TGP-JE-GTPT-000-QC-ACP-0012-Heat Exchanger Action Plan
TGP-JE-GTPT-000-QC-ACP-0012-Heat Exchanger Action Plan
TGP-JE-GTPT-000-QC-ACP-0012-Heat Exchanger Action Plan
1 All modified name plate cannot It has been confirmed with the B 15‐Oct‐22
accepted, need replace with new one. vendor that the nameplate needs to
Need AI agreement.Some mistakes be recreated under the supervision
were detected on Nameplates of some of AI. After the new nameplate be
equipment must be corrected. Need AI on site.During the replacement
agreement. process, the original nameplate will
be destroyed in accordance with
ASME regulations.
2 All the internal of the Heat Exchangers noted C closed
had not been checked in order to keep
actual items preservation
3 Name plate Tunisianfication stamp Tunisification stamp will be C 15‐Oct‐22
required to be performed by TPI, stamp stamped by TPI after new name
is missing because TPI witness were plate on site.
performed by remote video inspection
4 All of the Heat Exchangers tell‐tale done C closed
holes and Nameplates support inner
side need sealing (since the Nameplate
support not welded from inner side).
5 All equipment need wooden dunnage done C closed
according to project storage procedure.
6 Some flange heavy Hex nuts face inside Consortium has confirmed with the B 01‐Dec‐22
out. local resource, and the heavey Hex
nuts face inside will be changed
before installation.
7 According to Surface preparation and Consortium has confirmed with the B closed
painting procedure TGP‐JE‐GTPT‐000‐ vendor, here are the explanation
QC‐PRO‐02006_000 , there are 6 from the vendor, The slightly color
Heater exchangers from 7 (except difference cause of the operating
stainless steel Heater Exchanger TAG temperature is over 90 degrees, the
N ° : GTPT‐H‐240‐002 painting not high temperature paint is used, and
required) painting finish color should the silicone heat resistant paint
be RAL7035, during inspection only applied is only black and silver, the
TAG NO. GTPT‐E‐240‐001 was qualified silver color of the silicone is similar
and the 5 others have slightly color to RAL9006, with a metallic color,
1/4
Construction of Gas Treatment Plant-Tataouine Gas Project
3/4
Construction of Gas Treatment Plant-Tataouine Gas Project
Reported By Approved By
JEREH ETAP
Name: Pang Eryuan Name:
Signature: Signature:
4/4