This document provides an interim guideline advisory to supplement FEMA-267 regarding the evaluation, repair, modification, and design of welded steel moment frame structures. It summarizes the findings of continuing research conducted by the SAC Joint Venture on improving the seismic performance of these structures. This advisory supersedes the previous Interim Guidelines Advisory No. 1 and incorporates additional data from the SAC Phase 2 research program and other independent studies. Final design recommendations are scheduled for publication in early 2000. Users are cautioned that research is ongoing and the recommendations may need modification as understanding improves.

Uploaded by

xcv
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
51 views15 pages

Intro2 PDF

This document provides an interim guideline advisory to supplement FEMA-267 regarding the evaluation, repair, modification, and design of welded steel moment frame structures. It summarizes the findings of continuing research conducted by the SAC Joint Venture on improving the seismic performance of these structures. This advisory supersedes the previous Interim Guidelines Advisory No. 1 and incorporates additional data from the SAC Phase 2 research program and other independent studies. Final design recommendations are scheduled for publication in early 2000. Users are cautioned that research is ongoing and the recommendations may need modification as understanding improves.

Uploaded by

xcv
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 15

FEDERAL EMERGENCY MANAGEMENT AGENCY FEMA 267b / June, 1999

Interim Guidelines
Advisory No. 2
Supplement to FEMA-267
Program to Reduce the Earthquake Hazards of
Steel Moment Frame Structures
INTERIM GUIDELINES ADVISORY NO. 2
Supplement to FEMA-267 Interim Guidelines:
Evaluation, Repair, Modification and Design of
Welded Steel Moment Frame Structures
Report No. SAC-99-01

SAC Joint Venture


a partnership of:
Structural Engineers Association of California (SEAOC)
Applied Technology Council (ATC)
California Universities for Research in Earthquake Engineering (CUREe)

Prepared for SAC Joint Venture Partnership by


Guidelines Development Committee
Ronald O. Hamburger, Chair
John D. Hooper Thomas Sabol
Robert E. Shaw C. Mark Saunders
Lawrence D. Reaveley Raymond H.R. Tide

Project Oversight Committee


William J. Hall, Chair
John N. Barsom Richard Holguin
Shirin Ader Nestor Iwankiw
John Barsom Roy G. Johnston
Roger Ferch Len Joseph
Theodore V. Galambos Duane K. Miller
John Gross John Theiss
James R. Harris John H. Wiggins

SAC Project Management Committee


SEAOC: William T. Holmes Program Manager: Stephen A. Mahin
ATC: Christoper Rojahn Investigations Director: James O. Malley
CUREe: Robin Shepherd Product Director: Ronald O. Hamburger
Federal Emergency Management Agency
Project Officer: Michael Mahoney Technical Advisor: Robert D. Hanson

SAC Joint Venture


555 University Avenue, Suite 126
Sacramento, California 95825
916-427-3647

June, 1999

i
THE SAC JOINT VENTURE
SAC is a joint venture of the Structural Engineers Association of California (SEAOC), the Applied Technology Council
(ATC), and California Universities for Research in Earthquake Engineering (CUREe,) formed specifically to address both
immediate and long-term needs related to solving problems of the Welded Steel Moment Frame (WSMF) connection that
became apparent as a result of the 1994 Northridge earthquake. SEAOC is a professional organization composed of
more than 3,000 practicing structural engineers in California. The volunteer efforts of SEAOC’s members on various
technical committees have been instrumental in the development of the earthquake design provisions contained in the
Uniform Building Code as well as the National Earthquake Hazards Reduction Program (NEHRP) Provisions for Seismic
Regulations for New Buildings. The Applied Technology Council is a non-profit organization founded specifically to
perform problem-focused research related to structural engineering and to bridge the gap between civil engineering
research and engineering practice. It has developed a number of publications of national significance including ATC 3-
06, which serves as the basis for the NEHRP Recommended Provisions. CUREe is a nonprofit organization formed to
promote and conduct research and educational activities related to earthquake hazard mitigation. CUREe’s eight
institutional members are: the California Institute of Technology, Stanford University, the University of California at
Berkeley, the University of California at Davis, the University of California at Irvine, the University of California at Los
Angeles, the University of California at San Diego, and the University of Southern California. This collection of
university earthquake research laboratory, library, computer and faculty resources is among the most extensive in the
United States. The SAC Joint Venture allows these three organizations to combine their extensive and unique resources,
augmented by subcontractor universities and organizations from around the nation, into an integrated team of
practitioners and researchers, uniquely qualified to solve problems related to the seismic performance of WSMF
structures.

