BOM With DETAILED SOLUTION

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 31

Project: PROPOSED 1-Storey COMMERCIAL BUILDING

Owner:
Location:

BILL OF MATERIALS
ITEM NO. DESCRIPTION QUANTITY UNIT UNIT COST AMOUNT
A MOBILIZATION
B CLEARING OF AREA
C CLEARING OF DEMOLISHED DEBRIS
D ENCLOSURE OF AREA
Sub-total -
E EARTHWORKS
E.1 EXCAVATION
1 Footings
E.2 BACKFILLING / FILLING& COMPACTING
1 Gravel Fill (G1) 5.00 cu.m. 300 1,500.00
Sub-total 1,500.00
F FORMWORKS & SCAFFOLDINGS 2,500.00
G CONCRETE WORKS
G.1 CONCRETE FOOTINGS
1 Portland Cement 19.00 bags. 210.00 3,990.00
2 Screened sand 2.00 cu.m. 1250.00 2,500.00
3 ¾” Gravel 3.00 cu.m. 1200.00 3,600.00
4 10mm Ø Reinforced Steel bar 51.00 pcs. 105.00 5,355.00
5 #16 G.I. Tie Wire 5.00 kgs. 80.00 400.00
G.2 CONCRETE COLUMNS
1 Portland Cement 13.00 bags. 210.00 2,730.00
2 Screened sand 1.00 cu.m. 1250.00 1,250.00
3 ¾” Gravel 2.00 cu.m. 1200.00 2,400.00
4 10mm Ø Reinforced Steel bar 36.00 pcs. 105.00 3,780.00
5 8mm Ø Reinforced Steel bar 22.00 pcs. 77.00 1,694.00
6 #16 G.I. Tie Wire 15.00 kgs. 80.00 1,200.00
G.3 WALL FOOTING
1 Portland Cement 10.00 bags 210.00 2,100.00
2 Screened sand 2.00 cu.m. 1250.00 2,500.00
3 ¾” Gravel 3.00 cu.m. 1200.00 3,600.00
4 10mm Ø Reinforced Steel bar 22.00 pcs. 105.00 2,310.00
5 #16 G.I. Tie Wire 10.00 kgs. 80.00 800.00
G.4 CONCRETE BEAMS
1 Portland Cement 19.00 bags 210.00 3,990.00
2 Screened sand 2.00 cu.m. 1250.00 2,500.00
3 ¾” Gravel 3.00 cu.m. 1200.00 3,600.00
4 10mm Ø Reinforced Steel bar 52.00 pcs. 105.00 5,460.00
5 8mm Ø Reinforced Steel bar 27.00 pcs. 77.00 2,079.00
6 #16 G.I. Tie Wire 15.00 kgs. 80.00 1,200.00
G.5 SLAB ON GRADE
1 Portland Cement 33.00 bags 210.00 6,930.00
2 Screened sand 5.00 cu.m. 1250.00 6,250.00
3 ¾” Gravel 10.00 cu.m. 1200.00 12,000.00
4 10mm Ø Reinforced Steel bar 42.00 pcs. 105.00 4,410.00
5 #16 G.I. Tie Wire 15.00 kgs. 80.00 1,200.00
G.6 CHB WALL& PLASTERING
1 CHB 4" 750.00 nos 15.00 11,250.00
2 Cement 50.00 bags 210.00 10,500.00
3 Screened Sand 3.00 cu.m 1250.00 3,750.00
4 Fine Sand 3.50 cu.m 1400.00 4,900.00
5 Tie wire G.I. #16 15.00 kls 80.00 1,200.00
6 10mmØ x 6m RSB 63.00 pcs 105.00 6,615.00
Sub-total 128,043.00
H ROOF & ROOF FRAMING
1 2"x2"x 2mm Angle bar- Rafter 0 bd.ft 40.00 0.00
2 2"x2"x 2mm Angle bar- HT 0 bd.ft 40.00 0.00
3 1"x10" Fascia Board 0 bd.ft 40.00 0.00
4 Welding rod. 2.5mm dia. 0 kgs. 60.00 0.00
5 Long Span Deck (pre painted) 25ft length 21 sheets 910.00 19,110.00
6 Umbrella Nails 2.00 kls. 80.00 160.00
7 Vulca seal 1.00 tube 75.00 75.00
