Practice Notes For Quantity Surveyors - Cost Control and Financial Statements 202109
Practice Notes For Quantity Surveyors - Cost Control and Financial Statements 202109
Practice Notes For Quantity Surveyors - Cost Control and Financial Statements 202109
PRACTICE
NOTES
FOR
QUANTITY
SURVEYORS
Disclaimer
All parties must rely exclusively upon their own skill and judgment when making use
of this document. Neither The Hong Kong Institute of Surveyors, Association of Con-
sultant Quantity Surveyors nor any of the committee members and any other con-
tributor assumes any liability to anyone for any loss or damage caused by any error
or omission, whether such error or omission is the result of negligence or any other
cause. Any and all such liability is disclaimed.
Cost Control and Financial Statements
PREFACE
The Practice Notes are not intended to promulgate a standard of practice, but rather
to produce some basic guidelines for the following core practices:
^ jointly prepared by The Hong Kong Institute of Surveyors and Association of Consultant Quantity Surveyors
The members of the Working Committee who updated the Practice Notes for the Cost
Control and Financial Statements are:
1
Cost Control and Financial Statements
1. NATURE AND PURPOSE
2. IMPORTANCE
(a) The growth in size and complexity of projects and high cost involved.
(c) Where the Employer is the Government or a public body, and a funding
arrangement has been adopted. It is imperative that the final cost of a
project must be kept within the approved budget.
Cost control is one of the core services provided by Quantity Surveyors within
the construction industry. The basic objectives are to demonstrate good value
for money for the employers, achieve the required balance of expenditure
between the various components / elements of the project, and keep the final
expenditure within the Employers’ approved budget.
2
Cost Control and Financial Statements
4. FORMAT
For those Employers who would like to know the up-to-date contract sum
as well as the estimated final contract sum, a running total should first
be calculated without taking into account the contingency sum for further
variations or the forecast of value of fluctuations to give the up-to-date
contract sum. The contingency sum for further variations and the forecast of
value of fluctuations are then added to the up to date contract sum to give the
estimated final contract sum.
The statement number and the date up to which the financial statement is
prepared are given to indicate the period the financial statement is related to.
Such information is important to avoid confusion with a periodic report which
is prepared at regular intervals.
The contract details should be listed to give the basic project information.
These include the Contract Title, Contract Number, Contract Period, Date of
Commencement, Date for Completion, the name of the Employer and the
Contractor.
6. FINANCIAL ADJUSTMENTS
To arrive at the Estimated Final Contract Sum for the project, the Original
Contract Sum is first listed, and then adjustments made for the following
items.
The Provisional Sum for Contingencies, which has been included in the
Contract Sum to cover the cost of variations and of works which could
not be entirely foreseen at the time the tender documents are issued, is
first omitted from the Contract Sum.
The Prime Cost Sums, which have been included in the Contract Sum to
cover the cost of works or services to be executed by Nominated Sub-
Contractors or for materials or goods to be obtained from Nominated
Suppliers, are adjusted after the award of such Nominated Sub-Contracts
or Nominated Supply Contracts. The profit on the respective P.C. Sums
should also be adjusted.
3
Cost Control and Financial Statements
For Nominated Sub-Contracts or Nominated Supply Contracts which have
not been awarded, the original Prime Cost Sums should be listed to give
information to the Employer and Architect of the sums that are subject to
adjustment when the contracts have been awarded.
(d) Variations
For those variation orders that have been measured but not yet agreed
with the Contractor, a contingency should be included in each variation
order to allow for future negotiation and agreement. The amount of this
contingency will be affected by the number of ‘Star rates’ included in the
calculation or whether there are special working conditions that would
result in extra expense to the Contractor.
Quantity Surveyors should try to identify which variations are major and
which are minor. Special attention should be given to variations with a
major cost effect.
4
Cost Control and Financial Statements
(e) Instructions confirmed by the Contractor but for which Architect’s
Instructions have not been issued
(f) Anticipated Variation Works for which no instructions have been issued
The cost effect of any proposed variation works which are under
consideration should be included in the financial statement.
(g) Contingency for further variations during the remainder of the Contract
5
Cost Control and Financial Statements
(h) Provisional assessment of amount of direct loss and/or expense resulting
from disturbance to the regular progress or works
The amount of the certified gross value for payment up to the date of
the financial statement is listed for the Employer’s cash flow planning
by comparing his current financial commitment and the estimated final
financial commitment.
6
Cost Control and Financial Statements
The purpose of AI Pre-approval is to provide a rough estimate of the financial
and time impacts of the proposed changes to the Employer for decision
making. It should not be mixed up with the valuation of variations which is a
detailed assessment of the cost of the changes instructed, and the Employer
should be reminded of this purpose.
The cost estimate for the proposed changes under an AI Pre-approval must
be completed as soon as possible in order not to delay the decision making
and, if the changes are desired (and unavoidable), issuance of the formal
Architect’s instruction.
On the other hand, the Employer would see the cost estimate for the proposed
changes under an AI Pre-approval as the upper limit not to be exceeded. As
such, the cost estimate should only be a quick and rough indication of cost
but sufficient enough with buffers to cover the above circumstances to serve
as a budgetary allowance, which is more important than emphasizing on
trivial accuracy. It is not necessary to estimate in detail, which will cause delay
in making decisions and issuance of the formal Architect’s instruction.
7
Cost Control and Financial Statements
The Quantity Surveyor should communicate with the relevant design
consultant(s) to sort out all ambiguous issues under a proposed change,
make and state all necessary assumptions/exclusions in the cost estimate for
an AI Pre-approval. For changes under an AI Pre-approval involving new rates,
the Contractor can be requested to provide quotations for information.
(a) Reference No. (preferably of the same no. of the Architect’s Instruction to
be subsequently issued)
(f) Indicative cost estimate and/or time impact of the Architect’s Instruction
Where the Mechanical and Electrical (M&E) consultants have been employed
to deal with the financial aspects of the M&E works in the project, the
financial report in respect of the M&E works will usually be prepared by these
consultants. The Quantity Surveyor should collect this cost information from
the M&E consultants for incorporation into the financial statement.
8
Cost Control and Financial Statements
10. PROJECT COST REVIEW STATEMENT
9
Cost Control and Financial Statements
September 2021