0% found this document useful (0 votes)
96 views9 pages

Design The BIM Process - BIM Project Execution Planning Guide, Version 3.0

This document discusses designing the BIM (Building Information Modeling) process for a construction project. It describes mapping the overall BIM process in two levels: 1) A high-level "BIM Overview Map" shows the relationship between different BIM Uses (applications) over the project lifecycle and key information exchanges. 2) "Detailed BIM Use Process Maps" define the specific steps and responsibilities for each BIM Use. The document provides guidance on populating these maps, including identifying responsible parties, information requirements, and exchanges within and between processes. An example BIM Overview Map is shown for a sample laboratory project.

Uploaded by

S. B.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
96 views9 pages

Design The BIM Process - BIM Project Execution Planning Guide, Version 3.0

This document discusses designing the BIM (Building Information Modeling) process for a construction project. It describes mapping the overall BIM process in two levels: 1) A high-level "BIM Overview Map" shows the relationship between different BIM Uses (applications) over the project lifecycle and key information exchanges. 2) "Detailed BIM Use Process Maps" define the specific steps and responsibilities for each BIM Use. The document provides guidance on populating these maps, including identifying responsible parties, information requirements, and exchanges within and between processes. An example BIM Overview Map is shown for a sample laboratory project.

Uploaded by

S. B.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 9

19.10.21, 16:53 Design the BIM Process – BIM Project Execution Planning Guide, Version 3.

Home Read Sign in

Search in book …

BIM PROJECT EXECUTION PLANNING GUIDE, VERSION 3.0

CONTENTS

4 DESIGN THE BIM PROCESS

After identifying each Model Use, it is necessary to understand the implementation


process for each Model Use and the implementation process of the project as a whole.
This chapter describes a procedure to design the BIM Project Execution Process. The
process map developed in this step allows the team to understand the overall BIM
process, identify the information exchanges that will be shared between multiple
parties, and clearly define the various processes to be performed for the identified BIM
Uses. The use of process mapping techniques allows the team to effectively perform this
step. Process maps also serve as the basis for determining other important
implementation topics including contract structure, model deliverable requirements,
information technology infrastructure, and selection criteria for future team members.

Mapping the Project Execution Process


Mapping the BIM Process for the project requires the project team to first develop an
overview map which shows how the different Model Uses will be performed. Then,
detailed BIM Use Process Maps are developed to define the specific BIM
implementation at an increased level of detail. To implement this two-level approach,
Previous: Select Model Uses
Business Process Modeling Notation (BPMN) has been adopted so that consistently
formatted process maps will be created by the various project
Next: Define team members.
the Information Exchanges

https://psu.pb.unizin.org/bimprojectexecutionplanning/chapter/process/ 1/9
19.10.21, 16:53 Design the BIM Process – BIM Project Execution Planning Guide, Version 3.0

Level 1: BIM Overview Map


The Overview Map shows the relationship of Model Uses on the project. This process
map also contains the high-level information exchanges that occur throughout the
project lifecycle.

Level 2: Detailed BIM Use Process Maps


Detailed BIM Use Process Maps are created for each identified BIM Use on the project
to clearly define the sequence of various processes to be performed. These maps also
identify the responsible parties for each process, reference information content, and
the information exchanges which will be created and shared with other processes.

Creating a BIM Overview Map


This section details out how to create a BIM Overview Map.

1) Place potential BIM Uses into a BIM Overview Map


Once the team identifies the Model Uses for the project (refer to the Model Use
Selection Worksheet from Chapter Three), the team can start the mapping process by
adding each of the Model Uses as a process within the map. It is important to
understand that a Model Use may be added to the overview map at several locations if it
is performed at several times within the project lifecycle.

To help achieve this task, a template Microsoft Visio file containing process maps is
published at the BIM Project Execution Planning Guide Website. A Microsoft Visio
Stencil file is also posted in the same location and can be used by the project team to
develop the process maps easily. If the project team members do not have Microsoft
Visio, the team can use other process mapping or graphics software to create the
process maps. Additionally, versions of the templates are in Appendix D – Template
Process Maps.

2) Arrange Model Uses according to project sequence in the BIM Overview Map
After developing the process for each implemented model use on the project, the team
should sequentially order these processes. One of the purposes of the Overview Map is
to identify the phase for each Model Use (e.g., plan, design, construct or operate) and
provide the team with the implementation sequence. For simplistic purposes, the Model
Uses should align with the BIM deliverables schedule.

