Contoh Progress
Contoh Progress
MANUNGGAL ENGINEERING
CP. BAHARI 4 x 30 MW
COAL FIRED STEAM POWER PLANT PROJECT
LAMPUNG
We undersigned :
Act for and behalf PT. Manunggal Engineering, further more as Party I
Act for and behalf PT. Manunggal Engineering, further more as Party II
According to Monthly Progress Report 8 th, hereby we acknowledge and accept the contrction -
work for Civil Foundation & Concrete Structure for CP. Bahari 4 x 30 MW Coal Fired Power Plant -
Project with contract number ME-C006/CPB-0108 dated January 29, 2008 has been finished : 39.267%
by PT. SAMTRA TRIDAYA as contractor from PT. Manunggal Engineering.
Our signature attests to approval of the work and acceptance of this complaetion .
Party I Party II
Pekerjaan untuk proyek Civil Foundation & Concrete Structure, CP Bahari power plant 2 x 30 MW, dilokasi -
PT. Manunggal Engineering - Lampung, telah mencapai kemajuan (progress) sebesar : 39.267% (sesuai -
( S. Wardoyo )
Site Manager
Owner :
PT. MANUNGGAL ENGINEERING
Contractor :
PT. SAMTRA TRIDAYA
Ged u n g A K A L t . 8
J l . B an g k a Ray a No . 2
MONTHLY PRORESS
K eb . B ar u - J ak ar t a Sel at an
A Preparation Work
1 Survey 13,500.00 m2 0.077% 10,395.00 77.0% 0.059% - 0.0% 0.000% 10,395.00 77.0% 0.059%
2 Mobilization & Demobilization 1.00 ls 0.738% 0.69 69.0% 0.509% - 0.0% 0.000% 0.69 69.0% 0.509%
3 Direction Keet 1.00 ls 1.230% 1.00 100.0% 1.230% - 0.0% 0.000% 1.00 100.0% 1.230%
Total - A : 2.045% 1.799% 0.000% 1.799%
27 NSG Grouting 37.40 m3 1.982% - 0.0% 0.000% 8.84 23.6% 0.469% 8.84 23.6% 0.469%
28 Water Stop 157.60 m' 0.095% - 0.0% 0.000% - 0.0% 0.000% - 0.0% 0.000%
Total - D : 12.666% 1.801% 0.469% 2.270%
59 Formwork Exposed 448.20 m2 0.200% - 0.0% 0.000% - 0.0% 0.000% - 0.0% 0.000%
60 Rebar 133,339.80 kg 5.366% - 0.0% 0.000% - 0.0% 0.000% - 0.0% 0.000%
61 Wiremesh M6 2,849.00 kg 0.150% - 0.0% 0.000% - 0.0% 0.000% - 0.0% 0.000%
62 Wiremesh M8 5,076.20 kg 0.254% - 0.0% 0.000% - 0.0% 0.000% - 0.0% 0.000%
63 Concrete K-125 16.60 m3 0.004% - 0.0% 0.000% - 0.0% 0.000% - 0.0% 0.000%
64 Concrete K-225 1,065.70 m3 0.378% - 0.0% 0.000% - 0.0% 0.000% - 0.0% 0.000%
65 Vertical Down Pipe 4,766.40 Kg 0.416% - 0.0% 0.000% - 0.0% 0.000% - 0.0% 0.000%
66 Handrail 1,389.60 Kg 0.126% - 0.0% 0.000% - 0.0% 0.000% - 0.0% 0.000%
67 Embedded Plate 513.50 kg 0.027% - 0.0% 0.000% - 0.0% 0.000% - 0.0% 0.000%
68 Steel ladder 1.00 ls 0.121% - 0.0% 0.000% - 0.0% 0.000% - 0.0% 0.000%
69 Sand Blasting 185.60 m2 0.019% - 0.0% 0.000% - 0.0% 0.000% - 0.0% 0.000%
70 Painting 185.60 m2 0.058% - 0.0% 0.000% - 0.0% 0.000% - 0.0% 0.000%
Total - G : 8.256% 0.000% 0.000% 0.000%
94 Concrete K-125 302.50 m3 0.073% 71.52 23.6% 0.017% - 0.0% 0.000% 71.52 23.6% 0.017%
95 Formwork Unexposed 836.00 m2 0.209% 1,147.56 137.3% 0.286% - 0.0% 0.000% 1,147.56 137.3% 0.286%
96 Formwork Exposed 2,464.00 m2 1.100% 2,024.86 82.2% 0.904% - 0.0% 0.000% 2,024.86 82.2% 0.904%
97 Concrete K-250 1,216.00 m3 0.431% 1,257.41 103.4% 0.446% - 0.0% 0.000% 1,257.41 103.4% 0.446%
98 Rebar 150,785.00 kg 6.068% 127,711.06 84.7% 5.140% - 0.0% 0.000% 127,711.06 84.7% 5.140%
Total - I : 8.076% 7.202% 0.000% 7.202%
K Miscellaneous
109 Indirect cost 1.00 ls 4.110% 0.40 40.2% 1.652% 0.30 29.8% 1.225% 0.70 70.0% 2.877%
110 Over Head + Profit 1.00 ls 4.762% 0.40 40.2% 1.914% 0.30 29.8% 1.420% 0.70 70.0% 3.333%
Total - K : 8.872% 3.566% 2.645% 6.210%
Total I - K : 19.601% 10.768% 2.645% 13.413%
REKAPITULATION
PROJECT TITLE : CP BAHARI 2 X 30 MW CAPTIVE - COAL FIRED POWER PLANT
OWNER : PT. MANUNGGAL ENGINEERING
LOCATION : DENTE, TELADAS - TULANG BAWANG - LAMPUNG
WORK TITLE : CIVIL FOUNDATION & CONCRETE STRUCTURE
J Coal Chute, Crusher & Handling Trestle 2.653% 0.000% 0.000% 0.000%