Seminar Report
Seminar Report
On
Submitted by
Guided by
Prof.Vinayak Kale
CERTIFICATE
This is to certify that the following student has satisfactorily carried out the seminar
work entitled “ ”. This work is being submitted for the award of degree of Master of
Civil Engineering (Construction & Management). It is submitted in the partial
fulfillment of the prescribed syllabus of Savitribai Phule Pune University, Pune for
the academic year 2023 – 2024.
Examination Seat No. Name of the Student
Vasudha Ninad Jadhav
Mr.Vinayak Kale
(Guide)
External Examiner
ACKNOWLEDGEMENT
I hereby take this opportunity to express my profound thanks and deep sense of
gratitude towards my guide, Prof.Vinayak Kale Associate Professor, Department of
Civil Engineering. He gave me a precious time from his busy schedule & his valuable
guidance has been a constant encouragement.
I would also like to thank Dr. Lalit Kumar Wadhwa, Principal, Dr. Deepa A. Joshi,
Head of the Department of Civil Engineering, and the faculty of the Department of
Civil Engineering, whose constant encouragement and expert guidance was
instrumental in the completion of this seminar work.
Let me, at the end, express gratitude to all those from whom I received co-operation,
help & motivation during seminar work.
Name of student
Vasudha Jadhav
ACKNOWLEDGEMENT iii
SYNOPSIS iv
NOTATIONS vi
LIST OF TABLES vii
LIST OF FIGURES viii
LIST OF GRAPHS ix
CONTENTS
2. LITERATURE REVIEW
3. SITE DETAILS
4. CONCLUSIONS
LIST OF FIGURES
1. Aggregate
● Aggregate are the important constituents in concrete. They give body
to the concrete, reduce shrinkage and effect economy. The mere fact
that the aggregates occupy 70-80% of the volume of concrete.
● The size of aggregate bigger than 4.75 mm is considered as coarse
aggregate and aggregate whose size is 4.75 mm and less is considered
as fine aggregate.
2. Cement
● Cement is a binder material which sets and hardens indepently, and
can bind other materials together.
● Cement is made up of four main compounds:
3. Admixture
4. Fly Ash
Water
5. Equipment Required
RMC PLANT
Mixing Process
Disadvantages of RMC
● The materials are batched at a central plant, and the mixing begins at
that plant, so the traveling time from the plant to site is critical over
longer distances.
● Access roads, and site access have to be able to carry the weight of
the truck and load concrete is approx 2.5 tone.
TEST ON CONCRETE
•
Raw material testing machine
Trial mixer
SLUMP TEST
Conclusion
● Ready mix concrete is a modern technique of production of concrete
in massive quantities away from the actual site of placing.
● It is very useful where demand of concrete is very high and
construction sites are in congested areas, where mixing on site is not
possible due to lake of storage place.
● RMC is ready to use material. It is widely adopted throughout the
world.
● It gives higher strength to the structure and it also provides higher
Durability to the structure.
● It is suitable for huge industrial and residential projects where time
plays a vital role.