Sub-total 19,345.00
I PLUMBING
1 1/2"Ø PVC Pipe (blue) 0.00 pcsx3m 90.00 -
2 1/2" coupling (blue) 0.00 pcs 20.00 -
3 1/2" Elbow (blue) 0.00 pcs 20.00 -
4 1/2" Tee (blue) 0.00 pcs 25.00 -
6 4" pipe (orange) 0.00 pcsx3m 550.00 -
7 4" elbow 45° (orange) 0.00 pcs 160.00 -
8 4" elbow 90° (orange) 0.00 pcs 160.00 -
9 4" Wye (orange) 0.00 pcs 160.00 -
10 4" Cleanout cap 0.00 pcs 80.00 -
11 4" Tee (orange) 0.00 pcs 170.00 -
12 2" pipe (orange) 0.00 pcsx3m 225.00 -
13 2" elbow 90° (orange) 0.00 pcs 45.00 -
14 2" Wye (orange) 0.00 pcs 160.00 -
15 PVC Solvent 0.00 cans 70.00 -
Septic Vault 0.00
16 Cement 22.00 bags 210.00 4,620.00
17 Sand 0.00 cu.m 1,250.00 -
18 Gravel 0.00 cu.m 1,200.00 -
19 Fine Sand 0.00 cu.m 1,400.00 -
20 CHB 4" 228.00 pcs. 15.00 3,420.00
21 10mmØ x 6m RSB 128.00 nos. 105.00 13,440.00
22 4" pipe (orange) 0.00 pcs 550.00 -
23 4" Tee (orange) 0.00 pcs 180.00 -
24 Kitchen Sink/faucet/fittings 0.00 sets 2,500.00 -
25 Water closet & accessories 0.00 set 6,000.00 -
26 Shower & accessories 0.00 set 2,500.00 -
27 Lavatory/Fittings/faucet 0.00 set 2,500.00 -
28 Floor drain 0.00 set 500.00 -
Sub-total 21,480.00
J DOORS AND WINDOWS
1 D1 - 2.4x2.3m Fabricated Plywood Door 1.00 set 1,000.00 1000.00
2 D2 - 0.8x2.1m Fabricated Plywood Door 5.00 sets 500.00 2500.00
3 D3 - 0.7x2.1m Fabricated Plywood Door 2.00 sets 750.00 1500.00
4 Door jambs 8.00 sets 750.00 6000.00
5 W1 - 1.8x1.5m Fabricated Plywood window 1.00 set 500.00 500.00
6 W2 - 1.5x1.2m Fabricated Plywood window 2.00 sets 500.00 1000.00
7 W3 - 2.9x1.3m Fabricated 2" Cyclone window 1.00 set 750.00 750.00
8 W4 - 1.0x1.5m Fabricated Plywood window 1.00 set 500.00 500.00
9 Door Knobs 8.00 sets 350.00 2800.00
10 Door hinges 21.00 sets 75.00 1575.00
Sub-total 18,125.00
K ELECTRICAL
1 Fuse Box 1.00 pcs 245.00 245.00
2 Fuse 20amp 1.00 pcs 25.00 25.00
3 Fuse 15amp 1.00 pcs 20.00 20.00
4 2.0mm2 TW Cu. Wire 20.00 mts 25.00 500.00
5 3.5mm2 TW Cu. Wire 10.00 mts 29.00 290.00
6 1/2"Ø PVC electrical pipes 3.00 pcsx3m 150.00 450.00
7 1/2" elbow 0.00 pcs 15.00 0.00
8 1/2" PVC clamp 0.00 pcs 3.00 0.00
9 Junction box 0.00 pcs 50.00 0.00
10 utility box 3.00 pcs 40.00 120.00
11 duplex outlets 0.00 pcs 85.00 0.00
12 1-gang switch 0.00 pcs 60.00 0.00
13 3-gang switch 0.00 pcs 85.00 0.00
14 Electrical tape 2.00 pcs 35.00 70.00
15 pvc solvent 1.00 cans 80.00 80.00
Sub-total 1,800.00
L POWER TOOLS
M CLEARING
N Material Cost 192,793.00
O Contengencies
P Labor Cost
Q Supervison Fee
R TOTAL PROJECT COST Php192,793.00

