Report

The project is currently 12% complete overall. Several key tasks are past due including the 132kV grid station, civil works, and switchyard construction. Upcoming milestones include completion of the 132kV grid station by November 2nd. The document provides status updates for over 50 subtasks of the electrical substation construction project broken into categories like switchyard works, control building construction, equipment installation, testing and commissioning.

Uploaded by

MUHAMMAD TAYYAB
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
17 views4 pages

Report

The project is currently 12% complete overall. Several key tasks are past due including the 132kV grid station, civil works, and switchyard construction. Upcoming milestones include completion of the 132kV grid station by November 2nd. The document provides status updates for over 50 subtasks of the electrical substation construction project broken into categories like switchyard works, control building construction, equipment installation, testing and commissioning.

Uploaded by

MUHAMMAD TAYYAB
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

PROJECT OVERVIEW % COMPLETE

Status for all top-level tasks. To see the status for subtasks, click on the chart and update the
outline level in the Field List.

100% 100% 100%


84%
TUE 19/07/22 - SUN 17/09/23 90%
80%
70%
60%
% COMPLETE 50%
40%
30%

12% 20%
10%
0%
0% 0% 0% 5% 0% 0% 0%

MILESTONES DUE
Milestones that are coming soon.

Name Finish

132kV Grid Station EMAAR Wed 02/11/22


LATE TASKS
Tasks that are past due.

Name Start Finish Duration % Complete Resource


Names

132kV Grid Station Wed Wed 02/11/22 0 days 0%


EMAAR 02/11/22

Approval of Design Wed Tue 08/11/22 7 days 0% TSW[1]


From TSW 02/11/22

Tandering Wed Wed 02/11/22 1 day? 0%


Completion 02/11/22

Commencement of Wed Wed 02/11/22 1 day 0% XEN T&G


civil works 02/11/22

132kv Switchyard Sun 11/09/22 Wed 26/10/22 45 days 0% Contracor


Cable Trenches and
Other works

Switch Yard Mon Mon 31/10/22 36 days 0% Contracor


Drainage System 26/09/22

Switchyard Fence Thu 06/10/22 Sun 13/11/22 39 days 0% Contracor


and Fence Gate

Transformer way Sun 16/10/22 Thu 24/11/22 40 days 0% Contracor

Backfilling and Fri 11/11/22 Fri 25/11/22 15 days 0% Contracor


Compaction
Gravel Spreading Sat 26/11/22 Sat 10/12/22 15 days 0% Contracor

Demarcation of CHB Fri 19/08/22 Fri 19/08/22 1 day? 0% Contracor,COS

Excavation of CHB Fri 29/07/22 Fri 29/07/22 1 day? 0% Contracor

Substructure Fri 29/07/22 Wed 21/09/22 55 days 0% Contracor

Construction of Thu 22/09/22 Sun 30/10/22 39 days 0% Contracor


Framework

Brick work Mon Mon 05/12/22 36 days 0% Contracor


31/10/22

Plaster Tue 06/12/22 Wed 04/01/23 30 days 0% Contracor

Trenches in CHB Mon Sun 20/11/22 21 days 0% Contracor


31/10/22

Watersupply Fri 29/07/22 Wed 17/08/22 20 days 0% Contracor


sanitary and
Sewerage / Drainage
Works

Flooring and Ceiling Thu 05/01/23 Sun 29/01/23 25 days 0% Contracor

Electrification Mon Tue 14/02/23 16 days 0% Contracor


30/01/23

Finishing and Allied Wed Thu 16/03/23 30 days 0% Contracor


works 15/02/23

Water Borings Wed Wed 16/11/22 15 days 0% Contracor


02/11/22

Substructure Wed Sat 31/12/22 60 days 0% Contracor


02/11/22

Ground Floor Gray Sun 01/01/23 Tue 14/02/23 45 days 0% Contracor


Structure

First Floor Gray Wed Fri 31/03/23 45 days 0% Contracor


strcuture 15/02/23

Finishing works Sat 01/04/23 Mon 15/05/23 45 days 0% Contracor

Finishing and Allied Tue 16/05/23 Wed 14/06/23 30 days 0% Contracor


works

Civil Works Wed Wed 02/11/22 1 day? 0%


Completed 02/11/22

Material Shifting Wed Thu 01/12/22 30 days 0% LS with team


from store to Site 02/11/22

Installtion of Power Fri 02/12/22 Fri 09/12/22 8 days 0% LS with team


Transformers

Installtion of Fri 06/01/23 Sun 15/01/23 10 days 0% LS with team


Gantries & Eath
Mast
Installtion of Beams Mon Thu 19/01/23 4 days 0% LS with team
16/01/23

Installtion of Bays Fri 20/01/23 Fri 03/02/23 15 days 0% LS with team

Installtion of Surge Sat 04/02/23 Sun 05/02/23 2 days 0% LS with team


arrestors

Jumpers& Dropers & Mon Fri 17/02/23 12 days 0% LS with team


Gantry Span & 06/02/23
Skywire

Installtion of 11KV Sat 18/02/23 Sat 25/02/23 8 days 0% LS with team


Switchgear Panels

Installtion of Control Sun 26/02/23 Tue 28/02/23 3 days 0% LS with team


and Relay Panels

Laying and Wed Wed 15/03/23 15 days 0% LS with team


Termination of 01/03/23
Control and Power
Cables

Installtion of Thu 16/03/23 Wed 29/03/23 14 days 0% LS with team


Capacitor Banks

Installtion of Thu 30/03/23 Mon 03/04/23 5 days 0% LS with team


Batteries and
Battery Chargers

Installtion of Pad Tue 04/04/23 Wed 05/04/23 2 days 0% LS with team


Mounted
Transforemer

Internal Interfacing Fri 03/03/23 Fri 17/03/23 15 days 0% LS with team


(Wiring)

Stringing of Thu 23/03/23 Fri 24/03/23 2 days 0% LS with team


Condcutor (Subject
to Shut Down on
Existing Line)

Dy-Hydraton of PTF Thu 06/04/23 Wed 19/04/23 14 days 0% T&I

Testing of Power Thu 20/04/23 Sat 22/04/23 3 days 0% T&I


Transformer

Testing of Thu 06/04/23 Wed 12/04/23 7 days 0% T&I


Swicthgear

HI pot test Thu 13/04/23 Thu 13/04/23 1 day 0% T&I

Testing of MV Thu 13/04/23 Tue 18/04/23 6 days 0% T&I


Swicthgear, Control,
Relay Panels etc

Scheme Checks & Wed Thu 20/04/23 2 days 0% T&I


Pre-Commissioning 19/04/23
Activites
Ready for Fri 21/04/23 Mon 24/04/23 4 days 0% T&I
Energization

End of the Project Tue 25/04/23 Tue 25/04/23 1 day 0% PD GSC


(Commissioning &
Energization)