FULLTEXT01
FULLTEXT01
FULLTEXT01
B 2388
May 2020
Sofia Lovisa Andersson, Klara Westling, Sofia Andersson, Jesper Karlsson, Mayumi Narongin, Gabriel
Persson
In cooperation with
Author: Sofia Lovisa Andersson, Klara Westling, Jesper Karlsson, Mayumi Narongin (IVL Swedish
Environmental Research Institute) Sofia Andersson and Gabriel Persson (Stockholm Vatten och
Avfall)
Funded by: Stiftelsen IVL and Stockholm Vatten och Avfall
Photographer: Sofia Lovisa Andersson
Report number B 2388
ISBN 978-91-7883-198-2
Edition Only available as PDF for individual printing
This report has been reviewed and approved in accordance with IVL's audited and approved
management system.
Preface
This report presents work performed during 2018, within the long-term pilot study trials of
municipal wastewater treatment with Membrane Bioreactors (MBR), including sludge treatment.
The study is carried out in cooperation between IVL Swedish Environmental Research Institute
and Stockholm Vatten och Avfall AB (Stockholm Water and Waste Company). The trials are
performed at the R&D pilot facility Hammarby Sjöstadsverk in Stockholm, Sweden and they are
jointly financed by the IVL foundation and Stockholm Vatten och Avfall AB.
Table of contents
Summary ................................................................................................................................ 6
Sammanfattning..................................................................................................................... 8
Terminology ......................................................................................................................... 10
1 Introduction .................................................................................................................. 12
2 Background ................................................................................................................... 13
5 Method ......................................................................................................................... 29
5.1 Sampling and analyses .................................................................................................................... 29
5.2 Online measurements ..................................................................................................................... 31
5.3 Evaluation parameters .................................................................................................................... 32
5.3.1 Membrane performance ........................................................................................................ 32
5.3.2 Sludge quality.......................................................................................................................... 33
7 Field trip to five MBR plants with strict effluent requirements ................................... 82
8 Conclusions ................................................................................................................... 83
9 Further studies.............................................................................................................. 84
11 Bibliography .................................................................................................................. 85
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
Summary
Henriksdal wastewater treatment plant (WWTP) in Stockholm is currently being extended and
rebuilt for increased capacity and enhanced treatment efficiency. The new process configuration at
the Henriksdal WWTP has been designed for a capacity of 1.6 million population equivalents (PE)
which is about twice as much as today. The design maximum flow of the biological treatment is 10
m3/s which is equivalent to 850 Mega Liters per Day (MLD). In addition, the treatment process has
been designed to reach low nutrient concentrations in the effluent (5 mg BOD7/L, 6 mg TN/L and
0.2 mg TP/L). The extension of the plant will include new primary treatment, new primary settlers
and a new treatment step for thickening of primary and waste activated sludge. The reconstruction
will include retrofitting of the existing conventional activated sludge (CAS) tanks with a new
membrane bioreactor (MBR) process containing 1.6 million m2 of membrane area. Digestion of
thick sludge (~6% TS) will be done at thermophilic conditions instead of mesophilic digestion of
thin sludge (~3-3.5%).
Results from previous years have verified that the process is able to treat a hydraulic load
equivalent to the design load, and a nutrient load greater than the design load, to effluent
concentrations below the future discharge limits. In addition, the function and resilience of the
membrane design have been verified.
Mimicking the start-up operation of the first treatment line in full scale
The first full scale MBR treatment line at Henriksdal WWTP will be operated in a different way
compared to the process design, during the first three years of operation. This include a high fixed
flowrate, reject water connected to inlet, only ferrous sulphate (no ferric chloride) and no external
carbon source. To gain knowledge of the treatment performance during these conditions the pilot
was operated in this way for ten weeks (March to June). The results indicate that the process can
manage TP below 0.2 mg/L and TN below 10 mg N/L in the effluent at the higher load expected for
the first treatment line without use of ferric and external carbon. Also, no negative effects were
observed regarding the membrane performance and permeability was similar before and after the
trial.
6
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
large potential savings in both chemical and energy use when operating the membrane tanks,
without risking any decrease in membrane capacity.
Membrane cleaning
In order to study any possible differences in cleaning effect and membrane performance, the acid
used for cleaning one of the membrane tanks (MT1), was, throughout 2018 oxalic acid, whereas the
other membrane tank (MT2) was cleaned with citric acid. The results showed that the effect of
cleaning with oxalic acid was at least as good as when cleaning with citric acid. Since oxalic acid is
less expensive than citric acid, there is a large economic saving potential in switching to oxalic acid.
Also, high phosphorus concentration peaks detected in the effluent during citric acid cleaning
events, was not detected when using oxalic acid cleaning.
Before and after recovery cleaning the membranes were lifted for inspection (after two years of
operation, new membranes were installed in 2016) and membrane fibers were sent for membrane
autopsy to study the type of fouling on the membrane surface. The membranes were in good
condition, the foulant before recovery cleaning contained mainly iron, some organic material and
trace amounts of calcium phosphate. After recovery cleaning most fouling had been removed and
the foulants left contained trace amounts of iron and organic material.
Phosphorus removal
The consumption of precipitation chemicals for phosphorus removal decreased significantly
during 2017 leading to a hypothesis that enhanced biological phosphorus removal (EBPR) occurred
in the pilot although there is no anaerobic zone presence. During 2018 this was confirmed by
regular phosphate release tests showing high, but varying EBPR-activity over the year.
7
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
Sammanfattning
Henriksdals avloppsreningsverk i Stockholm är under ombyggnad för att öka kapaciteten och
avskiljningsgraden. Det nya reningsverket är designat för en kapacitet på 1,6 miljoner
personekvivalenter (pe), vilket motsvarar ungefär dubbelt så mycket som 2018. Det nya
reningsverket är också designat för att klara strikta utsläppskrav med avseende på fosfor, kväve
och BOD7 (5 mg BOD7/L, 6 mg N-tot/L och 0,2 mg P-tot/L).
MBR är en relativt väl beprövad teknik inom både industriell och kommunal avloppsrening men
införandet i Henriksdal innebär en rad utmaningar för vilka tekniska och driftsmässiga lösningar
utvecklas och testas i ett pilotprojekt på forskningsanläggningen Hammarby Sjöstadsverk.
Projektet har pågått sedan 2013 och kommer att fortsätta så länge det bedöms att det finns ett
behov av pilottester för Henriksdals framtida process. Under 2017 utökades projektet genom att
MBR-piloten kompletterades med slambehandling för att även kunna studera framtida
rötningsprocess för Henriksdal. Projektet är gemensamt finansierat av IVL Svenska Miljöinstitutet
och Stockholm Vatten och Avfall. I den här delrapporten redovisas resultat från år 2018 (projektår
5) av pilotförsöksprojektet.
Resultat från tidigare års försök har visat att processen kan rena en hydraulisk belastning som
motsvarar den dimensionerande belastningen och en näringsämnesbelastning som överstiger den
dimensionerande belastningen till utgående koncentrationer som underskrider de framtida
reningskraven. Även membranens funktion och uthållighet har verifierats tidigare.
Minskad resursförbrukning
Under 2018 har stort fokus legat på att minska resursförbrukningen relaterad till driften av
membranen. Försök att minska mängden luft som används i membrantankarna och mängden
kemikalier som används för membranrengöring har genomförts. Försöken är inte slutförda utan
kommer fortsätta under 2019, men redan nu finns indikationer på stora potentiella besparingar i
både kemikalie- och energiförbrukning för membranen utan att risk för minskad kapacitet.
8
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
Membranrengöring
För att studera eventuella skillnader i rengöringseffekt och membranprestanda så användes
oxalsyra för rengöring av ena membrantanken (MT1) under hela 2018 medan den andra
membrantanken (MT2) rengjordes med citronsyra. Resultaten visade att effekten av rengöring med
oxalsyra var minst lika bra som vid rengöring med citronsyra. Eftersom oxalsyra är billigare än
citronsyra finns det en stor ekonomisk besparingspotential i att byta citronsyra mot oxalsyra. Höga
fosforhalter i utgående behandlat vatten har noterats i samband med citronsyrarengöring.
Motsvarande toppar har inte uppstått vid rengöring med oxalsyra.
Före och efter återhämtningsrengöring lyftes membranen ur sina tankar för visuell inspektion
(efter två års drift, nya membran installerades 2016) och membrantrådar klipptes av och skickades
för ”membranobduktion” för att studera typ av beläggning som fanns på membranytan.
Membranen var i gott skick och den beläggning som fanns innan återhämtningsrengöring bestod
av järn, vissa organiska material och små mängder kalciumfosfat. Efter rengöringen hade det
mesta av beläggningen tvättats bort och kvar var små mängder järn och organiskt material.
Fosforrening
Förbrukning av fällningskemikalie för fosforrening minskade kraftigt under 2017 vilket resulterade
i en hypotes om att utökad biologisk fosforrening (bio-P) utvecklats i processen trots avsaknaden
av en anaerob zon. Under 2018 bekräftades detta med hjälp av regelbundna fosforsläppstester som
visade på en hög varierad bio-P-aktivitet över året.
Slampbehandling
Slambehandlingslinjen (som inkluderar förtjockning, anaerob rötning och slamavvattning) var i
drift med mesofil rötning under 2018. På grund av de många driftstörningar som uppstod
spenderades stor del av året på att uppgradera, bygga om och justera de olika behandlingsstegen.
Försök för att förbättra både förtjockning och avvattning genomfördes.
Kartläggning av mikroföroreningar
En tvååring studie för kartläggning av förekomsten av mikroföroreningar, såsom läkemedelsrester,
mikroplast, bakterier, PFAS och klororganiska halogener i behandlingsprocessen startade under
hösten 2017 och resultaten från den andra och tredje provtagningskampanjen (av totalt fyra,
studien avslutas under 2019) presenteras i denna rapport.
Under 2018 genomfördes studiebesök i USA på avloppsreningsverk med MBR och liknande
utsläppskrav och recipient som Henriksdals reningsverk. Erfarenheter från dessa anläggningar
sammanfattas i denna rapport.
9
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
Terminology
ADM1 Anaerobic Digestion Model No. 1
Aerobic Aerated
Anoxic Non-aerated
AOX Adsorbable organic halogensm (mg/L)
BB1 Bio-Block 1. First biological full scale treatment line to be reconstructed to MBR at Henriksdal
WWTP.
BOD7 Biochemical Oxygen Demand, 7 days (mg/L)
BR1 to BR6 Biological reactor 1 to 6, sampling points
BSM2 Benchmark Simulation Model No. 2
CAS Conventional Activated Sludge
CFD Computational Fluid Dynamics
COD Chemical Oxygen Demand (mg/L)
cTOC collodial Total Organic Carbon (mg/L)
DDMS Dewatered digested mixed sludge, sampling point
DMS Digested mixed sludge, sampling point
DO Dissolved Oxygen (mg/L)
DS Daily composite sample (flow proportional)
EFF Effluent water, sampling point
EOX Extractable organic halogens (mg/L)
Fe Iron (mg/L)
F/M ratio Food to Mass, incoming substrate in relation to the amount of microorganisms
(kg BOD7/kg SS, d)
Flux Flow rate per unit area (L/(m2·h)). Flux is a measurement of the load on the membranes
Fouling Clogging of the pores in the membranes, causing reduced flow rate through the membranes
FS Flat sheet (membrane type)
GS Grab sample
Hepta Iron(II)sulfate heptahydrate
HF Hollow fibre (membrane type)
HFO Hydrous ferric oxides
IN Influent wastewater, sampling point
MBR Membrane BioReactor, bio reactor with membrane separation
MLD Million litres per day
MLSS Mixed liquor suspended solids (mg SS/L)
MT1 Membrane tank 1 (of 2), sampling point
MT2 Membrane tank 2 (of 2), sampling point
MC Maintenance cleaning
MS Mixed sludge (PS+WAS), sampling point
NIT Nitrification zone
NH4-N Ammonium nitrogen (mg/L)
NO2-N Nitrite nitrogen (mg/L)
NO3-N Nitrate nitrogen (mg/L)
Org-N Organically bound nitrogen (mg/L)
PA Pre-aeration tank
PE Population equivalent (defined as 70 g BOD7 per person and day)
Permeability Flux per TMP (L/(m2·h·bar)). Permeability is a measure of how well a specific flux permeates
the membranes. The permeability gradually decreases with time due to fouling
Permeate The treated wastewater that has passed through the membranes
PFAS Perfluorinated Alkylated Substances
PIX PIX 111, iron(III)chloride solution
PO4-P Phosphate phosphorus (mg/L)
Pre-DN Pre-denitrification (Anoxic)
Post-DN Post-denitrification (Anoxic)
10
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
1 www.stockholmvattenochavfall.se/en/sfa-start/
11
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
1 Introduction
This report presents the results from year 2018 (project year 5), of the pilot scale trials with
membrane biological treatment of municipal wastewater, carried out in cooperation between IVL
Swedish Environmental Research Institute and Stockholm Vatten och Avfall AB (SVOA) at the
R&D facility Hammarby Sjöstadsverk, in Stockholm, Sweden. In the trials, an activated sludge
process with a new process configuration is combined with membrane filtration to reach a higher
level of purification, operational stability and treatment capacity. In addition, the sludge is treated
by thickening, digestion and dewatering with the goal to evaluate high loaded thermophilic
digestion with short retention time. Project years 2014-2017 are presented in separate reports.
In the initial chapters (2-3), the project background and the configuration of the pilot plant are
described. An overview of the experimental plan is presented in chapter 4, followed by a method
description in chapter 5. Finally, all results are presented and discussed in chapter 6.
12
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
2 Background
Within the project Stockholm’s Framtida Avloppsrening (SFA, Stockholm’s future wastewater
treatment), the Henriksdal WWTP in Stockholm, Sweden, is being extended and rebuilt for
increased capacity and enhanced treatment efficiency. The decision to extend and rebuild is based
on several factors such as; (i) SVOA´s WWTP in Bromma (which is already over loaded with very
limited space available for extension) will be decommissioned in 2025 to give space to new housing
areas, and the wastewater will be led to the Henriksdal WWTP in a new 14 km long sewage tunnel,
(ii) the population in the Stockholm region is increasing at a high rate, resulting in an increased
influent load, and, (iii) the Swedish Environmental Court has decided to sharpen the effluent
requirements on the WWTPs in the Stockholm region, which demands more efficient wastewater
treatment processes.
The new process configuration at the Henriksdal WWTP has been designed for a capacity of 1.6
million population equivalents (PE) which is about twice as much as today. The design maximum
flow of the biological treatment is 10 m3/s which is equivalent to 850 MLD. In addition, the
treatment process has been designed to reach low nutrient concentrations in the effluent
(5 mg BOD7/L, 6 mg TN/L and 0.20 mg TP/L). The extension of the plant will include new primary
treatment, new primary settlers and a new treatment step for thickening of primary and waste
activated sludge. The reconstruction will include retrofitting of the existing conventional activated
sludge (CAS) tanks with a new MBR-process containing >1.6 million m2 of membrane area. The
first MBR-line, out of seven, will be taken into operation in 2020 and the retrofitting of all seven
lines will take an additional 8-9 years. The sand filters, currently used as a final polishing step for
phosphorus removal, will in the future be used for wet weather overflow treatment. Digestion of
thick sludge will be done at thermophilic conditions instead of mesophilic digestion of thin sludge.
Design data for the future Henriksdal WWTP can be found in Table 1, Table 2 and Table 3.
The MBR technology is well-known internationally with long term experiences from both
industrial and municipal WWT. In Italy and Germany relatively large municipal WWTPs with
MBR-technology have been in operation for around 15 years (Brepols, 2010; Judd, 2010). In USA,
China, Japan, South Korea, France, Great Britain and Spain, there are several large MBR-plants
(50,000-80,000 PE) which have been in operation for 5-10 years (Judd and Judd Limited, 2017). The
largest MBR-plant in operation today is Huaifang Water Recycling Project in Beijing, China
(commissioned in 2016), designed for an average inflow of 6.9 m3/s, which is slightly larger than
the capacity of the future Henriksdal WWTP (design average 6.1 m3/s). Europe’s largest MBR in
operation, also the largest ZeeWeed (SUEZ) plant is Seine Aval in France (commissioned in 2016),
with a design average inflow of 2.6 m3/s (www.thembrsite.com, 2019-07-11).