Prepred by:

Engr. Michael John A. Apgao


PRC # 094128
TIN # 495-906-416
PTR # 1024790
Project: PROPOSED HYDROBOSS REFILLING STATION
Owner: MS. JACKIE LOU G. MARCOS
Location: BRGY. DANSULAO, MALANGAS ZSP.

B I L L OF M A T E R I A L S

ITEM NO. DESCRIPTION QUANTITY UNIT UNIT COST AMOUNT

A MOBILIZATION 1.00 LS 5000 5,000.00


B CLEARING OF AREA 1.00 LS 1000 1,000.00
C CLEARING OF DEMOLISHED DEBRIS 1.00 LS 1000 1,000.00
D ENCLOSURE OF AREA
Sub-total 7,000.00
E EARTHWORKS
E.1 EXCAVATION
1 Footings 12.50 cu.m 450 5,625.00
E.2 BACKFILLING / FILLING& COMPACTING
1 Gravel Fill (G1) 0.55 cu.m. 1250 687.50
2 Soil fill 1.90 cu.m. 300 570.00
Sub-total 6,882.50
F FORMWORKS & SCAFFOLDINGS Sub-total 8,000.00
G CONCRETE WORKS
G.1 CONCRETE FOOTINGS
1 Portland Cement 23.00 bags. 285.00 6,555.00
2 Screened sand 2.00 cu.m. 1250.00 2,500.00
3 ¾” Gravel 3.00 cu.m. 1200.00 3,600.00
4 12mm Ø Reinforced Steel bar 51.00 pcs. 330.00 16,830.00
5 10mm Ø Reinforced Steel bar 36.00 pcs. 190.00 6,840.00
6 #16 G.I. Tie Wire 15.00 kgs. 80.00 1,200.00
G.2 CONCRETE COLUMNS
1 Cement 14.00 bags. 285.00 3,990.00
2 Gravel 1.00 cu.m. 1250.00 1,250.00
3 Sand 2.00 cu.m. 900.00 1,800.00
4 12mm Ø Reinforced Steel bar 38.00 pcs. 330.00 12,540.00
5 10mm Ø Reinforced Steel bar 24.00 pcs. 190.00 4,560.00
6 #16 G.I. Tie Wire 15.00 kgs. 80.00 1,200.00
G.6 SLAB ON GRADE
1 Portland Cement 97.00 bags 285.00 27,645.00
2 Screened sand 5.00 cu.m. 1250.00 6,250.00
3 ¾” Gravel 10.00 cu.m. 1200.00 12,000.00
4 10mm Ø Reinforced Steel bar 85.00 pcs. 190.00 16,150.00
5 #16 G.I. Tie Wire 15.00 kgs. 80.00 1,200.00
G.7 CHB WALL& PLASTERING
1 CHB 4" 2118.00 nos 15.00 31,770.00
2 Cement 287.00 bags 285.00 81,795.00
3 Screened Sand 8.00 cu.m 1250.00 10,000.00
4 Fine Sand 9.00 cu.m 900.00 8,100.00
5 Tie wire G.I. #16 15.00 kls 900.00 13,500.00
6 10mmØ x 6m RSB 98.00 pcs 190.00 18,620.00
Sub-total 345,760.00
H ROOF & ROOF FRAMING
1 2"x 6"x 1/16" x 6m C-Purlins 6.00 ea. 550.00 3,300.00
2 2"x 3"x 1/16" x 6m C-Purlins 23.00 ea. 650.00 14,950.00
3 1"x1"x3mm Angle (Angle cleat) 1.00 ea. 350.00 350.00
4 1"x1"x2mm Angle (fascia frame) 16.00 ea. 350.00 5,600.00
5 red primrer oxide (liters) 5.00 ea. 230.00 1,150.00
6 Welding rod (kls) 5.00 gal. 650.00 3,250.00
7 prepainted 0.4mm thk. Coloroof (1.05m x 6m) 13.00 ea. 2700.00 35,100.00
8 Pre-formed Spanish flashing 18.00 ea. 450.00 8,100.00
9 1/4" x 12" pre-cut cement board fascia 4.50 ea. 650.00 2,925.00
10 Tek screw 300.00 ea. 3.00 900.00
11 Rivets 2.00 ea. 2.00 4.00
12 Vulca seal 3.00 tube 75.00 225.00
Sub-total 75,854.00
I CEILING WORKS
1 Insulation foam (meter lengthx1m width) 102.00 sq.m 70.00 7,140.00
2 Marine plywood, 1/4" thk. 39.00 shts 450.00 17,550.00
3 Metal furring system 90.00 lt. 220.00 19,800.00

