gauge block and
pressure gauge shall be supported separately.
b. The DSS small bore branch (2” & smaller) with forged branch fittings (e.g
Nippolet/weldolet) shall be braced as per the standard drawings irrespective of service
conditions.
10. Any small bore connections that are needed at the following locations shall be DN 80
(NPS 3) or larger:
a. on piping between the compressor nozzle and pulsation bottles;
b. on all piping directly connected to the compressor.
11. For situations where vibration of piping could be expected, like near compressors,
small bore branch fittings connecting points to the main piping should be located at
positions where vibration amplitudes are lower, such as near fixed points at pipe
supports.
12. If the recommendation above (Part I, 1.5, Item 11) cannot be achieved, then the small-
bore piping shall be braced to the main piping in accordance with Standard Drawings
S 44.030, S 44.031, and S 44.032.
Page 22 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.
Revision: 01
Petroleum Development Oman LLC Effective: Dec-2021
2. For installations where bulk hydrotest fluids can be safely and efficiently removed
through other connections, the low point drain and high point vent size may be
reduced to DN 20 (NPS ¾) for all run pipe sizes DN 20 (NPS ¾) and greater.
a. The supply connection should be of a size that will allow the system to be filled
within a reasonable time and be fitted with a temporary, flanged globe valve to be
used for depressurising.
3. Vent flanges for HP steam and MP steam pipes may be replaced by welded caps after
the hydrostatic test.
a. These welds shall be non-destructively examined to the same standards as the
other welds in the system
Page 24 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.
Revision: 01
Petroleum Development Oman LLC Effective: Dec-2021
Page 25 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.
Revision: 01
Petroleum Development Oman LLC Effective: Dec-2021
c. taking the sample will not impair the safety of personnel or plant or cause
environmental impact.
6. Samples should be taken from a vertical pipe where possible.
7. Where samples are taken from a horizontal pipe section, the sample take-off location
shall be oriented as follows:
a. for gaseous products, at the top of the pipe;
b. for liquid products, at the side of the pipe, no further than the 5 o'clock position.
The preferred location is the 4 o'clock position.
8. Sample take-off connections shall not be located at dead ends of piping.
9. Sample pipes shall not be longer than 8 m (26 ft).
a. Sample piping should be as short as possible.
10. As far as practicable, sample connections should be grouped together and provided
each with a sample cabinet which can be connected to one common drain facility.
11. If bleed lines are installed, they shall be led to a safe location.
12. For HFE aspects of piping systems associated with sampling systems, refer to SP-
2215.
Page 26 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.
Revision: 01
Petroleum Development Oman LLC Effective: Dec-2021
3. If thermowells longer than 255 mm (10 in.) are required for pipes (e.g., if solidified
product on the pipe wall might influence the measurement), longer thermowells from
the equipment range may be applied after the mechanical strength of the thermowell
has been checked with respect to the flow speed and vibration.
4. In pipes with turbulent flow, only thermowells with a maximum length of 230 mm (9 in)
should be used in order to reduce vibration and forces on the thermowell.
Rationale: In pipes with turbulent flow, the temperature difference between the
centre of the pipe and near the pipe wall is negligible so the shorter thermowell will
not adversely affect the measurement accuracy.
5. Thermowells should not be installed in pipes with continuous two-phase flow.
As the vortex shedding frequency (i.e., Strouhal Frequency) approaches the
thermowell natural frequency, the tip displacement and stresses are greatly
magnified and the thermowell can fail due to the large amount of energy it absorbs.
6. The thermowell Manufacturer/Supplier shall supply thermowell vibration calculations
per ASME PTC 19.3 TW to demonstrate that the ratio of wake frequency (fw) to natural
frequency (fn) is less than 0.8 where in-line resonance is not a concern.
a. If in-line resonance is a concern, the ratio of wake frequency to natural frequency
shall be 0.4.
b. If the design does not meet ASME PTC 19.3 TW requirements, in order to
comply with ASME PTC 19.3 TW one or both of the following shall be applied:
i. increase the thermowell base diameter;
ii. reduce the thermowell insertion length.
7. Thermowell insertion length may be reduced at no loss of accuracy where the flow
regime is of a high Reynolds number (i.e., 1 x 107 or greater) in order to satisfy ASME
PTC 19.3 TW requirements.
Rationale: In high Reynolds flow regimes (1 x 107 and greater), the boundary layer
is very thin.
Measures to avoid vibrations include:
• the use of short thermowells;
• the use of welded thermowells;
• roughening the part of the thermowell exposed to the flow, e.g., by knurling
(standard design);
Page 27 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.
Revision: 01
Petroleum Development Oman LLC Effective: Dec-2021
Page 28 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.
Revision: 01
Petroleum Development Oman LLC Effective: Dec-2021
Page 29 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.
Revision: 01
Petroleum Development Oman LLC Effective: Dec-2021
iv. for extractions in the 9-11 o’clock or 1-3 o’clock orientation: mechanical-
telescopic tools may be used, if an external liquid source is provided for
back-pressurization and forward flushing;
v. for extractions in the 11-1 o’clock orientation: pressure balanced retrieval
tools may be used without external liquid back-pressurization and forward
flushing facilities;
vi. at the orientation boundaries, the least restrictive requirements may be
selected.
3. Refer to DEP 31.38.01.20-Gen. or DEP 31.01.10.10-Gen., whichever is applicable, for
the requirements for injection points and injection quill systems.
4. Where installations are on the bottom half of the line, hydraulic systems shall be
selected.
5. Where installations are on the top half of the line, hydraulic or mechanical systems
may be used.
6. Where mechanical systems are selected they shall be provided with the following:
a. hydraulic pump for back pressurization prior to unseating the plug;
b. wire brush tool for pressurized thread cleaning;
c. thread chaser for pressurized thread cleaning for cases where wire brush
cleaning proves ineffective;
d. thread tap for pressurized thread tapping for cases where thread chasing proves
ineffective;
e. set of three no-go thread gauges to gauge bottom, middle and top parts of the
internal access fitting threads, to allow periodic thread condition monitoring;
f. adaptor fitting to fit over an access fitting, if threads become worn out;
g. abandonment fitting, to abandon access fittings and protect the created dead leg
from continued corrosion.
