PRU - 90% Model Review Checklist
PRU - 90% Model Review Checklist
1 Closure of 30% and 60% Model Review tags Intecsa/MEIL Yes Completed
Conduct Internal 90% Model review of INTECSA / MEIL, and submit
2 Intecsa/MEIL No MEIL/INTECSA to carry out Internal model review before 90% MR
the Comments Resolution Report.
Neat 3D Model without Proposal/ Temporary Models as per the 3D
3 Intecsa/MEIL No MEIL/INTECSA to clean model prior to 90% Model review
CAD Procedure.
Modelled Items shall be clearly split based on Design area with no
4 Intecsa/MEIL No Under Progress
Overlap of Items across Design Area.
MEIL/Intecsa to consider PMC code -B comments in design and
5 Issuance of IFC P&ID. Intecsa/MEIL Yes issue the markup copy for PMC/IOCL review before 2 weeks from
90% Model review
Intecsa to issue Unit plot plan for Control Room and Sub-station.
6 IFC of Unit Plot Plan and General Plot Plan. Intecsa/MEIL No
Intecsa to clear all HOLDS in the next revision of plot plan.
Completion and Update of review Tags of all 3D Model Reviews of Package Model review to be done prior to 90% MR and if any
9 Intecsa/MEIL No
Packages. comments the same as to be close before 90% MR
1. Control Room/Sub-station:-
MEIL should update model and Tie-in arrangment drawings as per
PMC comments.
12 All Interphases Tie-Ins to be Closed. Intecsa/MEIL No 2. Process Tie-in:-
MEIL should resubmit the Tie-in arrangement drawings for PMC
review and update model based on previous revision of PMC
comments.
MEIL - Electrical/
20 Finalisation of Equipment layout (Substation & Control room) Yes
Instrumentation
MEIL -
23 Availability of all the telecom instruments with the VDR G.A drawing. No Vendor Drawings not available in SDB
Instrumentation
MEIL -
24 OFF Line Instrument with Stanchion 100% to be modelled. No Under Progress
Instrumentation
MEIL - Junction Box TAG nos are not assigned in model.Total J.B list is
25 All the junction boxes for P1,P2 Packages to be modelled. No
Instrumentation required to confirm
MEIL -
26 Control room / Substation/ all the buildings MCT to be modelled. Yes
Instrumentation
MEIL -
27 lnstrument Prefabricated Hookups No MEIL to update in model
Instrumentation
Firewater network layouts for the entire scope area including MEIL - Process WILL BE DONE BY
32 Yes
buildings shall be issued and reviewed by Client/PMC in code 2/3. Safety DECEMBER 5TH
WORK IN PROGRESS
Fire and gas detectors including the orientation, elevation and MEIL - Process
37 No Under Progress WILL BE COMPLETED
location shall be completely modelled. Safety
BY DEC 10TH
MEIL - Process MEIL to ensure the safety shower quantity and Escape route to be WILL BE DONE BY DEC
38 All safety systems (eye wash safety showers, escape routes) No
Safety model as per layout without any clashes 10TH
All Firefighting systems (like hose reels, hydrant, monitors, dry risers, WORK IN PROGRESS
MEIL - Process
39 all deluge piping No Under Progress WILL BE COMPLETED
Safety
around equipment & all sprinkler system) BY DEC 10TH
HPC Done.
N2 Compressor and Condensate recovery package pending for
Hazop & SIL.
41 Closeout report of QRA, HAZID, HAZOP & SIL Reviews. Intecsa/MEIL No
Hazid recomendation closeout report - 4 action points out of 10 are
still pending.
QRA recomendation closeout report to be submit.
42 HVAC calculation and modelling for Control Room and Substation. Intecsa/MEIL No MEIL to prepare calculation report. PO not yet placed for HVAC
All UG items including UG piping are fully modelled, and they are
44 Intecsa/MEIL No MEIL to check and clear all the UG clashes
clash free.
All Miscellaneous pipe supports, Paved area with surface slopes,
45 Intecsa/MEIL No Grade miscellaneous pipe supports input/design under progress
Roads, Culverts complete.
Structural steel modelling along with major fabrication connections
TS-03/TS-04/SH-01/SH-02 drawings still under preparation
46 duly modelled to reserve the space and to see no clash with others Intecsa/MEIL No
TS-01/TS-02 under MEIL Piping review
due to connection plates.
47 PFP - Fireproof modelling on structural steel. MEIL - Civil No Fireproofing to update in model as per requirement
All Interfaces are complete and demonstrate no mismatch with
48 Intecsa/MEIL No MEIL to ensure the interface with Octomax/CT contractors
others contractors model.
Clash report to be auto generated, clashes to be resolved and close-
49 Intecsa/MEIL No Not done
out status to be submitted.
50 Packages Step file to be updated. Intecsa/MEIL Yes Vendor step files available