Page 1 of 31
4 Blind rivets 4.00 box 350.00 1,400.00
Sub-total 45,890.00
J PAINTING WORKS
1 Concrete Neutralizer 33.00 gals 415.00 13,695.00
2 Boysen Flat Latex White 11.00 pail 3,200.00 35,200.00
3 Boysen Semi-gloss Latex topcoat 11.00 pail 3,700.00 40,700.00
4 Masonry putty 9.00 pail 1,200.00 10,800.00
5 Painting accessories 10.00 sets 800.00 8,000.00
6 Sand paper (assorted) 20.00 pcs 40.00 800.00
Sub-total 109,195.00
K TILE WORKS
1 60 x 60 porcelain tiles 63.00 pcs 171.00 10,773.00
2 ABC Tile Adhesive or equivalent 10.00 bags 270.00 2,700.00
Sub-total 13,473.00
M DOORS AND WINDOWS
1 D1 - 0.9x2.1m solid door panel 2.00 set 8,000.00 16,000.00
2 W1 - 1.2x1.2 Sliding glass window 2.00 sets 5,200.00 10,400.00
3 W2 - 0.6x0.6 Awning glass wIndow 2.00 sets 3,200.00 6,400.00
4 Cylindrical type (chrome finish) lockset 2.00 sets 1,500.00 3,000.00
5 Door hinges (heavy duty) 6.00 set 75.00 450.00
6 Dead bolt for main doors 1.00 sets 250.00 250.00
Sub-total 36,500.00
SUMMARY OF COST ESTIMATES
TOOLS & EQUIPMENTS (RENTAL COST) P 8,106.00
A. Total Estimated Material Cost P 648,554.50
Total Estimated Labor Cost P 162,139.00
TOTAL ESTIMATED DIRECT COST (EDC) P 818,799.50
OCM, Overhead, Contingency & Misc. (10% of EDC) P -
B. Profit (10% of EDC) P -
VAT ( 7% of EDC + OCM + Profit) P -
TOTAL ESTIMATED INDIRECT COST (EIC) P -

C. TOTAL ESTIMATED PROJECT COST Php818,799.50

Prepred by:

Civil Engineer

Page 2 of 31
CONTINGENCY INPUT 15%

Item Description L/H (m) W (m) T (m)

Footings
1 F1 1.0 1.0 0.2

2 Wall Footing 42.0 0.30 0.15


Su
Concrete Class A ColFooting WF Unit
Cement 23 20 bags
Gravel 3 3 cu.m
Sand 2 2 cu.m

Columns
1 Columns C1 3.00 0.2 0.2
2

Su
Concrete Class A Unit
Cement 14.00 bags
Gravel 2.00 cu.m
Sand 1.00 cu.m

Beams
1 Beam B1 45.00 0.2 0.2
2

Su
Concrete Class A Unit
Cement 19.00 bags
Gravel 3.00 cu.m
Sand 2.00 cu.m
Slab
1 Slab on grade 10.5 8 0.1