Page 30 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.
Revision: 01
Petroleum Development Oman LLC Effective: Dec-2021
1.17.2 Design
1. All piping components of the tie-in connection shall be in accordance with the existing
piping system piping class up to the first isolation valve.
2. Branch connections shall be designed in accordance with the ASME B31.3.
1.17.3 Location
1. For hot tap tie-in connection location requirements refer to DEP 31.38.60.10-Gen.
1.17.4 Welding and inspection
1. Refer to SP-2404 for the requirements for welding and inspection of piping tie-in
connections.
1.17.5 Documentation
1.17.5.1 Hot tie-in connections
1. The supporting documentation for a hot tie-in connection shall consist of the following:
a. design calculations for branch connection;
b. drawings;
c. work procedure.
2. The tie-in design package shall, as a minimum, include a general
arrangement/isometric view to define the tie-in connection.
3. The work procedure shall include the following:
a. site preparation;
b. cleaning/purging/flushing;
c. reinstatement;
d. Tie-in connection check list completed at each step by the relevant action party.
1.17.5.2 Hot tap tie-in connection
1. Refer to DEP 31.38.60.10-Gen. for the requirements for hot tap tie-in connection
documentation.
2. The Hot tie -in proposal needs Prior PDO approval and all the relevant documents
shall be reviewed and approved by PDO TA2.
Page 31 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.
Revision: 01
Petroleum Development Oman LLC Effective: Dec-2021
a. As a minimum, a clearance of 1000 mm (3.3 ft) between the two banks shall be
provided.
4. Where individual pipes at grade are required to cross a road, they shall be designed in
accordance with the requirements given in Part I, 1.3.
a. Where pipetracks cross under roads the piping shall be routed through open
concrete culverts or through conduit pipe.
5. Wherever possible, changes in direction should be accomplished by in-plane turning.
6. Where pumps associated with storage tank are located at a distance more than 100 m
(300 ft) away from the tank, the suction lines shall not be pocketed.
7. Except for in-line piping components and in-line instrumentation items, the use of
flanges should be avoided in offsite piping systems.
2.1 GENERAL
1. If equipment flanges deviate from the standard sizes selected from the piping classes,
the matching pipe flanges shall be ordered with the equipment.
2. Piping and pipe supporting structures shall be designed so that access is provided for
maintenance or removal of valves, in-line instruments, tube bundles and shell/channel
covers (e.g., cranes and trucks) and for operational reasons (e.g., filter cleaning).
a. Removal or replacement of equipment shall be possible with a minimum
dismantling of piping.
Removable pipe spools could be required. If needed, the installation of removable
spools will need to take into account the spool asymmetry, vertical clearances and
manoeuvring space available, and insulation.
b. Small pieces of equipment and ancillaries which need regular supervision or
maintenance should be installed on elevated plinths in order to improve access.
3. Valves shall be installed on all equipment drains and equipment vents;
4. Equipment and piping containing slurries shall have minimum size DN 25 (NPS 1)
drain connections, unless the type of drain valve dictates a larger size (e.g., ram-type
valve);
5. Refer to DEP 30.06.10.12-Gen. for the requirements for operational drains for
equipment and piping containing liquefied petroleum gases to be in accordance with
DEP 30.06.10.12-Gen.;
6. If equipment can be adequately drained or vented via connected piping, then the
installation may be executed without the use of a dedicated equipment drain or
dedicated equipment vent.
7. For drainage systems refer to SP-1126.
8. For ergonomic aspects of elevated work platforms and decks associated equipment
refer to SP-2215.
Page 33 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.
Revision: 01
Petroleum Development Oman LLC Effective: Dec-2021
Page 34 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.
Revision: 01
Petroleum Development Oman LLC Effective: Dec-2021
8. A longer straight length than shown Table 6 might be required, therefore it should be
studied how unequal flow to the impeller eye can best be prevented.
a. The advice of the pump Manufacturer/Supplier should be sought in this respect.
2.2.3 Steam turbines
1. Piping shall be designed to permit steam-blowing up to the inlet and outlet flanges of
the turbine before start-up.
2.2.4 Compressors
1. The length of straight pipe required upstream/downstream of compressor inlet/outlet
nozzles shall be as per Table 7 and Table 8.
a. For components not listed, a minimum of 3D shall be used.
Table 7 Minimum straight length for compressor inlet
2. With the following exception, if two or more compressors are combined, their suction
pipes should enter at the top of the header,
a. Suction pipes at least one pipe size smaller than the header may enter at the side
of the header.
3. The suction pipe between a knock-out drum and the compressor shall slope down
towards the knock-out drum, having no pockets in the line.
a. The suction pipe between a knock-out drum and the compressor should be as
short as reasonably practicable.
Page 35 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.
Revision: 01
Petroleum Development Oman LLC Effective: Dec-2021
2. Sufficient space for access and maintenance shall be kept between adjacent heat
exchanger inlet and outlet valve manifolds.
a. The piping shall be designed to provide wrench room for unbolting exchanger
channels, and maintain 150 mm (6 in) minimum clearance between the following
components:
i. pipe flanges and the exchanger shell or insulation;
ii. pipe or insulation and the exchanger flanges.
3. Channel piping shall be arranged with a removable section between the exchanger
and block valves so that full access is available for bundle pulling and tube cleaning.
a. To allow removal of covers, heads, channels, bundles and shells, pipes shall not
be supported on heat exchanger shell or heads.
4. For HFE aspects of piping systems associated heat exchangers, refer to SP-2215.
2.3.2 Reboiler piping systems
1. Thermosyphon reboiler should be located as close as possible to the columns that
they serve.
2. All reboiler piping runs should be as short as possible, dictated by process and
mechanical stress requirements and not for layout convenience.
3. Thermosyphon outlet piping shall not include any pocketed or downward sloping
sections.
a. Reboiler return piping shall be free-draining.
4. For vertical thermosyphons, including printed circuit and plate-fin exchanger types, the
reboiler return piping shall contain no more than one 90° long radius bend and one
horizontal section of minimum length.
