Estimate of Gyaneshwor For Septic Tank
Estimate of Gyaneshwor For Septic Tank
Estimate of Gyaneshwor For Septic Tank
2 CONCRETE WORKS
2.1 P.C.C
2.1.1 P.C.C (1:3:6) Works
formworks with 19/12 mm thick water proof ply wood & steel
adjustable props for all kinds of RCC works for foundations, columns,
shear walls, beams, slab, staircase, lintel, sill, pergola, including nails,
6.4 EXTERIOR WEATHER COAT PAINT Total Cost of Civil Works 3,055,738.32
Trench Plan
For Septic Tank 1 4.50 4.50 0.06 6.08
At Inlet 1 1.08 1.41 0.06 0.46
Manhole 2 0.92 0.92 0.06 1.63
Total= 8.16 Cu.m
5 PCC (1:3:6)
Trench Plan
For Septic Tank 1 Area 0.54 4.50 12.26
At Inlet 1 Area 0.12 1.41 0.87
Manhole 2 0.92 0.92 0.08 2.21
Total= 15.34 Cu.m
5 PCC (1:1.5:3)
For Septic Tank
For Inlet 1 0.98 1.21 0.10 0.59
Cover slab 1 4.20 4.20 0.10 8.82
slab for soak pit 1 Area 2.99 0.10 1.49
Manhole 2 0.82 0.82 0.10 2.15
Total= 13.06 Cu.m
7.2 BRICK MASONRY WORKS ( 1 : 4 c/s )
Providing and laying first class chimney fired brick one or more
brick thick wall in cement mortar 1:4 (1 cement : 4 coarse sand)
in foundation up to plinth and other specified places in all heights
and level including the cost of single or multi stage scaffolding,
soaking bricks, curing, raking joints, provision for recesses,
openings, toothing etc., all complete as per drawing,
specifications and instructions of the Engineer.
Septic Tank
baffle wall 1 1.53 3.12 23.79
Manhole
Long Wall 4 0.82 0.13 0.59 3.87
Short Wall 4 0.57 0.13 0.59 2.69
Total= 30.35 Sq.m
9.0 FORM WORKS
Supplying and laying centering, shuttering of various pattern
formworks with 19 mm thick water proof ply wood & steel
adjustable props for all kinds of RCC works for foundations,
columns, shear walls, beams, slab, staircase, lintel, sill, pergola,
including nails, propping scaffolding, staging, supporting and
bracing in proper lines and level, sealing the joints with heavy
duty brown self adhesive tape, aligning to line and levels
including Ties, PVC Spacer, Providing openings/ cutouts/
pockets, applying De-shuttering chemical, De-shuttering as
approved by the Engineer etc., complete at all levels as per
drawing, specifications and instructions of the Engineer.
Septic Tank
For Inlet 1 0.98 1.71 8.38
Cover slab 1 4.20 4.70 98.70
slab for soak pit 1 Area 2.99 14.93
Manhole (Soil and Waste)
PCC (1:3:6) 2 3.68 0.60 70.66
PCC (1:1.5:3) 2 3.28 0.10 10.50
Total= 203.16 Sqm
10.0 STEEL REINFORCEMENT
Providing and fixing in position Fe 500 steel reinforcement of
various diameter confirming to relevant IS code in R.C.C. works
including straightening, cutting, bending, binding with 20 SWG
annealed wire for tying the reinforcement bars at each junctions
(binding wire shall not be measured separately) including all
waste and cut pieces, provision for adequate numbers of spacers,
chairs, providing and placing cement mortar (1:1) cover blocks to
keep the bars in intended position at all levels all complete as per
drawings, specifications and instructions of the Engineer.
(Authorized lap length and for the bar length exceeding 10 meter
in length shall be measured for the payment).
Wall
Internal wall of internal room 4 3.74 1.71 127.91
For Baffle Wall 2 3.12 1.74 54.29
For Inlet
Short 2 0.75 0.51 3.83
Long 2 1.17 0.51 5.94
Manhole
Long Wall 4 0.82 0.59 30.96
Short Wall 4 0.57 0.59 21.52
Total= 244.45 Sq.m
Project Name : Prepartion of Detailed Architectural, Structural Design & Cost Estimate of Multi Storey Admin Building.
#REF!
#REF!