DISCLAIMER

The purpose of this document is to serve as a supplement to the FEMA-267 publication Interim Guidelines: Evaluation,
Repair, Modification and Design of Welded Steel Moment Frame Structures. This Advisory, which is intended to be used
in conjunction with FEMA-267, supercedes and entirely replaces Interim Guidelines Advisory No. 1 (FEMA 267a).
FEMA-267 was published to provide engineers and building officials with guidance on engineering procedures for
evaluation, repair, modification and design of welded steel moment frame structures, to reduce the risks associated with
earthquake-induced damage. The recommendations were developed by practicing engineers based on professional
judgment and experience and a preliminary program of laboratory, field and analytical research. This preliminary
research, known as the SAC Phase 1 program, commenced in November, 1994 and continued through the publication of
the Interim Guidelines document. This Interim Guidelines Advisory No. 2, which updates and replaces Interim
Guidelines Advisory No. 1, is based on supplementary data developed under a program of continuing research, known as
the SAC Phase 2 program, as well as findings developed by other, independent researchers. Final design
recommendations, superceding both FEMA-267 and this document are scheduled for publication in early 2000.
Independent review and guidance in the production of both the FEMA-267, Interim Guidelines and the advisories was
provided by a project oversight panel comprised of experts from industry, practice and academia. Users are cautioned that
research into the behavior of these structures is continuing. Interpretation of the results of this research may invalidate or
suggest the need for modification of recommendations contained herein. No warranty is offered with regard to the
recommendations contained herein, either by the Federal Emergency Management Agency, the SAC Joint
Venture, the individual joint venture partners, their directors, members or employees. These organizations and
their employees do not assume any legal liability or responsibility for the accuracy, completeness, or usefulness of
any of the information, products or processes included in this publication. The reader is cautioned to carefully
review the material presented herein. Such information must be used together with sound engineering judgment when
applied to specific engineering projects. This Interim Guidelines Advisory has been prepared by the SAC Joint Venture
with funding provided by the Federal Emergency Management Agency, under contract number EMW-95-C-4770. The
SAC Joint Venture gratefully acknowledges the support of FEMA and the leadership of Michael Mahoney and Robert
Hanson, Project Officer and Technical Advisor, respectively. The SAC Joint Venture also wishes to express its gratitude
to the large numbers of engineers, building officials, organizations and firms that provided substantial efforts, materials,
and advice and who have contributed significantly to the progress of the Phase 2 effort.

ii
Interim Guidelines Advisory No. 2 SAC 99-01

PREFACE

Purpose
The purpose of the Interim Guidelines Advisory series is to provide engineers and building
officials with timely information and guidance resulting from ongoing problem-focused studies of
the seismic behavior of moment-resisting steel frame structures. These advisories are intended to
be supplements to FEMA-267 Interim Guidelines: Evaluation, Repair, Modification and Design
of Welded Steel Moment Frame Structures first published in August 1995.

The first Interim Guidelines Advisory, FEMA-267a, was published in January 1997. The
specific revisions and updates to the Interim Guidelines contained in FEMA-267a were developed
based on input obtained from a group of engineers and building officials actively engaged in the
use of the FEMA-267 document, in the period since its initial publication in August 1995. That
input was obtained during a workshop held in August 1996, in Los Angeles, California.