5. Reboiler vapour return piping shall be free draining and drain towards the reboiler.
2.3.3 Air cooled heat exchanger piping systems
1. Piping of air cooled heat exchangers should be arranged symmetrically to provide
uniform distribution to inlet manifolds.
2.3.4 Printed circuit, plate-and-frame, and plate fin heat exchanger piping systems
1. The design of the permanent strainer shall be such that it could withstand a reverse-
flow condition.
Page 36 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.
Revision: 01
Petroleum Development Oman LLC Effective: Dec-2021
6. The range of the level transmitters shall cover the full range of the level indicator.
The specific gravity of the fluid to be measured will be specified by the Principal.
7. Butt welds shall be examined in accordance with the appropriate construction class in
SP-2404.
8. Pressurized floats shall not be used.
9. Floats shall be installed after hydrostatic pressure testing.
10. Flanged vent and drain connections shall be provided.
11. The housing shall be designed so that no moisture or dirt can enter (e.g., filled with
inert gas and hermetically sealed).
12. Gate valves that isolate the level measurement chamber from the process shall have
the same flange rating as the vessel nozzle and the same size as the connections to
the level chamber.
2.7.2.2 Gauge glasses
2.7.2.2.1 General
1. Gauge glasses shall only be used for interface level measurement.
a. Single section gauge glasses shall be used for liquid/liquid interface level
applications.
b. Separate vessel nozzles shall be provided for single section gauge glasses for
interface level applications.
2. Gauge glasses for applications in temperature below 0 °C (32 °F) shall have non-
frosting extension blocks in accordance with MESC SPE 76/045.
3. When specifying a level gauge in condensing services (e.g., steam), the process
temperature/pressure in the vessel shall be used.
4. Tubular gauge glasses shall not be used for any level application.
5. To ensure clear visual access for the operator, level gauges shall not be placed
behind pipes or other obstacles.
a. The level gauge shall be positioned so that it can be read from the operator's
normal working position at ground level, platforms or ladders.
6. Sufficient clearance for access and maintenance shall be provided if lighting is to be
installed on level gauges.
7. If a light is needed to read the level gauge, the level gauge shall meet one of the
following:
a. preferably, be less than 1 m (40 in) away from where the operator is standing;
b. if above is not possible, then install lighting behind the level gauge.
2.7.2.2.2 Plate-type level gauges
1. For details of plate-type level gauges, see Standard Drawing S 38.059.
Plate-type level gauges have standard centre-to-centre nozzle distances of 450 mm
(17.8 in), 840 mm (33 in) and 1230 mm (48.4 in).
2. Reflex-type level gauges without lighting shall be used except as follows:
a. Through-vision type level gauges with lighting may be used for adhesive liquids
which give unclear readings on reflex-type level gauges (i.e., where a liquid film
remains after the level has dropped).
Page 38 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.
Revision: 01
Petroleum Development Oman LLC Effective: Dec-2021
2.8 INSTRUMENTATION
1. Refer to DEP 32.31.00.32-Gen. for the requirements for mounting in-line instruments
2. Refer to DEP 32.37.10.11-Gen. for the requirements for instrument impulse pipes.
Page 39 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.
Revision: 01
Petroleum Development Oman LLC Effective: Dec-2021
3 UTILITY PIPING
3.1 GENERAL
1. For utility connection requirements, see utility, drain and vent connections section of
this SP.
2. Piping materials for all utility services shall be selected from applicable piping classes.
3.4 STEAM
1. Refer to DEP 30.75.10.10-Gen. for the requirements for piping in steam systems.
2. Atmospheric relief device discharge piping should be corrosion resistant (e.g., hot dip
galvanized or stainless steel construction)
a. Atmospheric relief discharge piping shall have a weep hole of 13 mm diameter (½
in) at the lowest point of pipe to ensure complete removal of all liquids
accumulated in the discharge piping system.
3. All steam pipes shall have a drip leg (boot) with steam trap at the low points and at the
end to remove steam condensate (e.g., during commissioning).
Page 40 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.
Revision: 01
Petroleum Development Oman LLC Effective: Dec-2021
4. A drip leg (boot) with steam trap shall be installed at the following locations in both
saturated and superheated service:
a. in saturated steam lines at a maximum interval of 50 m (165 ft)
b. in superheated steam lines at a maximum interval of 150 m (500 ft).
5. The end of main steam headers shall be provided with valved blow-off connection of
size minimum DN20 (NPS ¾).
6. Selection of steam traps shall be in accordance with Table 9:
Table 9 Steam trap selection
Low pressure steam (1.3.2) drip service inverted bucket style mechanical traps or
bimetallic thermostatic style traps
Medium pressure steam (1.3.2) drip service Disc type thermodynamic traps
High pressure steam (1.3.2) drip service thermodynamic piston/disc type traps
7. Steam traps used for process services shall be provided with a unique equipment tag
number.
8. Steam traps up to and including DN 40 (NPS 1 ½) should be welded and have
removable internals to allow repair without performing hot work.
9. Refer to DEP 30.75.10.10-Gen. for the layout requirements for steam systems.
10. Open steam trap discharges shall be located away from doors, windows and air
intakes.
a. In areas subject to freezing, icing-up of personnel access areas shall be
prevented.
Page 41 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.
Revision: 01
Petroleum Development Oman LLC Effective: Dec-2021
4. If relatively small-bore pipes are installed along with bigger pipes in tank pits having a
concrete floor (e.g., in chemical plants), steel frame supports may be used as
intermediate supports between concrete sleepers.
5. There shall be access to manholes, mixing nozzles, drains and other facilities on the
tanks.
a. Small bore utility piping required for more than one tank may be routed along an
interconnecting overhead walkway, if available.
6. Pipes may only be routed through bund walls if they cannot be passed over such walls
(e.g., suction pipes).
a. For bundwall crossings, refer to DEP 34.11.00.11-Gen.
