Fabrication - Flow Chart
Fabrication - Flow Chart
Client Approval:
Submit TEKLA model to the client for approval.
Address any client feedback and make necessary adjustments.
Obtain final approval from the client.
Detailing:
Generate detailed fabrication drawings from the approved TEKLA model.
Include dimensions, materials, weld symbols, and other specifications.
Review and verify the detailing with the project requirements.
Fabrication:
Assign the project to the fabrication team.
Procure necessary raw materials based on detailed drawings.
Fabricate steel components according to the detailed drawings.
Conduct quality checks during the fabrication process.
Painting:
Prep steel components for painting by cleaning and priming.
Apply the specified paint system to protect against corrosion.
Ensure compliance with environmental and safety regulations.
Assembly:
Assemble fabricated steel components into the final structure.
Ensure proper alignment and fit based on the assembly drawings.
Final Inspection:
Delivery:
Prepare the final product for shipping.
Coordinate with logistics for transportation to the client's site.
Ensure proper documentation and delivery schedule adherence.
terminator
pre-defined
process
process
decision
p
connec
tor preparation
multi document
Receipt of General Arrangement Drawing (GAD):
GAD is received from the client or project manager.
Verify the completeness and accuracy of the GAD.
TEKLA Modeling:
Assign the project to a TEKLA modeler.
Create a 3D model of the structure using TEKLA Structures software.
Ensure that the model is accurate and reflects the details in the GAD.
Client Approval:
Submit TEKLA model to the client for approval.
Address any client feedback and make necessary adjustments.
Obtain final approval from the client.
Detailing:
Generate detailed fabrication drawings from the approved TEKLA model. connec
Include dimensions, materials, weld symbols, and other specifications. tor
Review and verify the detailing with the project requirements.
Fabrication:
Assign the project to the fabrication team.
Procure necessary raw materials based on detailed drawings.
Fabricate steel components according to the detailed drawings.
Conduct quality checks during the fabrication process.
Painting:
Prep steel components for painting by cleaning and priming.
Apply the specified paint system to protect against corrosion.
Ensure compliance with environmental and safety regulations.
p
Quality Control (QC):
preparation
Perform quality control checks at various stages of fabrication and painting.
Address any issues identified during QC inspections.
Ensure the final product meets industry standards and client specifications.
Assembly:
Assemble fabricated steel components into the final structure.
Ensure proper alignment and fit based on the assembly drawings.
Final Inspection:
Conduct a final inspection of the assembled structure.
Verify that all components meet quality standards.
Address any last-minute issues before delivery.
Delivery:
Prepare the final product for shipping.
Coordinate with logistics for transportation to the client's site.
Ensure proper documentation and delivery schedule adherence.
Receipt of General
Arrangment Drawing
(GAD)
Verify the
Completeness and
accuracy of the GAD
TEKLA MODELING
Assign the project to TEKLA
modeler.
connec
tor
Create a 3D model of the
structure using TEKLA
Structures Software, ensuring
the accuracy and reflects the
detail in the GAD
CLIENT
APPROVAL Rejected
Submit to
client for
Approval
preparation
Approved
FABRICATION
Assign the project to TEKLA
modeler.
tion
TEKLA
ns,
other
GAD is received from the client or
Receipt of General project manager.
Arrangment Drawing Verify the completeness and accuracy of
(GAD) the GAD.
CLIENT
APPROVAL Rejected Address Comments by the
Submit to Client.
client for
Approval
Approved
DETAILING Include dimensions, materials, weld
Generate detailed fabrication symbols, and other specifications.
drawings from the approved TEKLA Review and verify the detailing with the
model. project requirements.
PROJECT
JO# RES# PROJECT NAME QUANITY UNIT START FINISH
MANAGER
COMPLETION (To Day), Tons BUDGET(To Complete)
%
STATUS
(To LABOR TOOLS &
EQUIPMENT
Date) PLAN ACTUAL VARIANCE CONSUMABLES
(PhP)
( PhP) (PhP)
ACTUAL (To Date) BALANCE(To Complete)
DESCRIPTION &
JO# RES# PROJECT NAME QUANITY UNIT START FINISH
MARK NO.
COMPLETION (To Day), Tons BUDGET(To Complete)
%
STATUS
(To LABOR TOOLS &
EQUIPMENT
Date) PLAN ACTUAL VARIANCE CONSUMABLES
(PhP)
( PhP) (PhP)
ACTUAL (To Date) BALANCE(To Complete)