This second Interim Guidelines Advisory has been prepared as a series of updates and
revisions both to the FEMA-267, Interim Guidelines which it supplements and to the FEMA-
267a, Interim Guidelines Advisory publication, which it supercedes. The material contained in
this Interim Guidelines Advisory No. 2 is based on the extensive analytical and laboratory
research that has been conducted by the SAC Joint Venture and other researchers during the
intervening period, along with recent developments in the steel construction industry. The
material contained in this Advisory has been formatted to match that contained in the original
Interim Guidelines, to permit the user to insert this material directly into appropriate sections of
that document. This Advisory is not intended to serve as a self-contained text and should not be
used as such. It does, however, completely replace the material contained in FEMA-267a.

A new set of recommendations for the design, analysis, evaluation repair, retrofit and
construction of moment-resisting steel frames is currently being prepared as part of the Phase 2
Program to Reduce Earthquake Hazards in Steel Moment Frame Structures. These new Seismic
Design Criteria, which are anticipated to be completed early in the year 2000, will replace in their
entirety the FEMA-267 Interim Guidelines and this Interim Guidelines Advisory No. 2.

Background
The Northridge earthquake of January 17, 1994, dramatically demonstrated that the
prequalified, welded beam-to-column moment connection commonly used in the construction of
welded steel moment resisting frames (WSMFs) in the period 1965-1994 was much more
susceptible to damage than previously thought. The stability of moment frame structures in
earthquakes is dependent on the capacity of the beam-column connection to remain intact and to
resist tendencies of the beams and columns to rotate with respect to each other under the
influence of lateral deflection of the structure. The prequalified connections were believed to be
ductile and capable of withstanding the repeated cycles of large inelastic deformation explicitly
relied upon in the building code provisions for the design of these structures. Although many
affected connections were not damaged, a wide spectrum of unexpected brittle connection

iii
Interim Guidelines Advisory No. 2 SAC 99-01

fractures did occur, ranging from isolated fractures through or adjacent to the welds of beam
flanges to columns, to large fractures extending across the full depth of the columns. At the time
this damage was discovered, the structural steel industry and engineering profession had little
understanding of the specific causes of this damage, the implications of this damage for building
safety, or even if reliable methods existed to repair the damage which had been discovered.
Although the connection failures did not result in any casualties or collapses, and many WSMF
buildings were not damaged, the incidence of damage was sufficiently pervasive in regions of
strong ground motion to cause wide-spread concern by structural engineers and building officials
with regard to the safety of these structures in future earthquakes.

In response to these concerns, the Federal Emergency Management Agency (FEMA) entered
into a cooperative agreement with the SAC Joint Venture to perform problem-focused study of
the seismic performance of welded steel moment connections and to develop interim
recommendations for professional practice. Specifically, these recommendations were intended to
address the inspection of earthquake affected buildings to determine if they had sustained
significant damage; the repair of damaged buildings; the upgrade of existing buildings to improve
their probable future performance; and the design of new structures to provide more reliable
seismic performance. Within weeks of receipt of notification of FEMA’s intent to enter into this
agreement, the SAC Joint Venture published a series of two design advisories (SAC, 1994a; SAC,
1994b). These design advisories presented a series of papers, prepared by engineers and
researchers engaged in the investigation of the damaged structures and presenting individual
opinions as to the causes of the damage, potential methods of repair, and possible designs for
more reliable connections in the future. In February 1995, Design Advisory No. 3 (SAC, 1995a)
was published. This third advisory presented a synthesis of the data presented in the earlier
publications, together with the preliminary recommendations developed in an industry workshop,
attended by more than 50 practicing engineers, industry representatives and researchers, on
methods of inspecting, repairing and designing WSMF structures. At the time this third advisory
was published, significant disagreement remained within the industry and the profession as to the
specific causes of the damage observed and appropriate methods of repair given that the damage
had occurred. Consequently, the preliminary recommendations were presented as a series of issue
statements, followed by the consensus opinions of the workshop attendees, where consensus
existed, and by majority and dissenting opinions where such consensus could not be formed.

