Work Breakdown Structure
Work Breakdown Structure
Example of a product oriented work breakdown structure of an aircraft system. A work breakdown structure (WBS) in project management and systems engineering, is a deliverable oriented decomposition of a project into smaller components. It defines and groups a project's discrete work elements in a way that helps organize and define the total work scope of the project.[1] A work breakdown structure element may be a product, data, a service, or any combination. A WBS also provides the necessary framework for detailed cost estimating and control along with providing guidance for schedule development and control. .[1]
Contents
[hide]
1 Overview
2 History 3 WBS design principles o 3.1 The 100% rule 3.1.1 Mutually exclusive elements o 3.2 Planned outcomes, not planned actions o 3.3 Level of detail o 3.4 WBS coding scheme o 3.5 Terminal element 4 Example 5 Misconceptions 6 See also 7 References 8 Further reading
[edit] Overview
Example of work breakdown structure applied in a NASA reporting structure.[2] The work breakdown structure is a tree structure, which shows a subdivision of effort required to achieve an objective; for example a program, project, and contract. [2] In a project or contract, the WBS is developed by starting with the end objective and successively subdividing it into manageable components in terms of size, duration, and responsibility (e.g., systems, subsystems, components, tasks, subtasks, and work packages) which include all steps necessary to achieve the objective. The work breakdown structure provides a common framework for the natural development of the overall planning and control of a contract and is the basis for dividing work into definable increments from which the statement of work can be developed and technical, schedule, cost, and labor hour reporting can be established.[2] A work breakdown structure permits summing of subordinate costs for tasks, materials, etc., into their successively higher level parent tasks, materials, etc. For each element of the work breakdown structure, a description of the task to be performed is generated.[3]
This technique (sometimes called a system breakdown structure [4]) is used to define and organize the total scope of a project. The WBS is organised around the primary products of the project (or planned outcomes) instead of the work needed to produce the products (planned actions). Since the planned outcomes are the desired ends of the project, they form a relatively stable set of categories in which the costs of the planned actions needed to achieve them can be collected. A well-designed WBS makes it easy to assign each project activity to one and only one terminal element of the WBS. In addition to its function in cost accounting, the WBS also helps map requirements from one level of system specification to another, for example a requirements cross reference matrix mapping functional requirements to high level or low level design documents.
[edit] History
The concept of work breakdown structure developed with the Program Evaluation and Review Technique (PERT) in the United States Department of Defense (DoD). PERT was introduced by the U.S. Navy in 1957 to support the development of its Polaris missile program. [1] While the term "work breakdown structure" was not used, this first implementation of PERT did organize the tasks into product-oriented categories.[5] By June 1962, DoD, NASA and the aerospace industry published a document for the PERT/COST system which described the WBS approach.[6] This guide was endorsed by the Secretary of Defense for adoption by all services.[7] In 1968, the DoD issued "Work Breakdown Structures for Defense Materiel Items" (MIL-STD-881), a military standard requiring the use of work breakdown structures across the DoD.[8] This standard established top-level templates for common defense materiel items along with associated descriptions (WBS dictionary) for their elements. The document has been revised several times, most recently in 2005. The current version of this document can be found in "Work Breakdown Structures for Defense Materiel Items" (MIL-HDBK-881A).[9] It includes instructions for preparing work breakdown structures, templates for the top three levels of typical systems, and a set of "common elements" that are applicable to all major systems and subsystems.