Su
Concrete Class A Unit
Cement 97.00 bags
Gravel 10.00 cu.m
Sand 5.00 cu.m

CEMENT 173.00
GRAVEL 21.00
SAND 12.00
12MM DIA. RSB 177
10MM DIA. RSB 136
1.15

Rebar length Rebar length


Total Vol. + 15%
Vol. (m3) Qty LONG/ Top&bot TRANS/ Top&bot
Contingency
(m) (m)

0.200 10 2.30 7.2 6


0.000 0.00 0.0 0.6
0.000 0.00 0.0 0.6
0.000 0.00 0.0 0.6
1.890 1 2.17 139 46
Subtotal 4.47

Main Bars

Reqd length +
Size
15% contingency

0.12 10 1.32 227.7 4 - 12Ø


0 0.00 0 4 - 16Ø

Subtotal 1.32

No of top bars No of bot. bars

1.800 1 2.070 2 4
0.000 1 0.000 2 4

Subtotal 2.070
Trans (total) Long (total)

8.400 1 9.660 222.60 220.73

Subtotal 9.660
Total Required +
Equivalent no. of
Rebar Size(Ø) 15% contingency
6-meter bars
(m)

12Ø 303.6 51
12Ø 0 0
12Ø 0 0
12Ø 0 0
10Ø 212.5 36

ain Bars Tie Bars

Equiv. nos of 6-
Equiv. nos of 6- Bar length each No. of
Size meter length (w/
meter length tie loop loops/length
15% contingency)

38 0.58 21 10Ø 24
0 -0.22 5 10Ø 0

Stirrups
Total length of bars
Eq. nos of 6-
(m) + 15% Rebar Size Size No. of beams
meter length
contingency
310.5 12Ø 52 10Ø 3
0 12Ø 0 10Ø 4
Total rebars length
Total equiv.nos of
(m) + 15% Size
6-meter length
contingency

509.8 10Ø 85
Stirrups

Total No. of stirrup length of Total reqd stirrup Equiv. nos of 6-


loops bar/loop length + 15% (m) meter length

242 0.58 161.414 27


22 -0.22 -5.566 0
CONTINGENCY INPUT 10%
1.1
MATERIALS SUMMARY FOR STEEL

Qnty Reqd of 6-
Item Total Length meter + 10%
contingency
Board Feet
2"x2"x 2mm Angle bar- Rafter 0 0
2"x2"x 2mm Angle bar- HT 0 0
1"x10" Fascia Board 0 0
Welding rod. 2.5mm dia. 0

CONTINGENCY INPUT 15%


MATERIALS SUMMARY FOR STEEL

Qnty Reqd of 6-
Item Total Length meter + 15%
contingency

2"x 6"x 1/16" x 6m C-Purlins 32.4 6


2"x 3"x 1/16" x 6m C-Purlins 121.6 23
1"x1"x3mm Angle (Angle cleat) 2.2 1
1"x1"x2mm Angle (fascia frame) 83.5 16
red primrer oxide (liters) 5 5
Welding rod (kls) 5
Item Reqd length (m) length (ft) Unit price/length

prepainted 0.4mm thk. Coloroof 15 6 19.68 350.00

Pre-formed flashing 11.1 250.00

Insulation foam (meter lengthx1m width) 63 70.00


Umbrella Nails 2 80.00

Vulca seal 1 500.00

Item Reqd length (m) length (ft) Unit price/length

prepainted 0.4mm thk. Coloroof (1.05m x 6m) 13 7.7 25.256 100.00


Pre-formed Spanish flashing 18 2.44 250.00
1/4" x 12" pre-cut cement board fascia 4.5
Tek screw 300 500.00
Rivets 2 500.00
Vulca seal 3 500.00
unit price/pc Subtotal
2,100.00 735,000.00