• high seasonal variations in water temperature and inflow, affecting both the membrane
performance and the nitrogen removal,
• to meet the strict effluent requirements for phosphorus (0.20 mg TP/L and 27 tons/year,
which equals <0.15 mg/L before 2040) by means of pre- and simultaneous precipitation (no
final polishing step), without affecting membrane performance and
• to minimize the resource consumption.
There are MBR-plants in the USA, eg. Broad Run and King William County in Virginia, Ruidoso in
New Mexico and Cauley Creek and Yellow River in Georgia, that reach very low effluent nutrient
13
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
concentration, 0.05-0.10 mg TP/L and 0-6 mg TN/L without final polishing steps (Pellegrin &
Neethling, 2015). Phosphorus removal at these plants is achieved by a combination of biological
phosphorus removal (EBPR) and precipitation using a trivalent metal ion (Al3+ or Fe3+). However,
none of these treatment plants use ferrous (Fe2+), which is planned to be utilized at the Henriksdal
WWTP, or have as low incoming water temperatures as the Henriksdal WWTP.
Membrane filtration requires aeration and chemicals for maintenance and cleaning of the
membranes. However, each plant is unique, and the cleaning schedule can and should be
optimized for the local conditions in order to save resources.
The SFA-project will also affect the sludge treatment. The load on the digesters is expected to
double but the digester volume will not be expanded. Consequently, digestion must be performed
with high organic load and short hydraulic retention time. To manage this, the raw sludge will be
thickened, and digestion will be performed at thermophilic conditions. There are several
uncertainties regarding the sludge handling, including: function of thickening of fine particulate
MBR-sludge, stability of the digestion process, biogas production potential, smell, pumping of
thick sludge, and function of dewatering of thermophilic digested sludge.
14
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
Figure 1. Flow scheme of the pilot WWTP. The biological treatment consists of 6 bioreactors (BR), BR1+BR2
are anoxic, BR3 is flexible, BR4+ a part of BR5 are aerobic, remaining part of BR5 is deox and BR6 is anoxic.
The reactor volumes of the pilot plant and the function of each reactor are specified in Table 1
together with a comparison to the future Henriksdal WWTP design.
Table 1. Reactor volumes in the wastewater treatment line in the pilot compared to the future Henriksdal
WWTP (SFA).
Tank Pilot (m3) Future Scale factor Specification
H-dal (m3) H-dal/Pilot
Pre-treatment
PA (sand trap) 0.7 2 460 - Pre-aeration. Dosing point 1 Fe2+.
SED 3.3 30 000 9 200 Primary settler. Withdrawal of primary sludge.
Membrane bioreactor (MBR)
BR1 4.8 33 500 7 000 Stirred. Pre-denitrification.
BR2 4.8 33 500 7 000 Stirred. Pre-denitrification.
BR3 4.8 40 000 8 300 Stirred/(aerated). Pre-denitrification/(nitrification). FLEX.
BR4 4.8 31 000 6 500 Aerated. Nitrification. Dosing point 2 Fe2+
BR5ox 1.5 10 000 6 700 Aerated. Nitrification.
BR5DeOx 3.3 15 000 4 500 Stirred. DeOx.
BR6 4.8 24 000 5 000 Stirred. Post-denitrification. Dosing external carbon. Dosing point 3 Fe3+.
MT1 1.45 9 750 6 700 Aerated. Membrane tank.
MT2 1.45 9 750 6 700 Aerated. Membrane tank.
RAS-DeOx 2.7 18 000 6 700 Stirred. DeOx. Addition of reject water (RWD). Withdrawal of WAS (before
addition of RWD.
Summary MBR
Total MBR 34.4 224 500 6 500 BR1-6, MT1-2, RAS-DeOx
Sludge treatment
MS tank 0.4 1 060 2 650 Stirred. Tank for PS + WAS before thickening
Digester 5.9* 38 000 6 500 Stirred. Anaerobic digestion volume
DMS tank 0.2 9 000 45 000 Circulation mixing. Tank for digested mixed sludge before dewatering.
*The volume is set by choosing the liquid level in the digester and can be increased or decreased.
15
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
Since the influent to the pilot is set by the scaled down flow rate, and not a scaled down load, the
incoming load on the pilot plant is proportionally higher than the corresponding design load for
the Henriksdal WWTP, year 2040, see Table 2.
In addition, the incoming wastewater to the pilot has a higher temperature than incoming
wastewater to Henriksdal. Previously, the incoming wastewater was during some periods cooled
in heat exchangers. In April 2017 heat exchangers were taken out of operation due to repeated
clogging after installation of a new coarser fine screen. At the end of March 2018 new heat
exchangers were installed, however, due to continuous problems with clogging they were only in
operation for shorter periods. The temperatures in the incoming wastewater to Henriksdal and to
the pilot are presented in Figure 3. On average the temperature of the water to the pilot was about
2.5 °C higher than the influent wastewater to Henriksdal.
16
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
25
20
Temp. °C
15
Henriksdal
10 Pilot
Heat exchanger in operation
5
0
01-jan 01-feb 01-mar 01-apr 01-maj 01-jun 01-jul 01-aug 01-sep 01-okt 01-nov 01-dec
Figure 3. Influent temperatures to the MBR pilot (black line) and the Henriksdal WWTP (green line).
3.1.2 Pre-treatment
The pre-treatment steps in the pilot consisted of a 6 mm punch hole screen (efficiency similar to 2
mm step screen), a pre-aeration tank with ferrous sulfate dosing and a vertical flow primary settler,
with a surface area of 1.13 m2 and a water depth of 4.3 m. The primary settler in the pilot plant is
proportionally smaller than the one in Henriksdal (scale 1:9,200 compared to the future Henriksdal
design) since it was decided to use an existing installation, modified in 2017, instead of
constructing a new. Finally, a 0.6 mm punch hole drum sieve was installed between the primary
settling tank and the biology, see Figure 4. The small hole size of the drum sieve was chosen to
enable the study of clogging tendencies (2 mm will be used in full scale).
17
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
activated sludge (WAS) was taken out from the return sludge stream, after the membrane tanks
and prior to the RAS-DeOx. Precipitation chemicals for phosphorus removal were dosed in BR4
and BR6.
The biological treatment set-up was almost identical to the design of the future Henriksdal WWTP
in scale 1:6700, with few minor exceptions. The deox zone in BR5 and the post-denitrification zone
in BR6 were slightly over dimensioned. The discrepancy is due to the size of the existing tanks in
the pilot plant and the difficulties in creating zones within the tanks. When setting up the pilot, a
correct volume of the aerated zones for nitrification was given priority (BR4 and BR5ox), as the size
of these zones will be crucial for the nitrogen removal.
Another difference between the pilot and the future Henriksdal WWTP is that the pilot lacks a
RAS-channel. Instead, the RAS flowed directly from the membrane tanks into the RAS-Deox from
where it was pumped back into BR1. In the full-scale plant, the RAS will flow into a RAS-channel
by gravity and then be pumped into the RAS-Deox zone from where it will flow to the pre-
denitrification zone by gravity. The volume of the RAS-channel will be small (HRT ~ 2 minutes)
which puts a lot of pressure on the RAS-pumps. This could not be tested in the pilot since the RAS-
Deox volume is much larger (HRT ~ 10 min). Table 1 shows the size of the treatment volumes in
the pilot plant compared to the design of the future full-scale system at Henriksdal.
18
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
b)
a)
c) d)
Figure 6. The membrane during installation in the pilot. a) Membrane cassette with three membrane
modules, b) cassette lowered into the tank, view from above, c) mounting and aeration equipment at the
bottom of the cassette, d) permeate connections (yellow) at the top of the cassette.
The total membrane surface area in the pilot (204 m2) corresponds to the design membrane surface
installed in six (out of seven) treatment lines in the full-scale plant. The reasons for this are both
that it corresponds to two standard design pilot cassettes from the manufacturer and that the SFA
design has accounted for that the design max flow rate to the biological treatment could be treated
even if one of the seven treatment lines are out of operation.
In future Henriksdal WWTP, each treatment line (a total of 7) will have 12 membrane tanks each
that can be taken into and out of operation depending on the influent flow rate. Each membrane
tank is equipped with 12 cassettes, consisting of 48 modules. This provides good flexibility and an
opportunity to always have a constant flux across the membrane surface. In the pilot there are only
two membrane tanks, which give less flexibility than will be found at future Henriksdal WWTP. At
design flow rate and normal operation, a membrane area of approximately 160 m2 would have to
be in operation in the pilot, which corresponds to 4.7 modules. However, as a pilot cassette
contains three modules, the pilot could only be operated with three or six modules in operation. To
enable operation at a constant flux, the pilot was equipped with permeate recirculation, meaning
that the flow through the membranes was higher than the inflow but this was compensated by
having a partial flow of the permeate recycled to the membrane tank.
The airflow requirement for membrane cleaning in the pilot plant is higher than the corresponding
airflow in the Henriksdal design since both cassettes in the pilot plant must be aerated all the time.
In future Henriksdal, only the number of membrane tanks required for the current flow will be in
19
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
operation and only the membrane tanks in operation will be constantly aerated, which means a
minimum air consumption.
The two membrane cassettes in the pilot were parallel to enable comparisons of different
operational strategies.
Torch
MS DS
SED MT
Heat exchanger Digested
Pre-heating DWS dewatered
sludge tank
TMS DMS DMS RWD
Mixed RWT Heat exchanger Heat exchanger Digested Scale
PS WAS Digester
sludge tank Recirculation cooling sludge tank
Reject
water from circuit Reject water
thickening from dewatering
To inlet To RAS-
of MBR deox-zone
in MBR
Figure 7. Process set-up for the sludge treatment line. PS=primary sludge, WAS=waste activated sludge,
MS=mixed sludge, RWT=reject water from thickener, TMS=thickened mixed sludge, DMS=digested mixed
sludge, DS=digested sludge, DWS=dewatered sludge, RWD=reject water from dewatering.
3.2.1 Thickening
Primary sludge and waste activated sludge was intermittently pumped to the stirred mixed sludge
tank. Mixed sludge was then pumped to a rotating drum sieve thickener (Hjortkaer), se Figure 8.
The goal was to reach 5-7% TS after thickening. Polymer was dosed inline in one of three possible
dosing points. Reject water from the thickener flowed by gravity into a tank and was pumped back
to the pre-aeration tank in the wastewater treatment line if the SS content was not too high.
Thickened mixed sludge was injected into the digesters heat exchanger recirculation circuit by an
eccentric screw pump and fed into the digester.
A major difference between the sludge treatment pilot and the future Henriksdal WWTP is that the
primary and the waste activated sludge will be thickened separately at Henriksdal while the two
sludge types are mixed before thickening in the pilot. This solution was chosen because of space
and budget limitations and the fact that the main purpose with the pilot is to study high loaded
digestion with short HRT. In addition, at Henriksdal, centrifuges and band thickeners will be used,
not drum sieves. Choice of equipment for the pilot was done based on price and availability of
small size machines.
During 2018 several attempts to optimize and control the function and result of the thickener were
done, some of which were part of an MSc-project (Jirblom, 2019).
20
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
3.2.2 Digestion
The digester is cylindrical with a base area of 2.54 m2 and a variable water level. During 2018 the
volume was kept at 5.9 m3 which corresponds to full digester capacity in the future Henriksdal
WWTP (scale 1:6,700). The sludge in the digester is homogenised and kept in suspension by a
stirrer and by the recirculation flow. The recirculation circuit consist of a pump which is operated
at its minimum capacity, approximately 3 m3/h, and a heat exchanger controlled by a temperature
meter in the digester. Digested sludge is pumped out of the digester, through a heat exchanger
which can cool the sludge to a chosen temperature, and into an equalization tank (digested sludge
tank).
Thickened mixed sludge was digested at mesophilic conditions. During 2018, the goal was to
obtain a mesophilic (37 °C) reference period, and tests of increasing the temperature were done in
order to verify that the heating system could reach thermophilic conditions (55 °C). During 2019,
thermophilic digestion will be applied, which will be the mode of operation at the future
Henriksdal WWTP.
No external organic material was fed to the digester during the pilot operation. In the future
Henriksdal design, fat from restaurant drains and industrial byproducts like glycerol will be co-
digested with wastewater treatment sludge.
3.2.3 Dewatering
Digested sludge was pumped out of the digested sludge tank into a pressurised, stirred mixing
tank. Polymer was dosed inline just before the inlet to the mixing tank. From the mixing tank
digested sludge was fed into a screw press. Dewatered sludge was collected in a vessel and
weighted. The dewatering equipment is shown in Figure 9. The dewatering unit was not
continuously operated during 2018.
Reject water from digested sludge dewatering was collected in a tank and was intended to be
pumped through a filter into the RAS-Deox zone in the wastewater treatment line. Since the
dewatering unit was not in constant operation in 2018, reject water was not returned to the
treatment line during most of the year. Reject water from Henriksdal WWTP was used prior to
21
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
primary sedimentation week 10-23 for imitation of first full scale treatment line operation and
added to the RAS-Deox week 36-41 for separate evaluation of the RAS-Deox. Other times of the
year the pilot was operated without reject water.
The average incoming flowrate in 2018 was higher than the design flow rate; 3.5 m3/h compared to
the design average flow rate 3.16 m3/h. This was done in accordance with the test plan for the pilot
which included testing operational strategies with high load.
22
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
Table 2. Operation and design data for the wastewater treatment line in the pilot plant and design data
(year 2040) for the future Henriksdal WWTP.
Parameter Unit Value Pilot Design Pilot Design Design future
future H-dal H-dal/ Value
Piloti
Flowrates
Average influent flowrate, Qin m3/h 3.5 3.16 20 880 6 000
Design flowrate, Qdim m3/h 3.32 21 960 6 600
Max flowrate m3/h 5.5 5.44 36 000 6 500
Min flowrate m3/h 1.8 1.8 11 600 6 400
Nitrate recirculation flowrate m3/h 5.1-13.1 3.8-13.3 - -
Nitrate recirculation flowrate × Qin 2.6 1.2-4.2ii 0-4 -
RAS flowrate m3/h 4.1-19.6 3.6-19 - -
RAS flowrate × Qin 3.6 1.1-5.9ii 4 (3-5) 1.1
Incoming load
BOD7 influent mg/L 265 206iii 216 0.8
SS influent mg/L 322 201iii 280 0.9
TN influent mg/L 46 44iii 37 0.8
TP influent mg/L 6.1 5.7iii 4.9 0.8
Primary settler (SED)
BOD7 reduction over SED % 25 46 50iv 2.0
SS-reduction over SED % 35 60 60iv 1.7
TN reduction over SED % 1 10 10iv 10
TP reduction over SED % 12 40 40iv 3.3
BOD7 PTW mg/L 197 112 108 0.5
SS PTW mg/L 200 80 112 0.6
TN PTW mg/L 46 40 33 0.7
TP PTW mg/L 5.4 3.4 3.0 0.6
SS removed over SED kg SS/d 9.6 13.3v 89 300 9 300
Primary sludge production kg SS/d 16.1 17.2v 115 000 7 100
VS-concentration PS % of TS 88% 77% 77% -
Biological treatment
BOD7-load PTW (at average kg BOD7/d 16.3 8.6 57 500 3 500
flowrate)
Specific WAS-production vi kg SS/kg BOD7 0.87 1.02 1.02 1.2
WAS production, average kg SS/d 14.1 8.8 58 600 4 200
VSS-concentration WAS % of SS 73% 64% 64% 0.9
SS in biological tanks mg/L 7 100 8 000 8 000 1.1
SS in membrane tanks mg/L 9 800 10 000 10 000 1.0
Total sludge age d 23.8 32.0 31.2 1.3
Membrane tanks
Installed membrane area (gross) m2 206 206 1 600 000 7 800
Permeate recirculation m3/h 0.03-0.9 0.05-2 - -
Net flux average (at average T) l/m2,h 19.7 17.9 20.9 1.1
Net flux max l/m2.h 28.2 30.8 30 1.1
Permeate pumping max m3/h 7.0 12.4 62 250 8 900
Permeate pumping min m3/h 0 0 0 -
Specific air demand at Leap-Lo vii Nm3/h, m2 0.136 0.136 0.098 0.7
Specific air demand at Leap-Hi vii Nm3/h, m2 0.252 0.252 0.196 0.8
i Design SFA divided by Value pilot. Value either 6 700 or 1 for complete compliance.
ii Based on average flowrate 3.2 m3/h.
iii Design based on data from 2015.
v Calculated based on incoming load/scaled from SFA design with factor 6 700.
vii Aeration of the membranes had two modes, one with lower (Leap-Lo) and one with higher air flowrate (Leap-Hi).
