Loop Test Procedure
Loop Test Procedure
1 Purpose
The purpose of this document is to describe the loop test process and required tools
drawing, materials, inprovision Field Instrument at IKPT, this procedure
shall be applied calibration and ensure that each instrument is functionally correct and
correctly calibrated
2 Scope Of Work
The scope of work shall be covered all function testadditional capacity at IKPT
3 Responsibilities
3.1 Instrument Leader
Ensure relevant permits are raised and received prior to commencement of work with full
compliance by all instrument foreman, technician, and labour regarding excutions of work
in accordance with the IKPT project requirments and specification. Confirm the anailability
of the material, tools, equipment personnel who will carry out work
3.3 Safety
ensure that personal comply with all safety rulles and requipments in the conduts of all
instrument equipment installation activities performed in the project
4 Technical requirement
4,1 Tools for Loop Test
a_ Digital multi-meter
b. DC standard voltage and current generator
c. Standard resistance box and thermocouple
d. Hand Held Communicator for Smart Transmitters and Smart
e. Hand pump
f. Pressure gauge / digital pressure gauge
g. Precision air regulator
h. Compressor / Nitrogen with air pressure
i. Connector, Tubing of various sizes
j. Others, if any
Safety precaution:
a. Make sure the PPE is use Correctly
b. Make sure all equipment before using it in good condition and has passed inspection.
c. Ensure all employees who work above the level attended training working at heigth.
d. Use acces up and down and work, with scaffolding that has been in the inspection.
e. Ensure full body harness is hung acces strong and above the head.
f. In the work place should be displayed safety sign.
g. Barricade the work place.
h. Fit to work for working at height location.
-----END-----