5 PIPING COMPONENTS
5.1 GENERAL
1. For instrument connections, manual sampling connections, vent and drain
connections, length of the connections should be as short as possible
5.1.1 Special piping components
1. Piping components not typically specified in piping classes, such as certain types of
blow-down valves, non-slam check valves, injection quills and non-standard thermo-
well or branch devices shall be defined as special piping components. Refer to GU-
1006 for standardized piping & static special components.
a. Special piping component number shall be allocated and used on all relevant
documents, including the PEFS drawings.
5.2 PIPE
5.2.1 Metallic pipe
1. For metallic pipe, refer to DEP 30.10.02.11-Gen. and ASME B31.3.
2. Metallic pipe shall be in accordance with ASME B36.10M or ASME B36.19M.
3. The corrosion allowance for carbon steel and ferritic alloy steel pipes shall be at least
1 mm (0.04 in).
5.2.2 Non-metallic pipe
1. For the selection of non-metallic materials, refer to DEP 30.10.02.13-Gen.
2. For glass-fibre reinforced plastic (GRP) piping systems, refer to DEP 31.40.10.19-Gen
and SP-2092.
a. For GRP piping classes, refer to DEP 31.38.01.14-Gen.
5.2.3 Lined piping
1. For plastic-lined piping classes, refer to DEP 31.38.01.14-Gen.
2. All internally lined carbon steel pipes with a diameter of DN 250 (NPS 10) and larger
shall be fabricated in flanged sections.
a. All flanged sections shall be hydrotested prior to coating.
b. Field welding of coated piping components shall not be permitted.
3. The design shall address the following design condition limitations for lining material:
a. pressure – temperature rating combination;
b. conveying fluid compatibility;
Page 42 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.
Revision: 01
Petroleum Development Oman LLC Effective: Dec-2021
c. coupling materials;
d. electrical conductivity of the piping system.
4. Nominal sizes of lined piping shall be in accordance with ASME B36.10M or
ASME B36.19M, unless otherwise specified.
5. Plastic-lined piping shall be in accordance with ASTM F1545, except that welding neck
flanges are allowed.
a. Threaded flanges shall not be used.
Page 43 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.
Revision: 01
Petroleum Development Oman LLC Effective: Dec-2021
Page 44 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.
Revision: 01
Petroleum Development Oman LLC Effective: Dec-2021
8. The use of non-sour service bolts on flanges of sour systems shall comply with all of
the following:
a. the bolts are not in contact with the sour fluid;
b. the bolts are not insulated;
c. natural air ventilation is unrestricted.
d. tape, if used, is removed immediately after successful testing of the joint.
Rationale: If non-sour service bolts are used on flanges of sour systems, the
practice to use masking tape for flange tightness testing carries the risk of bolt
corrosion in case this tape is not removed after start-up.
i. The tape shall be brightly contrasting in colour.
9. Where austenitic stainless steel bolting grades are required, following grades shall be
selected:
a. ASTM A193 Grade B8M-Class 2 (AISI 316) for the following services:
i. Non-sour service in non-maritime structures (onshore non-jetty facilities)
where valve heads and manifold bodies are AISI 316, Alloy 400, or Alloy
500
b. ASTM A193 Grade B8M-Class 1 (AISI 316) for the following services:
i. Sour service in non-maritime structures (onshore non-jetty facilities) where
valve heads and manifold bodies are AISI 316 stainless steel
c. ASTM A193 B8MLCuN-Class 1B (6Mo) for the following services:
i. Where valve heads and manifold bodies are Alloy 6B, or Alloy C276
10. The use of hardened washers should be considered on TSA-coated flanges,
especially at flange locations that will be frequently broken and re-made
Rationale: Damage to the TSA coating (due to galling) can lead to aluminium
deposits on the nut bearing surface causing inaccuracy when torque tightening the
bolts.
5.3.1.4 Coated bolts
1. Refer to DEP 30.48.00.31-Gen. for the requirements for coating of bolts (fasteners).
5.3.1.5 Threaded joints
1. Threaded joints, where permitted, shall be NPT pipe threads per ASME B1.20.1.
2. Where non-seal-welded threaded pipe joints are used, a thread sealant/lubricant shall
be used on the pipe threads of all connections to ensure the threads are tight.
3. Where pipe unions are acceptable, they shall be limited to Class 300 systems:
a. Unions shall be made of forged steel;
b. Unions shall have a working pre ssure of at least 3000 psi;
c. Unions shall be of the ball-to-full bearing arc or ball-to-cone, metal-to-metal
seated type;
d. Unions shall consist of a head or cone piece, a tail or ball piece, and a connecting
nut.
e. Gasketed unions shall not be used.
f. Unions should not be used between large bore (Part I, 1.3.2) piping and the first
branch valve.
Page 45 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.
Revision: 01
Petroleum Development Oman LLC Effective: Dec-2021
5.4 FITTINGS
5.4.1 General
1. Fittings shall be in accordance with ASME B16.5, ASME B16.9, ASME B16.24 or
ASME B16.47, as applicable for the type of fitting.
2. Fabricated fittings employing intersection welds shall only be used in crosses, and
when designed in accordance with the relevant design codes or regulations.
3. The use of reducing elbows, straight crosses, reducing outlet crosses and short radius
elbows shall be subject to approval by the Principal
4. Short radius elbows shall not be used where the likelihood of erosion is high in
accordance with ISO 13703.
Rationale: This could result in a threat to the integrity of the piping system.
Where short radius bends are used, the pressure drop and the stresses in the
piping system to be kept within the allowable limits. Although ISO 13703 is
specific to offshore applications, the principles for this clause apply equally to
onshore applications.
5. For very toxic - acute fluids fluid services, “pipe-to-pipe” branch connections shall not
be used.
Page 46 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.
Revision: 01
Petroleum Development Oman LLC Effective: Dec-2021
Page 47 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.
Revision: 01
Petroleum Development Oman LLC Effective: Dec-2021
Page 48 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.
Revision: 01
Petroleum Development Oman LLC Effective: Dec-2021
Page 49 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.
Revision: 01
Petroleum Development Oman LLC Effective: Dec-2021
Spades weighing more than 23 kg (50 lbs) are shown in Table 11.
Table 11 Spades heavier than 23 kg (50 lb)
6. Spades and their corresponding spacers shall be clearly tagged and stored in
adequate facilities when not in use.