23
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
Table 3. Operation (average 2018, except week 25-33) and design data for the sludge treatment line in the
pilot plant and design data (year 2040) for the future Henriksdal WWTP.
Parameter Unit Value Design Design Design future H-
Pilot Pilot future H-dal dal/ Value Pilot
Into thickener
Flow mixed sludge (MS) L/h 50 70 444 000a 8 900
TS-concentration MS % 1.4% 1,6% 1.6% 1.1
VS-concentration MS % of TS 83% 72% 72% 0.9
TS-load MS kg TS/d 16.5 27.5 173 600 10 500
Polymer consumption g/kg TS 6.4 5 6 0.9
After thickener (TMS into digester)
Flow thickened mixed sludge (TMS) L/h 12 16,6 118 000 9 800
TS-concentration TMS % 5.1% 6.7% 6.0% 1.2
TS-load TMS kg TS/d 12.6 27.0 172 000 13 700
VS-load TMS kg VS/d 10.5 19.5 124 000 11 800
Flow reject RWT L/h 46 53.4 326 000 7 100
SS-concentration reject RWT mg/L 2 800 650 500 0.2
VSS-concentration reject RWT % of SS 77 - - -
Digestion
Digester temperature °C 37 37/55 55 -
Retention time d 20 5-20 13c 0.7
Specific VS-load kg VS/m3,d 2.1 3.3 3.3c 1.6
Digestion efficiency % of VSin 46% 50% 42%c 0.9
VFA-concentration mg/L 225 - - -
pH - 7.2 - 7 1.0
Alkalinity mg CaCO3/l 4 600 - - -
VFA/Alkalinity mg/mg 0.05 - - -
NH4-N mg/L 949 - - -
Out of digester
Flow DMS L/h 13 16.6 123 000 9 500
TS-concentration DMS % 2.9% 4.4% 3.9% 1.3
VS-concentration DMS % of TS 72% 56% 60% 0.8
TS-load DMS kg TS/d 9.0 18.0 124 000 13 800
VS-load DMS kg VS/d 6.5 9.8 74 000 11 400
Specific biogas production Nm3/kg VSdigested 1.0d 1.0 1.0 1
Flow biogas Nm3/d 4.8d 9.7 52 000c 10 800
Methane content biogas % 60% 65% 65% 1.1
Dewatering
Flow DDMS L/h 1.4 16.6 17 000 12 100
TS-concentration DDMS % 27% 30% 30% 1.1
Flow reject RWD L/h 11.6 14.2 114 000 10 300
SS-concentration reject RWD mg/L 3 350 1 050 <900 0.3
Polymer consumption dewatering g/kg TS 15 10 6-10 0.4-0.7
a) WAS and PS are thickened separately in the future Henriksdal process.
b) Not equal to the production of mixed sludge due to repeated operation failures.
c) Numbers without addition of external organic material (fat and glycerol)
d) m3/d not Nm3/d.
3.4 Chemicals
During 2018 methanol was used as external carbon source in the post denitrification zone. The
phosphorus was precipitated using ferrous sulfate at two dosing points and ferric chloride in one
point. For membrane cleaning sodium hypochlorite was used for both membrane tanks (MT) while
one MT was cleaned using citric acid and the other one using oxalic acid.
24
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
The dosing point of methanol was in BR5 deox-zone from mid-June 2017. Before that the dosing
point was in the post-denitrification zone (BR6). The change was made in order to prolong the
residence time for the added carbon and avoid leakage into the membrane tanks. However, it was
noted that the carbon source consumption increased when dosed in the BR5 deox-zone. Week 45
2018 the dosing point was changed again, to a point in-between the BR5 deox-zone and BR6, to
avoid recirculation back to BR1 from the BR5 deox-zone.
More about carbon source addition and treatment results can be found in section 6.2.2
Denitrification and section 6.10 Resource consumption.
Hepta was collected in diluted form from Henriksdal treatment plant in batches of about 500 L.
The iron content of the hepta solution varied during the experimental period between 14-71 g/L.
For the batches used in the experiment, the iron content was determined by density measurement
for each batch.
PIX was delivered as solution with a concentration of 35-45% by weight as specified by the
supplier. The iron concentration used for control and dose calculation was 195.6 g Fe/L.
Sodium hypochlorite was delivered as a solution with a concentration of 10-20% by weight (150-
185 g Cl2/L), as specified by the supplier. The chlorine concentration in sodium hypochlorite
decreases during storage. To prevent fast degradation the sodium hypochlorite has been stored in
a closed, dark container. According to literature the rate of the degradation also decreases if the
solution is diluted upon delivery (Svenskt Vatten, 2010a). During 2018, both diluted and
concentrated sodium hypochlorite in the storage tank has been tested, and pumping have been
adjusted to provide the right concentration in the solution entering the membranes during
cleanings. Dilution was done with tap water to a concentration of about 60 g Cl2/L. The
concentration of sodium hypochlorite in the storage tank varied between 5 and 148 g Cl2/ L during
the year. A good correlation between conductivity and chlorine concentration was confirmed
25
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
during 2017 and from the end of June 2018 an on-line sensor for conductivity was installed in the
sodium hypochlorite container in order to monitor the chlorine degradation in detail.
Citric acid solution was delivered with 51% by weight as specified by the supplier.
Oxalic acid was delivered as powder which was dissolved in batches to a saturated solution (8% by
weight).
For more information on how the cleanings were carried out, see section 6.5.3 Membrane cleaning.
3.4.4 Polymers
For thickening of mixed sludge different anionic polymers were tested, namely:
Towards the end of the year it was decided to continue with the Flopam EM 640 HIB polymer for
sludge thickening. For dewatering of digested sludge, Superfloc C-1598 was used. Polymer was
delivered in solution and prepared to the selected concentrations in % by weight solution in
automated polymer make up units.
26
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
Trial Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Imitation of first phase operation SFA
Mapping of micro-pollutants
RAS-DeOx evaluation
Thickening tests
During spring 2018, the pilot was operated with a high fixed flowrate, no addition of external
carbon source or ferric chloride (PIX) and with reject water from sludge dewatering dosed prior to
the primary sedimentation tank instead of to the RAS-deox. This was done to imitate the planned
operation of the first full-scale MBR-line at Henriksdal during phase 2 of the SFA-project year 2020-
2023. In phase 2, the first full-scale MBR line, out of seven, will be taken into operation and two of
the remaining six activated sludge treatment lines will be shut down for rehabilitation to MBR. The
total biological capacity at Henriksdal WWTP will be low and therefore the MBR-line will be
operated above its design values. Tanks for new process chemicals will be constructed in a later
phase of the project, thus external carbon source and PIX will not be available in phase 2. In
addition, the new dewatering building at Henriksdal will not be taken into operation during phase
2 of the SFA-project, thus the reject water from dewatering of digested sludge will continue to be
added to the inflow in Sickla and not added to the RAS-deox zone in the MBR-line as intended.
The aim of the trial was to test if the treatment process could meet the current and future effluent
requirements under these conditions and to study the effect on the membrane operation.
The RAS-deox zone has multiple functions, the most important ones are to remove the oxygen
content in the sludge before recirculation to the pre-denitrification zone and to nitrify the ammonia
from the reject water that is added to the zone using oxygen from membrane aeration. It has been
proven previously that oxygen levels decrease in the RAS-deox zone but it is not clarified if it was
removed by nitrification or other microbial activities. Therefore, the function of the RAS-deox zone
was evaluated during autumn.
27
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
In order to determine the emission of greenhouse gasses from the membrane process, two
measurement campaigns for nitrous oxide emissions carried out during 2018.
During 2017 it was noticed that the phosphorus removal and the precipitation chemical
consumption did not add up and it was discovered that enhanced biological phosphorus removal
(EBPR) mysteriously appeared in the process. Therefore, in 2018 the EBPR activity was monitored
regularly and, in the summer, the iron dosage was completely stopped for three months in order to
evaluate the dynamics of iron in sludge, effluent phosphorus and EBPR activity.
Optimisation of resource consumption has continuously been in the spotlight during 2018.
Especially regarding the carbon source addition, chemicals used for membrane cleaning (focus this
year was to minimize the consumption of oxalic acid), and energy for membrane aeration.
Throughout 2018 the sludge treatment line (including sludge thickening, anaerobic digestion and
sludge dewatering) was in focus. The goal was to obtain steady operation at mesophilic conditions
– a “reference period”, and to evaluate the thickener and its function. However, the operation was
characterized by technical problems and several minor adjustments and reconstructions were done
in order to make it function over time. The optimization of the thickening step included testing
different polymer doses and dosing points and a comparison of thickening MBR sludge and waste
activated sludge from Henriksdal.
A two years long study on mapping of micro pollutants through the treatment process, such as
pharmaceutical residues, micro plastics, bacteria, PFAS and chloro-organic halogens was started
during autumn 2017. In 2018, the second sampling campaign (out of a total of four planned
campaigns) was carried out and the results are presented in this report.
28
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
5 Method
5.1 Sampling and analyses
Eurofins Environment Sweden AB (Lidköping) conducted analyses of water samples from five
different sampling points: IN (influent wastewater), PTW (primary treated water), EFF (effluent
water), activated sludge from bioreactor BR4 (SLUDGE 1) and return sludge from RAS-DeOx
(SLUDGE 2), and analyses of sludge samples from three different sampling points: PS (primary
sludge), WAS (waste activated sludge) and DS (digested and dewatered sludge).
PH2040_1, augusti 2018
External
Precipitation Precipitation Precipitation
carbon
chemical chemical chemical
source
IN PTW EFF
6 mm
0,6 mm
Henriksdal Membrane
Pre- tank 1 OUT
IN Primary settler Anoxic Flex Aerobic Deox Anoxic
precipitation Membrane
Heat exchanger, tank 2
possibility of cooling Nitrate recirkulation
incoming water
PS Return activated sludge
RAS DeOx
WAS
DS Mixed
Dewatered Sludge Anaerobic Sludge sludge
digested sludge dewatering digester thickener
Reject water
Reject water
Figure 10. Sampling points in pilot process marked as black circles (SLUDGE1 and SLUDGE2 sampling
points not included in figure).
Three different sampling types were used: daily composite samples, weekly composite samples
and grab samples. Daily samples were taken with automatic samplers set for flow proportional
sampling. Weekly samples were mixed from the daily samples proportionally to the mean flow
during the respective days. Grab samples were an instantaneous sample taken from the respective
tank. The weekly composite samples were conserved with 1 part 4M sulfuric acid to 100 parts
sample volume, except for the samples analysed for TOC which were conserved with 2M
hydrochloric acid in corresponding proportions.
Table 5 lists the parameters analysed at the accredited laboratory for the respective sampling
points and sample types. One portion of the grab sample of sludge from the RAS-DeOx which was
sent to accredited laboratory (Eurofins), was used to measure sludge volume (SVI) and time to
filter (TTF) at IVL’s internal laboratory at Hammarby Sjöstadsverk.
29
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
Table 5. Sampling points, parameters and number of samples sent per week for external analyses.
Parameters
NO3-N + NO2-N
Fe (digested)
P (digested)
NH4-N
PO4-P
BOD7
cTOC
COD
TOC
VSS
Sampling point
TN
TP
SS
Daily composite samples
IN 1 1 1 1 1 1 1
PTW 1 1 1 1 1 1 1
EFF 1 1 1 1 1 1
Grab samples
RAS-DeOx 1 1 1 1 1
Reject water mixed sludge thickening 1 1
Reject water digested sludge
1 1 1 1 1 1 1 1
dewatering
Weekly composite samples
IN 1 1 1 1 1 1 1
PTW 1 1 1 1 1 1 1
EFF 1 1 1 1 1 1
Total number 6 2 3 7 4 6 7 1 4 3 4 8 1
In addition to the samples and analyses presented in Table 5, a monthly composite sample of
dewatered digested sludge (DDMS) was sent to external accredited laboratory for analysis of TS,
VS, pH, nitrogen, phosphorus, chlorine, and 15 different metals. Multiple organic parameters and
three more metals were analysed each quarter, including Polybrominated diphenyl ethers (PBDE,
24), Triclosan, Polychlorinated biphenyls (PCB, 7), Polycyclic aromatic hydrocarbons (PAH, 6),
organotin compounds (10), Phenols (19), Perfluorooctanoic acid (PFOA), Perfluorooctanesulfonic
acid (PFOS) and Per- and polyfluoroalkyl substances (PFAS).
In addition to the external analyses, analyses were also performed internally at IVL’s laboratory at
Hammarby Sjöstadsverk. Water phase samples were analysed by means of colorimetric methods
using a spectrophotometer (WTW photolab 6600) and standard cuvette tests. The daily composite
samples were analysed according to Table 6. Additional analyses of daily composite samples or
grab samples were also done in order to calibrate process instruments.
Table 6. Internal analyses on daily composite samples from effluent water samples.
Weekday
Analysis Monday Wednesday Friday
EFF COD X
EFF NH4-N X
EFF NO3-N X X X
EFF TN X
EFF PO4-P X X X
EFF TP X
Sludge phase samples were analysed regarding total solids (TS (%)) and volatile solids (VS (%))
between 2-3 times per week. This applies to all different sludges; primary sludge, waste activated
30
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
sludge, mixed sludge, thickened mixed sludge, digested sludge and dewatered and digested
sludge. The reject water from sludge thickening and sludge dewatering was internally analysed at
the Hammarby Sjöstadsverk´s laboratory with the same approximate frequency regarding total
suspended solids (mg/L). To monitor the digestion process, a sample from the digester was taken
once per week and pH, VFA, alkalinity and ammonium were analysed. Measurements of methane,
carbon dioxide and hydrogen sulphide in the produced biogas was conducted weekly with a
portable gas meter.
31
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
As the membranes are operated in cycles with 10 minutes of permeate withdrawal and 1 minute
relaxation, the membrane performance parameters can be calculated as gross values (using only
data from the 10 minutes of actual permeate withdrawal) or as net values (using average data from
the full operation cycle, permeation and relaxation = 11 minutes). The gross values are higher than
the net values, however the net values corresponds better to the average operation. All values for
the parameters described below are given as net values in this report.
1) Flux: Flowrate per membrane area, unit L/(m2·h). The flux is describing the hydraulic load on the
membranes. Flux is calculated as permeate flow divided by membrane area.
2) TMP: Transmembrane pressure, unit mbar. The difference in pressure before and after the
membranes. TMP is the driving force for transportation through the membrane. TMP is measured
using online pressure transmitters in the membrane tank and on the permeate pipe.
3) Permeability: Flux per TMP, unit L/(m2·h·bar). Permeability is a measurement of how well a
certain flux is withdrawn through the membranes. The permeability is gradually decreasing with
time due to fouling.
𝐿𝐿
𝑁𝑁𝑁𝑁𝑁𝑁𝑁𝑁𝑁𝑁𝑁𝑁𝑁𝑁𝑁𝑁𝑁𝑁𝑁𝑁 𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝 � 2 𝑎𝑎𝑎𝑎 𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡 20 °𝐶𝐶 � = 𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑖𝑖𝑡𝑡𝑡𝑡 ∙ 𝜃𝜃 (20−𝑇𝑇)
𝑚𝑚 ∙ ℎ ∙ 𝑏𝑏𝑏𝑏𝑏𝑏
where
32
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
Trash content
The method for Trash content is described in detail in last year’s report (Andersson et al. 2017). In
short, the sludge is filtered through sievs with different slot width and the amount of trash
captured in the sieves is measured. This analysis was carried out once every month in order to
assure that particles larger than 2 mm, which could harm the membranes, would not accumulate in
the treatment line. For a well-functioning process, the amount of trash content in the sludge, at a
sieve size of 2 mm, should not exceed 2 mg/L (information from the membrane supplier).
33
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
Trial Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Imitation of first phase operation SFA
SS in incoming ww
500
400
300
mg SS/L
200
100
0
2014 2015 2016 2017 2018
Figure 11. Incoming SS concentration to the pilot line after passing through 2, 3 or 6 mm punch hole screen
and to Henriksdal (about half of the flow not screened, half screened through 3 mm step-screen).