During the first half of 1995, an intensive program of research was conducted to more
definitively explore the pertinent issues. This research included literature surveys, data collection
on affected structures, statistical evaluation of the collected data, analytical studies of damaged
and undamaged buildings and laboratory testing of a series of full-scale beam-column assemblies
representing typical pre-Northridge design and construction practice as well as various repair,
upgrade and alternative design details. The findings of this research (SAC 1995c, SAC 1995d,
SAC 1995e, SAC 1995f, SAC 1995g, SAC 1996) formed the basis for the development of FEMA
267 - Interim Guidelines: Evaluation, Repair, Modification, and Design of Welded Steel Moment
Frame Structures (SAC, 1995b), which was published in August, 1995. FEMA 267 provided the
first definite, albeit interim, recommendations for practice, following the discovery of connection
damage in the Northridge earthquake.

iv
Interim Guidelines Advisory No. 2 SAC 99-01

As a result of these and supplemental studies conducted by the SAC Joint Venture, as well as
independent research conducted by others, it is now known that a large number of factors
contributed to the damage sustained by steel frame buildings in the Northridge earthquake. These
included:

• design practice that favored the use of relatively few frame bays to resist lateral
seismic demands, resulting in much larger member and connection geometries than had
previously been tested;

• standard detailing practice which resulted in the development of large inelastic


demands at the beam to column connections;

• detailing practice that often resulted in large stress concentrations in the beam-column
connection, as well as inherent stress risers and notches in zones of high stress;

• the common use of welding procedures that resulted in deposition of low toughness
weld metal in the critical beam flange to column flange joints;

• relatively poor levels of quality control and assurance in the construction process,
resulting in welded joints that did not conform to the applicable quality standards;

• excessively weak and flexible column panel zones that resulted in large secondary
stresses in the beam flange to column flange joints;

• large variations in the strengths of rolled shape members relative to specified values;

• an inherent inability of material to yield under conditions of high tri-axial restraint such
as exist at the center of the beam flange to column flange joints.

With the identification of these factors it was possible for FEMA 267 to present a
recommended methodology for the design and construction of moment-resisting steel frames to
provide connections capable of more reliable seismic performance. This methodology included
the following recommendations:

• proportion the beam-column connection such that inelastic behavior occurs at a


distance remote from the column face, minimizing demands on the highly restrained
column material and the welded joints;

• specify weld filler metals with rated toughness values for critical welded joints;

• detail connections to incorporate beam flange continuity plates, to minimize stress


concentrations;

• remove backing bars and weld tabs from critical joints to minimize the potential for
stress risers and notch effects and also to improve the reliability with which flaws at
the weld root can be observed and repaired;

v
Interim Guidelines Advisory No. 2 SAC 99-01

• qualify connection configurations through a program of full-scale inelastic testing of


representative beam-column assemblies, fabricated in the same manner as is proposed
for use in the structure;

• increased participation of the design professional in the specification and surveillance


of welding procedures and the quality assurance process for welded joints.

In the time since the publication of FEMA-267, SAC has continued, under funding provided
by FEMA, to perform problem-focused study of the performance of moment resisting connections
of various configurations. This work, which is generally referred to as the SAC Phase II program,
includes detailed analytical evaluations of buildings and connections, parametric studies into the
effects on connection performance of connection configuration, base and weld metal strength,
toughness and ductility, as well as additional large scale testing of connection assemblies. The
intent of this study is to support development of final guidelines that will present more reliable and
economical performance-based methods for:

• identification of damaged structures following an earthquake and determination of the


extent, severity and consequences of such damage;

• design of effective repairs for damaged structures;

• identification of existing structures that are vulnerable to unacceptable levels of


damage in future earthquakes;

• design of structural upgrades for existing vulnerable structures;

• design of new structures that are suitably resistant to earthquake induced damage;

• procedures for construction quality assurance that are consistent with the levels of
reliability intended by the design criteria.

This Phase II program of research, which is being conducted by the SAC Joint Venture in
parallel and coordination with work by other researchers, is anticipated to be complete in late
1999. It is the intent of FEMA and the SAC Joint Venture to ensure that pertinent information
and findings from this program are made available to the user community in a timely manner
through the publication of this series of design advisory documents. This Interim Guidelines
Advisory No. 2 is the second such publication.

