PMP Mock Exams Set2
PMP Mock Exams Set2
http://www.tuto rialspo int.co m/pmp-e xams/pmp_mo ck_e xams_se t2.htm Co pyrig ht © tuto rials po int.co m
1. Memos
3. Videos
Answer:E
3. Coordinator
4. Expeditor
Answer:D
Answer:B
(5 4) In neg otiating with functional department manag ers, project manag ers often find themselves using what
two-party conflict manag ement approach?
1. Win-Lose
2. Win-Win
3. Lose-Lose
Answer:C
(5 5 ) A leadership style in which the project manag er shares problems with team members and formulates
solutions as a g roup is called:
1. Autocratic
2. Consultation in a g roup
3. Consensus
4. One-to-one consultation
Answer:C
(5 6) A type of org anization in which the project manag er has little formal authority and basically acts as a staff
assistant to an executive who is ultimately responsible for the project is called:
1. Functional
2. Weak matrix
3. Project coordinator
4. Project expediter
Answer:D
Answer: B
(5 8) In which of the following org anizations is the project manag er role likely to be part-time?
1. Weak matrix
2. Functional
3. Balanced matrix
4. a and b
Answer:C
(5 9) Project Risk Manag ement includes all of the following processes except:
1. Risk Quantification
2. Risk Identification
3. Risk Analysis
Answer:E
(60) Using the PMBOK definition of conting ency reserve, which of the following statements about conting ency
reserves is false?
1. A conting ency reserve is a separately planned quantity used to allow for future situations which may be
planned for only in part.
4. Conting ency reserves are normally included in the project's cost and schedule baselines.
Answer:C
1. T he risk can be deflected or transferred to another party throug h a contract or insurance policy.
4. a and c
5. a and b
Answer:D
1. A planned response that defines the steps to be taken if an identified risk event should occur.
2. A workaround
3. A reserve used to allow for future situations which may be planned for only in part.
4. a and c
5. a and b
Answer:A
(63) Deflection or transfer of a risk to another party is part of which of the following risk response categ ories?
1. Mitig ation
2. Acceptance
3. Avoidance
4. Analysis
Answer:A
(64) Manag ement reserves are used to handle which type of risk?
1. Unknown unknowns
2. Known unknowns
3. business risks
4. pure risks
Answer:A
(65 ) Which of the following is considered during the Procurement Planning Process?
1. Whether to procure
2. How to procure and how much to procure
4. b and c
Answer:E
2. Procurement planning does not include consideration of potential subcontracts since this is the duty of the
contractor.
Answer:A
2. Invitation for Bid and Request for Proposal are two examples of procurement documents.
3. Procurement documents should be structured to facilitate accurate and complete responses from
prospective sellers.
4. b and c
Answer:E
(68) Which of the following is a method for quantifying qualitative data in order to minimize the effect of personal
prejudice on source selection?
2. Screening system
3. Selecting system
Answer:A
3. Overhead costs
4. a and b
5. a and c
Answer:E
(70) Which of the following contract types places the g reatest risk on the seller?
1. Cost-plus-fixed-fee contract
3. Fixed-price-incentive contract
4. Firm-fixed-price contract
Answer:D
(71) In which of the following contract types is the seller's profit limited?
2. Cost-plus-fixed-fee contract
3. Fixed-price-plus-incentive
4. b and c
Answer:D
(72) A cost-plus-percentag e-cost (CPPC. contract has an estimated cost of $120,000 with an ag reed profit of
10% of the costs. T he actual cost of the project is $130,000. What is the total reimbursement to the seller?
1. $143,000
2. $142,000
3. $140,000
4. $132,000
Answer:A
(73) A fixed-price-plus-incentive-fee (FPI. contract has a targ et cost of $130,000, a targ et profit of $15,000, a
targ et price of $145,000, a ceiling price of $160,000, and a share ratio of 80/20. T he actual cost of the project
was $150,000. How much profit does the seller make?
1. $10,000
2. $15,000
3. $0
4. $5,000
Answer:A
1. T he subcontractor possesses special technical and eng ineering skills that the contractor does not have.
3. T he subcontractor can perform the work at a lower cost than the contractor.
5. a and c
Answer:E
(75 ) Which type of bilateral contract is used for hig h dollar, standard items?
1. Purchase order
Answer:C
(76) In which stag e of the neg otiation meeting are points of concession identified?
1. Probing
2. Closure
3. Ag reement
Answer:D
1. Assistance
2. Sealed Bidding
3. Competitive proposals
4. Acquisition
5. Small purchases
6. No answer provided
Answer:D
1. If there are seven points on one side of mean, then an assig nable cause must be found.
4. A process is not out of control even thoug h seven measurements fall outside the lower and upper control
limits.
Answer:A
(79) T here is project with CPI of 0.81 and T CPI=1.00001 this project is:
2. Underbudg et
Answer:D
(80) A collection of g enerally sequential project phases whose name and number are determined by the control
needs of the org anization or org anizations involved in the project, is called:
Answer: A
4. Remaining Duration
Answer: D
(82) Who is responsible for risk identification, risk quantification, risk response development, risk Monitor and
Control?
Answer: D
Answer: B
(84) T wo Point Delphi Estimate, T he Best and Worst Case effort calculation:
Answer: A
ANSWER: C
ANSWER: D
1. T rue
2. False
ANSWER: A
(88) 7. ________ means that every project has a definite beg inning and a definite end.
1. Overall
2. Project Chart
3. T emporary
4. Duration
ANSWER: C
(89) T he smallest unit of time used in scheduling the project is known as:
1. Calendar Unit
2. Scope unit
3. T ime Measurement
ANSWER: A
2. T he customer.
3. T he Sub-contractors/vendors.
Answer: E
Answer: C
1. A reimbursement of allowable cost of services performed plus an ag reed upon percentag e of the
estimated cost as profit.
2. A reimbursement of allowable costs plus a fixed fee which is paid proportionately as the contract
prog resses.
3. T he supplier with a fixed price for a delivered performance plus a predetermined fee for superior
performance.
Answer: A
(93) Project success depends on a no. of interrelated factors, including time, cost and scope control. T he
success of any project depends primarily on:
1. Customer acceptance.
2. Customer satisfaction.
Answer: B
(94) Which of the following is the most efficient means of product quality inspection:
1. Acceptance sampling .
2. 100% inspection.
4. A and C.
Answer: A
Answer: C
(96) Pareto Analysis, cause and effect diag rams and flow charts are used in quality.
1. Control.
2. Assurances.
3. Planning .
4. Verification.
Answer: A
4. Neg otiations.
Answer: B
(98) A condition which will lead an org anization towards conflict is:
1. Conflict of interest.
4. Both A and B.
Answer: D
1. Conflict is bad.
5. A, B and C.
Answer: D
1. Project justification, backg round, scope, objectives, available resources, org anizational responsibilities,
a project schedule, estimates, procurement schedule, and any imitations that top manag ement wants to
apply.
2. Project justification, backg round, scope, objectives, available resources, org anizational responsibilities,
detailed project schedules, estimates, and detailed procurement schedules responsibilities, a project
schedule, and any limitations that top manag ement wants to apply.
3. Project justification, backg round, scope, objectives, available resources, org anizational apply.
Answer: D