2012 02-21 CC Itm 06
2012 02-21 CC Itm 06
2012 02-21 CC Itm 06
NEEDS: For the City Council to consider awarding a contract for a surface water treatment plant
design.
FACTS: 1. The City must design and construct a treatment facility to use Lake Nacimiento
water.
2. Selection criteria for a water-treatment-plant design firm were approved by the
Council Ad-Hoc Committee on February 20, 2007; three firms were interviewed
March 1, 2007.
3. The top two ranked firms were asked to propose on the final design of a 4 million-
gallon per day (MGD) treatment plant on September 8, 2010.
4. AECOM was selected for final design-phase services of the 4-MGD water
treatment plant (estimated to cost $25M). Their treatment process would have
resulted in lower capital and operating costs and would utilize available preliminary
engineering (technical analysis, soils investigation, survey, etc.) and drafting
performed to date.
5. Continued delays in adoption of a water rate combined with decreased water sales
and increasing capital expenses placed a heavy burden on the City’s water fund.
6. Due to strained financial circumstances, on November 15th, 2011 City Council
reprioritized capital expenditures, settled on a reduced-capacity water treatment
plant, and directed staff to begin contract negotiations with AECOM for final
design of a 2-MGD water treatment plant.
7. The construction of the Phase-I 2 MGD treatment plant is expected to cost
approximately $12.M.
ANALYSIS &
CONCLUSION:
An RFP was prepared and submitted to both Black and Veatch and AECOM for
preparation of final plans and specifications for a 4-MGD surface water treatment
plant. The RFP was distributed on August 8, 2010 and proposals were received
October 1, 2010.
AECOM’s proposed treatment process would result in lower capital and operating
costs and utilize available preliminary engineering (technical analysis, soils
investigation, survey, etc.) and drafting performed to date. The design firms were
asked to submit a design fee for final design of the 4-MGD treatment concept.
AECOM proposed a design fee of $0.921M and Black and Veacth $0.995M.
&&$JHQGD,WHP3DJHRI
The Phase-1 2-MGD plant concept recommend by AECOM (a scaled version of
the 4-MGD process proposed in 2010) will meet the City’s treatment goals at
significantly reduced construction costs compared to previous concepts. The design
is scheduled to be completed twelve months following contract execution.
AECOM’s proposed design fee for the 2-MGD treatment plant is $899,588 and
construction is expected to cost approximately $12M.
POLICY
REFERENCE: Economic Strategy; Integrated Water Resource Plan; Nacimiento Water Project
Entitlement Contract.
FISCAL IMPACT: AECOM proposes professional engineering design services for a cost of $899,588.
Because of the scope of the Nacimiento Water Project, complexities involved in
design of a public drinking water treatment facility, and the possibility of design
amendments, particularly those that may come up during regulator reviews, design
workshops, bidability and constructability reviews, a $105,000 contingency should
be included.
Below are current account balances in Nacimiento Related funds as of January 31,
2012.
Nacimiento Water Development Fee Fund 226 $1.91 M
Nacimiento Water User Fee Fund 606 $12.2 M
Nacimiento Water Treatment Development Fee Fund 229 $.078 M
OPTIONS: a. Adopt Resolution No. 12-xxx authorizing the City Manager to enter into a contract
with AECOM in the amount not to exceed $1,004,588 to provide professional
engineering design services associated with the design of the 2-MGD treatment
facility.
Attachments (2)
1) Resolution
2) Scope of Work
&&$JHQGD,WHP3DJHRI
Attachment 1
WHEREAS, the City of Paso Robles is a partner in securing water from Lake Nacimiento; and
WHEREAS, integration of Nacimiento Water into the City’s distribution system will require the construction
of a two million gallon per day treatment facility; and
WHEREAS, the design process will require a professional engineering firm to ensure its functionality; and
WHEREAS, because of their demonstrated depth of experience, understanding of the purpose of the
treatment plant, direct experience with the Nacimiento Pipeline Project, and the needs of the City retain the
service of AECOM to provide Professional Engineering Design Services for the design of the treatment
facility at a cost not to exceed. $899,588 plus a contingency of $105,000 for unforeseen design amendments.