34
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
Table 10. Reduction over the primary settler and primary sludge production
Parameter 2018 2017 2018: Henriksdal Design future
WWTP Henriksdal WWTP
SS (%) 35% 37% 53% 60%
BOD7 (%) 25% 30% 48% 50%
TP (%) 10% 14% 30% 40%
TN (%) 1% 4% 9% 10%
TOC (%) 18% 17% 29% -
PS production (kg/d) 16.1 13.1 82 000 115 000
80
500
400 60
300 40
200
20
100
0 0
w01 w04 w07 w10 w13 w16 w19 w22 w25 w28 w31 w34 w37 w40 w43 w46 w49 w52
The results have been consistent since the current screen/sieve configuration was implemented. In
addition, visual inspection of the membrane cassettes (see 6.5.4 Membrane autopsy) show very
little build-up of trash indicating that the measured values are good. The 2017 data after changing
to 6 mm fine sceen and installing the 0.6 mm fine sieve is presented as one average from March to
35
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
December and one average from May to December. The exclusion of the first two months of data
gives about half as much trash content caught by the 1 mm sieve. This can be explained by the fact
that it takes at least 3 sludge retention times to exchange the sludge filled with larger particles from
the previous period. The trash content measurements from 2018 show similar values as to the later
part of 2017. The finest trash content (1 mm) were slightly reduced compared to 2017.
Table 11. Trash content in waste activated sludge (WAS) with various screen/sieve-configurations.
Screens/sieves and hole size Date Trash content - Trash content -
1 mm sieve 2 mm sieve
mg/L mg/L
3 mm fine screen at inlet pump Dec 2013 11.6 ± 5.4 1.0 ± 0.7
2 mm fine screen at inlet pump Nov 2016 – Feb 2017 6.4 ± 2.4 1.1 ± 0.7
6 mm fine screen at inlet pump and 0.6 mm Mar 2017 → Dec 2017 4.1 ± 3.8 0.6 ± 0.3
fine sieve before biology
6 mm fine screen at inlet pump and 0.6 mm May 2017 → Dec 2017 2.2 ± 1.6 0.6 ± 0.3
fine sieve before biology
6 mm fine screen at inlet pump and 0.6 mm Jan 2018 → Nov 2018 2.0 ± 1.1 0.6 ± 0.5
fine sieve before biology
The concentration difference will affect the biological treatment including WAS production (and
thereby SRT and the amount of phosphorus assimilated in sludge), pre-denitrification capacity and
simultaneous precipitation. It can be noted that the iron dosage in the primary settler was low in
the pilot compared to the full-scale and the future Henriksdal. This is due to enhanced biological
phosphorus removal (EBPR) which is described in chapter Table 12.
Table 12. Data on pre-treated wastewater (PTW) from the pilot compared to data from Henriksdal 2018 and
the design data for the future Henriksdal WWTP.
Parameter Value Pilot 2018 Value Henriksdal Design future Design H-dal/
2018 Henriksdal Value Pilot
Pre-treated wastewater (PTW) – into biological treatment
SS (mg/L) 200 ± 74 186 113 0.6
BOD7 (mg/L) 197 ± 45 148 108 0.5
TN (mg/L)* 46 ± 8 41 33 0.7
TP (mg/L) 5.3 ± 0.9 6.7 3.0 0.6
Fe (mg/L) 7.3 ± 4.9 16 12 1.6
BOD7/TN (mg/mg) 4.3 4.2 3.3 0.8
*At Henriksdal the reject water from dewatering of digested sludge is added to the inlet while in the pilot and future Henriksdal it will be
added to the RAS-deox zone in the biological treatment.
36
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
Trial Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Imitation of first phase operation SFA
RAS-DeOx evaluation
Nitrogen concentrations in the incoming water to the biological treatment (PTW, primary treated
water) and in the effluent are presented in Table 14. On average the effluent total nitrogen
concentration was 4.6 mg/L and 3 out of 52 weekly composite samples was above the limit
concentration of 6 mg N/L. The reduction of total nitrogen (measured in primary treated water)
including reject water was 90.1%.
Table 14. Nitrogen concentrations in primary treated water (PTW) and effluent (permeate) during 2018.
Parameter Limit Average Min Max No. of weekly samples
TN PTW (mg/L) - 46 30 67 52
TN EFF (mg/L) 6 4.6 2.8 6.6 52
Effluent nitrogen concentrations as weekly composite samples are presented in Figure 13. From
week 10 to week 22 the load was high and no external carbon source was used (see description of
trial imitating the first full scale treatment line operation in section6.6. During this period effluent
TN was close to 6 mg/L while ammonium concentrations were low. The increase in TN until week
41 was mainly related to reduced nitrification due to limited aeration capacity in the biology.
37
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
70 20
60
50 15
mgN/L eff
mg N/L in
40
10
30
20 5
10
0 0
2018-01
2018-04
2018-07
2018-10
2018-13
2018-16
2018-19
2018-22
2018-25
2018-28
2018-31
2018-34
2018-37
2018-40
2018-43
2018-46
2018-49
2018-52
Figure 13. Incoming and effluent nitrogen concentrations from analysis of weekly composite samples.
Limit for effluent total nitrogen was set to 6 mg N/L.
In Table 15, key values for the nitrogen removal in the pilot are presented and compared to the
design value for the future Henriksdal WWTP. The amount of removed total nitrogen was 15%
higher compared to the design. The external carbon source used throughout this year was
methanol, however, it should be noted that the external carbon dosage was not in use for 26 weeks
(from week 10 to week 36) due to separate trials where the biological treatment was operated
without use of external carbon source. On yearly average the methanol consumption was 4.8 g
COD/m3 (148 kg COD/year). If excluding week 10 to week 36 when the methanol dosage was
deliberately off, the dosage was on average 10 g COD/m3 corresponding to about 297 kg COD/year,
or 45% of SFA design. Although yearly effluent nitrogen concentrations were low with low
methanol dosage, the dosage is not comparable with the dosage required if effluent nitrate should
have been controlled throughout the year. The yearly average of nitrogen removal in the pilot was
slightly lower this year (3.6 kg N/d) compared to last year (3.7 kg N/d) but the water temperature
this year was about 1.7 degrees higher because the heat exchangers on the inlet water was out of
operation.
The nitrogen removal rate presented in Table 15 was lower in the pilot which comes from the fact
that the VSS content in the sludge was 76% while it was estimated to 63% in the design. The
parameter that stood out the most was the aeration of the biology which was almost 6 times higher
than the design. One reason for a higher value is that the basins in the pilot were about 4 times less
deep than the design. The aeration of the biology is about the same as previous year (2017) when it
was 54 m3/h. From comparing aeration in biology with the first year when membrane aeration was
higher, reduced aeration of the membranes result in a higher demand for oxygen in the biology
which indicates that some nitrification occurred in the membrane tanks.
38
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
Table 15. Comparison of parameters related to the nitrogen removal between operational data from the
pilot and the SFA design.
Parameter Unit Value SFA Value pilot /
Pilot design Scaledvi SFA
design
Removed nitrogen (including reject water) kg N/d 3.6 21 000 115%
Nitrogen removal rate g N/kg VSS, d 19.6 22 89%
Aerated sludge age (including membrane d 7.5 9,4vii 79%
tanks)
Air consumption biology (activated sludge) Nm3/h 52.4viii 62 000 566%
Specific oxygen demand (SOTR) kg O2/d 60ix 260 000 155%
Consumption of external carbon kg COD/d 0.8x 12 000 45%
vi The value of SFA-design divided by the scale factor 6 700
vii Assumed that ¾ of all membrane tanks are in operation as a yearly average.
viii m3/h not Nm3/h
ix SOTR was calculated from the measured airflow and a water depth (aerator surface to water surface) of 3,19 m and a specific
oxygenation capacity of 0,015 kg O2/Nm3, m.
x Excluding week 10 to week 36.
6.2.1 Nitrification
The total load of ammonium nitrogen (including reject water) compared to the reduction and
related to total aeration (including the membrane tanks) is presented in Figure 14. The aeration
trend follows the load although more aeration was used per NH4-N reduced in the beginning of
the year and during the summer period.
Total NH4-N reduction (kg/d) Total NH4-N load (kg/d) Total aeration (m3/d)
6.0 3500
5.0 3000
2500
4.0
2000
kg N/d
m3/d
3.0
1500
2.0
1000
1.0 500
0.0 0
2018-01
2018-04
2018-07
2018-10
2018-13
2018-16
2018-19
2018-22
2018-25
2018-28
2018-31
2018-34
2018-37
2018-40
2018-43
2018-46
2018-49
2018-52
Figure 14. The total load and reduction of NH4-N together with total aeration of biology and membrane
tanks. Note that the load and reduction of NH4-N is almost the same.
When comparing the aeration of the biology with aeration of the membrane tanks (Figure 15) it can
be observed that the membranes most of the time was operated at the lower aeration level (Leap-
Lo corresponding to 14 m3/h each, 28 m3/h in total) with only a few peaks above 28 m3/h. The
aeration of the biology varied as weekly average between 27 and 87 m3/h and was on average 52.4
m3/h.
39
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
100 2.0
1.4
60 1.2
1.0
40 0.8
0.6
20 0.4
0.2
0 0.0
2018-01
2018-04
2018-07
2018-10
2018-13
2018-16
2018-19
2018-22
2018-25
2018-28
2018-31
2018-34
2018-37
2018-40
2018-43
2018-46
2018-49
2018-52
Figure 15. Aeration need in biology and membrane tanks (MT) together with effluent NH4-N.
On average, the aeration of the membranes accounted for 36% of the total aeration, same as last
year (2017). This is a significant reduction compared to the first year (2016) when 54% of total
aeration was used for the membranes. In week 47 in 2016 fouling control was implemented for the
membrane aeration. Fouling control is part of the membrane suppliers’ strategy to optimize the air
consumption for cleaning of the membranes, and it controls how much air to be used in the
membrane tanks. With fouling control, the air flow set point to the membrane tank automatically
switches between two air flow rates based on how fouled the membranes are (higher aeration
when indication of fouling).
The initial aim for the pilot was to operate at a total sludge age of 25 days. However, as the
membrane supplier terms states that the membranes should not be operated in sludge
concentration above 10 000 mg SS/L for longer periods, the sludge age has not been controlled.
Waste activated sludge (WAS) flowrate has been manually adjusted to keep the suspended solids
concentrations in the RAS-DeOx normally between 8 000 and 10 000 mg SS/L, and during special
trials at higher concentrations to study fouling of the membranes.
Total and aerated (including membrane tanks) sludge age is presented in Figure 16 together with
suspended solids concentration in RAS as well as the WAS flowrate. The calculations of sludge age
are uncertain because of foaming in the aerated bioreactors leading to overflow and loss of sludge
not accounted for in the calculations. The sludge concentration decreased during June and July and
by the end of July the WAS pump was stopped for about one week to increase the sludge
concentration in the system. The low WAS flow resulted in a high peak in the sludge age during
summer (July to September). The total sludge age was on average 24 days and the aerated sludge
age (including membrane tanks) was 7.5 days.
40
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
90 16 000
80 14 000
70 12 000
60
10 000
50
mg/L
d, L/h
8 000
40
6 000
30
20 4 000
10 2 000
0 0
Dec-17 Feb-18 Mar-18 May-18 Jul-18 Aug-18 Oct-18 Dec-18 Jan-19
Aerated sludge age [d] Total sludge age [d] Q WAS [L/h]
SS RAS-DeOx [mg/L] TSS RAS (mg/L)
Figure 16. Total and aerated (incl. MTs) sludge age (moving average one month back in time) together with
WAS flowrate and online SS in the RAS DeOx as well as lab analysis of TSS on grab samples from the
RAS-DeOx.
The aeration of the biology has been problematic this year due to excessive foaming in the
bioreactors and some equipment failures. Previously, mainly dissolved oxygen (DO) control using
fixed setpoints have been used. In 2017 the first aerated bioreactor (BR3) was intermittently aerated
to a fixed DO set point based on a threshold value on ammonium entering the aerated part of the
biological treatment (measured in BR2). In the beginning of 2018 ammonium feedback control was
implemented to control the DO setpoint for BR3 and BR4. DO setpoints could vary between 1 mg/L
and 3.5 mg/L to reach setpoint of 2 mg NH4-N/L in BR5. The aim of this control strategy was to
save aeration in the biology, especially during night when the load was low, by allowing a lower
DO concentration. As can be seen in Figure 17, the DO concentrations in BR3 and BR4 show a large
variation from week 3, compared to previous control strategy.
3
DO BR3
mg/L
2 DO BR4
1 DO BR5ox
0
2018-01
2018-03
2018-05
2018-07
2018-09
2018-11
2018-13
2018-15
2018-17
2018-19
2018-21
2018-23
2018-25
2018-27
2018-29
2018-31
2018-33
2018-35
2018-37
2018-39
2018-41
2018-43
2018-45
2018-47
2018-49
2018-51
Figure 17. Dissolved oxygen (DO) concentrations in the three aerated bioreactors (BR3, BR4 and BR5ox).
BR5 was initially aerated to keep a DO concentration of 2 mg/L. In week 10 the load was increased
which also increased the need for aeration and problems with foaming in the aerated reactors
started in week 11. In week 15 the aeration in BR5 could not maintain DO concentration 2 mg/L
and during that period there were severe problems with foaming in BR4. In week 18 the aeration in
41
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
BR5 was set to a low fixed flowrate as the aeration control was not functioning. BR4 and BR5 were
drained for inspection in week 24 and it was found that the wall separating the aerated
compartment and the deox-compartment in BR5 had collapsed, blocking the diffusers in BR5. Once
the wall was fixed, aeration could be started again in BR4 and BR5. At the same time, due to
warmer temperatures and less need for aeration, BR3 was used as anoxic zone.
As part of an EU funded research project (R3Water) a different aeration equipment was tested
since 2016 in BR4. This aeration equipment is based on so called oscillating aeration with the target
of getting more efficient oxygen transfer from air to water. Week 34, after some tubing problems in
aeration equipment in BR4, the test equipment was removed, and the standard aeration equipment
was put in operation. After this, aeration of BR4 was started and another attempt to use
ammonium feedback control was made, this time only in BR4. However, the foaming and overflow
of sludge occurred as soon as aeration was started. Aeration in BR3 was started in week 31 with at
fixed airflow to evaluate if this could help the problems with foaming and overflow in BR4.
Aeration of BR4 had to be either manually controlled with fixed flowrate or completely stopped in
the period from week 29 to week 41 to avoid too much overflow of foaming sludge.
Because of the problems with foaming, unreliable DO sensor readings in the foamy sludge and
several aeration equipment failures this year, no deeper evaluation of the aeration control
strategies have been made.
6.2.2 Denitrification
For the post denitrification (BR6) external carbon source has been added using different carbon
sources and control strategies in previous trials. This year only methanol has been used as carbon
source. For a long period this year, the post denitrification was operated without dosage of
methanol as to mimic the first years of the full scale treatment line operation (when it will not be
possible to dose methanol).
On Tuesday 6th of March (week 10) the methanol dosage was stopped. Until then the dosage had
been controlled based on effluent nitrate concentrations with a setpoint of 4 mg NO3-N/L in the
effluent. The setpoint was increased from 3 mg/L to 4 mg/L at the beginning of the year as previous
operation showed that the effluent concentration during night was very low and therefore the
daily average was always lower than the setpoint. As can be seen in Figure 18, the setpoint of 4
mg/L resulted in an average nitrate concentration of 3 mg/L or less. When methanol dosage was
stopped in week 10, the nitrate concentration increased at first and then decreased as temperature
increased towards summer. The methanol dosage was started again in week 36, again with
setpoint 4 mg NO3-N/L. Dosage was only needed during short periods each day at the daily peak
load which resulted in low average consumption of methanol. In week 45 the dosage point was
changed from dosing directly into BR5 to a point in the piping between BR5 and BR6. This was
done in order to avoid carbon source recycling back to the pre-denitrification tanks with the nitrate
recirculation flow. After this change the required dosage decreased even more.
42
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
Nitrate BR6 mg/L Nitrate Effluent mg/L Dosage Methanol L1-BR6 mg/L
6 100
5 80
mg NO3-N/L
mg COD/L
60
3
40
2
1 20
0 0
2018-01
2018-04
2018-07
2018-10
2018-13
2018-16
2018-19
2018-22
2018-25
2018-28
2018-31
2018-34
2018-37
2018-40
2018-43
2018-46
2018-49
2018-52
Figure 18. Nitrate in BR6 and dosage of methanol as daily average values and effluent nitrate analysed in
weekly composite samples.
The nitrate sensor in BR5deox was taken out of operation in October 2017 and was replaced with a
new sensor by the end of February 2018, about at the same time as the methanol dosage was
stopped. From the online measurements of nitrate as weekly average data (Figure 19) the effect of
starting methanol dosage in week 36 is not clear as the dosage only was active a few hours per day.
