Exss-Stm-Hk-Mos-014 Nh4oh 25%, H2o2 30%, HCL 37%, HF 49%, H2so4 96% PT
Exss-Stm-Hk-Mos-014 Nh4oh 25%, H2o2 30%, HCL 37%, HF 49%, H2so4 96% PT
Exss-Stm-Hk-Mos-014 Nh4oh 25%, H2o2 30%, HCL 37%, HF 49%, H2so4 96% PT
Client : STMicroelectronics
System : NH4OH 25%, H2O2 30%, HCL 37%, HF 49%, H2SO4 96% Systems
Document Title : Work Method of Statement for NH4OH 25%, H2O2 30%, HCL 37%,
HF 49%, H2SO4 96 % Systems
APPROVED BY
TABLE OF CONTENTS
1.0 Purpose 3
4.0 Locations 3
1.0 PURPOSE
Ensure no one gets injured and get no incident/accident during Pressure test for
Ammonium Hydroxide 25%(NH4OH 25%), Hydrogen Peroxide 30%(H2O2 30%),
Hydrochloric Acid 37%(HCL 37%), Hydrofluoric Acid 49%(HF 49%), Sulphuric
Acid 96%(H2SO4 96%) double containment chemical Systems in under Hook-Up
Package work be performed at STMicroelectronics (AMK) project.
To conduct pressure test of the NH4OH 25%, H2O2 30%, HCL 37%,HF 49%, H2SO4 96%
Hook-Up Package, Ammonium Hydroxide 25%, Hydrogen Peroxide 30%,
Hydrochloric Acid 37%, Hydrofluoric Acid 49%, Sulphuric Acid 96% chemical Systems
pipe work in STMicroelectronics (AMK) project.
4.0 LOCATIONS
STM(Ang Mo Kio) AMK6, 6E, 2E, AMJ9 Level-1 sub-fab, cleanroom level-2 & level- 3
5.0 TEST PRESSURE AND HOLDING TIME
Testing Pressure : 29 psi Clear PVC (Outer Layer)
Holding time : 2 hours as per STM specification
Allowance of pressure drop : Zero decay
Test boundary and test limit clearly show in P&ID (or) Lay-out drawing.
1) Conduct line walk/check with Exyte Services team, STM QA and STM hook-up
team member/engineer
2) Pipe work Hook-Up qualification checklist to sign and Punch list ‘A’ item need to be
cleared prior to pressure test
3) Apply permit for pressure testing and get approval from STM engineer and safety
department
4) Find out the isolation points and pressure gauge location,
5) Prepare N2 air charge in point (Use N2 cylinder for charging) ,
6) Mark all the location layout drawing (Highlighted in the attached drawing)
7) Check pressure gauge calibration certificates, pressure gauge range, and pressure
gauge calibration period shall be within one year.
8) Take over the area and barricade with warning signboard to prevent from any
accident/incident during pressure test.
4) Connect hoses from nitrogen cylinder source to charge in the chemical lines.
5) Open N2 cylinder main valve to charge in the clear PVC outer layer pressure test.
6) Pressure up 0~5 psi, hold pressure for 15-20 minutes and check for any leakage and
monitoring.
7) Slowly increase pressure up from 5~10psi, 10psi~15psi, 15psi~20psi, 20psi~29psi
gradually pressure increase for monitoring.
8) Ensure all inline valves are opened within the test boundary limit.
9) If found no leak, hold pressure at 29 psi(for Clear PVC Outer Layer) and follow
QA/QC procedure for testing.
10) Install PFA tube into outer layer pipe lines after outer layer testing is passed.
11) Blank off the PFA tube both end sides for nitrogen air testing.
12) Connect hose from nitrogen cylinder source to charge in the PFA tube for testing.
13) Open N2 cylinder main valve to charge in the PFA tube(inner layer) pressure test.
14) Pressure up 0~5 psi, hold pressure for 15-20 minutes and check for any leakage &
monitoring.
15) Slowly increase pressure up from 5~15psi, 15psi~25psi, 25psi~35psi, 35psi~45psi
45 psi~ 55 psi gradually pressure increase for monitoring.
16) If found no leak, hold pressure at 58 psi for PFA tube inner layer and follow
QA/QC procedure for testing.
III) DEPRESURIZATION