SECTION 2. The City Council does hereby award a contract to AECOM for Professional Engineering
Design Services associated with the design of the treatment facility in an amount not to exceed $1,004,588
and authorizes the City Manager to execute the contact.
PASSED AND ADOPTED by the City Council of the City of Paso Robles this 21st day of February 2012
by the following votes:
AYES:
NOES:
ABSTAIN:
ABSENT:
&&$JHQGD,WHP3DJHRI
Attachment 2
AECOM 805 542 9840 tel
1194 Pacific Street 805 542 9990 fax
Suite 204
San Luis Obispo CA 93401
www.aecom.com
Please find attached as Exhibit B AECOM’s detailed Scope of Services for the design phase
of the 2-MGD Nacimiento Water Treatment Plant Project (Project). This design is to be
based on the studies and design efforts prepared during prior iterations of the project and
the Feasibility Study prepared by AECOM in August 2011.
We hope this proposed scope meets your expectations. We look forward to working with
you on this important project.
Sincerely,
Jon Hanlon, PE
Managing Engineer
&&$JHQGD,WHP3DJHRI
February 13, 2012
Exhibit B
Scope of Services
Design of 2-MGD Nacimiento Water Treatment Plant
for the City of Paso Robles
Background
The City of Paso Robles (City) is a Project Participant in the Nacimiento Water Project (NWP)
implemented by the San Luis Obispo County Flood Control and Water Conservation District.
The NWP is a regional water supply system that conveys raw water from Lake Nacimiento to
communities in San Luis Obispo County, including the City. The City plans on constructing a
surface water treatment plant to treat surface water received from Lake Nacimiento, with the
goal of utilizing this additional water source to increase supply reliability, particularly during the
summer months.
In December 2010 AECOM Technical Services Inc. (AECOM) submitted a Scope of Services to
the City for design of a 4 million gallon per day (MGD) surface water treatment plant expandable
to 6 MGD. The City placed that water treatment plant project on hold shortly after AECOM’s
original Scope of Services was submitted. In August 2011, at the request of the City, AECOM
submitted a 2.0-MGD Nacimiento WTP Feasibility Study (Feasibility Study) that evaluated the
feasibility of constructing a 2-MGD treatment plant with a reduced project budget. The City has
decided to proceed with design and construction of the 2-MGD treatment plant described in the
Feasibility Study. However, prior to designing the treatment plant, the City wishes to evaluate
the incremental cost of increasing the treatment plant capacity (up to an additional 0.5 MGD) to
support development projects that are anticipated to be annexed into the City. This Scope of
Services is for evaluation and design of a stand-alone water treatment plant with a daily
treatment capacity of approximately 2.0-2.5 MGD.
The City currently owns the site for the treatment facility. The site which is approximately 18
acres in size contains four groundwater wells (the Thunderbird wells) and one monitoring well.
The site is located between the Salinas River and US 101, northeast of the intersection of US
101 and Highway 46 West. A California Environmental Quality Act (CEQA) determination has
already been completed by the City. A topographic survey has also been completed for this
project. A geotechnical investigation of the site was previously completed for the 4-MGD
project, but the field exploration did not adequately cover the portion of the site proposed for the
new 2-MGD project. This Scope of Services includes supplemental geotechnical investigations
of the specific project area proposed for the 2-MGD facility, and a new, stand alone
geotechnical report for the proposed project. The City has provided existing boundary survey
map, topographic survey map, and prior geotechnical reports to AECOM.
The treatment plant will have an average treatment capacity of between 2 and 2.5 MGD (3.1 to
3.9 cubic feet per second). It has been assumed that there will be no dedicated
“standby/backup” pretreatment or membrane treatment trains. The water produced by this
project will be distributed to the East distribution zone through existing infrastructure. The
treated water pumping station shall have a pumping capacity of approximately 1,500 GPM,
approximately equivalent to the treatment plant capacity. Treated water storage will be limited
to that required to provide chlorine contact time.
