This drawing provides a lifting plan for moving a TMC SQS250TL compressor on a lay down area, showing the required lifting gear including two 4-ton capacity webbing slings and two 3/4 inch shackles each with a 4.75 ton safe working load. The plan is for lifting the steel structure of the compressor unit located on the lay down area.

Uploaded by

aan hardiyansyah
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
62 views

TMC - Steel Loading-Unloading

This drawing provides a lifting plan for moving a TMC SQS250TL compressor on a lay down area, showing the required lifting gear including two 4-ton capacity webbing slings and two 3/4 inch shackles each with a 4.75 ton safe working load. The plan is for lifting the steel structure of the compressor unit located on the lay down area.

Uploaded by

aan hardiyansyah
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

THIS DWG

NCC SUBSTATION (10-SS-001)


DRY GAS SEAL PANEL
GAUGE BOARD

G OF COMPRESSOR
GAUGE BOARD

CG OF GEAR BOX
CG OF MOTOR

ACCESS WAY
00
65
R
Detail Lifting Gear

Webbing Sling 4 Ton


SWL : 4 Ton, 2 Pcs

Shackle for Lifting Lug


LINE PROJECT
Shackle 3/4 Inch, SWL : 4,75 Ton, 2 Pcs

Equipment : Steel Structure

Description :Lifting Plan For TMC SQS250TL on Lay Down Area

Tanggal gambar : Sheet :


29 Juli 2023 1/1