7. Spades without a spacer shall not be used for spading rotating equipment, in order to
avoid distortion problems.
To remove a spacer (or its replacement spade) half of the bolts need to be removed
and the flanges opened slightly. To install a spade between two flanges that did not
have a spacer, requires the flanges to be opened by a distance equal to the
thickness of the spade plus one gasket.
a. Spades without a spacer should only be applied in relatively flexible piping
systems.
8. Spacers and spades exceeding a weight of 23 kg (50 lbs) shall be provided with a
lifting lug.
9. A removable spool and blind flanges shall be used in the following situations:
a. where the nozzle is used for entry into the equipment;
b. where the nozzle is used for hoisting (e.g., top nozzles on columns);
c. where the nozzle (e.g., the head of a heat exchanger) is used to remove internals
(e.g., the tube bundle);
d. where the nozzle is used for loading/unloading of solids (e.g., catalyst).
5.8 VALVES
5.8.1 General
The scope of this section includes standard valves, selected for DEP piping classes. It
does not include designs of pressure relief valves (refer to DEP 80.36.00.30-Gen.) or
control valves (refer to SP-2350) Valves are categorised in a standard selection and one
requiring a deviated selection due to the service. This can be the valve type or design.
Page 50 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.
Revision: 01
Petroleum Development Oman LLC Effective: Dec-2021
Page 51 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.
Revision: 01
Petroleum Development Oman LLC Effective: Dec-2021
the seat. In the other shut-off direction, shut-off is less reliable but the operating
torque is substantially lower, enabling smaller actuators to be used.
2. Butterfly valves shall not be installed back to back, due to the disc protruding beyond
the face or valve end.
3. Soft seated butterfly valves should not be used in dirty services.
Rationale: Soft seated butterfly valves are cheaper than metal seated but have a
limited service temperature).
4. Wafer-type valves shall not be used because of their increased vulnerability to fire.
Rationale: The exposed tie bolts will expand quickly when near a fire, causing joint
leakage.
5. Wafer-lug type valves have shielded bolting and may be selected for water service.
6. Double flanged valves should be used for process applications for maintenance
reasons
Rationale: Double flanged valves can simply be un-bolted and lifted from the line,
whereas with corroded threaded wafer lug type, removal of the studs might not be
possible.
7. To prevent closure of the disc in turbulent services, butterfly valves shall be installed
with stem orientation dissecting the flow pattern in two symmetrical halves.
8. If it is specified that the valve will be installed underground or at a level below the
operator’s position, the valve shall have a stem extension and extension casing.
a. The casing shall be fully enclosed and externally coated for corrosion prevention.
9. For gear operated valves, the gearbox shall be mounted directly on the valve.
a. The gearbox input shaft shall be extended.
10. The design of the stem extension and protector (if applicable) shall be subject of
approval by the Principal.
5.8.2.4 Gate valves
1. Gate valves should be selected for steam service.
2. Gate valves ends shall be as per SP-2342 for steam service
3. Depending on the size, the following wedge gate valves may be selected:
a. DN 15 (NPS ½) up to DN 40 (NPS 1 ½): solid wedge type gate valve;
b. flexible-wedge type gate valves larger than DN 40 (NPS 1 ½):
c. flanged, hub type, butt weld or socket weld valve ends as allowed per (Part II,
8.3.1.2).
4. Through conduit slab gate valves should be considered for dirty or fouling service
where the body bowl of a wedge gate valve could collect solids that will interfere with
the movement of the gates.
Rationale: Through conduit expanding gate valves have a further advantage of a special
design which incorporates a gate made in two segments, which are expanded when
closed to give gas tight shut off on both seats. The performance of both seats can be
verified via a body bleed valve.
5. Gate valves shall include a seal between the male and female segments to isolate the
valve centre cavity from pipeline debris.
5.8.2.5 Globe valves
1. The valve ends shall be flanged for all services and upto 400 deg cel.
Page 52 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.
Revision: 01
Petroleum Development Oman LLC Effective: Dec-2021
Page 53 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.
Revision: 01
Petroleum Development Oman LLC Effective: Dec-2021
S.S & DSS A193 B8M Class 1 A 194-8M -196 °C (-320 °F) +550 °C (1020 °F)
Page 54 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.
Revision: 01
Petroleum Development Oman LLC Effective: Dec-2021
Class 2 can be used for non-sour, but Class 1 is same cost and max temp. 500 °C
(930 °F).
Page 55 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.
Revision: 01
Petroleum Development Oman LLC Effective: Dec-2021
Material Min. lower Max. Max. seat Max. Max seal Application notes
design seat design seal design
temperature pressure temperature pressure temperature
class class
Virgin/filled/ Not suitable for
-200 °C 150 °C
modified 300 Styrene/Butadiene
(-330 °F) (300 °F) 200 °C service
PTFE 2500
(390 °F)
-200 °C 150 °C
Filled PTFE 600
(-330 °F) (300 °F)
-200 °C 120 °C 120 °C Use for low
PCTFE 1500 2500 temperature services
(-330 °F) (250 °F) (250 °F)
Page 56 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.
Revision: 01
Petroleum Development Oman LLC Effective: Dec-2021
3. For rising stems, the upper and lower packing shall be braided with either graphite or
carbon yarn.
Rationale: These packings have the ability to wipe the stem clean.
5.8.7 Valve selection criteria
5.8.7.1 General
1. Table 15 should be used to select a valve, taking the following into account:
a. piping / design requirements:
i. size;
ii. pressure rating;
iii. end connections;
b. process requirements:
i. fluid characteristics;
ii. maximum operating and design pressures;
iii. lower design temperature, maximum operating temperature and design
temperature; refer to Part II of DEP 01.00.01.30-Gen.
iv. flow capacity/resistance;
v. liquid or gas;
vi. clean service;
vii. suspended solids;
viii. fouling service;
ix. bi/uni-directional shut-off;
x. shut-off requirement (bubble tight, firesafe);
xi. Shell toxicity classification, per Part III of DEP 01.00.01.30-Gen.
xii. frequency of operation;
xiii. manual or actuated;
xiv. throttling requirement;
xv. total cost of ownership
Page 57 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.
