Module 2 - Deep Foundation - 2
Module 2 - Deep Foundation - 2
DEEP FOUNDATION
These piles are formed by making holes in the ground and then filling them with sand.
If sand is kept confined, it possesses great crushing strength and becomes
incompressible.
These piles are formed by making holes in the ground and then filling them with sand.
If sand is kept confined, it possesses great crushing strength and becomes
incompressible.
BMC II MODULE 2 S3
SPECIAL PILES
• Pile driving is very noisy and causes massive vibrations through the
soil.
• For this reason, it is sometimes difficult to use them in sensitive
locations.
• For example, if an operational hospital or science lab is to be
extended, driving piles would cause unwanted disturbance. Their use
is also restricted in residential areas in many countries.
• The vibrations could also cause structural damage to older buildings
that are close by. In such situations it is possible to
use micropiling or helical piling, neither of which rely on
hammering.
BMC II MODULE 2 S3
BMC II MODULE 2 S3
Micropiles or minipiles are small piles that are constructed in the following way:
Step 1: a hole a little larger than the pile diameter and the full length of the pile is
dug into the ground using an apparatus like a soil boring machine.
Step 3: a concrete grout is poured into the gap between the pile and the earth.
Helical piles are steel tubes that have helical (spiral) blades attached to them.
These can be drilled into the ground, meaning that the pile acts as a giant drill bit,
and is rotated and pushed into the ground from above, much like a screw drills
into wood. Once the steel pile is driven into the ground, a pile cap is poured on
top of the pile to prepare it for the construction above.
BMC II MODULE 2 S3
STEEL PILES
•H-Piles
•Pipe-piles
•Box pile
•Screw piles
•Disc piles
BMC II MODULE 2 S3
H-Piles
BMC II MODULE 2 S3
H-Piles
BMC II MODULE 2 S3
Pipe-piles
BMC II MODULE 2 S3
The diameter of the pipes used for piling varies from 25 cm to 120 cm and their shell
thickness varies from 8 mm to 12 mm The use of this type of pile for depths of 30 in
or more is quite common.
BMC II MODULE 2 S3
Box pile
BMC II MODULE 2 S3
Screw Pile
• A screw pile consists of a cast iron or steel shaft of external diameter normally varying
from 15 to 30 cm and terminating into a helix or screw base.
• The pile shaft maybe hollow or solid. The diameter of the screw at its base varies from 45
cm to 150 cm.
• The pile is sunk by screwing the pile down inside the ground by use of an electric motor.
• Screw piles function most efficiently in soft clay or loose sand.
BMC II MODULE 2 S3
Disc Pile
BMC II MODULE 2 S3
TIMBER PILES
BMC II MODULE 2 S3
COMPOSITE PILES
BMC II MODULE 2 S3
NON LOAD BEARING PILES Refer Building Construction-Rangwala
Chapter :Deep Foundation pg 132-137
SHEET PILES
BMC II MODULE 2 S3
BMC II MODULE 2 S3
Sheet piling is an earth retention and excavation support technique that retains
soil, using sheet sections with interlocking edges.
BMC II MODULE 2 S3
Concrete sheet piles
Concrete sheet piles are made in square or rectangular cross-section and are driven
similar to wooden piles to form a continuous wall. The interlock between two piles is
normally provided with the help of tongue and groove joint. The tongue and groove
extend to the full length of the piles in most of the cases.
BMC II MODULE 2 S3
Steel sheet piles
Steel sheet pile is a rolled steel section consisting of a plate called the web with integral
interlocks on each edge.
BMC II MODULE 2 S3
Timber sheet piles
BMC II MODULE 2 S3
PILE ACCESSORIES
• PILE CAP
• PILE SHOE
BMC II MODULE 2 S3
PILE CAP
A pile cap is a thick concrete mat that rests on concrete or timber piles that have been
driven into soft or unstable ground to provide a suitable stable foundation.
It usually forms part of the foundation of a building
To protect the top of pile from blow of hammer on top, pile cap is provided.
BMC II MODULE 2 S3
BMC II MODULE 2 S3
PILE CAP
The shape and plan dimensions of the pile cap depend on two factors.
1.Number of piles in the group and
2.The spacing between each pile.
3 Pile
2 Pile
BMC II MODULE 2 S3
PILE SHOE
BMC II MODULE 2 S3
PULLING OF PILE
• To replace the damaged piles during the driving operation.
• To reuse the existing piles when the structure above the pile is
demolished.
BMC II MODULE 2 S3
Method For Pulling Of Pile
The method for pulling of piles will depend on the type of pile,
equipment availability.
BMC II MODULE 2 S3
BMC II MODULE 2 S3
BMC II MODULE 2 S3
FAILURE OF PILE
BMC II MODULE 2 S3
CAUSES OF FAILURE OF PILE
• Most common causes of failure of piles;
• Absence of statistical data of nature of soil strata
• Load coming on pile is high than design load.
• Bad workmanship
• Attack by insets on wood
• Breakage due to over driving (timber pile)
• Buckling of pile
• Damage due to absence of protective cover
• Improper type of pile, method of driving, classification of soil
• Insufficient reinforcement in case of R.C.C
• Misinterpretation of result from pile load test.
• Wrong formula use for determining load bearing capacity.
BMC II MODULE 2 S3