Practice Notes For Quantity Surveyors - Cost Control and Financial Statements 202109

Download as pdf or txt
Download as pdf or txt
You are on page 1of 12

Cost Control and Financial Statements

PRACTICE
NOTES
FOR
QUANTITY
SURVEYORS

Cost Control and


Financial Statements
Cost Control and Financial Statements
Contents
CONTENTS
Page
Preface 1
1. Nature and Purpose 2
2. Importance 2
3. Role of Quantity Surveyor 2
4. Format 3
5. Contract Details and Information 3
6. Financial Adjustments 3
7. Architect’s Instruction Pre-approval (AI Pre-approval) 6
8. Mechanical and Electrical works 8
9. Submission of Financial Statements 8
10. Project Cost Review Statement 9

Disclaimer

All parties must rely exclusively upon their own skill and judgment when making use
of this document. Neither The Hong Kong Institute of Surveyors, Association of Con-
sultant Quantity Surveyors nor any of the committee members and any other con-
tributor assumes any liability to anyone for any loss or damage caused by any error
or omission, whether such error or omission is the result of negligence or any other
cause. Any and all such liability is disclaimed.
Cost Control and Financial Statements
PREFACE

A Working Committee with representatives of The Hong Kong Institute of Surveyors,


Association of Consultant Quantity Surveyors and Hong Kong Construction
Association was set up in October 2010 to establish a set of Practice Notes for the
benefit of Quantity Surveying professionals in Hong Kong.

The Practice Notes are not intended to promulgate a standard of practice, but rather
to produce some basic guidelines for the following core practices:

Name of Practice Notes Latest Version


Pre-contract Estimates and Cost Plans October 2016 *
Procurement Strategy July 2021 ^
Tendering November 2012 *
Cost Control and Financial Statements September 2021 *
Valuation for Interim Payment Certificates August 2014 *
Valuation of Variations November 2012 *
Contractual Claims November 2012 *
Final Accounts November 2012 *
* jointly prepared by The Hong Kong Institute of Surveyors, Association of Consultant Quantity Surveyors
and Hong Kong Construction Association with input from Architectural Services Department and Hong Kong
Housing Authority

^ jointly prepared by The Hong Kong Institute of Surveyors and Association of Consultant Quantity Surveyors

As different employer organisations will have their own procedures and


requirements, the Practice Notes, which are prepared mainly for private sector
projects using the HKIA/HKIS Standard Forms of Building Contract, should be
adapted as appropriate. Employers should consult professional quantity surveyors
for advice to suit the specific requirements of individual projects.

The members of the Working Committee who updated the Practice Notes for the Cost
Control and Financial Statements are:

Representing The Hong Kong Institute of Surveyors


• Mr. Ho Yin WAN
• Mr. Ken HUI

Representing Association of Consultant Quantity Surveyors


• Mr. Thomas HO
• Mr. Ki Cheung TANG

1
Cost Control and Financial Statements
1. NATURE AND PURPOSE

A Financial Statement is a periodic cost report which shows the financial


status of a project at regular intervals during the construction stage. It gives
necessary cost information to the Employer, Architect and other relevant
parties to enable the project team to control the cost of the project.

2. IMPORTANCE

The necessity and growing importance of the provision of periodic cost


reports for cost control purposes are due to the following factors:

(a) The growth in size and complexity of projects and high cost involved.

(b) Where, in order to gain time, construction of projects sometimes start


without adequate planning and preparation.

(c) Where the Employer is the Government or a public body, and a funding
arrangement has been adopted. It is imperative that the final cost of a
project must be kept within the approved budget.

(d) The incessant fluctuation in construction cost in volatile years.

3. ROLE OF QUANTITY SURVEYOR

Cost control is one of the core services provided by Quantity Surveyors within
the construction industry. The basic objectives are to demonstrate good value
for money for the employers, achieve the required balance of expenditure
between the various components / elements of the project, and keep the final
expenditure within the Employers’ approved budget.