Page 1 of 27
&&$JHQGD,WHP3DJHRI
The following sections present our detailed Scope of Services for the design phase of the 2-
MGD Nacimiento Water Treatment Plant Project (Project). This design is to be based on the
studies and design efforts prepared during prior iterations of the project and the Feasibility
Study. It is anticipated that a separate Scope of Services or amendment to this Scope of
Services will be submitted for construction phase services.
Project Description
Based on the prior design studies prepared by Black & Veatch Corporation, the August 2011
Feasibility Study prepared by AECOM, and information provided by the City, the project has
been assumed to consist of the following major elements:
x Existing Nacimiento Pipeline turnout and metering structure
x New City-owned raw water flow control and metering equipment
x Potassium permanganate chemical pretreatment system
x Raw water flash mixer (static mixer)
x Commercially available packaged dissolved air flotation (DAF) treatment system (one or
two trains)
x Pre-engineered metal enclosure for the DAF units
x Packaged membrane filtration system with chemical clean-in-place (CIP), chemical
neutralization, and compressed air skids
x Features necessary to facilitate design and construction of an add-on ozone
disinfection/oxidation system in the future
x In-line booster pumping station between the membrane and GAC processes
x Four granular activated carbon (GAC) pressure vessel contactors downstream of the
membranes (with bypass) for post-treatment
x Sodium hypochlorite primary and residual disinfection
x Partially recessed cast-in-place concrete, baffled clearwell
x High-service booster pumping station connected to the City’s distribution system
x Pre-engineered metal operations/membrane building
x Chemical storage and feed systems in a covered enclosure
x Residuals equalization structure with all process residuals discharged to a nearby sewer
x Piping between residuals equalization tank and nearby Templeton Sewer Interceptor
x Interconnecting yard piping
x Treatment plant electrical service
x Integration of treatment plant with existing 500 kW generator (if feasible)
x Treatment plant SCADA system, including specifications to allow the City to retain a
contractor to provide integration services with the City’s existing SCADA system .
Page 2 of 27
&&$JHQGD,WHP3DJHRI
x Specification for basic integration of treatment plant SCADA system with City’s existing
SCADA system.
x Perimeter chain link fence around treatment plant
x Provisions for ozone to be added in the future
x Site lighting
x Extension of gravel roads to new facilities
x On-site storm water detention basin
A general site plan of these facilities and process flow diagram are presented in Attachments 1
and 2 respectively.
Work Tasks
AECOM’s PM and Principal-In Charge (PIC) will facilitate and attend a monthly progress
meeting with the City. AECOM will prepare the agenda and update the decision log for each
Page 3 of 27
&&$JHQGD,WHP3DJHRI
meeting. For budgeting purposes for a 12-month project schedule, a total of 12 regular formal
meetings are assumed. These meetings will be held either at the Client’s office in Paso Robles.
The workshops will be attended by the PM, PIC and up to two additional AECOM engineers.
This task consists of Fugro Consultants performing supplemental field exploration, laboratory
testing, and analyses within the proposed footprint of this project. Fugro will prepare a stand-
alone geotechnical report for the project taking advantage of previous work performed near the
project site and will review the construction documents for general conformance with the
recommendations presented in the new geotechnical report.
Four hard copies of the TMs will be provided in Draft form for City review and comment. Four
hard copies and electronic (MS Word and .PDF) versions of the final TMs incorporating City
comments will be provided to the City.