Example from MIL-HDBK-881, which illustrates the first three levels of a typical aircraft system.[10] Defense Materiel Item categories from MIL-HDBK-881A:
Aircraft Systems Electronic/Automated Software Systems Missile Systems Ordnance Systems Sea Systems Space Systems Surface Vehicle Systems Unmanned Air Vehicle Systems Common Elements
The common elements identified in MIL-HDBK-881A, Appendix I are: Integration, assembly, test, and checkout; Systems engineering; Program management; Training; Data; System test and evaluation; Peculiar support equipment; Common support equipment; Operational and site activation; Industrial facilities; and Initial spares and repair parts In 1987, the Project Management Institute (PMI) documented the expansion of these techniques across non-defense organizations. The Project Management Body of Knowledge (PMBOK) Guide provides an overview of the WBS concept, while the "Practice Standard for Work Breakdown Structures" is comparable to the DoD handbook, but is intended for more general application.[11]
One of the most important work breakdown structure design principles is called the 100% Rule.[12] It has been defined as follows: The 100% Rule...states that the WBS includes 100% of the work defined by the project scope and captures all deliverables internal, external, interim in terms of the work to be completed, including project management. The 100% rule is one of the most important principles guiding the development, decomposition and evaluation of the WBS. The rule applies at all levels within the hierarchy: the sum of the work at the child level must equal 100% of the work represented by the parent and the WBS should not include any work that falls outside the actual scope of the project, that is, it cannot include more than 100% of the work It is important to remember that the 100% rule also applies to the activity level. The work represented by the activities in each work package must add up to 100% of the work necessary to complete the work package.[13] [edit] Mutually exclusive elements Mutually exclusive: In addition to the 100% Rule, it is important that there is no overlap in scope definition between two elements of a work breakdown structure. This ambiguity could result in duplicated work or mis-communications about responsibility and authority. Such overlap could also cause confusion regarding project cost accounting. If the WBS element names are ambiguous, a WBS dictionary can help clarify the distinctions between WBS elements. The WBS Dictionary describes each component of the WBS with milestones, deliverables, activities, scope, and sometimes dates, resources, costs, quality.
A question to be answered in determining the duration of activities necessary to produce a deliverable defined by the WBS is when to stop dividing work into smaller elements. There are several heuristics or "rules of thumb" used when determining the appropriate duration of an activity or group of activities necessary to produce a specific deliverable defined by the WBS.
The first is the "80 hour rule" which means that no single activity or group of activities to produce a single deliverable should be more than 80 hours of effort. The second rule of thumb is that no activity or series of activities should be longer than a single reporting period. Thus if the project team is reporting progress monthly, then no single activity or series of activities should be longer than one month long. The last heuristic is the "if it makes sense" rule. Applying this rule of thumb, one can apply "common sense" when creating the duration of a single activity or group of activities necessary to produce a deliverable defined by the WBS.
can be realistically and confidently estimated; makes no sense practically to break down any further; can be completed in accordance with one of the heuristics defined above; produces a deliverable which is measurable; and forms a unique package of work which can be outsourced or contracted out.
[edit] Example
The WBS Construction Technique employing the 100% Rule during WBS construction. The figure on the right shows a work breakdown structure construction technique that demonstrates the 100% Rule and the "progressive elaboration" technique. At WBS Level 1 it shows 100 units of work as the total scope of a project to design and build a custom bicycle. At WBS Level 2, the 100 units are divided into seven elements. The number of units allocated to each element of work can be based on effort or cost; it is not an estimate of task duration. The three largest elements of WBS Level 2 are further subdivided at Level 3. The two largest elements at Level 3 each represent only 17% of the total scope of the project. These larger elements could be further subdivided using the progressive elaboration technique described above. WBS design can be supported by software (e.g. a spreadsheet) to allow automatic rolling up of point values. Estimates of effort or cost can be developed through discussions among project team members. This collaborative technique builds greater insight into scope definitions, underlying assumptions, and consensus regarding the level of granularity required to manage the project.
[edit] Misconceptions
A WBS is not an exhaustive list of work. It is instead a comprehensive classification of project scope. A WBS is neither a project plan, a schedule, nor a chronological listing. It specifies what will be done, not how or when. A WBS is not an organizational hierarchy, although it may be used when assigning responsibilities. See also: responsibility assignment (RACI) matrix (also called a Staffing Matrix).