Quantity Surveyors regularly prepare cost reports (financial statements) in the


form of a summary of the estimated final contract sum taking into account the
cost implications of issued variations, anticipated variations, possible claims
for loss and/or expense and, where appropriate, fluctuations in the costs
of labour and/or materials. This allows the Employer, Architect and Project
Team to have an up-to- date assessment of the financial state of the project
to enable them to take any necessary measures to control cost or redirect the
project if required.

In the preparation of financial statements, the Quantity Surveyor should work


closely with the Architect and other consultants so that all the information
that would affect the project costs is passed to the Quantity Surveyor without
delay and misunderstanding.

2
Cost Control and Financial Statements
4. FORMAT

The format of a financial statement is largely dependent upon the Employer’s


requirements.

For those Employers who would like to know the up-to-date contract sum
as well as the estimated final contract sum, a running total should first
be calculated without taking into account the contingency sum for further
variations or the forecast of value of fluctuations to give the up-to-date
contract sum. The contingency sum for further variations and the forecast of
value of fluctuations are then added to the up to date contract sum to give the
estimated final contract sum.

5. CONTRACT DETAILS AND INFORMATION

The statement number and the date up to which the financial statement is
prepared are given to indicate the period the financial statement is related to.
Such information is important to avoid confusion with a periodic report which
is prepared at regular intervals.

The contract details should be listed to give the basic project information.
These include the Contract Title, Contract Number, Contract Period, Date of
Commencement, Date for Completion, the name of the Employer and the
Contractor.

6. FINANCIAL ADJUSTMENTS

To arrive at the Estimated Final Contract Sum for the project, the Original
Contract Sum is first listed, and then adjustments made for the following
items.

(a) Omission of Provisional Sum for Contingencies

The Provisional Sum for Contingencies, which has been included in the
Contract Sum to cover the cost of variations and of works which could
not be entirely foreseen at the time the tender documents are issued, is
first omitted from the Contract Sum.

(b) Adjustment of P.C. Sums

The Prime Cost Sums, which have been included in the Contract Sum to
cover the cost of works or services to be executed by Nominated Sub-
Contractors or for materials or goods to be obtained from Nominated
Suppliers, are adjusted after the award of such Nominated Sub-Contracts
or Nominated Supply Contracts. The profit on the respective P.C. Sums
should also be adjusted.

3
Cost Control and Financial Statements
For Nominated Sub-Contracts or Nominated Supply Contracts which have
not been awarded, the original Prime Cost Sums should be listed to give
information to the Employer and Architect of the sums that are subject to
adjustment when the contracts have been awarded.

(c) Adjustment of Provisional Quantities, Provisional Sums and P.C. Rates

Adjustments should be made for works measured as Provisional


Quantities or allowed by way of Provisional Sums or P.C. Rates when the
details of these works are finalised. If these adjustments cannot be made
due to lack of information, a note should be made and a brief description
given next to the various sums allowed for to indicate the extent of sums
subject to further adjustment.

The remeasurements should be commenced as soon as the majority of


the necessary information is available so that an estimate of the final cost
effect can be calculated at the earliest possible date.

(d) Variations

All the instructed variations should be measured and adjustments made


to the Contract Sum. If time does not allow for detailed measurement
of all the issued variation orders at the time the financial statement
is prepared, estimates should be made to show the cost effect of the
unmeasured variations on the Contract Sum. The number of variation
orders for which estimates are prepared should be kept to a minimum to
increase the accuracy of the financial statement.

A note should be included against each instructed variation to show


whether it has been measured and the value agreed with the Contractor,
has been measured but is not yet agreed or is estimated only. Such
information is important to show the degree of accuracy and finalisation
of the estimated final contract sum as the more instructed variations that
have been measured and agreed with the Contractor, the more accurate
will be the estimated final Contract Sum.

For those variation orders that have been measured but not yet agreed
with the Contractor, a contingency should be included in each variation
order to allow for future negotiation and agreement. The amount of this
contingency will be affected by the number of ‘Star rates’ included in the
calculation or whether there are special working conditions that would
result in extra expense to the Contractor.