Revision: 01
Petroleum Development Oman LLC Effective: Dec-2021
Soft Metal Soft Metal Soft Soft Metal M/M Sleeved Lubr M/M M/M M/M M/M M/M Metal Metal Metal
Effort to operate 1 3 2 4 2 3 4 6 4 8 7 8 8 6 6 NA NA NA
Speed of operation 1 2 2 4 1 2 3 4 2 4 10 10 10 8 8 NA NA NA
Expected life clean service 1 2 2 4 1 2 3 3 2 1 2 1 1 2 2 2 2 2
Expected life dirty service 8 2 10 2 2 4 3 4 4 2 3 2 1 3 2 3 2 2
Possibility of being pigged NP NP 1 1 NP NP NP NP NP NP 1 1 1 NP NP NP 1 NP
Possibility of creating surge pressure 6 6 8 8 10 8 8 2 5 3 2 1 1 2 2 2 4 2
Possibility of exc. cavity pressure liquid
service 8/3 * 3 8/3 * 3 NA NA NA 3 3 8 9 9 9 NA NA NA NA NA
Weight 3 3 6 6 1 1 2 5 5 5 10 9 10 8 8 8 8 2
Size 3 3 5 5 1 1 2 4 4 4 10 9 10 8 8 8 8 3
Page 58 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.
Revision: 01
Petroleum Development Oman LLC Effective: Dec-2021
On-Off valves
Reduced bore Full bore Conc. Double Triple Reduced port Wedge Slab Expand Straight Y-
OS OS ing Type
Soft Metal Soft Metal Soft Soft Metal M/M Sleeved Lubr M/M M/M M/M M/M M/M
Ease of pneumatic actuation 1 1 1 1 1 1 1 1 1 2 10 10 10 10 10
Ease of hydraulic operation 1 1 1 1 1 1 1 1 1 2 2 2 2 2 2
Actuated
NA = Not Applicable
Page 59 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.
Revision: 01
Petroleum Development Oman LLC Effective: Dec-2021
Valves End * Size [DN] Size (NPS) ASME Valve standard MESC Emission
class SPE 77 class
rating
availability
Ball, floating, full bore, soft and FL 15 - 150 ½ - 6 150 ISO 17292 110 BH AH
metal seated
FL 15 - 100 ½ - 4 300 ISO 17292 110 BH AH
Ball, trunnion, full bore, soft FL 50 - 600 2 - 24 150-900 ISO 14313/ 130 BH AH
and metal seated API SPEC 6D
FL 50 - 400 2 - 16 1500 130 BH AH
FL
50 - 300 2 - 12 2500 130 BH AH
Butterfly, double offset, soft FL 200 - 1200 8 - 48 150-300 API 609 cat B 134 BH AH
seated
Butterfly, triple offset, metal FL 200 - 1200 8 - 48 150-300 API 609 cat B 134 BH AH
seated
FL 200 - 600 8 - 24 600 API 609 cat B 134 BH AH
Page 60 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.
Revision: 01
Petroleum Development Oman LLC Effective: Dec-2021
Page 61 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.
Revision: 01
Petroleum Development Oman LLC Effective: Dec-2021
Page 62 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.
Revision: 01
Petroleum Development Oman LLC Effective: Dec-2021
3. Because moisture can affect the performance, low temperatures valves shall be
supplied dry, degreased and sealed.
Low temperature valves are subject to temperature changes, consequently, any
liquid trapped within the valve cavity can expand and cause excessive cavity
pressure
5.8.8.3 Heat transfer fluid
1. To reduce the potential number of leak paths, valves having butt weld ends should
be used.
Rationale: Heat transfer fluid is flammable. Also, many heat transfer fluids are
carcinogenic.
Since the fluid is generally clean, the need for maintenance is minimal.
2. Valves should also either be bellows sealed or have emission class AH.
a. Refer to DEP 20.05.50.10-Gen. for the installation requirements.
3. Valves for heat transfer fluid shall be selected in accordance with Table 18.
Table 18 Valves for heat transfer fluid service
Valves End* Size [DN] Size [NPS] ASME Valve MESC Emission
class standard SPE 77 class
Min Max Min Max rating
Page 63 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.
Revision: 01
Petroleum Development Oman LLC Effective: Dec-2021
Table 19 Valves for cooling water service and fire-fighting water service
Valves End Size [DN] Size [NPS] ASME Valve standard MESC Emission
SPE 77 class
Min max Min max class
rating
Term Definition
Through A conduit gate valve is a type of parallel slide valve and is used in
Conduit Gate pipelines where pigs are run through the piping to perform cleaning
Valve or Slab of built up deposits or debris. Another area of application is in
Gate Valve erosive service. When fully open the valve has a continuous smooth
full bore.
Diaphragm A diaphragm valve is a valve which incorporates a resilient
Valve diaphragm which provides tight shutoff and also isolates the body
from its operator. The operator consists of a plunger and hand wheel
assembly. Diaphragm valves are ideal for corrosive, slurry and
sanitary services. They are easily and inexpensively actuated with
pneumatic and electric actuators.
Diverter/mixing A valve having more than one inlet/outlet. It is important that diverter
Valve valves are designed with an external position indication system that
is "mistake-proof" or similar and can be verified visually even if fitted
with an actuator. It is also important that the valve cannot be
disassembled and re-assembled incorrectly ensuring that the valve
always indicates the true position.
Flush bottom A drain valve without a dead nozzle end, used on equipment.
Valve
Knife Gate A knife gate valve is a gate valve used for solids slicing.
Valve
Pinch Valve A pinch valve is particularly suited for applications of slurries or
liquids with large amounts of suspended solids. It seals by means of
one or more flexible elements, such as a rubber tube, that can be
pinched to shut off flow.
Page 64 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.
Revision: 01
Petroleum Development Oman LLC Effective: Dec-2021
6 INSULATION
1. For thermal insulation of piping (including for personnel protection) of piping, refer
DEP 30.46.00.31-Gen.