3) Identify the responsible parties for each process


Responsible Parties should be clearly identified for each process. For some processes,
thisPrevious:
may beSelect
an easy task,
Model but for others, it may not. It is important in all cases to consider
Uses
which team member is best suited to successfully complete the task. Additionally, some
Next: Define the Information Exchanges

https://psu.pb.unizin.org/bimprojectexecutionplanning/chapter/process/ 2/9
19.10.21, 16:53 Design the BIM Process – BIM Project Execution Planning Guide, Version 3.0

processes may have multiple responsible parties. The identified party will be
responsible for clearly defining the information required to implement the process as
well as the information produced by the process.

The graphical notation and information format for the processes within the BIM
Overview Map are included in Figure 3-1. Each process should include a process name,
project phase, and the responsible party. Each process should also include a ‘Detailed
Map’ title which points to the detailed map (Level Two map) for the process. This
detailed map notation is used since several processes may share the same detailed map.
For example, a construction management company may perform cost estimating from
the building information provided by the designer. The Construction manager may
perform this estimate during the schematic design, design development, and
construction document phase, but it may use the same detailed workflow to accomplish
this task, which can represent a single detailed map. Therefore, the process for
performing the three estimates should be added into the high-level map at three
locations, but the team can reference a single detailed map for further information.

Figure 3.1: Notation for a Process in the Overview Process Map

4) Determine the Information Exchanges required to implement each BIM Use


The BIM Overview Map includes the critical information exchanges which are either
internal to a particular process or shared between processes and responsible parties. In
general, it is vital to include all information exchanges that will pass from one party to
another. In current applications, these exchanges are typically implemented through the
transfer of a data file, although it could also include the entry of information into a
common database. All the information exchanges identified in the BIM Overview Map
should be detailed, as defined in Chapter Five.
The exchanges which originate from a process box are exchanges which are internal to a
process. The exchanges which originate or flow into the sequence line are external
exchanges which are shared between high-level processes. For example, Figure 3-2
Previous:
shows Select Model
information Uses
exchanges arising from the ‘Perform 3D Coordination’ process box
for the Laboratory Project. These exchanges, although internal
Next: to the
Define the 3D Coordination
Information Exchanges

https://psu.pb.unizin.org/bimprojectexecutionplanning/chapter/process/ 3/9
19.10.21, 16:53 Design the BIM Process – BIM Project Execution Planning Guide, Version 3.0

Process, should be identified in the BIM Overview Map since multiple parties author the
exchanged information. This ensures that the exchanges will be detailed using the
information exchange definition procedure described in Chapter Five.

Figure 3.2: Portion of the BIM Overview Map for a Sample Laboratory Building Project

To illustrate the results of an overview mapping task, the BIM Overview Map for the
Laboratory Project defines the overall BIM Uses that the team has employed for the
project which are Design Authoring, Energy Analysis, 4D Modeling, 3D Design
Coordination, and Record Modeling (reference Figure 3-3). It identifies that Energy
Analysis is performed during the schematic design phase, whereas 4D Modeling and 3D
Design Coordination are performed during design development and the construction
document
Previous:phases. TheUses
Select Model map also identifies the critical Information Exchanges that are
shared between different parties.
Next: Define the Information Exchanges

https://psu.pb.unizin.org/bimprojectexecutionplanning/chapter/process/ 4/9
19.10.21, 16:53 Design the BIM Process – BIM Project Execution Planning Guide, Version 3.0

Figure 3.3: BIM Overview Map for a Sample Laboratory Building Project

Creating a Detailed BIM Use Map


After creating an Overview Map, a Detailed BIM Use Process Map must be created for
each identified BIM Use to clearly define the sequence of the various processes
performed within that Model Use. It is important to realize that each project and
company is unique, so there may be many potential methods that a team could use to
achieve a particular process. Therefore, these template process maps need to be
customized by project teams to accomplish the project and organizational goals. For
example, the template process map may need to be tailored to integrate a specific
computer application workflow or project teamwork sequence.
A Detailed BIM Use Process Map includes three categories of information which are
represented on the left side of the process map and the elements are included in the
horizontal lines (referred to as ‘lanes’ in the BPMN mapping notation):
1. Reference Information: Structured information resources (enterprise and external)
required to execute a BIM Use
2. Process: A logical sequence of activities that constitute a particular BIM Use
3. Information Exchange: The BIM deliverables from one process which may be required
as a resource for future processes
Previous: Select Model Uses
To create a Detailed Process Map, a team should:
Next: Define the Information Exchanges

https://psu.pb.unizin.org/bimprojectexecutionplanning/chapter/process/ 5/9
19.10.21, 16:53 Design the BIM Process – BIM Project Execution Planning Guide, Version 3.0

