0% found this document useful (0 votes)
123 views3 pages

Open Access Charges

This document outlines various charges applicable to open access consumers and generators in three categories: transmission charges, wheeling charges and losses, and cross subsidy surcharge. Transmission charges vary by voltage level and contract term. Wheeling charges and losses depend on voltage level and year. Cross subsidy surcharges differ by consumer category and year. Additional charges include an additional surcharge on wheeling, operating charges, energy banking charges, and an application processing fee.

Uploaded by

babusonaiitkgp
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
123 views3 pages

Open Access Charges

This document outlines various charges applicable to open access consumers and generators in three categories: transmission charges, wheeling charges and losses, and cross subsidy surcharge. Transmission charges vary by voltage level and contract term. Wheeling charges and losses depend on voltage level and year. Cross subsidy surcharges differ by consumer category and year. Additional charges include an additional surcharge on wheeling, operating charges, energy banking charges, and an application processing fee.

Uploaded by

babusonaiitkgp
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

Open Access Charges:

The following charges are applicable to open access consumers / generators.


The bill will include the following charges:
i) Wheeling Charges / Transmission Charges, as may be applicable;
ii) Cross Subsidy Surcharge, as may be applicable;
iii) Additional Surcharge on the Charges of Wheeling;
iv) Standby Charges;
v) Voltage Surcharge, as may be applicable;
vi) Operating Charges;
vii) Energy Banking charges in kind for infirm RE only;
viii) Charges in case of drawl from the grid.
ix) Application Processing Fee.
ix) Any other charge or other sum recoverable.
The existing various Open Access charges are as under:
Transmission Charges:
Voltage level of FY Power Transaction Types
drawl point Medium Term/long term Short Term/ Short
(Rs/KW/Month) term collective &
Renewable energy
(Rs/KWh)
EHV/66 KV and 16-17 204.24 0.28
above 17-18 239.88 0.32
18-19 253.82 0.34
19-20 242.08 0.32

The MERC in case no. 48 of 2016 dated 03.11.2016 has determined Wheeling
Charges /losses, Cross subsidy surcharge and additional surcharge on wheeling
as follows:

Wheeling Charges / losses:

Particulars Wheeling Loss % Wheeling Charges (Rs./kWh)


FY 2016-17
33 kV 6.00% 0.09
22 kV / 11 kV 9.00% 0.82
LT Level 12.00% 1.18
FY 2017-18
33 kV 6.00% 0.09
22 kV / 11 kV 9.00% 0.83
Page 1 of 3
LT Level 12.00% 1.21
FY 2018-19
33 kV 6.00% 0.09
22 kV / 11 kV 9.00% 0.82
LT Level 12.00% 1.18
FY 2019-20
33 kV 6.00% 0.08
22 kV / 11 kV 9.00% 0.73
LT Level 12.00% 1.11

Cross Subsidy Surcharge:


Category FY 2016-17 FY 2017-18 FY 2018-19 FY 2019-20
CSS Rs. kWh
HT Category – EHV (66
kV and above)
HT I (A): Industry 1.62 1.63 1.64 1.66
HT II : Commercial 2.63 2.65 2.67 2.68
HT IV: PWW 1.33 1.37 1.40 1.41
HT Category –33 kV
HT I (A): Industry 1.64 1.65 1.66 1.67
HT II : Commercial 2.53 2.55 2.57 2.59
HT IV: PWW 1.24 1.21 1.24 1.33
HT Category –22 kV &
11 kV
HT I (A): Industry 1.79 1.80 1.80 1.80
HT II : Commercial 2.67 2.70 2.72 2.72
HT IV: PWW 1.24 1.06 1.11 1.21
LT Category.
LT V (B): 0-20 kW. 0.16 -- -- --
LT V (B): Above 20 kW. 1.83 1.83 1.86 1.87

Page 2 of 3
Additional Surcharge on wheeling:
All Open Access consumers except captive self-use shall pay Rs. 1.11/unit
as additional surcharge on wheeling.

Operating Charges:
For Open Access Capacity <= 5 MW: Rs. 10,000 / Month.
For Open Access Capacity > 5 MW: Rs. 20,000 / Month.

Energy Banking Charges:


Banking Charges shall be in kind @ 2% of the energy banked.

Application Processing Fee:

Processing Fee
Open Access Capacity G.S.T. (18%) TOTAL
per Application
For Load up to 1 MW Rs. 10,000/- Rs. 1,800/- Rs. 11,800/-
For load more than 1 Rs. 15,000/- Rs. 2,700/- Rs. 17,700/-
MW and up to 5 MW
For load more than 5 Rs. 30,000/- Rs. 5,400/- Rs. 35,400/-
MW and up to 20 MW
For load more than 20 Rs. 50,000/- Rs. 9,000/- Rs. 59,000/-
MW

Page 3 of 3

You might also like