Nitrate BR5 (mg/L) Nitrate BR6 (mg/L) Nitrate eff online (mg/L)
7
6
5
4
mg/L
3
2
1
0
2018-01
2018-04
2018-07
2018-10
2018-13
2018-16
2018-19
2018-22
2018-25
2018-28
2018-31
2018-34
2018-37
2018-40
2018-43
2018-46
2018-49
2018-52
Figure 19. Online nitrate concentrations as weekly average. Methanol dosage was in operation week 1-10,
then stopped and started again in week 36.
For the period of week 36 to week 52 2018 the average COD dosage was 4.8 g COD/m3 influent to
the treatment line. This corresponds to 0.82 kg COD per day. In 2017 the methanol consumption
was about 30 g COD/m3 based on online measurements. Some reasons for the large difference in
dosage are the lower setpoint for nitrate (3 mg/L) used in 2017, the lower average temperature in
2017 (yearly average was 1.7 degrees lower compared to 2018) and the change in dosage point, first
changed from BR6 to BR5deox in 2017 which resulted in increased consumption and then changed
to the pipe in-between BR5deox and BR6 which reduced consumption.
43
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
The idea of the RAS-Deox zone is to collect the return sludge with a high oxygen concentration
from the membrane tanks and provide enough retention time for the oxygen concentrations to
decrease before the return sludge is pumped back to the pre-denitrification zone (BR1). As an
additional feature, reject water will be added in this zone in order to make use of the excess oxygen
to nitrify some of the ammonium in the reject water from dewatering of digested sludge. The RAS-
Deox tank is equipped with an oxygen sensor and an ammonium sensor in order to monitor to
what extent the oxygenated return sludge could be used to nitrify ammonium in the reject water.
The evaluation looked at different aeration levels of the membrane tanks (Leap-Hi and Leap-Lo)
and three different loads of ammonium from reject water to the RAS-Deox zone corresponding to
5, 10 and 15% of influent ammonium load.
The least favorable situation, with high aeration and low reject water addition (5%) resulted in DO
peaks reaching a maximum concentration above 2 mg/L. With higher reject water addition, the DO
decreased well below 0.2 mg/L (Figure 20).
2.5
2
A: Low, N 5%
1.5
mg O2/L
A: High, N 5%
A: Low, N 10%
1
A: High, N 10%
A: High, N 15%
0
00:00 02:00 04:00 06:00 08:00 10:00 12:00 14:00 16:00 18:00 20:00 22:00 00:00
Time (hh:mm)
Figure 20. Dissolved oxygen from online sensor in the RAS-DeOx for six days with varying aeration (A)
between low and high and ammonium (N) load.
The lower aeration level for the membranes was used most of the time. This means less oxygen
entering the RAS-Deox and low DO concentrations in the RAS-Deox could be achieved most of the
time even without addition of reject water (Figure 21).
44
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
8 1500
7
6
5
1000
mg O2/L
L/h
4
3
500
2
1
0 0
2018-10-01 2018-10-11 2018-10-21 2018-10-31 2018-11-10 2018-11-20 2018-11-30
Figure 21. DO concentrations in membrane tanks (MT) and in the RAS-DeOx zone with and without
addition of reject water.
Both sampling and simulations showed that there was simultaneous nitrification and
denitrification in the zone when reject water was added. From the sampling campaign it was
observed that the ammonium reduction varied, however most of the time it was above 60% (Figure
22). This indicates that nitrification occured, however no conclusion or performance indicator
could be calculated regarding how much oxygen was used for ammonium conversion. For nitrate
(assuming a decrease in NH4-N result in a corresponding NO3-N increase) a reduction of about 20
to 50% was observed.
1.5 100
Reduction [kg N/d]
1.2 80
Reduction [%]
0.9 60
Total reduction (kg)
0.6 40
Average NH4-N reduction (%)
0.3 20
Average NO3-N reduction (%)
0 0
A:Low A: A:Low A: A:Low A:
High High High
N-load: 5% N-load: 10% N-load: 15%
Figure 22. Results from sampling campaign in the RAS-Deox.
When comparing to process simulations (10% N load from reject water) a reduction of ammonium
nitrogen of about 50% was observed in the RAS-Deox (concentration from 1 mg NH4-N/L to 0.5 mg
NH4-N/L) and 10% reduction of nitrate (from 3.57 NO3-N + 0.5 N from ammonium conversion, to
3.62 mg NO3-N exiting the RAS-Deox zone).
Based on the DO readings at sampling, a larger decrease in DO was observed when the
ammonium load increased (Figure 23). For the first three days the DO was higher in the first
sample (at time 09:00) because of lower load. With reject load corresponding to 5% of the inlet load
the morning samples indicated that peaks with remaining DO concentrations in the return sludge
of 1-2 mg O2/L will occur. This indicates peaks in return sludge if reject water load is low or if no
reject water is added to the RAS-Deox zone. However, when comparing to a longer period (Figure
21) with and without reject water addition, peaks above 1 mg/L in the RAS-Deox zone seldom
occur.
45
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
6
mg O2/L
4 O2 MT1
2 O2 MT2
O2 RAS
0
A:Low A: High A:Low A: High A:Low A: High
.
N: 5% N: 10% N: 15%
Figure 23. DO concentrations in membrane tanks and RAS-DeOx at the times for sampling.
As a previous measurement campaign in 2014 indicated that the main part of the emissions
occurred in the aerated zones, these zones were in focus for this campaign.
Preliminary results showed that BR4 and BR5 were the zones where most of the nitrous oxide was
emitted (Figure 24). Approximately 20% of the total nitrous oxide emissions came from the
membrane tanks. Most of the methane emissions originated from the Pre-aeration and BR4.
1.0 8
g N2O/d
0.8 6
0.6
0.4 4
0.2 2
0.0
0
MBR1
MBR2
Presedimentation
pre-aeration
Br3
Br4
Br5
Br6
RAS
Pre-aeration
MBR1
MBR2
pre-sed
Br3
Br4
Br5
Br6
RAS
Figure 24. Preliminary results of nitrous oxide emissions (left) and methane emissions (right) from the
pilot process.
Based on the preliminary data from 2018 approximately 0.07% of the total NH4-N load was
converted to nitrous oxide nitrogen in the treatment line.
46
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
Trials Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Normal load, fixed dose
EBPR tests
The goal of reaching stable effluent phosphorus concentrations below 0.15 mg P/L had been
achieved previous year by using a control strategy with dosage of ferrous sulfate and ferric
chloride in three points in the process, where the first dosage was flow proportional and the
dosage in the other two points were controlled using feedback control from online effluent
phosphate measurements.
For the first part of 2018 (w.1- w.25) only ferrous sulfate was used as precipitation chemical and no
phosphate control of the dosage was used. After this period all dosage was stopped in order to
evaluate the potential of biological phosphorus removal during week 26 to week 42. The last part
of the year, dosage in three points was used, with ferrous and ferric dosages based on feedback
control from the phosphate analyser.
The phosphorus concentrations in and out from the biological treatment is presented in Table 17
and Figure 25 below. As no precipitation was used for a long time, the yearly average effluent
concentration was high, 0.75 mg P/L, however if excluding the weeks without precipitation (w.26-
w.41) the average effluent concentration was 0.14 mg P/L.
Table 17. Phosphorus concentrations in primary treated water (PTW) and effluent during 2018.
Parameter Limit Average Min Max Nr of weekly samples
TP PTW (mg/L) - 5.4 3.7 9.0 52
TP EFF (mg/L) 0.20 0.75 0.058 3.5 52
47
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
10 4
3.5
8
3
2.5
EFF mg/L
IN mg/L
6
2
4 1.5
1
2
0.5
0 0
2018-01
2018-04
2018-07
2018-10
2018-13
2018-16
2018-19
2018-22
2018-25
2018-28
2018-31
2018-34
2018-37
2018-40
2018-43
2018-46
2018-49
2018-52
Figure 25. Influent and effluent total phosphorus analysed on weekly composite samples.
To evaluate and compare phosphorus removal with different precipitation and operational
strategies, the year 2018 has been divided into four periods.
The first period (T1, week 1 to 9) was when the load and operation was normal except for not using
ferric, not using online phosphate to control precipitation chemicals and the treatment line was
operated without addition of reject water. The background for having this period was that the
phosphate analyser broke in October 2017 and a new analyser was not installed until the end of
January 2018. Due to some problems the first months after installation of the analyser, precipitation
chemical dosage was kept as flow proportional dose in pre-aeration, prior to pre-sedimentation
tank, and a fixed flow to BR4.
The second period (T2, week 10 to 24) was during the imitation of the first full scale treatment line
operation. This operational strategy included phosphorus removal using only ferrous sulfate and
the dosage was flow proportional to pre-aeration and a fixed flow to BR4. The reason this period is
separated from the first one is because it was operated at high load (high inflow and reject water
addition).
In between the second and third period, there was one week of continuation of the precipitation
dosage, however the inflow was reduced to normal and no reject water was added. The
precipitation chemical dosage was then stopped in the beginning of week 26. This short period
(week 25-26) was excluded in the evaluation of the four periods.
The third period (T3, week 27 to 41) started during summer when no precipitation chemicals were
used in order to evaluate the potential for enhanced biological phosphorus removal, EBPR, without
interference from chemical dosage. During this trial it was also of interest to study how the
concentration of iron in the sludge behaved.
The fourth period (T4, week 42 to 52) was during the last couple of months of the year when all
three dosing points were used, both ferrous and ferric was added and the online phosphorus
control was in operation.
Key parameters for the phosphorus removal, both for the pilot and for the SFA design, are
presented in Table 18. The phosphorus load on the biological treatment in the pilot was 1.5-2.3
48
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
times bigger than in the SFA design. In all experimental periods except T3 (no Fe dose) the uptake
in the biology was also bigger than in the SFA design. At the same time the iron to phosphorus
ratio was low, 1.5-1.9 mole/mole in the pilot which indicates enhanced biological phosphorus
uptake (see 6.3.2).
Table 18. Comparison of operational data from the pilot with data for the SFA design, yearly average
values.
Parameter Unit T1 T2 T3 T4 SFA Scaled
2018 2018 2018 2018 design SFA
design*
Phosphorus load influent kg P/d 0.43 0.61 0.43 0.59 2 594 0.39
Phosphorus load biology kg P/d 0.36 0.54 0.38 0.53 1 556 0.23
Phosphorus load effluent kg P/d 0.010 0.014 0.155 0.013 79 0.012
Phosphorus removed in kg P/d 0.35 0.53 0.22 0.52 1 477 0.22
biology
Iron consumption kg Fe/d 1.21 1.43 0 1.70 10 000 1.49
(PS+BR4+BR6)
Iron consumption per mole 1.9 1.5 0 1.8 2.8 -
removed phosphorus Fe/mole P
Phosphorus in sludge % of SS 3.0 3.0 3.5 3.7 5.4 -
Iron in sludge % of SS 9.1 7.8 2.8 7.4 - -
VSS in sludge % of SS 73 75 80 76 63 -
*SFA divided by 6700. Values comparable to pilot data.
6.3.1 Precipitation
The total amount of iron dosed is presented in Figure 26. The base dose of Fe2+ was added to the
pre-aeration which, when in operation, was controlled flow proportionally to a dose of 12 mg Fe/L
(except two shorter periods when 10 mg Fe/L was used due to low concentrations of effluent
phosphate). A supplementary dosage of Fe2+ was added to the aerated part of the biological
treatment (BR4). This dose was during most of the year controlled using a manually adjusted fixed
flow however a slow (time constant 1 h) online feedback control from effluent phosphate with a
maximum dosage of 17 mg Fe/L was used from week 42. The weekly average of the dose to BR4
varied in the range 0-11.5 mg Fe/L. A third and final polishing dose using Fe3+ was added in BR6
(just prior to the membrane tanks) during the last months of the year. This dose was added during
shorter peaks in effluent phosphate with a maximum dosage of 7 mg Fe/L (weekly average dosage
was 1.6 mg Fe/L during the period when it was used).
As this year included separate trials for enhanced biological phosphorus removal, the yearly
average cannot be used to compare to the SFA design. However, the total iron dosage for week 42
to 52 was 20 mg Fe/L which is the same as assumed in the SFA design and then an effluent
concentration of 0.15 mg P/L was reached. Iron dosage and effluent phosphate concentration is
presented as daily average values in Figure 26.
49
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
45 4.5
40 4.0
35 3.5
30 3.0
mg PO4-P/L
mg Fe/L
25 2.5
20 2.0
15 1.5
10 1.0
5 0.5
0 0.0
2018-01
2018-04
2018-07
2018-10
2018-13
2018-16
2018-19
2018-22
2018-25
2018-28
2018-31
2018-34
2018-37
2018-40
2018-43
2018-46
2018-49
2018-52
Fe3+ to BR6 Fe2+ to BR4 Fe2+ to pre aeration Effluent phosphate
Figure 26. Iron dosage (the sum of three dosing points) as daily average and effluent phosphate analysed
in daily composite samples.
Normal fluctuations of iron content in sludge was between 6.5 and 10% of TSS during normal iron
dosage to reach effluent phosphorus concentrations below 0.2 mg P/L (Figure 27). When iron
dosage was stopped, the iron content slowly decreased, reaching a minimum of 1.1% after 12
weeks without iron dosage. The phosphorus content in sludge (biologically and chemically bound)
varied between 2 and 3.7% in the period before iron dosage was stopped with an average of 3.0%.
During the period without iron dosage, phosphorus content in sludge was slightly higher, on
average 3.5%, and peaking at 4.3% of TSS. After starting the iron dosage again, phosphorus content
in sludge increased further, on average 3.7% of TSS.
Although the phosphorus concentration in the activated sludge increased when the iron dose was
stopped, the effluent phosphorus concentration increased directly when the dose was cut. The iron
buffer in the sludge when the Fe-dose was cut was 7-8% of TSS. The higher phosphorus
concentration in sludge without iron dosing can be explain by a higher TP concentration into the
biological treatment due to decreased pre-precipitation. These results can be compared with the
results from 2016 when the iron dose was cut for two weeks during the autumn and it took one
week before the effluent concentration of phosphorus increased. The initial concentration of iron in
sludge at that time was also around 8% of TSS and the phosphorus concentration in sludge was 3%
of TSS which was a slight decrease from the values before the dose was cut (3.2-3.4%).
50
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
12 3000
10 2500
8 2000
% of TSS
g Fe/d
6 1500
4 1000
2 500
0 0
0 10 20 week 30 40 50
Results from the P-release tests together with data on TP and Fe are shown in Figure 28 and Figure
29. In April the sludge from the pilot showed a higher P-release rate than the Henriksdal sludge
even though the Fe-dose was higher in the pilot than in Henriksdal (10-12 g Fe/m3 in Henriksdal).
In July to October when the Fe-dose was shut off completely in the pilot, P-release rates increased
to above 7 g P/kg VSS, h (with exception for august) which indicates a high EBPR-activity (Janssen
et al. 2002). Also, after the startup of the Fe-dosing the P-release rate remained significantly higher
than in the Henriksdal sludge. The results show a moderate correlation between the iron content in
WAS and the EBPR activity (Figure 30). However, more data is required to determine if there is a
true correlation or not. These results show that EBPR arose spontaneously in the process despite
the absence of a designated anaerobic zone and the relatively high dosage of Fe.
In order to determine where in the process the P-release and –uptake takes place, TP and PO4-P
was measured along the treatment line on three occasions; in February, June and August. Results
from February and August did not display results that indicated clear P-release or –uptake zones.
The results from June (see Figure 31), however, showed a small release in the second pre-
denitrification zone, BR2, where the nitrate levels generally are low (normally <1 mg N/L) and VFA
may be produced by endogenous hydrolysis, and an uptake in the two fist aerated zones, BR3 and
BR4. A second large release was seen in the post-denitrification zone, BR6, where the nitrate level
at the time was 2 mg N/L and methanol was dosed. In the following aerated membrane tanks, MT1
and MT2, phosphorus was taken up again, resulting in an effluent concentration of 0.06 mg PO4-
P/L.
51
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
Since there is only one profiling showing these results, more studies are needed in order to be able
to draw any conclusions. Therefore, more detailed studies of the EBPR and the concurrence with
chemical phosphorus removal are planned for the coming years.
6
5 15
˚C; g Fe/m3
4
10
3
2
5
1
0 0
feb mar apr jun jul aug sep oct nov dec
Figure 28. EBPR activity in the activated sludge from the MBR-pilot and Henriksdal WWTP (CAS). Dotted
lines show limits for EBPR-activity according to Janssen et al. 2002, values below the yellow line indicate
poor EBPR and values above the purple line indicate high EBPR.