ACHHAM & SURKHET DSTRICT RATE OF CONSTRUCTION MATERIAL AT FISCAL YEAR 2076/2077
Distance to Material Rate
Transportation
Material Site From Rate Per unit Including
S.N 0.00 UNIT Cost
Market (KM) Transportation Unit Weight
Rate KM (NRs.) (NRs.)
A B C D=BXC A+D
Page 9 of 32
SHREE VIDHYA MANDIR MODEL SECONDARY SCHOOL Material Rate
Page 10 of 32
SHREE VIDHYA MANDIR MODEL SECONDARY SCHOOL Material Rate
131 Different size MS plate kg 102.00 110.00 0.03 3.52 105.52 1.00
132 Diesel litre 97.00 110.00 0.04 3.94 100.94 1.12
133 Petrol litre 106.50 110.00 0.04 3.94 110.44 1.12
134 Bhusa kg 5.00 - 0.03 - 5.00 1.00
135 Gobar kg 5.00 - 0.03 - 5.00 1.00
136 Vibrator with needle hr 100.00 110.00 - - 100.00
137 Water litre 0.30 - - - 0.30
138 Mixture mechin hr 1,100.00 110.00 - - 1,100.00
139 Nail packet 25.00 110.00 - - 25.00
140 Bamboo bundle 350.00 20.00 - - 350.00
141 Bitumen(80-100 Graded) KG - 110.00 0.03 3.52 3.52 1.00
142 5 mm thick Glass Sqm 893.75 110.00 0.40 44.00 937.75 12.50
143 4 mm thick Glass Sqm 715.00 110.00 0.32 35.20 750.20 10.00
144 Metal Doors and Window Frame R.m - 110.00 0.09 10.03 10.03 2.85
145 Door Shutter sq.m 110.00 0.30 33.16 33.16 9.42
146 Window Shutter with Glass Sq.m 110.00 0.40 44.00 44.00 12.50
Page 11 of 32
SHREE VIDHYA MANDIR MODEL SECONDARY SCHOOL Summary of Rate
Summary of Work
For Achham District
Work Group 'A' Site cleaning work
Rate For F/Y 2076-2077
S.N Description
Cutting the grass and removing of Work
the roots breaking the large muds, leveling and Page No. Rate Unit
5 cleaning the site…. Rs. 16.53 Sq.m.
Page 12 of 32
SHREE VIDHYA MANDIR MODEL SECONDARY SCHOOL Summary of Rate
278 Constructing,Painting 3x20 mm metal grills with red oxide and rubbing with abrasive materiaRs 2,478.26 Sq.m.
280 Primer paint and fabrication of different size steel angles Rs 180.16 kg
287 Making truss with black metal pipe and fixing(along with primer paint) Rs 193.96 kg
Metal Doors and Window Frame Rs 586.54 r.m
Metal Door Shutter Rs 38.13 Sq.m.
Window Shutter with Glass Rs 50.60 Sq.m.
Making Metal Railing (Staircase and Passage) Rs 2,328.36 Sq.m.
Rs 2,095.53 r.m
Rs 200.97 k.g
Work Group:-Miscellaneous works
Page 13 of 32
SHREE VIDHYA MANDIR MODEL SECONDARY SCHOOL Rate Analysis
5 Cutting the grass and removing the roots breaking the large muds, leveling and cleaning the site
A3 For Rate analysis 1 sq.m is used
S.No. Particulars Unit Quantity Rate Amount
A Labours
Unskilled md 0.02 625.00 14.38
Total - A 14.38
Total -A 14.38
B Add 15% Contractor's OHP 2.16
Total (A+B) : 16.53
Rate per sq.m = 16.53
Rate per sq.ft = 1.54
10 Earthwork excavation in soft clay, silty soil including lift upto 1.5m and disposal upto 10m distance.
B1 For Rate analysis 1 cu.m is used
S.No. Particulars Unit Quantity Rate Amount
A Labours
Unskilled md 0.70 625.00 437.50
Total - A 437.50
B Materials
Total -B
C Equipments
welder including rod 0.03 13.13
Total -C 13.13
Total (A+B+C) : 450.63
D Add 15% Contractor's OHP 67.59
Total (A+B+C+D) : 518.22
Rate per cu.m. of Earthwork in Excavation in soft soil= 518.22
Rate per cu.ft. of Earthwork in Excavation in soft soil= 14.68
Earthwork excavation in medium stone without Explosive including lift upto 1.5m and disposal upto
12 10m distance.