Format
This Advisory has been prepared as a series of updates and revisions to the FEMA-267,
Interim Guidelines publication. It has been formatted in a manner intended to facilitate the
identification of changes to the original FEMA-267 text. Only those sections of FEMA-267 that
are being revised at this time are included. Other sections of FEMA-267 remain in effect as the
current best recommendations of the SAC Joint Venture. This Advisory replaces the earlier
Interim Guidelines Advisory, FEMA-267a, in its entirety.

vi
Interim Guidelines Advisory No. 2 SAC 99-01

To facilitate coordination of this Advisory with FEMA-267, the existing system of chapter and
section numbering has been retained. The Table of Contents lists all sections of the chapters
being revised, including those sections for which no revisions are included. Within the body of
this document, a section heading is provided for each section of the chapter; however, if no
revision to the section is currently being made, this is indicated immediately beneath the section
heading.

To facilitate reading of this document, where a revision is made to a section in FEMA 267, the
entire text of that section is included herein. Where existing text from FEMA-267 is reproduced
in this document, without edit, it is shown in normal face type for guidelines, and in italicized type
for commentary. Where existing text is being deleted, this is shown in strike through format. A
single strikethrough indicates text deleted in the first advisory, FEMA-267a. A double
strikethrough indicates text deleted in this current advisory. New text is shown in underline
format. A single underline identifies text added in the first advisory, FEMA-267a. A double
underline identifies text added in this current advisory. When a modification has been made to a
portion of text, relative to FEMA-267, this will also be noted by the presence of a vertical line at
the outside margin of the page. The following two paragraphs illustrate these conventions for
guideline and commentary text, respectively.

This sentence is representative of typical guideline text, that has been reprinted
from FEMA-267 without change.This sentence, is representative of the way in
which text being deleted from FEMA-267 in this Interim Guidelines Advisory is
identified. This sentence illustrates the way in which text deleted from FEMA-267
in the previous Interim Guidelines Advisory is identified. This sentence illustrates
the way in which text being added to FEMA-267 in this Interim Guidelines
Advisory is identified.This sentence illustrates the way in which text added to
FEMA-267 in the previous Interim Guidelines Advisory is identified.

Commentary: This sentence is representative of typical commentary text, that has


been reprinted from FEMA-267 without change. This sentence is representative of
the way in which commentary text being deleted from FEMA-267 in this Interim
Guidelines Advisory is identified. However, this sentence, is representative of the
way in which text being deleted from FEMA-267 commentary in the previous
Advisory is identified. This sentence indicates the way in which text added to the
FEMA-267 commentary in this Advisory is shown.This final sentence illustrates
the way in which text added in previous advisory, FEMA-267a, is identified.

Intent
This Interim Guidelines Advisory, together with the Interim Guidelines they modify, are primarily
intended for two different groups of potential users:

a) Engineers engaged in evaluation, repair, and upgrade of existing WSMF buildings and in
the design of new WSMF buildings incorporating either Special Moment-Resisting Frames
or Ordinary Moment-Resisting Frames utilizing welded beam-column connections. The

vii
Interim Guidelines Advisory No. 2 SAC 99-01

recommendations for new construction are applicable to all WSMF construction expected
to resist earthquake demands through plastic behavior.

b) Regulators and building departments responsible for control of the evaluation, repair, and
occupancy of WSMF buildings that have been subjected to strong ground motion and for
regulation of the design, construction, and inspection of new WSMF buildings.

The fundamental goal of the information presented in the Interim Guidelines as modified by this
Advisory is to help identify and reduce the risks associated with earthquake-induced fractures in
WSMF buildings through provision of timely information on how to inspect existing buildings for
damage, repair damage if found, upgrade existing buildings and design new buildings. The information
presented here primarily addresses the issue of beam-to-column connection integrity under the severe
inelastic demands that can be produced by building response to strong ground motion. Users are
referred to the applicable provisions of the locally prevailing building code for information with regard
to other aspects of building construction and earthquake damage control.