10 2.5
% of SS; mg TPin/l
8 2.0
mg TPeffl/l
6 1.5
4 1.0
2 0.5
0 0.0
feb mar apr jun jul aug sep oct nov dec
Figure 29. The content of phosphorus and iron in waste activated sludge (WAS) compared to P-release rate
and TP in and out of the biology.
52
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
0
0 2 4 6 8 10 12
Fe % of TS
Figure 30. The relationship between iron in waste activated sludge (WAS) and P-release rate in the MBR-
pilot.
20
release release
15
g PO4-P/h
uptake
10
uptake
5
0
In PA PTW BR1 BR2 BR3 BR4 BR5 BR6 MT Out RAS
Figure 31. Phosphate profiling along the MBR-line. The three first steps are the pre-treatment (no EBPR).
Purple bars are aerated volumes. The arrows indicate possible EBPR induced P-release and P-uptake.
53
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
0.08
0.06
0.04
0.02
0
2018-11-21
2018-11-22
2018-11-23
2018-11-24
2018-11-25
2018-11-26
2018-11-27
2018-11-28
2018-11-29
2018-11-30
2018-12-01
2018-12-02
2018-12-03
2018-12-04
2018-12-05
2018-12-06
2018-12-07
2018-12-08
2018-12-09
2018-12-10
2018-12-11
2018-12-12
2018-12-13
Endress+Hauser Metrohm Lab
Figure 32. Daily average values from the two phosphate analysers compared to lab values of daily samples.
Trial Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Optimisation of scouring air use
The membranes have been operated in cycles with 10 minutes of permeation followed by 1 minute
of relaxation. Both feed (pumping from BR6) and aeration was on during the normal operation
cycle. In order to manage the varying flowrate with only two membrane tanks, the pumping of
permeate was proportional to the feed, which in turn was proportional to the level in BR6.
54
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
As it is inefficient to operate the membranes at too low fluxes, the membrane tank longest in
operation went into standby mode at low influent flowrates (normally during night). In standby
mode the membranes were aerated intermittently 5 minutes every half hour.
The membranes had slightly too large surface area compared to the scale of the rest of the
treatment line. In order to maintain representative flux over the membranes a fraction of the
permeate was recycled back to the membrane tank. At normal flowrates one third of the permeate
was recycled. In order to also manage peaks in the flowrate, the permeate recirculation was
reduced with increased influent flow rate. The varying permeate recirculation affected the sludge
concentration in the membrane tanks and thus also the sludge concentration in return and waste
sludge. On average the permeate recirculation was about 17 % of withdrawn permeate during
2018.
6.5.1 Permeability
Permeability above 200 L/(m2·h·bar) is considered good according to the supplier. As can be seen in
Figure 33, the permeability was above 300 L/(m2·h·bar) throughout most of the year for both
membranes. During the beginning of the year (week 1 to 19) permeability was slightly higher for
MT1 (using oxalic acid for cleaning) and relatively stable permeability for both membranes. After
recovery cleanings performed in week 20 and 21 (see details regarding recovery cleaning in section
6.5.3.) the permeability increased. A decrease from week 22 can be seen and was considered related
to a peak flow test where influent was fixed at 5.5 m3/h for one week. For MT1 permeability
continued to increase during summer with higher temperature, while permeability for MT2
continued to decrease. Week 26 it was decided to switch acids for the two membranes, so MT2 was
cleaned with oxalic acid and MT1 was cleaned with citric acid. After four weeks with cleaning
using oxalic acid, the permeability for MT2 was increased to values close to MT1 and the acids was
switched back.
The increases in permeability that can be seen for MT1 in week 43 and week 51 are not related to
recovery cleaning, but the effect of maintenance cleaning with oxalic acid.
Permeability
RC
700
600
500
L/(m2·h·bar)
400
300 MT1
200 MT2
100
0
1 4 7 10 13 16 19 22 25 28 31 34 37 40 43 46 49 52
Week
Figure 33. Permeability (temperature compensated) for membrane 1 (MT1) and 2 (MT2) during project year
5 (2018). Recovery cleaning (RC) was carried out in week 20 and 21.
55
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
Flux
35
30
25
L/(m2·h)
20
15 MT1
10
MT2
5
0
1 4 7 10 13 16 19 22 25 28 31 34 37 40 43 46 49 52
Week
Throughout the period with low flux (below 20 L/(m2·h)) the transmembrane pressure (TMP) was
at its lowest, see Figure 35. Based on daily average data, TMP varied between 20 and 88 mbar
during 2018. The TMP decreased only slightly (from about 60-65 mbar to 45 mbar) after recovery
cleaning. This is likely due to the low initial TMP. Before the last recovery cleaning (RC) in 2017
TMP was 186 and 140 mbar for MT1 and MT2 respectively. TMP increased from mid-summer
towards the end of the year. The last weeks of 2018, TMP decreased again, for MT1 this was the
result of one oxalic acid maintenance cleaning (MC).
80
60
mbar
40 MT1
20 MT2
0
1 4 7 10 13 16 19 22 25 28 31 34 37 40 43 46 49 52
Week
56
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
Maintenance cleaning
The maintenance cleanings (MC) were automatically carried out every week. In order to keep the
treatment line in operation, each membrane was cleaned separately, and the cleanings were
scheduled at night when the influent flow rate was low. In order to assure that the influent flow
rate was not too high for the one membrane tank in operation, the influent flow set-point was set to
half of the current value, although never lower than 1.8 m3/h.
The MC takes about one hour and according to the cleaning schedule provided by the supplier
these cleanings should be carried out with acid about once per week (after 345 m3 of permeate were
produced by that membrane) and with sodium hypochlorite about twice per week (after 173 m3 of
permeate was produced). The cleaning chemical was mixed with permeate and back pumped in
pulses through the membranes. Normally there were nine back pulses (BPs), the first one a bit
longer (2-5 minutes) followed by eight shorter with relaxation in-between (30 seconds followed by
4.5 minutes of relaxation). The chemical solution was pumped with a back flux of 20 L/(m2·h) and
the target concentrations of the solution entering the membranes (after dilution with permeate)
were 200 mg Cl2/L for sodium hypochlorite, 2000 mg/L for citric acid and 1300 mg/L for oxalic acid.
Last year attempts of reducing the chemicals used for maintenance cleaning started. The time of
the initial backpulse was reduced from 5 minutes to 2 minutes and later the number of backpulses
were reduced from 9 (incl. the first longer one) to 7 in total.
During this year further work on primarily reducing the oxalic acid usage by altering the cleaning
intervals in between cleaning events. The operational settings have been divided into five trial
periods. An overview of the trials is presented in Table 20.
Table 20. Overview of trials with reduced acid for membrane cleaning. BP=backpulses.
Trial Start Trial
T1 Sept 2017 Citric vs Oxalic - Reduced BP (both MT)
T2 June 2018 Recovery Period (short switch between chemicals)
T3 July 2018 Trial reduced nr of BP oxalic acid, standard citric acid
T4 Aug 2018 Trial reduced nr of BP and 20% longer time in-between oxalic acid cleanings.
T5 Oct 2018 No oxalic acid cleanings
T5 Dec 2018 One oxalic acid cleaning
T5 Dec 2018 No oxalic acid cleanings
The amount of chemicals used normalized to the initial settings 2 (back pulse duration 2 minutes + 8
x 30 seconds carried out after 345 m3 permeate produced) are presented in Figure 36 together with
the permeability.
Trial 1 (T1) started in September 2017 when the number of backpulses were reduced from 9 (in
total) to 7. As M1 (cleaned with oxalic acid) had higher permeability than M2, the acids were
2 Inital settings previous year (2017) was calculated as 5 min initial backpulse, followed by 8 x 30 s backpulses.
57
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
switched (Trial 2, T2) so M1 was cleaned with citric acid and M2 was cleaned with oxalic acid for a
short period (19 days).
Permeability
T1 T2 T3 T4 T5
700 350
600 300
500 250
L/(m2·h·bar)
400 200
%
300 150
200 100
100 50
0 0
1 5 9 13 17 21 25 29 33 37 41 45 49 1
Week, 2018
Figure 36. Amount of acid used for maintenance cleaning (MC), normalized to back pulse duration of 5
minutes + 8 x 30 seconds carried out with interval of 345 m3 of permeate produced. M1 was cleaned with
oxalic acid, M2 was cleaned with citric acid. T1 – T5 are trial periods. T1 started in September 2017.
When permeability was similar for the two membrane tanks, trial 3 (T3) started in July (week 29).
M1 was again cleaned with oxalic acid with 7 backpulses (oxalic acid consumption corresponding
to 83 % of suppliers’ specification) and M2 where cleaned with citric acid and 9 backpulses (100%).
Trial 4 started in August, where the interval in-between acid cleanings were 20% longer for M1
(corresponding to 69% of specified consumption). As permeability for both membrane tanks were
similar during T4, it was decided to completely stop doing the acid cleanings for M1 (Trial 5) and
await a permeability decrease. M1 was operated for 53 days without acid cleaning, permeability
decreased from 544 to 289 L/(m2·h·bar). One maintenance cleaning with oxalic acid (7 backpulses)
restored permeability to 507 L/(m2·h·bar). M1 continued to operate without any oxalic acid into
2019.
Throughout 2018 maintenance cleaning with sodium hypochlorite has been carried out with
interval according to supplier, but with reduced backpulses; 2 min initial pumping followed by 6 x
30 seconds.
Recovery cleaning
During recovery cleaning (RC) the membrane tank was emptied, then filled with chemical solution
and the membranes where left to soak overnight.
According to the supplier the RC should be carried out twice every year with both sodium
hypochlorite and acid. Previously permeability has been good, and RC has only been needed once
per year. The previous RCs were carried out in Oct/Nov 2017 but this year it was decided not to
wait a full year but do the RCs in May although permeability was good (around 400 L/(m2·h·bar)).
58
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
The reason was to get more information from sampling during RC and to send some membrane
treads for membrane autopsy to characterize the fouling.
Since the previous RCs about 10 700 m3 permeate was produced by MT1 and 10 050 m3 permeate
by MT2. This corresponds to about 104 and 97 m3 per m2 membrane area for MT1 and MT2,
respectively.
Before and after the RC this time the membrane cassettes were lifted, the membranes were
inspected, and some threads were cut and sent for membrane autopsy. A technician from the
supplier was attending when the first cassette was lifted to give instructions for the inspection and
on how to cut the membrane treads and reseal the cut with special glue.
The cleanings were carried out first with sodium hypochlorite and then with acids (oxalic acid for
MT1 and citric acid for MT2) one week later.
The schedule for cleanings can be seen in Table 21 together with the amount of chemicals used and
conditions at start and end of the soaking. With oxalic acid the pH was lower (pH 2.16) compared
to using citric acid (pH 2.52). About five times larger volume of concentrated acid was needed for
the oxalic compared to citric, which for storage reasons is something the full scale plant will need
to consider.
When comparing the effect on permeability there was no great difference between oxalic and citric
acid (Figure 37). One week after the citric acid cleanings the permeability was almost the same for
the two membrane tanks, and about the same as prior to starting the sodium hypochlorite RC,
around 400 L/(m2·h·bar). One reason for no visible long term improvement of the permeability was
likely the high permeability prior to the RCs and that there were not much fouling or scaling to be
removed.
59
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
400
300
200
100
0
2018-05-07 2018-05-14 2018-05-21 2018-05-28
Analysis of the first permeate after RC is presented in Table 22. When comparing the two acids the
permeate after cleaning with citric acid contained higher concentrations of all analysed parameters.
Compared to previous RCs in 2017 the phosphate concentration after citric acid cleaning was much
lower; 2.2 mg/L 2018 compared to 12 mg/L 2017. One reason for this could be a longer sludge
recirculation time through the membrane tank prior to starting the permeation.
Table 22. Analysis of first permeate after recovery cleaning (RC) 2018 (2017 values in parenthesis). n.a., not
analysed.
Permeate analysis Chloride COD-Cr PO4-P Fe Mn
after RC (mg/L) (mg/L) (mg/L) (mg/L) (mg/L)
RC NaOCl MT1 160 (450) 67 (130) 0.21 (0.39) 0.21 (0.34) 0.014 (0.032)
RC NaOCl MT2 140 (460) 62 (120) 0 21 (0.38) 0.14 (0.29) 0.021 (0.025)
RC Oxalic acid MT1 n.a. 36 (69) 1.3 (0.46) 14 (12) 0.12 (0.31)
RC Citric acid MT2 n.a. 320 (470) 2.2 (12) 32 (55) 0.14 (0.74)
As observed before, the phosphate peak after oxalic acid cleaning was lower than after cleaning
with citric acid (Figure 38).
60
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
1.2
0.8
mg PO4-P/L
0.6
0.4
0.2
0
2018-05-21 2018-05-22 2018-05-23 2018-05-24
Figure 38. Phosphate concentration in effluent measured by automatic online analyser after RC with oxalic
acid (22nd of May) and after RC with citric acid (23rd of May).
The inspection of the cassettes showed that the stainless-steel frame was in good condition. There
was no corrosion, no cracks, no bending or any other damage to the frame could be identified.
Also, the plastic parts were tight and in good condition with no cracks, bending or any other
damage. The membranes were not sludged up and not stuck together, and there was no black
colouring (which could indicate anaerobic conditions). No broken fibers were seen. The colour of
the fibers were light grey-brown with a slight bio-fouling on the surface. A small amount of sludge
and fibric material was stuck in the top and bottom header (Figure 39). The membranes were
flexible and with a good slack. Generally, the membrane cassettes were in really good condition
after two years of operation.
61
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
Microscopic images of the membrane fibers showed decreased fouling on the membranes as the
recovery cleaning process progressed. The foulant before recovery cleaning contained mainly iron,
some organic material and trace amounts of calcium phosphate. The foulants on the samples after
cleaning contained trace amounts of iron and organic material, see Figure 40 and Figure 41.
Figure 41. Microscopic image of membrane fouling after recovery cleaning (with both sodium hypochlorite
and acid).
62
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
Fourier Transform Infrared Spectroscopy (FT-IR) of the membrane fibers before cleaning resulted
in several peaks related to the membrane material (PVDF), proteins and phosphate containing
compounds, whereas membrane fibers after cleaning only resulted in peaks related to PVDF, i.e.
most fouling had been removed.
Figure 42. FT-IR of membrane fibre before cleaning (left) and after cleaning (right). The peaks displayed
around 1400, 1200-1100 and 850 cm-1 are all related to the fibre material (PVDF) and can be seen in both
figures. In the left figure there can also be seen peaks around 1650 cm-1 which are associated with presence
of proteins and a broad peak around 1000 cm-1 which is associated with presence of phosphate containing
compounds. These peaks cannot be seen in the right figure.
As two activated sludge lines will be taken out of operation once the first MBR line is
commissioned, a high flow to the first MBR line will be required. The pilot operation involved a
high fixed inflow, reject water connected to inlet and ferrous sulfate to the inlet pipe prior to the
pre-aeration tank and BR4 as chemical addition. No ferric chloride and no external carbon source
were used.
The chemical dosages in BR6 was stopped on March 6th and reject from Sickla was added starting
on the 7th of March.
The test period was started on March 23th (Friday week 12) when the inflow was increased to a
constant flow of approximately 4.8 m3/h (Figure 43) which corresponds to 150% of design flow. The
test period ended on June 11th (Monday week 24). A separate high flow test (Qin=5.5 m3/h) was also
conducted during one week towards the end of the test period after RC was performed on both
membranes.
63
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
Evaluation period
6
4
m3/h
1
Inflow reduced during RC
0
2018-03-19 2018-04-02 2018-04-16 2018-04-30 2018-05-14 2018-05-28 2018-06-11
Figure 43. Influent flowrate during BB1 operation test. After seven weeks RC was carried out, first with
sodium hypochlorite, a week later with acids. After RC the maximum flow was tested for one week.
6
Feed/Permeate was adjusted
4
QRAS/QIN
0
2018-03-19 2018-04-02 2018-04-16 2018-04-30 2018-05-14 2018-05-28 2018-06-11
Figure 44. Return sludge flowrate related to influent. Recommended operating range is between 3-4 xQIN
(shadowed).
