Test and inspections are in the complete purview of the AMISP and its sub-
vendors. It shall be ensured that there are no conflicts in roles played between
AMISP personnel carrying out tests / inspections, and those assigned
responsibilities of quality assurance (QA) and quality control (QC).
The QA/QC organization of the AMISP shall be an independent administrative
and functional structure reporting via its manager to the AMISP’s top management.
The QA/QC manager(s) shall have the authority within the delegated areas of
responsibility to resolve all matters pertaining to quality when actual quality
deviates from that stated in the Work Statement. The personnel performing
QA/QC functions shall have well-defined responsibility, authority, and
organizational freedom to identify and evaluate quality problems and to initiate,
recommend, or provide solutions during all phases of the Contract.
The QA/QC Manager designate for the project shall be the custodian of all
inspection and test records/certificates. QA/QC Manager either directly or
through its authorized representative shall be responsible for all witness
testing, approval of test records and in general, management of the QA/QC
program of the project.
The responsibility for inspections and tests is borne by the Inspections and
Tests Manager. This team is responsible for creating the various inspection and
test procedures and under the general supervision of the QA/QC Manager,
conducts the tests.
In the event any imports are required for the purposes of this AMISP Contract,
such imports shall be in accordance with all applicable laws including those
issued by Ministry of Power (Order No. No.9/16/2016-Trans-Part(2) dated 18
November 2020; as amended and/ or modified from time to time) for testing of
imports including those from prior reference countries.
e) For pluggable NIC modules, the type tests shall be carried out with
the NIC module integrated in the field device, that is meters and
DCUs being supplied under the project.
h) The AMISP shall ensure that all type tests can be completed within
the time schedule offered in its Technical Proposal.
i) In case of failure during any type test, the AMISP shall follow the
conformance criteria as laid out in corresponding standard (refer
serial number c and d above)
j) For direct connected Smart Meters, the Data Exchange Protocol Tests
shall follow IS 16444 (Part 1) read in conjunction with IS 15959
(Parts 1 & 2). The sampling criteria for running these tests shall be
[one per one lakh] smart meters under production.
l) Documentation for all factory, field, and availability tests that apply to
the AMI system shall be provided in accordance with the
requirements defined in this section of specification
9.2.2 Quality Assurance and Quality Control Program
A Quality Assurance Program of the AMISP shall cover but not be limited to
the following:
b) Date of test
However, at any stage if QA/QC Manager feels that quality of variances calls for
suspension of the testing the testing shall be halted till satisfactory resolution of
variances, which may involve retesting.
The QA/QC Manager shall maintain and periodically distribute a variance summary
that lists for each variance the report number, a brief description of the variance, its
class, and its current status (open or resolved).
All actions taken to correct variances shall be documented on the variance report by
the AMISP. Sufficient information shall be recorded to enable QA/QC representative
to determine the need for and extent of retesting, the need for testing interactions
of the correlation with any previously tested hardware or software, and the need for
updating appropriate documentation. A variance shall be deemed resolved after
retesting has been performed satisfactorily and the test engineer and QA/QC
representatives have acknowledged correction of the variance on the variance
report.
9.2.4.2 Test Initiation
The following conditions must be satisfied before starting any test
a) All test plans and procedures for the test shall be available.
b) All test records have been documented and issued QA/QC acknowledges, in writing,
successful completion of the test.