B1 For Rate analysis 1 cu.m is used
S.No. Particulars Unit Quantity Rate Amount
A Labours
Unskilled md 3.00 625.00 1,875.00
Total - A 1,875.00
B Materials
Total -B
C Equipments
0.03 56.25
Total -C 56.25
Total (A+B+C) : 1,931.25
D Add 15% Contractor's OHP 289.69
Total (A+B+C+D) : 2,220.94
Rate per cu.m. of Earthwork in Excavation of soil contaning medium stone = 2,220.94
Page 14 of 32
SHREE VIDHYA MANDIR MODEL SECONDARY SCHOOL Rate Analysis
Rate per cu.ft. of Earthwork in Excavation of soil contaning medium stone = 62.90
Back filling withimported soil including levelling, water spraying and compaction at 15 cm layers
B2 including transportation from 10m distance. With mud from site
For Rate analysis 1 cu.m is used
S.No. Particulars Unit Quantity Rate Amount
A Labours
Unskilled md 0.50 625.00 312.50
Total - A 312.50
B Materials
Soil cu.m 1.50 0.00
Water lit. 5.00 0.30 1.50
Total -B 1.50
C Equipments
0.00 0.00
Total -C 0.00
Total (A+B+C) : 314.00
D Add 15% Contractor's OHP 47.10
Total (A+B+C+D) : 361.10
Rate per cu.m. of Earthwork Earth Filling Works using soil from site 361.10
Rate per cu.ft. of Earthwork Earth Filling Works using soil from site 10.23
Providing and laying chimney fired brick masonry works in cement mortar ( 1 : 4 ) above
32 Ground Floor,including material and transportation up to 30m
C2 For Rate analysis 1cu.m is used
S.No. Particulars Unit Quantity Rate Amount
A Labours
Skilled md 1.50 870.00 1,305.00
Unskilled md 2.20 625.00 1,375.00
Total - A 2,680.00
B Materials
Chimney Fired Brick nos 560.00 23.55 13,185.98
Cement mt 0.10 20,320.00 2,032.00
River Sand cu.m 0.28 2,496.00 698.88
Water lit. 130.00 0.30 39.00
Total -B 15,955.86
C Equipments
0.03 18.75
Total -C 18.75
Total (A+B+C) : 18,654.61
D Add 15% Contractor's OHP 2,798.19
Total (A+B+C+D) : 21,452.81
Rate per cu.m. of Chimney Fired Brick work above Ground Floor in cement 21,452.81
mortar 1:4 =
Rate per cu.ft. of Chimney Fired Brick work above Ground Floor in cement 607.56
mortar 1:4 =
Providing and laying machine made brick masonry works with one side Fairface in cement mortar (
25 1 : 4 ) ,including material and transportation up to 30m
C1 For Rate analysis 1cu.m is used
S.No. Particulars Unit Quantity Rate Amount
A Labours
Skilled md 1.50 870.00 1,305.00
Unskilled md 2.20 625.00 1,375.00
Unskilled md 0.00 625.00 0.00
Page 15 of 32
SHREE VIDHYA MANDIR MODEL SECONDARY SCHOOL Rate Analysis
Total - A 2,680.00
B Materials
Machine Made Brick nos 530.00 23.05 12,214.59
Cement mt 0.10 20,320.00 2,032.00
River Sand cu.m 0.27 2,496.00 673.92
Water lit. 120.00 0.30 36.00
Total -B 14,956.51
C Equipments
3% 18.75
Total -C 18.75
Total (A+B+C) : 17,655.26
D Add 15% Contractor's OHP 2,648.29
Total (A+B+C+D) : 20,303.55
Rate per cu.m. of Machine made Brickwork in cement mortar 1:4 = 20,303.55
Rate per cu.ft. of Machine made Brickwork in cement mortar 1:4 = 575.01
110 mm ( Half Brick ) Thick chimney Fired brick works in cement mortar( 1 : 4 ) with hoop
iron equivalent reinforcement. (per 10 sq.m.)
