Week 11 - Budgeting and Variance Analysis-1
Week 11 - Budgeting and Variance Analysis-1
Week 11 - Budgeting and Variance Analysis-1
Week 11 Lecture
Laura Mazzola
Required Reading A&L Chapter 9, Budgeting (p.298-306 this week; pp.282-298 last
week)
Budgeting
Learning Outcomes
After this week you should be able to:
• Explain how budgets can be compared to actual results to allow
control (variance analysis)
• Prepare a flexed budget
• Calculate and discuss sales, materials, labour and fixed overhead
variances
• Discuss benefits and challenges of variance analysis
3
Introduction
• Budgetary control is a typical component of an MCS
4
Introduction
• *Standard costs are predetermined costs or costs which should be incurred in
efficient operating conditions
• Standard cost is the planned unit cost of the products, components or services
produced in a period.
TH enalysis will help us to identiyfy the diferences betwed ou planned and our actual
performance
5
Introduction
BUDGETED
STD
COST
COST
6
Introduction
• Standard costing systems: purposes
is used to stimate what re future cost will be in the future in a perio of time
This will help us to produce a target we need to chieve and to motivate the managemnt
by setting a budget and some achieves we are abke to identify in what aspects we ned to put focus on to
achieve the goals
7
Introduction
8
Variance Analysis
• The differences between actual and budgeted costs are called
‘variances’
• Variances are calculated by comparing actual costs & income with
the budgeted (planned) costs & income
the actual outcome is beter than the
– when something goes better than planned, there will be a planned one
Adverse variances imply: selling less, selling at a lower price, having more cost than
budgeted
Favourable variances imply: selling more, selling at a higher price, having less cost than
budgeted
9
Variance Analysis
original budget
the overall material variance is the difference between price variance and
10
efficency variance
Variance Analysis
Variance
analysis
11
Variance Analysis
it can be changind supplier, how we can reduce the use of material instead of labour
It could be that we are completly worng in the original variance
12
Preparing a flexed budget
Budget Actual
Output for month 1,000 units 900 units What has driven that
we have sale less
(production & sales)
£ £
Sales revenue 100,000 £100 each 92,000 £102.22 each
Raw materials (40,000) (40,000 metres) (36,900) (37,000 metres)
Labour (20,000) (2,500 hours) (17,500) (2,150 hours)
Fixed overheads (20,000) (20,700)
Operating profit 20,000 16,900
¿What has drivven this differences?
13
Preparing a flexed budget
Preparing a flexed budget simply means revising the budget for the actual level
of output
For example, if you knew that output was going to be 900 units, what would
have been budgeted for sales revenue, raw materials etc.?
Only the output changes – the budgeted selling prices, estimated usage per
product, and costs per unit stay the same – what were these?
1. identityf standar unit and then calculate with all of the units we are using
14
Preparing a flexed budget
Original Flexed Actual
Budget Budget
£ £ £
Revenue 100,000 90,000 £100 92,000 £102.22
Materials (40,000) (36,000)(36000 metres) (36,900) (37000 metres)
Labour (20,000) (18,000)(2,250 hours) (17,500) (2,150 hours)
F/overheads (20,000) (20,000) (20,700)
Op. profit 20,000 16,000 16,900
This quickly identifies budgeted income & costs for actual activity
15
Preparing a flexed budget
Original Flexed Actual
Budget Budget
£ £ £
Revenue 100,000 90,000 £100 92,000 £102.22
Materials (40,000) (36,000)(36000 metres) (36,900) (37000 metres)
Labour (20,000) (18,000) (2,250 hours) (17,500) (2,150 hours)
F/overheads (20,000) (20,000) (20,700)
Op. profit 20,000 16,000 16,900
This quickly identifies budgeted income & costs for actual activity
16
Sales Variances
Overall, there is a difference of £2,000 between sales under the flexed budget
(£90,000) and actual sales (£92,000). The difference is favourable (revenue is
higher than we would have expected – positive impact on profit).