64
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
14000
Feed/Permeate was adjusted
12000
10000
mg SS/L
8000
6000
4000
Faulty sensor reading in BR4 due to problems
2000
with sludge foaming and overflow
0
2018-03-19 2018-04-02 2018-04-16 2018-04-30 2018-05-14 2018-05-28 2018-06-11
Figure 45. Online measurements of sludge concentration in the bioreactors (BR4) and in the return sludge
(RAS-DeOx).
Evaluation period
25
23
L/(m2·h)
21
19
17
15
MT1
MT2
MT1
MT2
MT1
MT2
MT1
MT2
MT1
MT2
MT1
MT2
MT1
MT2
MT1
MT2
MT1
MT2
MT1
MT2
MT1
MT2
MT1
MT2
MT1
MT2
w. 12 w. 13 w. 14 w. 15 w. 16 w. 17 w. 18 w. 19 w. 20 w. 21 w. 22 w. 23 w. 24
Figure 46. Net flux. The first two weeks of BB1 operation there was no permeate recirculation. With
permeate recirculation flux increased.
The permeability was even throughout the trial (Figure 47). No immediate effect of the higher
MLSS concentrations in the membrane tank during week 13-14 was observed. The permeability
decreased from 448 and 401 L/(m2·h·bar) the week before the trial started to 405 and 384
L/(m2·h·bar) prior to RC was conducted (RC with sodium hypochlorite week 20 and RC with acid
week 21) for MT1 and MT2 respectively. Only a small increase in permeability was observed after
RC, possibly due to a) the high permeability prior to RC and b) the week after RC (Thursday w.21
to Thursday w.22) the line was operated at peak flow (5.5 m3/h).
65
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
500
400
L/(m2·h·bar)
300
200
100
0
MT1
MT2
MT1
MT2
MT1
MT2
MT1
MT2
MT1
MT2
MT1
MT2
MT1
MT2
MT1
MT2
MT1
MT2
MT1
MT2
MT1
MT2
MT1
MT2
MT1
MT2
w. 12 w. 13 w. 14 w. 15 w. 16 w. 17 w. 18 w. 19 w. 20 w. 21 w. 22 w. 23 w. 24
Figure 47. Permeability. RC with sodium hypochlorite was carried out in week 20, RC with acid week 21.
The conclusions regarding membrane performance, during the BB1 operation test, was that a high
permeability was maintained at flux up to 25 L/(m2·h) with normal MLSS concentrations (8 000
mg/L in bioreactors and 10 000 in MT). No decreased permeability was seen when operating at
higher MLSS concentration (12 000 mg/L in MT, QRAS/QIN=2) when flux was between 22 and 24
L/(m2·h).
0.1
0.08
0.06
0.04
0.02
0
18-01 18-03 18-05 18-07 18-09 18-11 18-13 18-15 18-17 18-19 18-21 18-23 18-25 18-27 18-29
Figure 48. Food to mass. Only bioreactors 1-6 was used as biological volume when calculating the F/M
ratio. Week 18-19 data is missing.
Effluent nitrogen concentrations are presented in Figure 49. The nitrate and total nitrogen
concentrations decreased during the trial (as temperature increased). The total nitrogen
concentration was maintained below 7 mg N/L reaching as low as 3 mg N/L during the warmer
summer period although no external carbon source was used. Effluent ammonium concentration
peaked in week 21 at 1.7 mg NH4-N/L but was on average 0.7 mg NH4/L during the high flow
period (w.10 to w.23). The return sludge flow rate increased from 2xQIN to 4xQIN in week 15,
66
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
resulting in returning more nitrate to the pre denitrification zone, however it is not clear what
effect this had in the nitrate removal.
4
mg N/L
0
2018-01
2018-02
2018-03
2018-04
2018-05
2018-06
2018-07
2018-08
2018-09
2018-10
2018-11
2018-12
2018-13
2018-14
2018-15
2018-16
2018-17
2018-18
2018-19
2018-20
2018-21
2018-22
2018-23
2018-24
2018-25
2018-26
2018-27
2018-28
2018-29
2018-30
NH4-N (mg/L) NO3-N+NO2-N (mg/L) Org-N, beräknat (mg/L) T-N (mg/L)
Figure 49. Effluent nitrogen. Carbon source was not added from the mid of week 10. Not restarted until
week 36. Flow was high between week 13 and 24. Green box – no carbon source. Blue box – no carbon
source and high load.
The effluent phosphorus concentration was kept low (below 0.2 mg P/L) during most of the BB1-
trial (marked with blue box in Figure 50) although only ferrous sulfate was used as precipitation
chemical.
10
9
8
7
6
mg P/L
5
4
3
2
1
0
2018-01
2018-03
2018-05
2018-07
2018-09
2018-11
2018-13
2018-15
2018-17
2018-19
2018-21
2018-23
2018-25
2018-27
2018-29
2018-31
2018-33
2018-35
2018-37
2018-39
2018-41
2018-43
2018-45
2018-47
2018-49
2018-51
TP to bio TP effluent
Figure 50. Total phosphours. Blue box – only ferrous sulfate. Green box – no precipitation chemical.
One weekly composite sample (w.21) showed a higher effluent concentration (0.47 mg P/L) (Figure
51).
67
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
0.5
0.45
0.4
0.35
0.3
mg P/L
0.25
0.2
0.15
0.1
0.05
0
TP effluent
Figure 51. Total phosphorus in effluent during the imitation of BB1 operation.
The trial indicates that the process can manage TP below 0.2 mg/L and TN below 10 mg N/L in the
effluent at the higher load expected for the first treatment line without use of ferric and external
carbon.
The primary settlers in the Henriksdal WWTP are much more efficient than the one in the pilot.
Therefore, the production of primary sludge in the pilot corresponds to about half of the total
sludge production whereas it makes up 66-75% of the total sludge production in the full-scale
plant. The total sludge production in the pilot is significantly higher than the design data. This is
due to higher incoming load compared to design (see section 3.3). The WAS-production in the pilot
is almost twice as high as designed, which corresponds to the high BOD-load on the biology (due
to high incoming load and poor reduction over primary settlers). The high WAS-production causes
a short SRT (see section 3.3).
The difference in sludge production and composition between the pilot and full-scale plant will
affect results from thickening, digestion and dewatering of mixed sludge.
Similar to the results from 2016 and 2017, the SVI-value in the pilot was higher than in the full-scale
plant with conventional activated sludge (CAS) process. This is expected since the membranes
retain all sludge, also the floating and foaming sludge, in the process. In a CAS-process, sludge that
does not settle will be washed out from the secondary clarifiers and a natural selection of sludge
with good settling properties is achieved (at least in theory).
68
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
Table 23. Sludge data from the pilot year 2018 compared to design data for the pilot, data from the
Henriksdal WWTP 2018 and design data for the future Henriksdal WWTP (SFA-design).
Parameter Pilot data Pilot design Henriksdal WWTP SFA-design
2018 data* data 2018 2040
WAS production (kg SS/d) 14.1 8.8 23 800 59 000
Part of total sludge production (%) 47 34 23 34
VSS in WAS (% of SS) 73 63 68 63
Fe in WAS (% of SS) 6.3 - 11 -
PS-production (kg TS/d) 16.1 17.2 80 300 117 000
Part of total sludge production (%) 53 66 77 66
VS in PS (% of TS) 88 80 78 80
Total sludge production (kg TS/d) 30.2 26.3 104 100 176 000
Total sludge age, SRTtot (d) 24 28 11 28
Aerated sludge age, SRTox (d)** 7.5*** 7 5 7
SVI jan-jun (mL/g) 211 - 170 -
SVI jul-dec (mL/g) 138 - 141 -
*pilot design data is the scaled down SFA-design data (1:6700)
**yearly average, the aerated volume is adjusted based on water temperature using the flex-zones.
***including membrane tanks, without membrane tanks SRTox = 6.0 d
The function and efficiency of the membrane filtration depends on several parameters, amongst
them the sludge properties. Therefore, weekly analyses of time to filter (TTF) and colloidal TOC in
filtered sample (cTOC) was done, as suggested by the membrane supplier. Data on sludge
properties, membrane performance (transmembrane pressure, TMP) and temperature is shown in
Figure 52.
Like previous years, no strong correlations between any of the sludge properties and the
membrane performance (presented as TMP) was found. However, a moderate correlation (R2=0.61)
between TTF (normalised based on TSS) and TMP was found. This indicates that TTF could be a
good parameter to monitor in relation to membrane operation. In addition, weak correlations
between TMP and TSS (mg/L), VSS (% of TSS) and Fe (% of TSS) respectively was found. TTF and
the Fe content in WAS gave a moderate correlation (R2=0.53) showing that addition of ferrous
increases the filterability of the sludge, thus indicating that addition of ferrous is beneficial for
membrane operation.
No correlation at all was seen between TMP and SVI or TMP and cTOC. Similarly, no correlation
between SVI and TTF was seen while a weak correlation (R2=0.38) was found between the SVI and
cTOC values. Thus, analysis of SVI cannot replace analysis of TTF.
69
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
250
20
200
mg/l; % of SS; ˚C
s; ml/g; mbar
15
150
10
100
5
50
0 0
w1
w3
w5
w7
w9
w11
w13
w15
w17
w19
w21
w23
w25
w27
w29
w31
w33
w35
w37
w39
w41
w43
w45
w47
w49
w51
Temp. (C) TMP MT (mbar) TTF 100 (s)
SVI (mL/g) cTOC (mg/l) Fe (% of TSS)
In Table 24 the TSS concentration in waste activated sludge (WAS) as well as the content of iron,
phosphorus and VSS is listed for the four years the pilot plant has been in operation. The design
value for TSS in WAS is 10 000 mg/L. The values are quite similar from year to year, a part from the
iron concentration in the sludge which decreased over the first three years due to lower Fe dose
achieved by process optimization and development of precipitation strategies. The increase in 2017
is due to a lower production goal for phosphorus in the effluent, 0.15 mg TP/l compared to 0.20 mg
TP/l previous years, and the decrease during 2018 is due to EBPR activity (see 6.3.2).
Table 24. WAS composition (annual average) in the pilot over the 5 years of operation.
Year TSS Fe in sludge P in sludge VSS Fe/P in sludge
(mg/L) (% of TSS) (% of TSS) (% of SS) (mole/mole)
2018 8480 6.4 3.3 77 1.1
n 50 50 50 50 50
2017 9632 10.3 3.0 71 1.9
n 50 47 47 47 47
2016 8126 8.3 3.4 74 1.3
n 31 31 31 31 31
2015 9910 10.1 3.3 71 1.7
n 44 44 42 44 42
2014 9263 11.9 3.1 69 2.3
n 38 38 27 38 27
70
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
Trial Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Mesophilic operation
Thickening tests
The sludge pilot, comprising thickening of mixed sludge (PS and WAS), digestion and dewatering
of digested sludge, was taken into operation in September 2017. The year 2018 was characterized
by problem solving and optimization. During week 25-33 the sludge pilot operation and analysis
was reduced due to summer holiday period.
In January the heating system was tested to ensure that thermophilic conditions could be reached,
but the temperature stopped at 50˚C. After several improvements, including insulation and
installation of a new heat element, 55˚C could be reached in July. The thickener suffered from
various recurrent problems resulting in discontinuous operation of the digester. The problems
included clogging of the mesh in the thickener drum, problems with the output of thickened
sludge into the collecting trough, malfunctioning level transmission in the trough, inaccurate
online TS-measurements causing random polymer dosing, air in the flush water (effecting the
polymer concentration and the cleaning of the drum) etc. The trough was reconstructed in July
which improved the function slightly. During the spring the function of the thickener was
optimized and in the autumn tests of thickening of WAS from the pilot (MBR) and Henriksdal
(CAS) were done as part of an MSc-project.
Thickener
The thickener was operated discontinuously, as can be seen in Figure 53, over the year due to
several technical problems described in the section above. Figure 54 shows the weekly average
values for the flow and TS in and out of the thickener. The thickener was designed for a mixed
sludge average inflow of 70 L/h and a TS-concentration of 6.7% in the thickened sludge. Due to
repeated stops of the thickener, the weekly average inflow was <60 L/h 28 weeks out of the 41
when it was in operation. The TS of the thickened sludge varied a lot over the year. Out of 65 grab
samples analysed, 11 had a TS-concentration >6.0%.
71
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
120
100
80
L/h
60
40
20
0
01-jan 01-feb 01-mar 01-apr 01-maj 01-jun 01-jul 01-aug 01-sep 01-okt 01-nov 01-dec
60 6
TS (%)
50
40 4
30
20 2
10
0 0
w02 w05 w08 w11 w14 w17 w20 w23 w26 w29 w32 w35 w38 w41 w44 w47 w50
Figure 54. Flow and TS-concentration into and out of the thickener. Weekly averages.
The quality of the reject water from the thickener was monitored over time. Results are shown in
Table 21. Data was used for optimisation of polymer dose and operation as well as to control the
internal load on the biological process derived from recirculation flows.
Table 26. The quality of the reject water from the thickening unit.
An MSc-project study was conducted in the autumn with focus on the quality difference between
MBR and CAS sludge and the corresponding effect on the thickening process. The settling
properties (SVI) and filterability (TTF) of the MBR and CAS sludge respectively was analysed and
72
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
thickening trials were performed where the TS in thickened sludge and the SS in the reject water
were the main indicators. The study showed that the MBR sludge displayed slightly lower SVI-
values but poorer filterability compared to the CAS sludge. The poor filterability could be caused
by the higher TS-concentration (1% compared to 0.7%) or the presence of more fine particles in the
sludge. Thickening of MBR sludge resulted in higher TS in the thickened sludge compared to CAS
sludge. In addition, it also resulted in higher SS in the reject water, which was expected since the
MBR sludge theoretically should contain more fine particles than CAS sludge. The methods,
results and conclusions are described in more detail in the thesis report (Jirblom, 2019).
Experiment N2 and N6 both had the highest TS in thickened sludge and low SS in the reject water.
These two experiments both combined the highest polymer dosage (16 g/kg TS) and the lowest
rotational frequency of the drum (25 Hz) but different angle of the drum. The varying angle of the
drum had minor effect (compare the upper and lower graphs in Figure 55). Looking at the SS in the
reject water, the dominating factor was the polymer dosage, where a high dosage resulted in lower
SS in the reject and vice versa. For the thickened sludge a combination of high polymer and low
frequency gave increased TS. If only comparing the different slopes of the drum a lower slope
more often resulted in higher TS than a higher slope when the other settings were the same.
Table 27. Settings and results from the 11 experiments on thickener optimization. Red=bad, blue=good
results.
Exp Run TS in Qin Polymer dose Frequency Angle TS thickened SS in reject
Name Order (%) (L/h) (g/kg TS) drum (Hz) drum sludge (%) (mg/L)
N4 1 1.46 100 16 40 Low 4.71 343
N10 2 1.47 100 11 32.5 Low 4.84 1195
N7 3 1.33 100 6 40 High 3.99 4022
N8 4 1.45 100 16 40 High 3.79 337
N9 5 1.47 100 11 32.5 Low 5.10 1429
N5 6 1.45 100 6 25 High 4.61 3383
N2 7 1.39 100 16 25 Low 5.32 394
N3 8 1.42 100 6 40 Low 4.62 4127
N6 9 1.42 100 16 25 High 5.32 481
N1 10 1.42 100 6 25 Low 4.34 3480
N11 11 1.42 100 11 32.5 Low 4.99 1567
73
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
4.2
2000
2500
4.6
4.8
5
5.2
4.8
4.9 5 2500
3000
4.6 5.1
5.2
5.3
Figure 55. Response contour plots from the MODDE software showing TS in thickened sludge as % (left)
and SS in reject water (right) in relation to Frequency (Hz) on the y-axis and polymer dosage on the x-axis.
The two upper plots are for the tests with a higher slope of the drum and the two lower plots are for the
low slope of the drum.
Digestion
The 5.9 m3 digester was operated under mesophilic conditions the whole year, with exception of a
few shorter time periods when the thermophilic heating system was tested. The unintentional
intermittent operation of the thickener led to uneven loading of the digester, 4-23 kg VS/d, and
varying retention times, 9-40 d (weekly average values). The target values were 20 kg VS/d and a
retention time of 13 days. Results from the mesophilic digestion are shown in Figure 56 and
previously presented in section 3.3, Table 3.
74
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
Biogas (m3/d) OLR (kg VS/d) HRT (d) Digestion eff. (%) Methane (%)
Figure 56. Data from mesophilic digestion of thickened mixed sludge. Weekly averages.
Key performance indicators for the anaerobic digestion process is shown in Table 23. They are all
in line with common design figures (Metcalf & Eddy, 2014).