Page 4 of 27
&&$JHQGD,WHP3DJHRI
Task 310 – Incremental Capacity Analysis (TM No. 1)
This scope of work for this task is outlined in AECOM’s proposal dated December 22, 2011. The
Scope of Work includes preparation of an Incremental Capacity Analysis Technical
Memorandum (TM No. 1) identifying the additional Design, Capital, and ongoing Operations and
Maintenance Costs associated with increasing the baseline treatment plant capacity to
accommodate demands associated with annexation of a proposed project adjacent to the City
limits. The project, consisting of 270 acres, is located at the northwest corner of Highway 46
West and US 101. The project is estimated to require approximately 71 acre feet per year of
water. The TM will include the following topics:
x Evaluation of options for expanding the planned 2.0 MGD Baseline plant. AECOM will
consult with the selected membrane manufacturer to identify expansion options to
accommodate the additional capacity. The TM will identify the minimum capacity
increment necessary to meet the additional demand as defined by the City (up to 71
acre feet per year).
x A summary of treatment processes and equipment potentially impacted by the
incremental capacity. AECOM will evaluate each major treatment process to identify
elements that would require expansion or modification to accommodate the expansion.
This includes discussion of systems assumed to be deferred or added at a later time
such as ozone.
x A revised process flow diagram.
x Engineer’s Opinion of Probable Cost including:
o Engineering design fee estimate to include the incremental capacity in the design of
the base 2.0 MGD water treatment plant
o Incremental capital costs.
AECOM will host and attend a kickoff meeting via teleconference to discuss the project.
AECOM will attend one meeting upon completion of the draft TM to discuss the findings with
City staff. Meetings or presentations not specifically described in our Scope of Work will be
considered additional services.
Task 320 – Hydraulic and Water Quality Design Criteria (TM No. 2)
AECOM’s Scope of Work includes preparation of a Hydraulic and Water Quality Design Criteria
TM containing the following information:
x Raw water quality ranges and summary tables that will be incorporated into the contract
document procurement specifications. AECOM will use Nacimiento Project water
quality data obtained by the County of San Luis Obispo and previous studies prepared
by Black & Veatch to develop the design ranges. No significant water quality
degradation is anticipated in the pipeline, inclusive of algae growth.
x Quantity and capacity of treatment units and pumps for each process
Page 5 of 27
&&$JHQGD,WHP3DJHRI
x Preliminary hydraulic profile
x City sewer model run to confirm the capacity of the nearby Templeton Interceptor Sewer
directly to the west of the proposed project site. Our analysis will evaluate capacity under
existing conditions.
x Potassium permanganate and sodium hypochlorite dosage and feed rate calculations
x Description of features that will be included in the design to accommodate the future
addition of ozone.
x List of the City’s preferred instrument and control component manufacturers and models
x General project requirements including the influent water quality range and filtered water
quality requirements
x Specification defining the membrane system manufacturer’s meetings, submittals, and
field services obligations
x General equipment requirements
x Shipping, handling, and storage requirements
Page 6 of 27
&&$JHQGD,WHP3DJHRI
x Startup and testing support requirements
x Operation and maintenance manuals
x Training services
x Technical provisions of warranty terms
It has been assumed that detailed specifications for specific equipment items (e.g. pumps,
valves, interconnecting piping, coatings, etc.) will not be required. Instead, the City will identify
a preferred membrane system supplier and negotiations will start from the preferred supplier’s
standard scope of supply. AECOM will review the preferred supplier’s proposed, detailed scope
of supply and make recommendations to the City regarding the suitability and general standard
of quality of the proposed equipment. AECOM’s recommendations for changes that are
accepted by the City will then be forwarded to the preferred supplier for incorporation into their
scope of supply prior to arriving at a final price proposal.
We have assumed that AECOM’s PM will attend two (2) special meetings at the City’s office in
support of procurement negotiations with the preferred supplier. Assistance with development
of legal agreements with the supplier, including agreements pertaining to the transition of
equipment ownership between the City and the construction contractor, are not included in our
Scope of Services. At the City’s direction, we have not included pilot or membrane validation
testing as part of our Scope of Work.
x General – 10 sheets
x Civil – 21 sheets
x Architectural, HVAC, and Plumbing – 19 sheets
x Structural – 24 sheets
x Process – 27 sheets
x Electrical – 46 sheets
x Instrumentation – 20 sheets
x Landscape – 0 sheets (landscaping will not be a part of this project)
Should significant additional effort be needed that could not be discerned under initial review,
AECOM will alert the City to establish a strategy and determine if additional budget should be
authorized.