2. Refer to DEP 30.46.00.31-Gen. for the requirements for acoustic insulation.
3. Bolted joints with spectacle blinds, spades or spacers inserted shall only be
insulated, such that the status of the insert remains clearly visible to the operator at
all times and from the normal approach path or vantage point.
4. If bolted joints with a design temperature above 400 °C (750 °F) are insulated, the
bolt stress (after relaxation) shall remain within the required seating stress of the
applied gasket type.
Page 65 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.
Revision: 01
Petroleum Development Oman LLC Effective: Dec-2021
1.1 GENERAL
1. Up to and including size DN 600 (NPS 24), the pipe sizes in Table 1 shall be used
with the following limitations:
a. due to their vulnerability to damage and their limited mechanical strength, sizes
DN 15 (NPS ½) and DN 20 (NPS ¾) should not be used except for short branch
connections;
b. nominal pipe size in pipe tracks shall not be less than DN 50 (NPS 2);
c. nominal pipe size in pipe racks shall not be less than DN 40 (NPS 1-½).
Table 1 Pipe sizes
4. For Greenfield projects, refer to DEP 01.00.09.10‑Gen. for the identification of piping.
DEP 01.00.09.10‑Gen. excludes Brownfield projects and projects at existing sites
from its scope. Brownfield projects and existing site projects will use the existing
site conventions.
5. Refer to DEP 31.38.01.10‑Gen. for the requirements for the identification of piping
classes.
Page 66 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.
Revision: 01
Petroleum Development Oman LLC Effective: Dec-2021
where:
F = axial load on the support
Δp = pressure change (output from software packages dedicated to
surge analysis)
A = pipe cross sectional area
3. If the Δp calculated in (1.3.1.2, Item 2) divided by the distance between directional
changes (e.g., elbows) is less than 5 mbar/m (0.02 psi/ft) for a steel piping system,
then a detailed analysis of the anchor support may be omitted.
1.3.2 Two phase flow
1. If slug or intermittent flow regimes cannot be totally eliminated, the piping system
shall be analysed and supported in accordance with SP-2390.
1.3.3 Installation requirements for flow instruments
1. Refer to DEP 32.31.00.32‑Gen. for installation requirements for flow instruments.
2. PIPING BASICS
Page 67 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.
Revision: 01
Petroleum Development Oman LLC Effective: Dec-2021
DN 15 (NPS ½) DN 15 (NPS ½)
Page 68 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.
Revision: 01
Petroleum Development Oman LLC Effective: Dec-2021
2.7 NOISE
1. To protect personnel from harmful noise, the following should be considered to
minimise noise in piping systems where the Mach number exceeds 0.3:
a. prevent abrupt changes in flow direction;
b. maintain a minimum distance between the upstream elbow and a control valve
of 10D, and a minimum distance between a control valve and the downstream
elbow of 20D;
c. use venturi (conical) type reducers to prevent abrupt changes in flow pattern;
d. use flow-straightening vanes to reduce large-scale turbulence;
e. increase wall thickness of pipe and fittings to attenuate sound and vibration;
f. use acoustic insulation or shielding around pipe and fittings to absorb or isolate
sound;
i. refer to DEP 31.46.00.31‑Gen. for requirements and recommendations on
the use of acoustic insulation to control noise;
g. use flow stream silencers.
Most noise in piping systems can be attributed to control valves. The sound
pressure level can be calculated for control valves from formulae contained in
IEC 60534-8-3 or data supplied by the various manufacturers. Valve trims can be
selected which minimise the noise levels.
3. PIPING ADJACENT TO EQUIPMENT
Page 69 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.
Revision: 01
Petroleum Development Oman LLC Effective: Dec-2021
Page 70 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.
Revision: 01
Petroleum Development Oman LLC Effective: Dec-2021
4.2 STEAM
1. Steam pipes shall have valved isolation at the boundary of the process unit.
a. Flanges shall be provided at these locations to allow for spading (spades or
spectacle blinds) to isolate the steam systems during maintenance of the unit.
2. Pipes to consumers shall branch off from the top of the steam supply pipe in order to
prevent steam condensate from going to the steam consumers.
3. Exhaust steam pipes shall enter at the top of the exhaust collecting pipe to prevent
steam condensate from running back into neighbouring steam consumers.
5. PIPING COMPONENTS
Page 71 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.
Revision: 01
Petroleum Development Oman LLC Effective: Dec-2021
a. They may be used to give a more reliable isolation than single-seated valves, or
to prevent product contamination (e.g., in oil movement operations).
5.1.2 Positive isolation
5.1.2.1 General
1. The use of quick-acting blinds or line blind valves (e.g., "Hammer") for frequent pipe
blinding shall comply with the following:
a. all parts of the quick acting blind shall be suitable for the fluid medium;
b. operating these blinds can expose large openings to atmosphere, the quick
acting blind shall be installed between isolation valves, with vents and drains on
both sides of the quick acting blind;
c. quick-acting blinds shall not be used in following fluid services:
i. flashing fluid services.
ii. fouling /scaling fluid services.
5.2 VALVES
1. Tight Shut Off (TSO) valves shall be provided with facilities for testing of seat
tightness while on-stream
Page 72 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.
Revision: 01
Petroleum Development Oman LLC Effective: Dec-2021
Page 73 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.
Revision: 01
Petroleum Development Oman LLC Effective: Dec-2021
B.2.3 Identification
1. Piping shall be clearly marked "SULPHURIC ACID SERVICE" after prefabrication,
either by painting or by applying adhesive tape, to indicate that it is for sulphuric acid
service.
2. For sulphuric acid service, the piping class number and the pipe designation shall be
painted on each part.
Page 74 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.
Revision: 01
Petroleum Development Oman LLC Effective: Dec-2021
D.1 INTRODUCTION
This appendix specifies the basic design framework for development of “fit-for-
purpose” piping systems, and also ensures that selective attention is applied to critical
aspects of design development where needed to prevent costly omissions and design
effort recycle.
1. Piping system design development shall be in accordance with the following
framework
a. Step-1: Identify the hazards for the piping system based on pressure,
temperature and the contained fluid; refer to (D.2.2);
b. Step-2: Based on fluid categorization and associated hazards, construction
class ranking shall be determined; refer to (D.2.3) and (D.2.4);
c. Step-3: Piping design requirements shall be based on the construction class;
refer to (D.3).