Limitations
The information presented in this Interim Guidelines Advisory, together with that contained in the
Interim Guidelines it modifies, is based on limited research conducted since the Northridge
Earthquake, review of past research and the considerable experience and judgment of the professionals
engaged by SAC to prepare and review this document. Additional research on such topics as the effect
of floor slabs on frame behavior, the effect of weld metal and base metal toughness, the efficacy of
various beam-column connection details and the validity of current standard testing protocols for
prediction of earthquake performance of structures is continuing as part of the Phase 2 program and is
expected to provide important information not available at the time this Advisory was formulated.
Therefore, many of the recommendations cited herein may change as a result of forthcoming research
results.

The recommendations presented herein represent the group consensus of the committee of
Guideline Writers retained by SAC following independent review by the Project Oversight
Committee. They may not reflect the individual opinions of any single participant. They do not
necessarily represent the opinions of the SAC Joint Venture, the Joint Venture partners, or the
sponsoring agencies. Users are cautioned that available information on the nature of the WSMF
problem is in a rapid stage of development and any information presented herein must be used
with caution and sound engineering judgment.

viii
Interim Guidelines Advisory No. 2 SAC 99-01

TABLE OF CONTENTS
THE SAC JOINT VENTURE ii
DISCLAIMER ii
PREFACE iii
Purpose iii
Background iii
Format vi
Intent vii
Limitations viii

1 INTRODUCTION
1.1 Purpose 1-1
1.2 Scope 1-1
1.3 Background 1-1
1.4 The SAC Joint Venture 1-8
1.5 Sponsors 1-8
1.6 Summary of Phase I Research 1-8
1.7 Intent 1-8
1.8 Limitations 1-9
1.9 Use of the Guidelines 1-9

3 CLASSIFICATIONS AND IMPLICATIONS OF DAMAGE


3.1 Summary of Earthquake Damage 3-1
3.2 Damage Types 3-1
3.2.1 Girder Damage 3-1
3.2.2 Column Flange Damage 3-1
3.2.3 Weld Damage, Defects and Discontinuities 3-1
3.2.4 Shear Tab Damage 3-4
3.2.5 Panel Zone Damage 3-4
3.2.6 Other Damage 3-4
3.3 Safety Implications 3-5
3.4 Economic Implications 3-7

4 POST-EARTHQUAKE EVALUATION
4.1 Scope 4-1
4.2 Preliminary Evaluation 4-1
4.2.1 Evaluation Process 4-1
4.2.1.1 Ground Motion 4-1
4.2.1.2 Additional Indicators 4-1
4.2.2 Evaluation Schedule 4-1
4.2.3 Connection Inspections 4-2
4.2.3.1 Analytical Evaluation 4-2
4.2.3.2 Buildings with Enhanced Connections 4-3
4.2.4 Previous Evaluations and Inspections 4-3

ix
Interim Guidelines Advisory No. 2 SAC 99-01

4.3 Detailed Evaluation Procedure 4-3


4.3.1 Eight Step Inspection and Evaluation Procedure 4-3
4.3.2 Step 1 - Categorize Connections By Group 4-4
4.3.3 Step 2 - Select Samples of Connections for Inspection 4-4
4.3.3.1 Method A - Random Selection 4-5
4.3.3.2 Method B - Deterministic Selection 4-5
4.3.3.3 Method C - Analytical Selection 4-5
4.3.4 Step 3- Inspect the Selected Samples of Connections 4-5
4.3.4.1 Damage Characterization 4-5
4.3.5 Step 4 - Inspect Connections Adjacent to Damaged Connections 4-8
4.3.6 Step 5 - Determine Average Damage Index for the Group 4-8
4.3.7 Step 6 - Determine the Probability that the Connections in a
Group at a Floor Level Sustained Excessive Damage 4-9
4.3.7.1 Some Connections In Group Not Inspected 4-9
4.3.7.2 All Connections in Group Inspected 4-9
4.3.8 Step 7 - Determine Recommended Recovery
Strategies for the Building 4-9
4.3.9 Step 8 - Evaluation Report 4-9
4.4 Alternative Group Selection for Torsional Response 4-9
4.5 Qualified Independent Engineering Review 4-9
4.5.1 Timing of Independent Review 4-9
4.5.2 Qualifications and Terms of Employment 4-9
4.5.3 Scope of Review 4-9
4.5.4 Reports 4-9
4.5.5 Responses and Corrective Actions 4-10
4.5.6 Distribution of Reports 4-10
4.5.7 Engineer of Record 4-10
4.5.8 Resolution of Differences 4-10

