CPM PERT-1 Dec
CPM PERT-1 Dec
1-2 4 https://www.youtube.com/watch?v=kj-CxhG7XBw&ab_channel=StartPracticing
1-3 1
2-4 1
3-4 1
3-5 6
4-9 5
5-6 4
5-7 8
6-8 1
7-8 2
8-10 5
9-10 7
Float
Notes: forward Path
Free Float Zero will be the starting time
FFij=EFTj-ESTi-tij EFij= ESij-tij
0
Backward Path
0 For ending event assume E=L
0 LFij or Lj=LF-tij
3 Critical Path : An activity is said to be critical if the
0 total Float TFij for any activity ij is zero.
0
Critical Path
0 1-3-5-7-8-10
0 Total Time= 1+6+8+2+5= 22 days
5
0
0
5
Activity Duration
1-2 13 https://www.youtube.com/watch?v=R-oN1nMP78Q&ab_channel=KarpagamQ
1-3 12
2-4 2
3-4 8
2-5 15
4-5 2
Critical Path
What Is the Critical Path In Project Management?
In project management, the critical path is the longest sequence of tasks that must be
completed to execute a project. The tasks on the critical path are called critical activities
because if they’re delayed, the whole project completion will be delayed. To find the
critical path, project managers use the critical path method (CPM).
What Is the Critical Path Method (CPM)?
The critical path method (CPM) is a project management technique that’s used by
project managers to create an accurate project Schedule . The CPM method, also
known as critical path analysis (CPA), consists in using the CPM formula and a network
diagram to visually represent the task sequences of a project. Once these task
sequences or paths are defined, their duration is calculated to identify the critical path.
What Is the Critical Path Method (CPM)?
The critical path method (CPM) is a project management technique that’s used by
project managers to create an accurate project Schedule . The CPM method, also
known as critical path analysis (CPA), consists in using the CPM formula and a network
diagram to visually represent the task sequences of a project. Once these task
sequences or paths are defined, their duration is calculated to identify the critical path.
78Q&ab_channel=KarpagamQTcorner
Independent Float:
IF 1-2= LFT2-EST1-d12
Critical Path=
ESTj-LFTi-tij where TF=0
1-2-5
Independent float Total Time =13+15= 28 days
0
0 Total float :Total float is the amount of time a task or a project can be delayed
without impacting the overall project completion time
5 Free float is the amount of time an activity can be delayed without delaying the
0 -6 start of its successor activity. To calculate free float, you can use the following
formula:
0 time cannot be negative so its taken as 0
Free float = Early start of the successor activity - Early start of the current activity
0 -tij
Independent float It is defined as the amount of time an activity's start time can
be delayed without affecting the earliest start time of any successors. So
independent float is the delay in any project tasks that have no bearing on the
early finish date of the project (EST2-LFT1-tij)
Crashing1
Crashing2
10050+(50 10100
r crashing required
Most Optimistic Most Likely Pessimistic time Expected Time Standard Deviation
Activity To Tm Tp 4Tm Te=(To+4Tm+Tp)/6 σ=(Tp-To)/6
1-2 3 6 9 24 6 1
1-6 2 5 8 20 5
2-3 6 12 18 48 12 2
2-4 4 5 6 20 5
3-5 8 11 14 44 11 1
4-5 3 7 11 28 7
6-7 3 9 15 36 9
5-8 2 4 6 16 4 0.6667
7-8 8 16 18 64 15
33
X= 35 Days or below
Average Critical time= 33 weeks
SD= Sqrt(6.444)= 2.54
Z=(X-Mean)/SD Z=(35-33)/2.54 0.7874
p(X<=35 Days) 0.7823 Prob of 78.23 percent that project will finish on time
Variance https://www.youtube.com/watch?v=J1WwNKDdDC0&ab_channel=StartPracticing
σ2
1
0.4444
6.444
nish on time
Most OptimMost Likely Pessimistic time Expected Time Standard Deviation
Activity To Tm Tp 4Tm Te=(To+4Tm+Tp)/6 σ=(Tp-To)/6
1-2 3 6 15 24 7 2
1-3 2 5 14 20 6 2
1-4 6 12 30 48 14 4
2-5 2 5 8 20 5 1
2-6 5 11 17 44 11 2
3-6 3 6 15 24 7 2
4-7 3 9 27 36 11 4
5-7 1 4 7 16 4 1
6-7 2 5 8 20 5 1
25
X= 27Days or below
Average Critical time= 25 weeks
SD= Sqrt(32)= 5.66
Z=(X-MeanZ=(27-25)/sqrt(32) 0.3536
p(X<=27 Days) 0.6368 Prob of 63.68 percent that project will finish on time
Variance
σ2 https://www.youtube.com/watch?v=_EcebA6Nn6o&ab_channel=HAMEEDAMATHTUBER
4
4
16
1 a Show the network for the project, and identify the critical activiti
4 b What is the probability that the project will be completed in 20 d
4 c If X= 27 days,What is the probability that the project will finish on
16 X= 27Days or below
1 Average Critical time= 25 weeks
1 SD= Sqrt(32)= 5.66
32 Z=(X-Mean)/SD Z=(27-25)/sqrt(32)= 0.3536
p(X<=27 Days)= 0.6368 Prob of 63.68 percent that project will finis
and identify the critical activities and the expected project duration.
oject will be completed in 20 days?
y that the project will finish on time
0.3536
8 percent that project will finish on time
bility
e)
bility
ble)
ability
e)
b p( X<55)
p(Z< 55-47/3.496 2.2883295 2.29
C
to calculate the time as to when to start the work, we
have to obtain value of X corresponding to which an
area equal to 0.90 lies to the left of it. From the
normat area table, we observe that Z value
corresponding to area of 0.40 (area between X and
Mu) is 1.28. Thus we have
1.28=X-47/3.496, X= 51.47 or approx 52 days
d
A panelty woud be paid if the project is not completed in 50
days. For a panelty to be paid upto Rs.2000, the project
would complete between 50 to 54 days. The probability of
this would be given by the area marked by the Fig 3, We
have,
A panelty woud be paid if the project is not completed in 50
days. For a panelty to be paid upto Rs.2000, the project
would complete between 50 to 54 days. The probability of
this would be given by the area marked by the Fig 3, We
have,
Z1=(54-47)/3.496= 0.4772
Z2=(50-47)/3.496=0.3051
Required area= 0.4772-0.3051=0.1721
Activity
A 1-2
B 1-4
C 1-3
D 2-3
E 2-5
F 4-3
G 4-6
H 3-7
I 6-7
J 5-7
Following are the optimistic, pessimistic, and expected duration (in
days) for the activities required to be completed for a project.
Draw the network diagram (2 marks).
e project. (4
s (2 marks)