The concept of this framework is based on the following:
• The main function of pressure containing envelope piping system is to
reliably hold pressure and prevent leaks/loss of containment;
• Different piping systems represent different operational risks and/or
threats to successful project execution; and,
• There will always be limited resources to address all possible concerns
and threats in a completely exhaustive manner.
Page 76 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.
Revision: 01
Petroleum Development Oman LLC Effective: Dec-2021
The term construction class used in this Appendix is a different concept than the
design class used at the early stages of project development. Design class
determines an overall project approach such as plant layout, equipment
capacities, sparing, sizing, whereas construction classes focus on the integrity of
design.
2. Based on fluid categorization, selection of materials and associated hazards as
explained under Step-1, construction classes shall be assigned as follows:
a. Class-1 (sub-classifications as Class 1a, Class 1b) (D.2.3.2);
b. Class-2 (sub-classification as Class 2a,) (D.2.3.3);
c. Class-3 (sub-classifications as Class 3c, Class 3d) (D.2.3.4);
d. Class-4 (sub-classification as Class 4d) (D.2.3.5).
D.2.3.2 Class-1 (sub-classifications as Class 1a, Class 1b)
This construction class covers all very toxic (Part I, 1.3.2) piping systems (except
sulphuric acid, hydrochloric acid, acetic acid, sodium hypochlorite, caustic soda) and
also piping systems with fluid “Category K”. These systems are subjected to special
design and quality control attention as mentioned in the mitigation plan.
1. The quality framework shall address additional surveillance level for procurement
and construction phases to assure that all design parameters are met for these
piping systems.
D.2.3.3 Class-2 (sub-classification- as Class 2a,)
This construction class covers all normal fluid piping systems (including sulphuric acid,
hydrochloric acid, acetic acid, sodium hypochlorite, caustic soda) with flange ratings –
1500, 2500 and using “including Cr-Mo steels, stainless steel, and nickel base alloys”
as base material and also for Category N piping systems in elevated temperature
service / cryogenic service
1. Class 2 systems shall be designed and quality control attention as mentioned in the
mitigation plan.
D.2.3.4 Class-3 (sub-classifications as Class 3c, Class 3d)
This construction class covers all normal fluid piping systems (including sulphuric acid,
hydrochloric acid, acetic acid, sodium hypochlorite, caustic soda) with the following:
• Flange ASME Class ratings – 1500, 2500 and using “Carbon steel and C-Mn
steels with a minimum specified tensile strength ≤ 500 N/mm² (73 ksi)” as base
material.
• Flange ASME Class ratings – 150 to 900.
1. Class 3 systems shall be designed and quality-assured as mentioned in the
mitigation plan.
D.2.3.5 Class-4 (sub-classification as Class 4d)
Class 4 construction class is a “basic code design” with minimum or no special
requirements. This construction class is typically used for utilities (restricted to a
maximum design pressure of 1035 KPa (150 psi).
1. Under Class 4, “lower than usual” surveillance levels and pre-qualification efforts
may be applied, if approved, and known Manufacturers are selected.
2. Higher degree of reliance may be placed on the Supplier’s quality assurance (QA)
systems.
Page 77 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.
Revision: 01
Petroleum Development Oman LLC Effective: Dec-2021
However, in view of the criticality of these fluid services and piping, the following
additional measures shall be implemented as a precautionary safeguard for these piping
carrying “Very Toxic” fluid streams:
i. The size of branch shall be of minimum of 2”(inch).
ii. The >= DN 100 (NPS 4) for flange ASME Class ratings 300 and above shall be
qualified Flange leakage calculation.
iii. Full hydro test and Sensitive leakage test are mandatory.
Page 78 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.
Revision: 01
Petroleum Development Oman LLC Effective: Dec-2021
Construction class selection, which governs the NDT requirements and inspection levels,
shall be as per the following table.
In case of interface flange joint of HC piping DSS with GRE pipeline installed buried
without pit, all the below criteria shall be compiled:
1. Suitable material coating & wrapping requirement shall be addressed and applied in
the MSR.
2. Coating and soil back filling is required as per applicable standards & procedures.
3. Flange joint shall undergo gross leakage test (N2 @ 3-5 barg) followed by in-service
leak test as covered under SP-1208 and cross referred therein to SP-2290.
4. Flange joint will be externally coated only after successful In-service leak testing.
5. All flange management activities shall be witnessed and qualified by the PDO quality
inspector.
6. Use portable Gas monitor to detect HC near the interface area during in-service leak
test.
7. Provide Inspection program for the buried line & flange.
Page 79 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.
Revision: 01
Petroleum Development Oman LLC Effective: Dec-2021
For the tanks where isolation valves cannot be located directly on the tank shell side
nozzles due to lack of space to approach, accessibility, operability, pipe supporting and
othe reasons , the following shall be complied for locating the isolation valve away from
the tank Nozzle:
a. The piping between the nozzle and the first isolation shall be fully rated as per the piping
class.
b. Eliminating small bore branches (less than 2") which are prone to failure.
c. 100% RT for weld joints.
d. Flange management as per SP-2020 which is normal part of construction SOW.
Page 80 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.
Revision: 01
Petroleum Development Oman LLC Effective: Dec-2021
APPENDIX D SHALL [PS] STATEMENT FOR DEP 31.38.01.24 (VER.44) AND DEP 31.38.01.25 (VER.45)
Appendix D-
MANDATORY SHALL (PS) REQUIREMENTS.xlsx
Page 81 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.
Revision: 01
Petroleum Development Oman LLC Effective: Dec-2021
APPENDIX E: SKETCH OF ALUMINIUM CLADDING FOR CRA PIPE PROTECTION FROM MOLTEN ZINC (Ref. Part-I, clause 1.3.2 point 18)
Page 82 Piping – Engineering & Layout Design Requirements SP-2376 Printed 19/12/2021
The controlled version of this PCF Document resides online in CMS. Printed copies are UNCONTROLLED.