5 POST-EARTHQUAKE INSPECTION
5.1 Connection Types Requiring Inspection 5-1
5.1.1 Welded Steel Moment Frame (WSMF) Connections 5-1
5.1.2 Gravity Connections 5-3
5.1.3 Other Connection Types 5-3
5.2 Preparation 5-4
5.2.1 Preliminary Document Review and Evaluation 5-4
5.2.1.1 Document Collection and Review 5-4
5.2.1.2 Preliminary Building Walk-Through 5-4
5.2.1.3 Structural Analysis 5-4
5.2.1.4 Vertical Plumbness Check 5-4
5.2.2 Connection Exposure 5-4
5.3 Inspection Program 5-6
5.3.1 Visual Inspection (VI) 5-6
5.3.1.1 Top Flange 5-6
5.3.1.2 Bottom Flange 5-6

x
Interim Guidelines Advisory No. 2 SAC 99-01

5.3.1.3 Column and Continuity Plates 5-6


5.3.1.4 Beam Web Shear Connection 5-7
5.3.2 Nondestructive Testing (NDT) 5-7
5.3.3 Inspector Qualification 5-9
5.3.4 Post-Earthquake Field Inspection Report 5-9
5.3.5 Written Report 5-9

6 POST-EARTHQUAKE REPAIR AND MODIFICATION


6.1 Scope 6-1
6.2 Shoring 6-1
6.3 Repair Details 6-1
6.4 Preparation 6-1
6.5 Execution 6-1
6.6 Structural Modification 6-1
6.6.1 Definition of Modification 6-1
6.6.2 Damaged vs. Undamaged Connections 6-1
6.6.3 Criteria 6-1
6.6.4 Strength and Stiffness 6-4
6.6.4.1 Strength 6-4
6.6.4.2 Stiffness 6-6
6.6.5 Plastic Rotation Capacity 6-7
6.6.6 Connection Qualification and Design 6-10
6.6.6.1 Qualification Test Protocol 6-11
6.6.6.2 Acceptance Criteria 6-11
6.6.6.3 Calculations 6-12
6.6.6.3.1 Material Strength Properties 6-13
6.6.6.3.2 Determine Plastic Hinge Location 6-16
6.6.6.3.3 Determine Probable Plastic Moment at Hinges 6-18
6.6.6.3.4 Determine Beam Shear 6-19
6.6.6.3.5 Determine Strength Demands on Connection 6-20
6.6.6.3.6 Check Strong Column - Weak Beam Conditions 6-21
6.6.6.3.7 Check Column Panel Zone 6-23
6.6.7 Modification Details 6-24
6.6.7.1 Haunch at Bottom Flange 6-24
6.6.7.2 Top and Bottom Haunch 6-26
6.6.7.3 Cover Plate Sections 6-26
6.6.7.4 Upstanding Ribs 6-28
6.6.7.5 Side-Plate Connections 6-29
6.6.7.6 Bolted Brackets 6-29