Providing and laying stone masonry works in cement mortar ( 1 : 6) including block stone and
40 transportation of 10 m
C6 For Rate analysis 1cu.m is used
S.No. Particulars Unit Quantity Rate Amount
A Labours
Skilled md 1.50 870.00 1,305.00
Unskilled md 5.00 625.00 3,125.00
Total - A 4,430.00
B Materials
Cement mt 0.11 20,320.00 2,153.92
Sand cu.m 0.47 2,496.00 1,173.12
Block Stone cu.m 1.00 2,848.00 2,848.00
Bond Stone cu.m 0.10 2,848.00 284.80
Water lit. 70.00 0.30 21.00
Page 16 of 32
SHREE VIDHYA MANDIR MODEL SECONDARY SCHOOL Rate Analysis
Total -B 6,480.84
C Equipments
0.00 0.00
Total -C 0.00
Total (A+B+C) : 10,910.84
D Add 15% Contractor's OHP 1,636.63
Total (A+B+C+D) : 12,547.47
Rate per cu.m. = 12,547.47
Rate per cu.ft. = 355.35
Providing and laying Dressed stone masonry works in cement mortar ( 1 : 6) including block stone
40.1 and transportation of 10 m
C6 For Rate analysis 1cu.m is used
S.No. Particulars Unit Quantity Rate Amount
A Labours
Skilled (additional 1.5 md for Stone dressing) md 3.00 870.00 2,610.00
Unskilled md 5.00 625.00 3,125.00
Total - A 5,735.00
B Materials
Cement mt 0.11 20,320.00 2,153.92
Sand cu.m 0.47 2,496.00 1,173.12
Block Stone cu.m 1.00 2,848.00 2,848.00
Bond Stone cu.m 0.10 2,848.00 284.80
Water lit. 70.00 0.30 21.00
Total -B 6,480.84
C Equipments
0.00 0.00
Total -C 0.00
Total (A+B+C) : 12,215.84
D Add 15% Contractor's OHP 1,832.38
Total (A+B+C+D) : 14,048.22
Rate per cu.m. = 14,048.22
Rate per cu.ft. = 397.85
Page 17 of 32
SHREE VIDHYA MANDIR MODEL SECONDARY SCHOOL Rate Analysis
Providing and Laying P.C.C. (1:3:6) in foundation, under floor, etc. as lean/levelling including
47 transportation up to 30m
D1 For Rate analysis 1 cu.m is used
S.No. Particulars Unit Quantity Rate Amount
A Labours
Skilled md 1.00 870.00 870.00
Unskilled md 4.00 625.00 2,500.00
Total - A 3,370.00
B Materials
Cement m.t 0.22 20,320.00 4,470.40
Aggregate 20 mm - 10 mm cu.m 0.65 2,424.00 1,575.60
Aggregate 10 mm & down cu.m 0.24 2,424.00 581.76
Sand cu.m 0.47 2,496.00 1,173.12
Water lit. 120.00 0.30 36.00
Total -B 7,836.88
C Equipments
0.00 0.00
Total -C 0.00
Total (A+B+C) : 11,206.88
D Add 15% Contractor's OHP 1,681.03
Total (A+B+C+D) : 12,887.91
Rate per cu.m. of P.C.C (1:3:6) = 12,887.91
Rate per cu.ft. of P.C.C (1:3:6) = 364.99
Providing and Laying P.C.C. (1:2:4) in foundation, under floor, etc. as lean/levelling including
48 transportation up to 30m
D1 For Rate analysis 1 cu.m is used
S.No. Particulars Unit Quantity Rate Amount
A Labours
Skilled md 1.00 870.00 870.00
Unskilled md 4.00 625.00 2,500.00
Total - A 3,370.00
B Materials
Cement m.t 0.32 20,320.00 6,502.40
Aggregate 20 mm cu.m 0.52 2,424.00 1,260.48
Aggregate 10 mm cu.m 0.22 2,424.00 533.28
Aggregate <10 mm & down cu.m 0.11 2,424.00 266.64
Sand cu.m 0.45 2,496.00 1,110.72
Water lit. 150.00 0.30 45.00
Total -B 9,718.52
C Equipments
0.00 0.00
Total -C 0.00
Total (A+B+C) : 13,088.52
D Add 15% Contractor's OHP 1,963.28
Total (A+B+C+D) : 15,051.80
Page 18 of 32
SHREE VIDHYA MANDIR MODEL SECONDARY SCHOOL Rate Analysis
Providing & laying PCC for RCC of grade M20(1:1.5:3) in Superstructure, deck slab and beam
50 including Transportation up to 30m.