AECOM will prepare technical specifications in the 2004 (6-digit) CSI format, utilizing AECOM’s
standard specifications as the basis. Front-end contract documents and general provisions
shall be prepared and provided by the City.
The Project Team will submit five (5) copies of draft construction documents (plans, technical
specifications, and opinion of probable construction cost) at the 30%, 60%, 90% and bid-level
stages of completion for review and comment by the City. A workshop with the Project Team
Page 7 of 27
&&$JHQGD,WHP3DJHRI
will be held during each City review cycle. Following incorporation of comments from the 90%
submittal, AECOM will prepare final bid documents. AECOM will provide the City one signed
reproducible hardcopy and electronic versions (in AutoCAD and .pdf format) of the construction
documents for bidding.
The fee estimate for Construction Contract Documents has been based on the schematic
design description included in Attachments 1 and 2 to this Scope of Services and as described
below. These descriptions assume a 2-MGD treatment plant. The treatment capacity may
range from 2.0 to 2.5-MGD depending on the outcome of the Incremental Capacity Analysis
described in Task 300.
Page 8 of 27
&&$JHQGD,WHP3DJHRI
Future Ozone Equipment Conceptual Layout
AECOM will prepare a preliminary assessment for an ozonation system that may be added to
the treatment plant in the future. The ozone system will be conceptually described in the Design
Criteria TM and shown schematically on the 30% construction document submittal. The future
ozone system will not be included in the construction documents, and will not be developed
beyond the preliminary assessment stage, or included the technical specifications. The intent of
this task is to demonstrate the feasibility of adding an ozone system in the future and to identify
the basic interfaces that may be anticipated, thereby reducing the cost of adding the system in
the future. As part of this task, AECOM will consult with up to two ozone manufacturers to
identify candidate equipment. Conceptual footprint will be provided on the 30% submittal. If
substantial design modifications are ultimately required to facilitate the future addition of ozone,
additional budget may be requested.
Page 9 of 27
&&$JHQGD,WHP3DJHRI
Operations/Membrane Building
The site will include a pre-engineered metal building used to house operations staff and
sensitive equipment. It is anticipated that the building will house the membrane skids and will
also include a single office, a conference room sized for six people, a unisex restroom,
approximately 150 square feet of shop space, and a small control room. The building will likely
house some electrical switchgear. The building is anticipated to be approximately 2,500 square
foot in size and approximately 15’ in height. Architectural design of the building exterior will
conform to a commercially available style.
AECOM will evaluate the compatibility of the City’s existing master SCADA system hardware
and software with the SCADA equipment proposed for use at the treatment plant. AECOM will
also prepare specifications that can be used by the City to retain a contractor to provide basic
integration services between the City’s master SCADA system and the treatment plant SCADA
system. Telemetry radio surveys is not a part of the scope of services. If requested by the City,
AECOM’s design will include the radio antenna support.
Electrical Facilities
It is anticipated that most of the pumping equipment at the treatment plant will be VFD-driven.
The site will also include basic security lighting and door and window entry switches at the
Page 10 of 27
&&$JHQGD,WHP3DJHRI
building. This Scope of Services includes evaluating the feasibility of using the City’s existing
standby generator to provide standby power to the treatment plant. The City does not wish to
install a new generator at the site. AECOM will submit a PG&E Rule 16 application for a new
electrical service.