7 NEW CONSTRUCTION
7.1 Scope 7-1
7.2 General - Welded Steel Frame Design Criteria 7-3
7.2.1 Criteria 7-3
7.2.2 Strength and Stiffness 7-4

xi
Interim Guidelines Advisory No. 2 SAC 99-01

7.2.2.1 Strength 7-4


7.2.2.2 Stiffness 7-5
7.2.3 Configuration 7-6
7.2.4 Plastic Rotation Capacity 7-9
7.2.5 Redundancy 7-13
7.2.6 System Performance 7-15
7.2.7 Special Systems 7-15
7.3 Connection Design and Qualification Procedures - General 7-15
7.3.1 Connection Performance Intent 7-15
7.3.2 Qualification by Testing 7-16
7.3.3 Design by Calculation 7-16
7.4 Guidelines for Connection Qualification by Testing 7-16
7.4.1 Testing Protocol 7-16
7.4.2 Acceptance Criteria 7-16
7.5 Guidelines for Connection Design by Calculation 7-18
7.5.1 Material Strength Properties 7-18
7.5.2 Design Procedure - Strengthened Connections 7-23
7.5.2.1 Determine Plastic Hinge Locations 7-23
7.5.2.2 Determine Probable Plastic Moment at Hinge 7-24
7.5.2.3 Determine Shear at Plastic Hinge 7-26
7.5.2.4 Determine Strength Demands at Critical Sections 7-26
7.5.2.5 Check for Strong Column - Weak Beam Condition 7-27
7.5.2.6 Check Column Panel Zone 7-29
7.5.3 Design Procedure - Reduced Beam Section Connections 7-30
7.5.3.1 Determine Reduced Section and Plastic Hinge Locations 7-33
7.5.3.2 Determine Strength and Probable Plastic Moment in RBS 7-33
7.5.3.3 Strong Column - Weak Beam Condition 7-35
7.5.3.4 Column Panel Zone 7-36
7.5.3.5 Lateral Bracing 7-36
7.5.3.6 Welded Attachments 7-37
7.6 Metallurgy & Welding 7-38
7.7 Quality Control / Quality Assurance 7-38
7.8 Guidelines on Other Connection Design Issues 7-38
7.8.1 Design of Panel Zones 7-39
7.8.2 Design of Web Connections to Column Flanges 7-39
7.8.3 Design of Continuity Plates 7-40
7.8.4 Design of Weak Column and Weak Way Connections 7-40
7.9 Moment Frame Connections for Consideration in New Construction 7-40
7.9.1 Cover Plate Connections 7-40
7.9.2 Flange Rib Connections 7-43
7.9.3 Bottom Haunch Connections 7-44
7.9.4 Top and Bottom Haunch Connections 7-46
7.9.5 Side-Plate Connections 7-46
7.9.6 Reduced Beam Section Connections 7-46
7.9.7 Slip-Friction Energy Dissipating Connections 7-48

xii
Interim Guidelines Advisory No. 2 SAC 99-01

7.9.8 Column Tree Connections 7-48


7.9.9 Slotted Web Connections 7-48
7.9.10 Bolted Bracket Connections 7-50
7.10 Other Types of Welded Connection Structures 7-52
7.10.1 Eccentrically Braced Frames (EBF) 7-52
7.10.2 Dual Systems 7-52
7.10.3 Welded Base Plate Details 7-52
7.10.4 Vierendeel Truss Systems 7-52
7.10.5 Moment Frame Tubular Systems 7-52
7.10.6 Welded Connections of Collectors, Ties and Diaphragm Chords 7-53
7.10.7 Welded Column Splices 7-53
7.10.8 Built-up Moment Frame Members 7-53

8 METALLURGY & WELDING


8.1 Parent Materials 8-1
8.1.1 Steels 8-1
8.1.2 Chemistry 8-3
8.1.3 Tensile/Elongation Properties 8-3
8.1.4 Toughness Properties 8-10
8.1.5 Lamellar Discontinuities 8-10
8.1.6 K-Area Fractures 8-10
8.2 Welding 8-11
8.2.1 Welding Process 8-11
8.2.2 Welding Procedures 8-12
8.2.3 Welding Filler Metals 8-13
8.2.4 Preheat and Interpass Temperatures 8-17
8.2.5 Postheat 8-17
8.2.6 Controlled Cooling 8-17
8.2.7 Metallurgical Stress Risers 8-17
8.2.8 Welding Preparation & Fit-up 8-17

12. REFERENCES 12-1

xiii
Interim Guidelines Advisory No. 2 SAC 99-01

This page intentionally left blank.