D2 For Rate analysis 1 cu.m is used
S.No. Particulars Unit Quantity Rate Amount
A Labours
Skilled md 0.80 870.00 696.00
Unskilled md 7.00 625.00 4,375.00
Total - A 5,071.00
B Materials
Cement m.t 0.40 20,320.00 8,128.00
Aggregate 20 mm cu.m 0.57 2,424.00 1,381.68
Aggregate 10 mm cu.m 0.29 2,424.00 702.96
Sand cu.m 0.43 2,496.00 1,060.80
Water lit. 200.00 0.30 60.00
Total -B 11,333.44
C Equipments
0.00 0.00
Total -C 0.00
Total (A+B+C) : 16,404.44
D Add 15% Contractor's OHP 2,460.67
Total (A+B+C+D) : 18,865.11
Rate per cu.m. of P.C.C for R.C.C M20 (1:1.5:3) = 18,865.11
Rate per cu.ft. of P.C.C for R.C.C M20 (1:1.5:3) = 534.27
Providing,bending and placing properly according to drawing and binding of steel reinforcment
59 along witht transpotation up to 30m
D9 For rate analysis 1 mt is taken
S.No. Particulars Unit Quantity Rate Amount
A Labours
Skilled md 12.00 870.00 10,440.00
Unskilled md 12.00 625.00 7,500.00
Total - A 17,940.00
B Materials
TMT rod Mt 1.05 94,520.00 99,246.00
GI tying wire Kg 10.00 118.52 1,185.20
Total -B 100,431.20
Total (A+B) : 118,371.20
C Add 15% Contractor's OHP 17,755.68
Total (A+B+C) : 136,126.88
Rate per m.t= 136,126.88
62
E6 Plywood formworks with steel adjustable pipe props for floor and slab
For rate analysis 100 sqm is taken
S.No. Particulars Unit Quantity Rate Amount
A Labours
Skilled md 17.20 870.00 14,964.00
Unskilled md 25.70 625.00 16,062.50
Total - A 31,026.50
B Materials
Page 19 of 32
SHREE VIDHYA MANDIR MODEL SECONDARY SCHOOL Rate Analysis
65
E5 19mm plywood formworks for beam including materials and removing with transpotation upto 30m
For rate analysis 10 sqm is taken
S.No. Particulars Unit Quantity Rate Amount
A Labours
Skilled md 2.67 870.00 2,322.90
Unskilled md 4.00 625.00 2,500.00
Total - A 4,822.90
B Materials
Ply board sqm 1.65 1,733.44 2,860.18
Local wood cum 0.04 149,442.00 5,828.24
Steel prop No. 0.40 24.64 9.86
Nail Kg 2.50 133.52 333.80
Total -B 9,032.07
Total (A+B) : 13,854.97
C Add 15% Contractor's OHP 2,078.25
Total (A+B+C) : 15,933.22
Rate per sq.m= 1,593.32
Rate per sq.ft= 148.08
Page 20 of 32
SHREE VIDHYA MANDIR MODEL SECONDARY SCHOOL Rate Analysis
Total -B 4,387.78
Total (A+B) : 7,232.78
C Add 15% Contractor's OHP 1,084.92
Total (A+B+C) : 8,317.70
Rate per sq.m= 831.77
Rate per sq.ft= 77.30
120 38 mm (1½" ) thk. Cement Concrete Flooring (1:2:4) with Neat Cement Finishing
11-1 (per
For 10 Analysis
Rate sq.m.) 10 sqm. is used
S.No.. Particulars Unit Quantity Rate Amount
A Labours
Skilled md 1.25 870.00 1,087.50
Unskilled md 2.00 625.00 1,250.00
Total - A 2,337.50
B Materials
cement MT 0.13 20,320.00 2,641.60
sand cu 0.18 2,496.00 449.28
12mm aggregate cu 0.36 2,424.00 872.64
Total -B 3,963.52
C Equipments
Total -C
Total (A+B+C) : 6,301.02
D Add 15% Contractor's OHP 945.15
Total (A+B+C+D) : 7,246.17
Rate per sq.m 724.62
Rate per sq.ft 67.34
Page 21 of 32
SHREE VIDHYA MANDIR MODEL SECONDARY SCHOOL Rate Analysis
133 Flooring of 25mm -37.5mm thick stone( flagstone) with 1:4 cement sand mortar.
11-9 For Rate Analysis 10 sqm.