2,775.00

4,410.00
160.00
-
500.00
Subtotal 742,345.00

unit price/pc Subtotal

2,525.60 252,560.00
610.00
600
150,000.00
1,000.00
1,500.00

Subtotal 404,170.00
CONTINGENCY
INPUT 5%
1.05

Effective Window Area


CHB Wall Length (m) Door Area (sq.m)
Height (m) (sq.m)

Inner & Outer walls 3.5 48 2.88 3.78

Effective wall
Cement
Cement mortar area + 5% CHB size Screened Sand
"Type-A"
(sq.m)

Outer walls 169.41 4" 134.17 7.37


0.00 4" 0.00 0.00
0.00 4" 0.00 0.00

Effective wall Plaster


Wall Area x 2
Plastering wall area + 5% Thickness Cement
face(sq.m)
(sq.m) (mm)

Inner & Outer walls 169.41 338.81 25 152.47


0.00 25 0.00
0.00 25 0.00

338.81

MATERIALS SUMMARY FOR MASONRY


Item Qnty Reqd Unit

CHB 4" 2118.0 nos


Cement 287.0 bags
Screened Sand 8.0 cu.m
Fine Sand 9.0 cu.m
Tie wire G.I. #16 15.0 kls
10mmØ x 6m RSB 98.0 pcs
Rebars
Effective wall area Total Reqd length
Required No. Of
(sq.m) + 5% Hor Ver Size (m) + 5%
CHB
contingency contingency

169.41 2118 280.0 280.0 10Ø 588.0


0.00 0 0.0 0.0 10Ø 0.0
0.00 0 0.0 0.0 10Ø 0.0
0.00 0 0.0 0.0 10Ø 0.0

Fine Sand

8.47
0.00
0.00
CONTINGENCY
INPUT 10% 1.1
Excavation Volumes
Volume
L (m) W (m) D (m) Qty
excavated (m3)

Footing F1 1.0 1.0 1.25 1.25 10


0 3
0 5
0 2

Wall Footing 42.0 0.00 0 0 0


Total excavation
Filling Materials
Area (sq.m) + Total Volume
Depth of fill (m)
10% contingency of fill (cu.m)

Gravel fill G1 11 0.05 0.55


Soil fill 11 0.15 1.9
Total Volume
Subtotal Area
(m3)

12.5 10.00
0 0.00
0 0.00
0 0.00

0 0.00
12.5
CONTINGENCY INPUT 10% 1.1
CEILING MATERIALS

Required Quantity
Qty Unit
+ 10% contingency

Ceiling Area 102 Sq.m 39

Required Quantity
Qty Unit
+ contingency

Marine plywood, 1/4" thk. 39 shts 39


Metal furring system 81.6 lt. 90
Blind rivets 3 box 4
CONTINGENCY INPUT 10 % 1.1
TILEWORKS
Area +10%
Location Area (sq.m) contingency
(sq.m)

Inner & Outer walls 339 373


Ceiling Area 102 112
0 0

Total Paint area 485

Items Unit Required qty


Concrete Neutralizer gals 33.00
Boysen Flat Latex White pail 11.00
Boysen Semi-gloss Latex topcoat pail 11.00
Masonry putty pail 9.00
Painting accessories set 10.00
Sand paper pcs (ft) 20.00
16.16318
16.16318
16.16318
CONTINGENCY INPUT 20% 1.2
TILEWORKS