1) Hierarchically decompose the BIM Use into a set of processes


The core processes of the BIM Use need to be identified. These are represented by a
‘rectangular box’ symbol within BPMN. These are placed in sequential order within the
Process swim lane.

2) Define the dependency between processes


Next, dependencies between the processes are defined. This is accomplished by
defining the connections between processes. The project team needs to identify the
predecessor and successor of each process. In some cases, it may be possible to have
multiple successors and /or predecessors. These processes are then connected using
the ‘sequence flow’ lines in BPMN.

3) Develop the Detailed Process Map with the following information


a. Reference Information: Identify the informational resources needed to accomplish
the BIM Use in the ‘Reference Information’ lane. Examples of reference information
include cost databases, weather data, and product data.
b. Information Exchanges: All the exchanges (internal and external) should be defined in
the ‘Information Exchange’ lane. These exchanges are further detailed out in Chapter
Four.
c. Responsible Party: Identifies the responsible party for each process. Figure 3-4
displays how to represent this information in the process map.

4) Add Goal Verification Gateways at crucial decision points in the process


A gateway can be used to ensure that the deliverables or results of a process are met. It
could also modify the process path based on a decision. Gateways provide the
opportunity for the project team to represent any decisions, iterations or quality
control checks required before the completion of a BIM task. Figure 3-4 demonstrates
how this can be accomplished within a Detailed BIM Process Map (Level-Two Map).

Figure 3.4: Example Goal Verification Gateway

5) Document, review and refine this process for further use


ThisPrevious:
Detailed Process
Select Map can be further used for other projects by the project team. It
Model Uses

should be saved and reviewed at various times throughout the BIM Implementation
Next: Define the Information Exchanges

https://psu.pb.unizin.org/bimprojectexecutionplanning/chapter/process/ 6/9
19.10.21, 16:53 Design the BIM Process – BIM Project Execution Planning Guide, Version 3.0

process. Throughout the project, detailed process maps should be updated periodically
to reflect the actual workflows implemented on the project. Additionally, after project
completion, it may be helpful to review the process maps to compare the actual process
used versus the planned process. Detailed process maps can likely be used on future
projects. Please reference Figure 3-5 for an example of a Detailed BIM Use Process
Map.

Figure 3.5: Detailed BIM Use Process Map for 4D Modeling

Symbols Used for Process Map Representation


For BIM Execution, the preferred notation for process mapping development is the
Business Process Modeling Notation (BPMN) developed by the Management Group.
One of the key elements of the BPMN is the visual appearance of the process map in
terms of the symbols and markers used. These should conform to the shapes defined in
BPMN specification.

The following symbols can be used to develop a Process Map for the BIM Plan:

Table 3.1: Process Mapping Notation for BIM Process Maps

Previous: Select Model Uses

Next: Define the Information Exchanges

https://psu.pb.unizin.org/bimprojectexecutionplanning/chapter/process/ 7/9
19.10.21, 16:53 Design the BIM Process – BIM Project Execution Planning Guide, Version 3.0

LICENSE SHARE THIS BOOK

BIM Project Execution Planning


Guide, Version 3.0 by Computer
Integration Construction Program is
licensed under a Creative Commons
Attribution-ShareAlike 4.0
International License, except where
otherwise noted.
Previous: Select Model Uses

Next: Define the Information Exchanges

https://psu.pb.unizin.org/bimprojectexecutionplanning/chapter/process/ 8/9
19.10.21, 16:53 Design the BIM Process – BIM Project Execution Planning Guide, Version 3.0

Powered by Pressbooks
Guides and Tutorials | Contact

Previous: Select Model Uses

Next: Define the Information Exchanges

https://psu.pb.unizin.org/bimprojectexecutionplanning/chapter/process/ 9/9

You might also like