Quantity Surveyors should try to identify which variations are major and
which are minor. Special attention should be given to variations with a
major cost effect.

4
Cost Control and Financial Statements
(e) Instructions confirmed by the Contractor but for which Architect’s
Instructions have not been issued

In accordance with the Conditions of Contract, any verbal instructions of


the Architect will have contractual effect if it is confirmed in writing by
the Contractor within seven days, and if not dissented from in writing
by the Architect to the Contractor within seven days from receipt of the
Contractor’s confirmation. Therefore, the cost implication of any such
confirmed instruction should also be included in the financial statement.
As with Instructed Variations, each such confirmation should have a note
to show whether it has been measured and the value agreed with the
Contractor, has been measured but is not yet agreed or is estimated only.

(f) Anticipated Variation Works for which no instructions have been issued

The cost effect of any proposed variation works which are under
consideration should be included in the financial statement.

The cost of such anticipated variations are usually estimated based on


preliminary sketches and information from the Architect. Such sketches
and information will probably change as the design of the anticipated
variations develops and requirements change. Hence it is important that
the information on which the estimate has been based should be clearly
spelt out in the description of each anticipated / proposed variation item
in the financial statement to avoid any misunderstanding. The Quantity
Surveyor should work closely with the Architect to ensure that the most
updated information is being used in the estimate.

Before commencing the preparation of each financial statement the


Architect should be asked whether any anticipated variations included in
the last financial statement are going to be dropped. If any anticipated
variations are no longer required they must be deleted from the
upcoming financial statement. Attention should also be paid to those
anticipated variations which have been covered by formal instructions
since the last financial statement. Such items should be deleted from the
anticipated variation works section to avoid double counting their cost
effect.

(g) Contingency for further variations during the remainder of the Contract

A contingency sum should be included in the financial statement for


possible further variations during the remainder of the Contract. The
amount allowed should relate to the stage of construction work and
the amount of works which still cannot be entirely defined or detailed.
Discussions should be held with the Architect before any contingency
allowance is made.

5
Cost Control and Financial Statements
(h) Provisional assessment of amount of direct loss and/or expense resulting
from disturbance to the regular progress or works

In accordance with the Conditions of Contract, the Contractor is entitled to


be reimbursed for any direct loss and/or expense by reason of the regular
progress of the works having been materially affected by the listed events
in the Contract. An amount should be allowed in the financial statement
where such loss and/or expense has been incurred and a provisional
assessment should be made if the actual amount cannot be calculated
due to inadequate information.

(i) Adjustment of Labour and / or Material Fluctuation Allowance

The Provisional Sum allowed for fluctuations in labour and / or material


costs in the original contract sum is first omitted. An amount is then
added back for the actual amount of fluctuations incurred plus a forecast
of the amount of fluctuations likely to be incurred during the remainder
of the contract. This is assessed based on the past trend of fluctuations.

(j) Rejected Claims

It may also be worthwhile to advise the Employer of the amounts of


any major claims from the Contractor which are in dispute or have
been rejected by the Consultants in case of the Contractor is able to
substantiate these claims at a late date. The amount of these claims
should not be included in the estimated final cost but should be given
separately for information only.

(k) Certified gross value for payment

The amount of the certified gross value for payment up to the date of
the financial statement is listed for the Employer’s cash flow planning
by comparing his current financial commitment and the estimated final
financial commitment.

7. ARCHITECT’S INSTRUCTION PRE-APPROVAL (AI PRE-APPROVAL)

To provide better cost control of a project, a cost estimate of a proposed


Architect’s instruction for changes could be prepared for approval by the
Employer before the said instruction is formally issued. The cost estimate can
help the Employer and the Project Team realize the financial impact to the
project and hence make decisions on whether the proposed changes may be
adopted, adjusted or cancelled. This process is of particular importance for
projects having tight budgets.

6
Cost Control and Financial Statements
The purpose of AI Pre-approval is to provide a rough estimate of the financial
and time impacts of the proposed changes to the Employer for decision
making. It should not be mixed up with the valuation of variations which is a
detailed assessment of the cost of the changes instructed, and the Employer
should be reminded of this purpose.