Tile area
Total Area
(sq.m) + 20% Tile Size
(sqm)
contingency

60 x 60 porcelain tiles 18.84 22.608 60x60


0 30x30

ABC Tile Adhesive or equivalent 10 bags


22.608
No. of Tiles Price Subtotal

63 170 Php 10,710.00


0 70 Php -

260 Php 2,600.00


Php 13,310.00
PLUMBING MATERIALS SUMMARY
Item Reqd Unit
1/2"Ø PVC Pipe (blue) pcsx3m
1/2" coupling (blue) pcs
1/2" Elbow (blue) pcs
1/2" Tee (blue) pcs
Gate Valve 1/2" (Falcon) pc
4" pipe (orange) pcsx3m
4" elbow 45° (orange) pcs
4" elbow 90° (orange) pcs
4" Wye (orange) pcs
4" Cleanout cap pcs
4" Tee (orange) pcs
2" pipe (orange) pcsx3m
2" elbow 90° (orange) pcs
2" Wye (orange) pcs
PVC Solvent cans
Septic Vault
Cement bags
Sand cu.m
Gravel cu.m
CHB 4" Chamber walls pcs.
Fine Sand cu.m
12mmØ x 6m RSB nos.
4" pipe (orange) pcs
4" Tee (orange) pcs
Kitchen Sink/faucet/fittings sets
Water closet & accessories set
Shower & accessories set
Lavatory/Fittings/faucet set
Floor drain set
Tissue holder set
Soap holder set
Septic Vault
L (m) W (m) T (m) Req'd Unit
Flooring foundation concrete 4.4 2 0.1 0.88 cu.m
Flooring/foundation rebars 108.90 m
Concrete Footing 11.52 0.35 0.15 0.60 cu.m
Footing Rebars 44.85 m
Top cover concrete 4.4 2 0.1 0.88 cu.m
Top cover rebars, 12Ø 99.90 m
CHB 4" Chamber walls 17.1 2 0.00 pcs
Wall rebars, 12Ø 58.65 m
Cement (mortar) 28.70 bags
Sand (mortar) 2.89 cu.m
Cement (cover/foundation) 19.51 bags
Sand (cover/foundation) 1.18 cu.m
Gravel (cover/foundation) 2.36 cu.m
Length Height Area Cement Fine sand
Internal wall plaster (16mm) 10.8 1.8 19.44 3 1
Item No. Description Qty Unit

1 D1 - 2.4x2.3m Fabricated Plywood Door 1 sets


2 D2 - 0.8x2.1m Fabricated Plywood Door 5 sets
3 D3 - 0.7x2.1m Fabricated Plywood Door 2 sets
4 Door jambs 8 sets
5 W1 - 1.8x1.5m Fabricated Plywood window 1 sets
6 W2 - 1.5x1.2m Fabricated Plywood window 2 sets
7 W3 - 2.9x1.3m Fabricated 2" Cyclone window 1 set
8 W4 - 1.0x1.5m Fabricated Plywood window 1 sets
9 Door Knobs 8 sets
10 Door hinges 21 sets
11 Dead bolt for main doors 11 sets

Item No. Description Qty Unit


1 D1 - 0.9x2.1m solid door panel 2 sets
3 W1 - 1.2x1.2 Sliding glass window 2 sets
4 W2 - 0.6x0.6 Awning glass wIndow 2 sets
5 Cylindrical type (chrome finish) lockset 2 sets
6 Door hinges (heavy duty) 6 sets
7 Dead bolt for main doors 1 sets
Item No. Description
1
2
3
Qty Unit
Items Qty. Unit Items
Fuse Box 245 pcs Panel Board 3 branches
Circuit breaker 60amp
Fuse 20 pcs Circuit breaker 15amp
2.0mm TW Cu. Wire
2 m 2.0mm2 TW Cu. Wire
3.5mm2 TW Cu. Wire m 3.5mm2 TW Cu. Wire
1/2"Ø PVC electrical pipes pcsx3m 1/2"Ø PVC electrical pipes
1/2" elbow pcs 1/2" elbow
1/2" PVC clamp pcs 1/2" PVC clamp
Junction box pcs Junction box
utility box pcs utility box
2-gang outlets pcs 2-gang outlets
1-gang switch pcs 1-gang switch
3-gang switch pcs 2-gang switch
Electrical tape pcs Electrical tape
pvc solvent cans pvc solvent
Qty. Unit
pcs
pcs
pcs
boxes
boxes
pcsx3m
pcs
pcs
pcs
pcs
pcs
pcs
pcs
pcs
cans

You might also like