Page 11 of 27
&&$JHQGD,WHP3DJHRI
will provide ongoing coordination with CDPH throughout the design phase of the project as
specified herein. AECOM will prepare and submit the necessary permit application forms and
will make minor modifications to the Basis of Design report to satisfy CDPH pre-design
documentation requirements. The following supporting documents, which may be required
before the permit amendment is approved, are not included in the Scope of Services for this
phase of the project.
x Sanitary survey of the raw water source. It has been assumed that a common sanitary
survey has been completed for all of the Nacimiento project participants.
x Operations Plan. It has been assumed that an operations plan will be required by CDPH
and prepared by AECOM during the construction phase of the project.
AECOM will incorporate a specification into the contract documents that requires the
construction contractor to prepare a Storm Water Pollution Prevention Plan (SWPPP) and
Construction Site Monitoring Plan for storm water discharges associated with construction
activity as required by the State Water Resources Control Board, Water Quality Order 2009-
0009-DWQ. This Scope of Services assumes that the City will not require erosion control plans
prior to production of the SWPPP.
Page 12 of 27
&&$JHQGD,WHP3DJHRI
Task 700 – Contractor Prequalification
AECOM will assist the City with pre-qualifying prime contractors through the process authorized
by Assembly Bill 574 and developed by the California Department of Industrial Relations.
AECOM will attend a contractor pre-qualification kickoff meeting at the City; prepare a request
for pre-qualification and questionnaire to be sent to prospective contractors; respond to
contractor questions during the advertisement period; assist the City with review of the
completed pre-qualification questionnaires (assumes 15 are received); and assist the City with
preparing a response letter that can be sent to the contractors. Advertising costs and assisting
the City with responding to contractor appeals will be considered additional services.
x Furnish one signed and stamped reproducible set of plans and specifications for use by
the City in preparing bid sets for distribution. It has been assumed that all advertising
and all printing and distribution of contract documents will be handled and paid for
directly by the City.
x AECOM will participate in one prebid meeting and site visit to acquaint prospective
bidders with the project.
x AECOM will answer bidders’ questions during the bidding period. Bidders’ questions will
be formulated in writing and submitted to AECOM by the City. A written response by
addendum to clarify the project plans and/or specifications will be prepared by AECOM
and delivered to the City to send to plan holders. Up to four addenda have been
assumed.
x AECOM will assist the City in evaluating the received bids for responsiveness to the
approved contract documents and will prepare a bid tabulation summarizing the bid
results.
1. Assistance with obtaining environmental permits and clearances for the project,
including through the CEQA and NEPA processes.
2. CEQA mitigation measures
3. Construction phase services
4. Start-up assistance
5. Pothole existing underground utilities.
6. Establishing traffic control criteria and preparation of traffic control plans
Page 13 of 27
&&$JHQGD,WHP3DJHRI
7. ROW or easement services
8. Surveying
9. Design of facilities within the 100-year flood plain
10. Support of water quality sampling and analyses
11. Off-site improvements except as specifically defined herein.
12. Organize or oversee pilot studies or membrane validation testing.
13. Contract documents for competitive bidding of membrane system.
14. Modifications to the Nacimiento water delivery system
15. Specialized detailed studies associated with noise or noise attenuation.
16. Services resulting from significant changes in extent of the project or its design including,
but not limited to, changes in size, complexity (such as design of buildings), the City’s
schedule, or character of construction or method of financing. Revising previously
accepted studies, reports, and design documents when such revisions are due to
causes beyond AECOM’s control.
17. Investigations involving detailed consideration of operations, maintenance, and
overhead expenses, including pilot testing or other evaluations required to evaluate
variable costs such as carbon or chemical usage; providing a separate formal value
engineering process during the course of design; the preparation of cash flow and
economic evaluations and rate schedules. Assistance in obtaining financing for the
project.
18. Prepare to serve or serve as an expert witness for the City in any litigation, public
hearing, or other legal or administrative proceeding involving the project.
19. Preparation of separate bid packages further subdividing the work or phasing of the
project into multiple projects except as specifically defined herein.
20. Any other specific services requested by the City or AECOM not identified in this
Agreement.