As we know the flexed budget and actual are based on 900 units, this variance
arises because of a difference in the sales price
17
Sales Variances
But what about the fact that we sold fewer units than expected? To understand
this, we use the
• Sales volume variance:
the impact of this in our overall profit--> sales volume variance
We compare our original budget and our flexed bufget op. porfit--> we compare the original
and what should´ve been
This variance uses the overall profit (not sales price) to estimate the impact of the
change on profit – which should be of interest to managers
This is an adverse variance as profit is lower because of the lower sales in units
Note that because profit is used here, sales price variance plus sales volume
variance do not equal the difference between originally budgeted and actual
revenue
18
Preparing a flexed budget
Original Flexed Actual
Budget Budget
£ £ £
Revenue 100,000 90,000 £100 92,000 £102.22
Materials (40,000) (36,000)(36000 metres) (36,900) (37000 metres)
Labour (20,000) (18,000) (2,250 hours) (17,500) (2,150 hours)
F/overheads (20,000) (20,000) (20,700)
Op. profit 20,000 16,000 16,900
This quickly identifies budgeted income & costs for actual activity
So, any variance here relates to cost being more or less than
budgeted
£ £ £
Revenue 100,000 90,000 £100 92,000 £102.22
Materials (40,000) (36,000)(36000 metres) (36,900) (37000 metres)
Labour (20,000) (18,000) (2,250 hours) (17,500) (2,150 hours)
F/overheads (20,000) (20,000) (20,700)
Op. profit 20,000 16,000 16,900
This quickly identifies budgeted income & costs for actual activity
21
Labour Variances
There is a difference of £500 between flexed budgeted direct
labour (£18,000) and actual labour (£17,500). The difference is
favourable (cost is lower than we would have expected – positive
impact on profit).
Total labour variance is the difference between
the actual direct labour cost
and
the direct labour cost according to the flexed budget
This variance excludes the impact of making 100 more units, and
we would then need to understand:
• Are we using less labour per product than expected?
• Is labour cheaper per hour than expected?
• Why might this be the case?
• Is further investigation/action needed?
22
Preparing a flexed budget
Original Flexed Actual
Budget Budget
£ £ £
Revenue 100,000 90,000 £100 92,000 £102.22
Materials (40,000) (36,000)(36000 metres) (36,900) (37000 metres)
Labour (20,000) (18,000) (2,250 hours) (17,500) (2,150 hours)
F/overheads (20,000) (20,000) (20,700)
Op. profit 20,000 16,000 16,900
This quickly identifies budgeted income & costs for actual activity
23
Materials Variances
There is a difference of £900 between flexed budgeted direct
materials (£36,000) and actual materials (£36,900). The
difference is adverse (cost is higher than we would have expected
– negative impact on profit).
and
24
Materials Variances
• At the end of the year the business has produced 3,000 units using 42,000 kg at
a cost of £672,000
Requirement:
• Calculate the Material Price Variance and the Material Usage variance, showing
at the same time the Total Materials Variance.
26
Materials variances
Example
Standard (budgeted) cost of material is £18 / kg
Standard (budgeted) usage is 11kg / unit
Planned output is 3,000 units
Therefore, budgeted cost = 3,000 x 11kg x £18 = £594,000 actual
29
Favourable & Adverse Variances
– Less material being used per unit than the standard indicates
– More material being used per unit than the standard indicates
efficency labour, ussage material
30
Making Variance Analysis Useful
• Advantages:
– Can be used for performance appraisal
– Indicates which department is responsible for the variance
– Allows ‘management by exception’
• Disadvantages:
– The existence of a variance says little about its cause
– Although variances can be split into several parts, this does not mean that all the
causes of the variance have been identified because there are interdependencies
between the variances
– Variances simply indicate where more investigation is needed
• Requirements
3. motivate our employeess
– Clear responsibility for budgeted areas e.g., who is responsible for materials price?
– Challenging but not impossible targets
– Regular, established reporting – e.g., monthly, available quickly after month end
– Provision of information relevant to specific manager’s responsibilities
– Investigation/action taken where variances are found
• Behavioural issues:
– Budgets are a useful tool to communicate information and monitor performance
– Budgets that are perceived as impossible, or too easy to meet, will not motivate
good performance
– Participation in the process can help with motivation
32
Some examples from
MyAccountingLab
Example 1 MyAccountingLab:
flexed budget for sales revenue: 84000/1200=700 per unit*1250=875000 flexed sales revenue
34
Example 2 MyAccountingLab:
35
Extended Example 2 MyAccountingLab:
What if the question told you actual profit was £62,000 and you had to work out
the original budget profit?
36
Example 3 MyAccountingLab:
Caspian manufactures kettles
Calculate the:
1. Sales volume variance
2. Sales price variance
3. Direct materials variance
4. Direct labour variance
5. Fixed overhead variance
In each case, indicate whether the variance is favourable (F) or adverse (A).
37
Learning Outcomes
After this week you should be able to:
• Explain how budgets can be compared to actual results to allow
control (variance analysis)
• Prepare a flexed budget
• Calculate and discuss sales, materials, labour and fixed overhead
variances
• Discuss benefits and challenges of variance analysis
38
Next Steps
• Atrill and Mc Laney 2022 (Chapter 9, p.298-306
this week; pp.282-298 last week)
• Computer class W11
• My Accounting Lab
- Practice Homework Week 11
- Assessed Homework Week 11