The cost estimate for the proposed changes under an AI Pre-approval must
be completed as soon as possible in order not to delay the decision making
and, if the changes are desired (and unavoidable), issuance of the formal
Architect’s instruction.

It may be possible that the proposed changes are cancelled or adjusted


if the cost estimate is beyond the expected budget of the Employer. It is
not desirable to wait till the proposed changes are finalized (e.g., in terms
of detailed drawings) before commencing the cost estimate, as this may
create unnecessary abortive work to the Project Team. Estimating based on
preliminary ideas of the proposed changes would mean that the cost estimate
can only be approximate.

When new rates are to be used, appropriate allowances should be included


in the cost estimate to cater for deviations in the market rates but should be
within a reasonable range. There may also be circumstances of some cost
elements not readily perceived at the time of the change proposed but may
eventually be part of the additional cost claims by the Contractor.

On the other hand, the Employer would see the cost estimate for the proposed
changes under an AI Pre-approval as the upper limit not to be exceeded. As
such, the cost estimate should only be a quick and rough indication of cost
but sufficient enough with buffers to cover the above circumstances to serve
as a budgetary allowance, which is more important than emphasizing on
trivial accuracy. It is not necessary to estimate in detail, which will cause delay
in making decisions and issuance of the formal Architect’s instruction.

Instead of spending unnecessarily long time to carry out detailed cost


estimate for the proposed changes under an AI Pre-approval, it is more
meaningful to spend the time saved to settle the variations with the
Contractor, which will give a more definite outcome for cost control.

Method applying approximate quantities and composite rates should be


adopted in preparing cost estimates for the proposed changes under an
AI Pre-approval and the Quantity Surveyor should focus on items with
substantial cost implication with reasonable round-up in Net Addition and
round-down in Net Omission, with buffers for deviations within a reasonable
range.

7
Cost Control and Financial Statements
The Quantity Surveyor should communicate with the relevant design
consultant(s) to sort out all ambiguous issues under a proposed change,
make and state all necessary assumptions/exclusions in the cost estimate for
an AI Pre-approval. For changes under an AI Pre-approval involving new rates,
the Contractor can be requested to provide quotations for information.

Different employers may have different forms for AI Pre-approval. In general,


the AI Pre-approval Form should normally include the following information:

(a) Reference No. (preferably of the same no. of the Architect’s Instruction to
be subsequently issued)

(b) Project particulars (project number, project and contract title)

(c) Description of the proposed Architect’s Instruction

(d) Drawings related to the Architect’s Instruction

(e) Reasons for justifications of the Architect’s Instruction

(f) Indicative cost estimate and/or time impact of the Architect’s Instruction

(g) Signature boxes for the Architect and/or design consultant(s)

(h) Signature/Approval box for the Employer

(i) Date of approval by the Employer

8. MECHANICAL AND ELECTRICAL WORKS

Where the Mechanical and Electrical (M&E) consultants have been employed
to deal with the financial aspects of the M&E works in the project, the
financial report in respect of the M&E works will usually be prepared by these
consultants. The Quantity Surveyor should collect this cost information from
the M&E consultants for incorporation into the financial statement.

9. SUBMISSION OF FINANCIAL STATEMENTS

It is advisable to include an Architect’s report section in the financial


statements and to send the draft financial statements to the Architect for
review with regard to funding approval and allocation, extension of time and
liquidated damages, etc. before forwarding the final version to the Employer.
Any items which are in doubt or are very significant should be drawn to the
attention of the Architect in the covering letter. The financial statement should
be arithmetically checked before it is sent out to the Architect.

8
Cost Control and Financial Statements
10. PROJECT COST REVIEW STATEMENT

Apart from the monthly financial statement described above, which is


for individual contracts, an overall project cost review statement may be
required by the Employer to show the financial state of the whole project
which may consist of several contracts. The preparation of the project cost
review statement is effected by combining the financial statements for each
individual contract in the project and is usually prepared quarterly or half-
yearly.

9
Cost Control and Financial Statements

September 2021

You might also like