H9
S.No.. Particulars Unit Quantity Rate Amount
A Labours
Skilled md 2.00 870.00 1,740.00
Unskilled md 4.50 625.00 2,812.50
Total - A 4,552.50
B Materials
37.5mm stone sqm 11.00 1,359.30 14,952.31
cement MT 0.06 20,320.00 1,219.20
sand from river cum 0.17 2,496.00 411.84
Total -B 16,583.35
C Equipments
Total -C
Total (A+B+C) : 21,135.85
D Add 15% Contractor's OHP 3,170.38
Total (A+B+C+D) : 24,306.23
Rate per sq.m 2,430.62
Rate per sq.ft 225.89
169 12.5mm thick plastering of cement sand mortar of ratio 1:4 on ceiling.
I1 Rate analysis per 100 Sqm
Total -B 14,576.32
C Equipments
0.00
Total -C 0.00
Total (A+B+C) : 40,126.32
D Add 15% Contractor's OHP 6,018.95
Total (A+B+C+D) : 46,145.27
Rate per Sq.m. 461.45
Rate per Sq.ft. 42.89
Page 22 of 32
SHREE VIDHYA MANDIR MODEL SECONDARY SCHOOL Rate Analysis
Total -B 17,448.00
C Equipments
0.00
Total -C 0.00
Total (A+B+C) : 41,503.00
D Add 15% Contractor's OHP 6,225.45
Total (A+B+C+D) : 47,728.45
Rate per Sq.m. 477.28
Rate per Sq.ft. 44.36
180 Flush Pointing on Brick wall by cement sand mortar of ratio 1:2
I8 Rate analysis per 100 Sqm
Total -C
Total (A+B+C) : 27,163.28
D Add 15% Contractor's OHP 4,074.49
Total (A+B+C+D) : 31,237.77
Rate per sq.m 312.38
Page 23 of 32
SHREE VIDHYA MANDIR MODEL SECONDARY SCHOOL Rate Analysis
199 One coat ready enamel painting (including one coat primer)
J4 Rate analysis per 100 Sqm
200 Two coat ready enamel painting (including one coat primer)
J4 Rate analysis per 100 Sqm
Page 24 of 32
SHREE VIDHYA MANDIR MODEL SECONDARY SCHOOL Rate Analysis
206
J26 Two coats weather coat (apex or similar) with one coat primer painting work
For rate analysis 100sqm is taken
S.No. Particulars Unit Quantity Rate Amount
A Labours
Skilled md 5.80 870.00 5,046.00
Unskilled md 5.80 625.00 3,625.00
Total - A 8,671.00
B Materials
Astar litre 8.00 378.94 3,031.54
Weather coat litre 16.00 895.94 14,335.08
Total -B 17,366.62
Total (A+B) : 26,037.62
C Add 15% Contractor's OHP 3,905.64
Total (A+B+C) : 29,943.26
Rate per s.qm= 299.43
Rate per s.ft= 27.83
227
J21 Double coating aluminium paint excluding astar
For rate analysis 100sqm is taken
S.No. Particulars Unit Quantity Rate Amount
A Labours
Skilled md 7.75 870.00 6,742.50
Unskilled md 7.75 625.00 4,843.75
Total - A 11,586.25
B Materials
Ready made aluminium paint litre 10.76 703.94 7,574.42
Abrasive 4.00 15.00 60.00
7,634.42
Total (A+B) : 19,220.67
C Add 15% Contractor's OHP 2,883.10
Total (A+B+C) : 22,103.77
Rate per s.qm= 221.04
Rate per s.ft= 20.54
238
Providing and applying Dustban/Permise chemicals for Anti Termite Treatment all complete
J29
For rate analysis 10sqm is taken
S.No. Particulars Unit Quantity Rate Amount
A Materials
Page 25 of 32
SHREE VIDHYA MANDIR MODEL SECONDARY SCHOOL Rate Analysis
245
K4 Laying one layer 500 gauge polyethene sheet
For rate analysis 10sqm is taken
S.No. Particulars Unit Quantity Rate Amount
A Labours
Skilled md 0.60 870.00 522.00
Unskilled md 0.60 625.00 375.00
Total - A 897.00
B Materials
Polyethene sheet 500 gauge sqm 11.00 102.36 1,125.94
1,125.94
Total (A+B) : 2,022.94
C Add 15% Contractor's OHP 303.44