21. Provide or acquire water rights as needed for the project.
1. Apply for and pay for all environmental clearances and permits.
2. Provide previous reports and studies related to the work.
3. Provide or acquire easements as needed for the project.
4. Apply for and secure approvals and permits from all governmental authorities having
jurisdiction of the project and such approvals from other entities or agencies as may be
necessary for the project, with the assistance of AECOM or as additionally authorized.
Client shall pay all fees and charges associated with securing permits and approvals.
5. Provide financial consulting and legal services required for the project.
Page 14 of 27
&&$JHQGD,WHP3DJHRI
6. Provide drawings and other data relating to layout and design of existing facilities,
easements, road right-of-ways, etc. that may relate to the project.
7. Uncover by excavation or otherwise expose and determine the depth of cover on all
underground utilities or facilities for which drawings are not available showing the
elevation and size of said facilities where such facilities may be in conflict with proposed
project facilities.
8. Reproduction, distribution and advertising of bid documents and keeping a detailed list of
plan holders.
9. Provide a copy of current dated Title Report for review relative to easements and other
property encumbrances.
Electronic Data
CADD/system disk files delivered to the City shall not include the professional stamp or
signature of an engineer. The City agrees that AECOM shall not be liable for claims, liabilities,
or losses arising out of, or connected with (a) the modification or misuse by the City, or anyone
authorized by the City, of CADD files; (b) the decline of accuracy or readability of CADD files
due to inappropriate storage conditions or duration; or (c) any use by the City, or anyone
authorized by the City, of CADD files for additions to this project, for the completion of this
project by others, or for any other project, excepting only such use as is authorized, in writing,
by AECOM.
Right to Rely
Except as otherwise noted in the Scope of Services, consistent with the professional standard of
care, AECOM shall be entitled to rely upon the accuracy of data and information provided by
Client or others without independent review or evaluation. Survey mapping, and water quality
data are examples.
Page 15 of 27
&&$JHQGD,WHP3DJHRI
Schedule
AECOM shall promptly pursue work tasks upon receipt of this signed Agreement and Notice to
Proceed from the City. These tasks shall be completed in phases as follows:
Page 16 of 27
&&$JHQGD,WHP3DJHRI
Compensation
AECOM shall be compensated monthly with progress payments by the City for services
provided by AECOM during the previous month pursuant to this Agreement and in accordance
with AECOM’s Hourly Rate Schedule (Exhibit B), which is attached hereto and made a part of
this Agreement. Payment of invoices approved by the City shall be made within 30 calendar
days from receipt of invoice by the City.
Compensation for AECOM’s Basic Services, as described herein shall be made on a time-and-
materials basis with a maximum not-to-exceed fee as identified below.
Fee
Task ($)
Task 100 Project Management $99,684
Task 200 Geotechnical $19,740
Task 300 Pre-Design TMs $54,215
Task 400 Membrane Procurement $18,312
Task 500 Construction Contract Docs $614,664
Task 600 Permitting Support $45,837
Task 700 Contractor Prequalification $16,546
Task 800 Bid Phase Services $30,590
Page 17 of 27
&&$JHQGD,WHP3DJHRI
Attachment 1 – Conceptual Site Plan
Page 18 of 27
&&$JHQGD,WHP3DJHRI
Page 19 of 27
&&$JHQGD,WHP3DJHRI
Attachment 2 – Conceptual Flow Diagram
Page 20 of 27
&&$JHQGD,WHP3DJHRI
Page 21 of 27
&&$JHQGD,WHP3DJHRI
Attachment 3 – Project team
Page 22 of 27
&&$JHQGD,WHP3DJHRI
Page 23 of 27
&&$JHQGD,WHP3DJHRI
Attachment 4 – Fee Breakdown and Standard Rate Sheet
Page 24 of 27
&&$JHQGD,WHP3DJHRI
Page 25 of 27
&&$JHQGD,WHP3DJHRI
Page 26 of 27
&&$JHQGD,WHP3DJHRI
Page 27 of 27
&&$JHQGD,WHP3DJHRI