Using the specific biogas production key figure 1 Nm3/kg VSdestroyed (Metcalf & Eddy, 2014) the
theoretical biogas production was calculated based on weekly average data on VS (kg/d) in and out
of the digester. This was done primarily to control the gas meter function. As can be seen in Figure
57, the theoretical values correspond well to the measured values.
15
m3/d
10
0
w02 w05 w08 w11 w14 w17 w20 w23 w26 w29 w32 w35 w38 w41 w44 w47 w50
Figure 57. The calculated theoretical and the actual measured biogas production.
75
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
Based on the available data from digester operation, there was no clear correlation between the
biogas or methane production and the OLR or HRT (Figure 58). This is most likely due to the
discontinuous operation of the digester.
9 9
8 8 y = -0.0758x + 6.5198
biogas production (m3/d)
Figure 58. Biogas production as a function of the specific organic loading rate (OLR) and HRT. Weekly
averages.
8000
1500
0 0
w3 w6 w9 w12 w15 w18 w21 w24 w27 w30 w33 w36 w39 w42 w45 w48 w51
7.4 0.25
VFA/Alk. (mg/mg)
7.2 0.20
7 0.15
pH
6.8 0.10
6.6 0.05
6.4 0.00
w3 w6 w9 w12 w15 w18 w21 w24 w27 w30 w33 w36 w39 w42 w45 w48 w51
pH VFA/Alk.
Figure 59. Data from the digester; a) shows VFA, NH4-N and alkalinity and b) shows pH and the
VFA/alkalinity ratio. Grab sample once per week.
76
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
The analyses of pH, alkalinity and NH4-N (Figure 59) gave stable results during the weeks with
relatively continuous feed (all except week 24-33). During the period with limited feeding (w 24-
33), alkalinity and ammonia increased while pH and VFA did not change significantly. VFA varied
more between the samples but in general the occasional high values coincided with high OLR-
values.
Dewatering
The dewatering unit was in operation with exception of some shorter periods during the beginning
of 2018 and summer holidays (week 24 to 35). The digested sludge was dewatered to TS
concentrations varying between 20% and 33% (Figure 60).
As weekly average the flow to the dewatering ranged from 6 to 17 L/h digested sludge. Different
polymer dosages were tested, from 8 to 20 g/kg TS.
35 40
30 35
30
25
25
g/kg TS, %
20
Polymer dosage (g/kg TS)
L/h
20
15
15 Flow to dewatering (L/h)
10 TS dewatered sludge (%)
10
5 5
0 0
2018-01
2018-05
2018-09
2018-13
2018-17
2018-21
2018-25
2018-29
2018-33
2018-37
2018-41
2018-45
2018-49
Figure 60. Flow of digested sludge to dewatering, polymer dosage and resulting TS concentration after
dewatering.
Varying quality of the reject water from the dewatering unit has been one issue throughout the
year. If suspended solids in the reject water from dewatering of sludge was below 2000 mg SS/L
the quality was considered acceptable and returned to the water treatment line. Obtained quality
concentrations in reject water when suspended solids were less than 2000 mg SS/L are presented in
Table 24.
Table 29. Reject water quality when dewatering unit operated with less than 2000 mg SS/L in reject water.
Min Max Median
SS (mg/L) 110 2000 580
VSS (mg/L) 65 1400 380
BOD7 (mg/L) 110 980 170
NH4-N (mg N/L) 88 690 400
PO4-P (mg P/L) 0.36 63 1.9
Total phosphorus (mg P/L) 5.4 160 20.7
Total nitrogen (mg N/L) 83 770 510
Iron (mg Fe/L) 17 150 51
77
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
Due to some interruptions in the operation of the dewatering only 8 monthly samples were
analysed during 2018 (Feb to May and Sept to Dec). The extended analysis was made on samples
from February, May and November.
A summary and comparison to Henriksdal values will be presented in the next yearly report.
External carbon source consumption 2018 (0.81 kg COD/d and 0.28 g COD/g N) was similar to 2016
when Brenntaplus was used (0.7 kg COD/d and 0.33 g COD/g N) and much lower than 2017 (2.14
kg COD/d and 0.84 g COD/g N) which was the year methanol dosage started. Effluent nitrate was
approximately the same as yearly average 2018 as previous years (3 mg NO3-N/L). The reduced
consumption of methanol from 2017 to 2018 is likely because external carbon dosage was not in use
for 26 weeks (from week 10 to week 36) as part of separate trials. On yearly average the methanol
consumption was 4.8 g COD/m3 (148 kg COD/year). If excluding week 10 to week 36 when the
methanol dosage was deliberately off, the dosage was on average 10 g COD/m3 corresponding to
about 297 kg COD/year, or 45% of SFA design. Other aspects contributing to reduced consumption
was less problems with the methanol pump, possibly improved performance once the bacteria had
time to adjust to methanol and a change of dosing point.
The iron consumption was calculated excluding the trial without iron dosage (week 27-41). The
values for 2018 (1.09 kg Fe/d and 1.67 mole Fe/mole P) was lower than 2017 (1.6 kg Fe/d and 2.1
mole Fe/mole P) and lower compared to the SFA-design. Effluent phosphate concentration was in
line with target concentration of 0.15 mg P/L.
The chemical consumption for membrane cleaning showed that sodium hypochlorite was 10%
higher than SFA design although the number of backpulses were reduced from 8 to 6 (corresponds
to 83 % of design consumption) and only one RC was performed instead of two. One explanation
to not having lower consumption is the high inflow (50% higher than design for almost 3 months
and then 10 % higher than design – in total 9,6% higher than 2017 when the sodium hypochlorite
consumption was 97% of the scaled SFA design) which means increased frequency of MC.
78
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
For the citric acid, as only one out of two membranes were cleaned with citric acid, the
consumption was 87% of the SFA design value (43% of design for two membrane tanks).
Compared to 2017 the citric acid consumption was reduced with 7%. Compared to cleaning
according to the membrane supplier recommendation3, the amount of citric used was 83% of
recommended.
The main efforts on reducing the amount of chemicals for MC have been focused on the oxalic acid
consumption. Compared to 2017 the consumption was reduced with 25%. As the oxalic was not
included in the SFA design consumption was only compared to the membrane supplier
recommendation3. The consumption 2018 was then 68% of recommended.
When comparing the impact of RC, two RC cleanings per year would mean that 25% of total acid
consumption and 45% of total sodium hypochlorite consumption would be used for RC. RC has a
larger impact on yearly sodium hypochlorite consumption than on the acid consumptions.
The air flow to the biological treatment line was 567% higher in the MBR-pilot than in the SFA
design. This is partly due to the water depth of the tanks which is 4.7 m compared to 12 m in full
scale. However, when calculating the theoretical air flow demand in the pilot based on the yearly
average BOD- and TN-load to the biology and the tank geometry the result was 1 027 Nm3/d (462%
of scaled SFA-design) which is lower than the measured 1 260 m3/h.
Also, the air flow to the membrane tanks were higher in the MBR-pilot than the scaled SFA-design
air flow. This is explained by the difference in number of membrane tanks in operation. In the full
scale plant, the number of tanks/trains in operation at average flow is 8 of 12 (67%) while in the
pilot it is 2 of 2 (100%).
3 Membrane supplier recommendation for cleaning: MC backpulsing 120 s + 8 x 30 s (every 173 m3 for hypo and every 345 m3 for
acid) and RC two times per year (2 with hypo and two with acid for each tank).
79
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
Due to the possible distributional change of micropollutants and microplastics when upgrading to
MBR, which might affect the possible future compilation of micropollutant removal regulations,
there is a need to further study the fate of micropollutants and microplastics in the MBR process,
compared to the CAS process. Funding for this specific study has been received by the Swedish
Water and Wastewater Association.
6.11.1 Method
A total of four separate sampling campaigns were planned in the study. The first two campaigns
were conducted in the autumn of 2017 and in the spring of 2018, including samples only from the
MBR pilot process. The remaining two sampling campaigns are planned for 2019 and are planned
to also include samples from the Henriksdal WWTP CAS process, for comparison. Both processes
treating the same influent wastewater.
Both water phase and sludge phase samples were included, 3 water phase sampling points (IN,
PTW and EFF) and 3 sludge phase sampling points (PS, WAS and DDMS), see Figure 61. Water
samples were taken as composite weekly samples and sludge samples were taken as daily grab
samples and then mixed.
The samples were analysed regarding pharmaceuticals, antibiotics, hormones, microplastics, PFAS
and chloro-organic halogens, which all are commonly found in WWTPs. Concentrations of chloro-
organic halogens are usually neglectable but here of interest since the membranes are being
cleaned with sodium hypochlorite which has been shown to be a source for different chlorinated
compounds (Ma et al. 2013).
Figure 61. Process scheme with sampling points (IN, PTW, EFF, PS, WAS, DDMS).
Table 26 shows from which sampling point samples were taken for each analysed parameter. The
decision to not include all sampling points for all parameters was taken in internal discussions
between the project group and the laboratories conducting the analysis.
80
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
6.11.2 Results
The results from the 2017 sampling campaign was presented in the yearly report of 2017
(Andersson et al. 2019) and also in the Master Thesis report connected to this specific study
(Murad, 2018). The samples from the 2018 sampling campaign were frozen after sampling and
stored for later analysis together with the 2019 samples. Therefore, no new results are presented in
this report. A full report from all four sampling campaigns will be presented in the 2019 yearly
report.
81
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
The MBR process was generally working well for all visited plants. The operation was stable, and
the treatment plants are complying with their effluent regulations. However, there are some
common general challenges that several of the visited plants were experiencing. It was difficult to
find material for decking of the membrane tanks that is light enough to be lifted but at the same
time stable enough to walk on. Corrosion has been noted on equipment handling hypochlorite, but
not if the equipment is made entirely of plastic material. Since the hypochlorite is degrading with
time storage should not exceed one month of usage. All visited plants have experienced problems
with foaming in the biological treatment step, but this has been reduced by installing sprinklers
containing water or a chlorine solution. For some plants, the power of the crane used to lift
membranes had to be increased, since wet, fouled membranes weighed more than initially
expected. The membranes in all plants were continuously cleaned using hypochlorite and citric
acid, based on a specific cleaning schedule. After some time, the plants have adjusted the cleaning
schedule to their specific needs, and they are all satisfied with the cleaning effect on the membrane
capacity. The two plants continuously monitoring effluent phosphate have both noted an increase
in effluent phosphate concentrations in connection to membrane cleaning with citric acid. This
effect has also been noted within this pilot project. The main focus of operation at the visited plants
was to comply with the effluent requirements and not much focus had been put on increasing the
resource and energy efficiency, such as chemical used for phosphorus and nitrogen removal and
energy used for aeration in the biological treatment step and in the membrane tanks.
82
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
8 Conclusions
The fifth year of the pilot plant operation of the future Henriksdal WWTP process has been
completed. The water treatment line was in operation throughout the year, without any longer
disturbances. Several shorter trials have been conducted and some longer trials and measurement
campaigns will continue into the next year. The sludge treatment line, although with discontinuous
operation, has provided some initial baseline data for mesophilic conditions and the equipment
has been modified to ensure stable operation also at thermophilic conditions in future tests.
The most important conclusions and results from project year five are listed below:
• In general, and as concluded previous years, operation of the water treatment line shows
stable effluent concentrations below target values of 5 mg N/L and 0.15 mg P/L for long
periods.
• The membrane permeability has continuously maintained good performance, above 300
L/(m2·h·bar) most of the year compared to reference value of 200 L/(m2·h·bar) which is
considered good according to the supplier.
• Effluent concentrations below limits of 10 mg N/L and 0.2 mg P/L could be met during a
trial with 150% inflow compared to design and without the use of external carbon source
and without ferric chloride addition.
• Attempts to reduce resource consumption related to membrane operation, both aeration in
the membrane tanks and chemicals used for membrane cleaning, has been in the spotlight
this year. Even though the trials are not finished, and will continue in 2019, results indicate
that there are large potential savings in both chemical and energy use when operating the
membrane tanks, without risking membrane capacity.
• Although measurements of chemical consumption are difficult and include great
uncertainties estimations indicate lower consumption of both external carbon source and
precipitation chemicals compared to the SFA design.
• Visual inspection of the membranes was conducted before and after recovery cleaning and
membrane fibers were sent for membrane autopsy. The membranes were in good
condition, the foulant before recovery cleaning contained mainly iron, some organic
material and trace amounts of calcium phosphate. After recovery cleaning most fouling
had been removed.
• When comparing thickening of MBR sludge with thickening of CAS sludge, no clear
difference was observed.
• To obtain a high TS of the thickened sludge, the polymer dosage was more important than
adjusting the thicker unit operational settings.
• Measurements of nitrous oxide emissions from the water treatment showed that 0.07 % of
the NH4-N load was converted to nitrous oxide.
• Measurements have shown high EBPR activity in periods. EBPR is present although iron is
dosed to the process but increased as iron dosage was stopped. EBPR is not enough to
manage the total phosphorus removal required to reach target effluent concentrations.
• Special attention has been given to reduction of oxalic acid and by the end of 2018 the
maintenance cleaning had been reduced to one cleaning per 8 weeks compared to design 1
cleaning per week while maintaining good permeability.
83
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
9 Further studies
Some of the planned activities for 2019 are to:
84
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
10 Related publications
Jirblom, M. (2019) Egenskaper och förtjockningspotential hos slam från MBR- respektive CAS-process.
Master Thesis. Uppsala university, Sweden.
Westling K., Andersson, S. L., Andersson, S. (2018) The world’s largest membrane bioreactor:
Henriksdal WWTP, Stockholm, Sweden – results from pilot scale trials, Membrane Technology
Conference and Exhibition, West Palm Beach, FL, USA, March 12-16, 2018.
Westling, K. & Andersson, S. (2019) Fem avloppsreningsverk med MBR-process och strikta reningskrav –
Rapport från en studieresa i USA, SVU-rapport 2019-5.
11 Bibliography
Andersson, S. L., Westling, K., Andersson, S. & Lindblom, E. (2019). Long term trials with membrane
bioreactor for enhanced wastewater treatment – pilot Henriksdal 2040. IVL B2334.
Andersson, S. L., Westling, K., Andersson, S., Laurell C., Baresel, C., Narongin, M., Royen, H. &
Bornold, N. (2017). Pilotförsök med membranreaktor för avloppsvattenrening, Delrapport 3 - försöksår 3.
IVL B2285.
Brepols, C. (2010). Operating Large Scale Membrane Bioreactors for Municipal Wastewater Treatment.
IWA Publishing ISBN: 9781843393054.
Ma, D., Gao, B., Hou, D., Wang, Y., Yue, Q. & Li, Q. (2013). Evaluation of a submerged membrane
bioreactor (SMBR) coupled with chlorine disinfection for municipal wastewater treatment and
reuse. Desalination 313, pp. 134-139.
Metcalf & Eddy (2014) Wastewater Engineering, Treatment and Resource Recovery, 5th Ed., McGraw-
Hill International Edition. ISBN 978-1-259-01079-8.
Janssen, P.M.J., Meinema, K. & van der Roest, H.F. (2002). Biological phosphorus removal -
Manual for design and operation. London: IWA Publishing.
Jirblom, M. (2019) Egenskaper och förtjockningspotential hos slam från MBR- respektive CAS-process.
Master Thesis. Uppsala university, Sweden
Murad, H. (2018). Membranbioreaktor och dess förmåga att avlägsna prioriterade mikroföroreningar.
Master Thesis, Uppsala University.
85
Report B 2388 pH2040 – Long term Membrane Bioreactor trials
Pellegrin, M.-L. & Neethling J. B. (2015). Application of Membrane Bioreactor Design Processes for
Achieving Low Effluent Nutrient Concentrations. Water Environment Research Foundation (WERF),
IWAP ISBN: 978-1-78040-675-6/1-78040-675-4.
Tykesson E., la Cour Jansen J. (2005) Evaluation of laboratory batch tests for enhanced biological
phosphorus removal. Vatten 61, pp. 43-50.
Westling, K. & Andersson, S. (2019). Fem avloppsreningsverk med MBR-process och strikta utsläppskrav
- Rapport från en studieresa till USA. Svenskt Vatten Utveckling, Rapport Nr 2019-5.
86
IVL Swedish Environmental Research Institute Ltd.
P.O. Box 210 60 // S-100 31 Stockholm // Sweden
Phone +46-(0)10-7886500 // Fax +46-(0)10-7886590 // www.ivl.se