Total (A+B+C) : 2,326.38
Rate per s.qm= 232.64
Rate per s.ft= 21.62
Constructing,Painting 3x20 mm metal grills with red oxide and rubbing with abrasive material and also
278 fixing
M1 For Rate analysis 10sq.m is taken
S.No. Particulars Unit Quantity Rate Amount
A Materials
3x20mm metal grill construction
and fixing sq.m 10.00 2,155.01 21,550.13
Total 21,550.13
B Add 15% Contractor's OHP 3,232.52
Total (A+B) : 24,782.65
Rate per sq.m 2,478.26
Rate per sq.ft 230.32
Note: 1.00sq.m=16.14kg
Page 26 of 32
SHREE VIDHYA MANDIR MODEL SECONDARY SCHOOL Rate Analysis
Total - A 10,440.00
B Materials
Cement Board Sq.m 27.00 10.56 285.12
Fixture R.m 15.40 450.00 6,930.00
Joint Filling R.m 36.00 125.00 4,500.00
Total - B 11,715.12
C Equipment/others
LS 150.00
Total - C 150.00
Total (A+B+C) : 22,305.12
D Add 15% Contractor's OHP 3,345.77
Total (A+B+C+D) : 25,650.89
Rate per sq.m. of V-board = 2,137.57
Page 27 of 32
SHREE VIDHYA MANDIR MODEL SECONDARY SCHOOL Rate Analysis
A Labours
Skilled md 40.00 870.00 34,800.00
Unskilled md 70.00 625.00 43,750.00
Total - A 78,550.00
B Materials
Cement Board sq.m. 109.00 10.56 1,151.04
Ceiling Sections rm. 242.00 90.00 21,780.00
Perimeter Channel rm. 42.00 55.00 2,310.00
Intermediate Channel rm. 91.50 90.00 8,235.00
Strap Hanger nos. 11.00 75.00 825.00
Connection Clips nos. 190.00 12.00 2,280.00
6 mm dia. Nuts & bolts nos. 22.00 5.00 110.00
Soffit Cleats nos. 75.00 6.50 487.50
Joint Filler kg. 24.00 50.00 1,200.00
Joint Finisher kg. 35.00 71.00 2,485.00
Joint Tape roll 1.50 280.00 420.00
12 mm dia. 40 mm long with 6mm
dia. Bolt dash fastener nos. 75.00 15.00 1,125.00
Total - B 42,408.54
C Equipment/others
256
L1
Demolition of wall on mud and disposal of waste at a distance of 10m
For rate analysis 1cu.m is taken
S.No. Particulars Unit Quantity Rate Amount
A Labours
Unskilled No. 1.06 625.00 662.50
Total 662.50
B Add 15% Contractor's OHP 99.38
Total (A+B) 761.88
Rate per cu.m= 761.88
Rate per s.ft= 21.58
257
L2
Demolition of wall on cement and disposal of waste at a distance of 10m
For rate analysis 1cu.m is taken
S.No. Particulars Unit Quantity Rate Amount
A Labours
Unskilled No. 2.12 625.00 1,325.00
Total 1,325.00
B Add 15% Contractor's OHP 198.75
Total (A+B) 1,523.75
Rate per cu.m= 1,523.75
Page 28 of 32
SHREE VIDHYA MANDIR MODEL SECONDARY SCHOOL Rate Analysis
258
L3
Demolition of RCC and RBC works and disposal of waste at a distance of 10m
For rate analysis 1cu.m is taken
S.No. Particulars Unit Quantity Rate Amount
A Labours
Unskilled No. 11.00 625.00 6,875.00
Total 6,875.00
B Add 15% Contractor's OHP 1,031.25
Total (A+B) 7,906.25
Rate per cu.m= 7,906.25
Rate per s.ft= 223.91
Dismantling of completely damaged building and disposing the debris including Transportation. For Rate
Analysis 100 sq.m is used
S.No. Particulars Unit Quantity Rate Amount
A Labours
Total - A 0.00
B Materials
Stone Masonry cu.m 47.70 761.88 36,341.44
Slab Dismanteling cu.m 10.00 3,953.13 39,531.25
Transportation cu.m 57.70 476.69 27,504.72
Total -B 103,377.41
C Equipments
0.00
Total -C 0.00
Total (A+B+C) : 103,377.41
D Add 15% Contractor's OHP 15,506.61
