Outfitting Bill - 1, H # 2
Outfitting Bill - 1, H # 2
Outfitting Bill - 1, H # 2
Shipbuilding Unit
South Pangoan, South Keranigonj, Dhaka -1311.
Subject: Work Percentage for Fabrication & Installation of Outfitting Works, Hull #-2 Date: 01/05/2023
Fitting Welding
Job Total Fitting Welding Total Overall Job
S/N Description of work Unit Percentage Percentage Amount(in BDT)
Percentage Quantity Quantity Quantity Percentage Percentage
(70%) (30%)
1 Manhole Installation on board 2.00% PC 30 30 30 100% 100.00% 100.00% 2.00%
2 Access Hatch Installation 0.20% PC 1 0% 0.00% 0.00% 0.00%
3 Vertical Ladder Installation 2.00% PC 25 25 10 100% 40.00% 82.00% 1.64%
4 Accommodation Stairway Installation 2.00% PC 12 4 33% 0.00% 23.33% 0.47%
5 Chin Locker Perforated Plate 1.00% PC 11 0% 0.00% 0.00% 0.00%
6 Sounding Pipe striking plate 1.00% PC 12 0% 0.00% 0.00% 0.00%
7 Door Installation 3.00% PC 41 0% 0.00% 0.00% 0.00%
8 Window and Side Scuttles Installation 2.00% PC 28 0% 0.00% 0.00% 0.00%
9 Porthole Installation 2.00% PC 12 0% 0.00% 0.00% 0.00%
10 RADAR & Antenna post Installation 0.50% PC 2 0% 0.00% 0.00% 0.00%
11 Masts and Flag Posts Installation 0.10% PC 2 0% 0.00% 0.00% 0.00%
12 Railing Fabrication & Installation 8.00% Meter 280 250 200 89% 71.43% 83.93% 6.71%
13 Drain Plug Installation 0.60% PC 7 4 57% 0.00% 40.00% 0.24%
14 Eco Sounder Installation 0.20% PC 1 0% 0.00% 0.00% 0.00%
23 Draft Mark & Pimsoll Mark Fitting 1.00% PC 6 0% 0.00% 0.00% 0.00%
24 Ship Name & IMO Number 1.00% PC 1 0% 0.00% 0.00% 0.00%
All Engine Room Checkered Plate
25 5.00% PC 16 0% #VALUE! #VALUE! #VALUE!
Installation with Base
26 Zinc Anode Fitting 1.00% PC 67 0% 0.00% 0.00% 0.00%
27 Sea Chest Gratings Installation 1.00% PC 3 3 100% 0.00% 70.00% 0.70%
28 Various Pump Foundation 1.00% PC 6 6 100% 0.00% 70.00% 0.70%
Various Foundation Works (Except
29 1.00% PC 3 0% 0.00% 0.00% 0.00%
Engine Foundation)
30 Rudder Works 2.60% PC 2 0% 0.00% 0.00% 0.00%
31 Loose Tanks fabrication & installation 3.00% PC 6 6 100% 0.00% 70.00% 2.10%
32 Ventilation Duct in ERM 1.00% PC 3 0% 0.00% 0.00% 0.00%
33 Louver Works 0.10% PC 1 0% 0.00% 0.00% 0.00%
34 Engine Control room Works 0.20% PC 1 0% 0.00% 0.00% 0.00%
35 Drip Tray Works 0.10% PC 8 0% 0.00% 0.00% 0.00%
36 Living area Bed Frame & Table 0.50% PC 10 0% 0.00% 0.00% 0.00%
37 Fender Hook Eye 1.00% PC 22 20 20 91% 90.91% 90.91% 0.91%
38 All Tank Testing 4.00% PC 17 0% 0.00% 0.00% 0.00%
Any other outfitting and its related works
39 (such as magnetic drilling, milling, 1.00% PC 6 0% 0.00% 0.00% 0.00%
machining etc.)
Conveyor System Bottom Part (Hopper
40 Gate, Hopper Guide Plate & Tank Top 8.00% PC 120 0% 0.00% 0.00% 0.00%
Roller & Roller Support)
41 Conveyor System Inclined Part 6.00% PC 1 0% 0.00% 0.00% 0.00%
42 Conveyor System Top Part 6.00% PC 1 0.5 0.5 50% 50.00% 50.00% 3.00%
43 Stanchion Pipe Support Installation 18.00% PC 118 118 100% 0.00% 70.00% 12.60%
Total 100.00% #VALUE!