Total (A+B+C+D) : 118,884.02
Dismantling of Damaged Building per sq.m 1,188.84
Dismantling of Damaged Building per sq.ft 110.49
Flag Pole
S.No. Particulars Unit Quantity Rate Amount
A Labours
1.00 LS 2,000.00 2,000.00
Total - A 2,000.00
B Materials
75 mm GI pipes kg 40.88 105.52 4,313.70
Top ornamental Portion Nis 1.00 800.00 800.00
Hook, Pully & ropes LS 1.00 1,500.00 1,500.00
Total -B 6,613.70
C Equipments
0.00
Total -C 0.00
Total (A+B+C) : 8,613.70
D Add 15% Contractor's OHP 1,292.05
Total (A+B+C+D) : 9,905.75
Rate of Flag Pole per Nos. 9,905.75
G1 Salwood Door and Window for choukosh (frame) Unit: 1 cu.m
Page 29 of 32
SHREE VIDHYA MANDIR MODEL SECONDARY SCHOOL Rate Analysis
Supplying and fitting salwood doors,special (Seasoned and Poisoned treated one side teak) with all necessary
G4 Unit:sqm
hardware all complete.
72. 38 mm thick Sisam/Salwood solid pannel shutter (size 1.07m x 1.982m = 2.114 sq.m.) Rate analysis for 2.114 sq.m. / 22.7255 sft.
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 10.000 Nos. 870.00 8700.00
b) Coolies 1.000 Nos. 625.00 625.00 9325.00
Materials Salwood 0.084 Cub M 149442.00 12553.13
100mm hinges 6.000 Nos. 40.35 242.11
150mm tower bolt 1.000 No 86.06 86.06
300mm tower bolt 1.000 No 112.11 112.11
300mm locking set 1.000 No 363.52 363.52
Handles Aluminum 2.000 Nos. 88.52 177.04
Screw nails 1.000 LS 100.00 100.00 13633.97
Actual rate 22958.97
Rate 15% contractor's overhead 3443.85
Per sqm. Per sft. Total 26402.81
12489.50 1160.95
74 . Openable glazed shutter with 38 x 75mm Salwood frame &5 mm thick glass
(for rate analysis 1.829 x 1.22 = 2.23 sq m / 23.97 sft. )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 9.000 Nos. 870.00 7830.00
b) Coolies 0.900 Nos. 625.00 562.50 8392.50
Materials salwood 0.049 Cub M 149442.00 7322.66
Page 30 of 32
SHREE VIDHYA MANDIR MODEL SECONDARY SCHOOL Rate Analysis
81 . Fixed glzed shutter with 5 mm thick glass (for 1 sq.m 10.76 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 0.060 Nos. 870.00 52.20
b) Coolies 0.006 Nos. 625.00 3.75 55.95
Materials 5 mm thick glass 1.000 S.m. 937.75 937.75
wooden listy 4.050 Rm 45.00 182.25
Screw nails 1.000 LS 100.00 100.00 1220.00
Actual rate 1275.95
Rate Rate 15% contractor's overhead 191.39
Per sqm. Per sft. Total 1467.34
1467.34 136.37
Providing and laying 6mm porcelain glazed tiles on walls and floor of approved colored laid with cement sand
23 mortar(1:4) finished with white cement including polishing all complete as per specification and instruction of site Unit: 10 sq m
engineer
Providing and laying 6mm porcelain non glazed tiles on walls and floor of approved colored laid with cement sand
24 mortar(1:4) finished with white cement including polishing all complete as per specification and instruction of site Unit: 10 sq m
engineer
Page 31 of 32
SHREE VIDHYA MANDIR MODEL SECONDARY SCHOOL Rate Analysis
25 Filling with sand, water spraying and compaction including transportation from 10m distance. Unit: 1 m3
S. N. Description Unit Quantity Rate (NRs.) Amount (NRs.) Remarks
A. Labour:
B. Material:
Page 32 of 32